ycps yorkshire common permit scheme for road works & street works

59
YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

Upload: preston-sanor

Post on 01-Apr-2015

228 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Yorkshire Common Permit Scheme For Road Works & Street Works

Page 2: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Introduction

The Yorkshire Common Permit Scheme for Road Works and Street Works is made pursuant to Part 3 of the TMA 2004,

Sections 32 - 39 and the Traffic Management Permit Schemes (England) Regulations 2007, Statutory Instrument 2007, No. 3372,

made on the 28th November 2007.

Page 3: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Introduction to Permit Schemes

Permit schemes were introduced by Part 3 of the Traffic Management Act 2004 (TMA) to improve authorities’ abilities to minimise disruption from street and highway works.

Permit Schemes provide a new way to manage activities in certain streets in the Public Highway.

Page 4: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Introduction to Permit Scheme

• In permit streets, instead of informing a Street Authority about their intentions to carry out works in the area, all works promoters will need to obtain a permit for their works.

• Permit schemes provide a change to the ‘Notification System’ under the New Roads and Street Works Act, 1991 (NRSWA).

Page 5: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Scheme Purpose and Objectives

• To enable improved LA coordination and control of works on highway.

• To reduce delay and disruption to travelling public.

• To save traffic congestion and reduce vehicle operating costs.

• To demonstrate parity.

Page 6: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Elements in Common with the NRSWA Notice System

• Registered Activities / Works;

• Categories of Activities / Works (Major, Standard, Minor and Immediate);

• Street Gazetteers, including street references, by means of Unique Street Reference Numbers (USRN) and Additional Street Data (ASD);

• The distinction between Main roads and Minor roads;

• Streets designated as protected, having special engineering difficulty or traffic sensitivity.

Page 7: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Key Points of Permits

• A permit is only valid for the period of time stated on the permit.

• The start and end dates will be in calendar days, even though many aspects of the scheme will operate on working days.

• Where a permit allows weekend and Bank Holiday work, then the permit start and end dates will accommodate that.

• A late start on site means duration lost. The end date cannot be ‘stretched’ without an approved variation.

Page 8: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Streets Covered

The scheme will cover all streets which are:

• Reinstatement Categories 0, 1 or 2

• Traffic Sensitive Streets

• Protected Streets

Page 9: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Exclusions from The Scheme(NRSWA Notices only)

•Trunk roads and motorways, for which the Highways Agency is the Highway Authority

•Private streets

•Category 3 or 4 streets that are not Traffic sensitive

Page 10: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

What Activities Need A Permit?

• Registerable activities that involve the breaking up or

resurfacing of any street in Cat. 0, 1 and 2 roads or Traffic

Sensitive, or Protected streets, at any time.

• All activities that involve the opening of the carriageway of Cat. 0, 1 or 2 roads, or Traffic Sensitive streets, or cycleways at Traffic Sensitive times.

Page 11: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

What Activities Need a Permit?(cont’d.)

• All activities that require Traffic Control.

• All activities that reduce the number of lanes used in a carriageway

of 3 or more lanes.

• All activities that require a Temporary Traffic Regulation Order, or Notice, or the suspension of pedestrian crossing facilities.

Page 12: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

What Activities Need A Permit?(cont’d.)

• All activities that require a reduction of width of the existing carriageway of a Traffic Sensitive street at any time.

• Pole testing which involves excavation, and any reinstatement following pole testing, whether it involves any of the above criteria or not.

Page 13: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

What Activities DON’T Need A Permit?

Non registerable activities:

• Traffic Census surveys.

• Pole testing which does not involve excavation.

• Road-marking works that are not part of other works, providing the ‘Registered Criteria’ do not apply.

• Works on Cat. 3 and 4 streets which are not Traffic Sensitive at any time or in any part.

Page 14: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Working DayNRSWA Section 98(2)

For the purposes of administration of the Permit Scheme ‘Working Day’ means a day other than a Saturday or Sunday, Christmas Day or Bank Holiday; and for the purpose of this permit scheme, a working day will be

treated as

08:00 to 16:30

Page 15: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Permit Activity Categories

Page 16: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Activity Categories

• Major

• Standard

• Minor

• Immediate

Page 17: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Activity Categories

Major Activities:

• Those works which have been identified or planned as

part of a programme

• Works requiring a Temporary Traffic Regulation Order

(Not a Temporary Traffic Notice).

• Works having a duration of 11 working days or more.

Page 18: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Activity Categories (cont’d)

Standard Activities:

• Works other than ‘major’ or ‘immediate’ that have a

planned duration of between 4 and 10 working days

inclusive.

Page 19: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Activity Categories (cont’d)

Minor Activities:

• Works other than ‘major’ or ‘immediate’ that have a

planned duration of 3 working days or less.

Page 20: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Activity Categories

Immediate Activities:

Emergency Works

• Required to end or prevent circumstances existing orimminent which can cause damage to people or property.

Urgent Activities – (Not being Emergency Works)

• To avoid substantial loss to the promoter.• To prevent unplanned interruption to service.• To re-connect supplies or services where the promoter will

be under civil or criminal liability if delayed.

