Progress Update: RIDFT
Group 27Daniel Escobedo Chelsea ArmbristerBrian LaTulip Divyesh BhaktaLuis Sura Joseph Gwaltney
Sponsor: Advisors: Dr. Okenwa Okoli Tarik Dickens
Dr. Nicholas Bembridge Dr. Peter N. Kalu
![Page 2: Progress Update: RIDFT](https://reader033.vdocuments.site/reader033/viewer/2022051701/56816717550346895ddb866d/html5/thumbnails/2.jpg)
AgendaBackgroundIntroductionProblem StatementNeeds AssessmentProject Goals/SpecificationsMain Issues EncounteredPreconceived Automation ModelProgress Since DecemberCurrent Project StatusProject TimelineClosing ThoughtsQuestions
2
![Page 3: Progress Update: RIDFT](https://reader033.vdocuments.site/reader033/viewer/2022051701/56816717550346895ddb866d/html5/thumbnails/3.jpg)
BackgroundWhat is the Resin Infusion between Double
Flexible Tooling (RIDFT)?
3
![Page 4: Progress Update: RIDFT](https://reader033.vdocuments.site/reader033/viewer/2022051701/56816717550346895ddb866d/html5/thumbnails/4.jpg)
IntroductionHow does it work?
What is it used for?Polymeric Bound Composites
4
![Page 5: Progress Update: RIDFT](https://reader033.vdocuments.site/reader033/viewer/2022051701/56816717550346895ddb866d/html5/thumbnails/5.jpg)
Problem StatementCurrent RIDFT Process Issues:
Labor IntensiveTime ConsumingProcess Repeatability
Proposed Solutions:Semi-AutomationFiber Placement MethodologyProcess Streamlining
5
![Page 6: Progress Update: RIDFT](https://reader033.vdocuments.site/reader033/viewer/2022051701/56816717550346895ddb866d/html5/thumbnails/6.jpg)
Needs AssessmentDevelop/Implement methodology for:
Semi-Automated PlacementSafe Removal of the Top and Bottom Frames Accurate Fiber Placement
Design an Ergonomic Handling System
Minimize Operational Footprint
6
![Page 7: Progress Update: RIDFT](https://reader033.vdocuments.site/reader033/viewer/2022051701/56816717550346895ddb866d/html5/thumbnails/7.jpg)
Project Goals/SpecificationsPrimary Objectives
Reduce Overall Process DurationReduce and Enable Safe Manpower UtilizationReduce Operational Footprint
Secondary ObjectivesDesign and Implement a Method for Accurate Fiber and Mold
PlacementErgonomic Handling System
ConstraintsSingle Operator Utilization$3,000.00 - $5,000.00
7
![Page 8: Progress Update: RIDFT](https://reader033.vdocuments.site/reader033/viewer/2022051701/56816717550346895ddb866d/html5/thumbnails/8.jpg)
Main Issues EncounteredSafety
Components issues Links Gears Hydraulics
BudgetPrevious Estimated Cost≈ $13,000
New Budget ≈ $3,000 - $5,000
8
![Page 9: Progress Update: RIDFT](https://reader033.vdocuments.site/reader033/viewer/2022051701/56816717550346895ddb866d/html5/thumbnails/9.jpg)
Preconceived Automated Model
9
![Page 10: Progress Update: RIDFT](https://reader033.vdocuments.site/reader033/viewer/2022051701/56816717550346895ddb866d/html5/thumbnails/10.jpg)
Progress Since DecemberStaff Meeting (ME Staff)
Discussed issues with previous design
Staff Meeting (Advisor/Customer)Discussed:
Budget constraints Safety Issues End of Semester Goal
Reassessed Project Timeline10
![Page 11: Progress Update: RIDFT](https://reader033.vdocuments.site/reader033/viewer/2022051701/56816717550346895ddb866d/html5/thumbnails/11.jpg)
Current Project StatusTerm Objective Shift
Previously: Design and PrototypeCurrently: Detailed Design
System ReassessmentSafetyCost“Workability” – ease of operationOperational Footprint
11
![Page 12: Progress Update: RIDFT](https://reader033.vdocuments.site/reader033/viewer/2022051701/56816717550346895ddb866d/html5/thumbnails/12.jpg)
Project Timeline
12
![Page 13: Progress Update: RIDFT](https://reader033.vdocuments.site/reader033/viewer/2022051701/56816717550346895ddb866d/html5/thumbnails/13.jpg)
Closing ThoughtsShift in Project Goals
Simply DesignNo Physical Working Model
Improve Upon Previous Years DesignIncrease System Stability/SafetyEase of UsePortable Semi-Automated System
13
![Page 14: Progress Update: RIDFT](https://reader033.vdocuments.site/reader033/viewer/2022051701/56816717550346895ddb866d/html5/thumbnails/14.jpg)
Questions?