  • 5/27/2018 _ 7

    1/2

    86 PEFS Process Engineering Flow Scheme

    87 PFS Process Flow Scheme

    88 E/R Engineering Requisition (= Material Requisition)

    89 MSD Material Selection Diagram (MM Preparation, PR Review)

    90 (+ /) * 95%(?)

    91 PMSA Progress Measuring System Application

    92 Project Tool P3, PMSA (MS Acess), Project Space(EDMS),

    ProjectITB -> -> -> KOM (Launch Meeting) -> ->

    -> PD Sign

    Work Flow -> -> -> (10 , )

    ( M/H , (Project Highlight ))

    94 P-code

    95 M/H (PM), ( ),

    96 Work package Cost Breakdown Structure ( , )

    97 Insulation(LIM) Insulation Limit

    98 EDIS Engineering Data Information System 6Package

    99 LDM Line Data Management

    100 NDM Nozzle Data Management

    101 ELM Equipment List Management

    102 ELD Equipment Loading Data

    PD, PM PE, ITB

    (BBJN ) , (Where-What)

    , (Purpose, Contents)

    , (Emphasis)

    , (Safty, Layout - Requirement)

    .

    (20 binders )2,

    22.

    104 BEDD Basic Engineering Design Data

    105 Engineering Portion 3~5%(??)

    106 NPC Notification of P&ID Change

    107 NEC Notification of ELP Change

    108 DCN/FCN Design/Field Change Notice

    109 MDR Master Document Register ( ? : )

    110 IFA Issued for Approval ( )

    111 IFC Issued for Construction

    112 As Built

    113 P&ID, Equipment Layout Plan(ELP),Underground(U/G) Composite Drawing

    114 Preliminary (Pre.) : PA, PB, --- , ,

    115 Issued for Information (IFI) : A, B, C, --- "IFI" or "AFC" "0"

    116 Issued for Review (IFR) : A, B, C, --- "IFI" or "AFC" "0"

    117 Issued for Approval (IFA) : A, B, C, --- "IFI" or "AFC" "0"

    118 Approved for Design (AFD) : 0, 1, 2, ---P&ID, EQ list, Process Data Sheet,

    etc.

    119 Issued for Construction or Approved for Construction (IFC or AFC) : 0, 1, 2, ---

    120 Issued for Purchase or Approved for Purchase (IFP or AFP) : 0, 1, 2, ---

    121 Issued for Fabrication or Approved for Fabrication (IFF or AFF) : 0, 1, 2, ---

    93

    103

  • 5/27/2018 _ 7

    2/2