Page 21: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Permit Applications

Page 22: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Requirements for a Permit

Any activity promoter who wishes to carry out any activity requiring registration in a permit street must obtain a permit from the Permit Authority.

The permit allows the promoter to carry out the specified activity:•At the specified location.•For a specific duration between the start and end dates shown.•Subject to any conditions which are specified, or agreed, by the promoter in the application.

Page 23: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Method of Making Permit Applications

• Permit applications should be made via EToN

(Where this is not possible, due to system failure, they may be made via alternative methods like fax, email or hand delivery.)

• Applications must comply with the technical specification for EToN.

Page 24: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Timing of Applications

The time period is measured from the time of receipt of the

application by the Permit Authority.

Major activities:

These require a Provisional Advanced Authorisation at least three months in advance of the activity and; a Permit Application at least ten working days before the activity is proposed to start.

Page 25: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Provisional Advanced Authorisation

Advanced authorisation is to be sought at least 3 months before start of Major activities.

A Provisional Advanced Authorisation (PAA) is an early provisional permit issued before the final details of an activity have been established. A PAA effectively ‘books’ the road space and ensures that others will not obtain a permit for conflicting planned works.

Page 26: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Timing of Applications(cont’d.)

Standard activities: Permit application required a minimum of ten days before the proposed start date.

Minor activities: Permit application required at least three days before the proposed start date.

Immediate activities: Permit application required within two hours of the works commencing (for out-of-hours, within 2 hours of the start of the

following working day).

Page 27: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Timing of Applications(cont’d.)

Page 28: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Information Requirements

Page 29: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Information Required

• Unique Permit Reference Number – System generated• Description of Activity• Location• Timing and Duration• Illustration• Technique to be used for Underground Activities

Page 30: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Information Required (Contd.)

• Traffic Management and Traffic Regulation Orders• Depth• Reinstatement Type• Inspection Units• Contact Person• Early Starts

Page 31: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Permit Conditions

Page 32: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Permit Conditions

Regulations provide provisions for permit authorities to attach conditions to permits and specify the types of conditions which may be attached.

They may also specify certain conditions which apply to works before a permit is obtained i.e. for immediate activities

Page 33: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Permit ConditionsThe range of conditions that can be applied to permits will fall under the following categories:

• Timing and duration of activity• Road space• Traffic management provisions• Methodology for carrying out activities• Consultation and publicity• Environmental conditions• Supplementary and local conditions:

e.g. provision for vulnerable people

special publicity.• Immediate activities.

Page 34: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Timing and Duration

• Start and end dates (calendar days)

• Bank Holidays, weekend, out of hours?

• For Traffic Sensitive Streets – include times of day

to be carried out

Page 35: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Road Space

• The amount of space that can be used in the street during works.

• In some locations a condition may be required by the Permit Authority to prevent materials and plant being stored on site.

Page 36: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Traffic Management Provisions

• Promoter must submit Traffic Management proposals - e.g. closure, one-way, temp. signals, width restriction, lane closure, parking restrictions.

• Changes during the course of the works to be explained.

• May require conditions to notify Authority before change brought in.

Page 37: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Methodology of Carrying Out Activities

• Seek to use minimum dig technology wherever possible.

• Permit Authority may require special provisions – in discussion

Page 38: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Consultation and Publicity

For all works, it is a requirement that the permit reference number, when issued, must be prominently displayed on the site information board at all times.

Where planned activities have the potential to be especially disruptive to local residents, businesses and/or road users, Permit Authorities can request a condition requiring the promoter to provide advanced notice to nearby householders or businesses, or to drivers or pedestrians using the road.

Page 39: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Environmental Conditions

• Activity promoters must contact relevant HA environmental health teams if proposing planned ‘out of hours’ work.

That is, outside of 8am – 6pm, Monday – Friday, and 8am – 1pm on Saturday (section 60: Control of Pollution Act, 1974).

• Conditions may be required to protect residents, as well as people working, and schools close to proposed activities. Will be requested asap to enable inclusion in permit application.

Page 40: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Environmental Conditions (cont.)

• Conditions may be needed where there is a concern about maintaining the site in a clean and tidy condition, including removal of any spillage of materials on the public highway during completion of the works.

• Where trees will be affected by activities, promoters must contact the Authority’s Arboriculture Officers.

Page 41: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Possible Local Conditions

• Updated information boards situated around work site.

• Stone cutting equipment to be used with dust suppression measures, i.e. water facility.

• New materials to be replaced like-for-like.

• Works to be restricted in narrow roads on days of refuse

collection.

• Where special materials are identified, works promoter must contact Highway Authority engineers.

Page 42: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

YCPS Model Conditions

YCPS Conditions_v6_20120309.doc

Page 43: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Permit Condition Inspections

•Permit compliance inspections may be made at the Permit Authority’s own expense.

•Breach of conditions is an offence for which an FPN may be given

Page 44: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Permit Variations

Page 45: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Permit Variations

Changing circumstances, for either an activity promoter or for the Permit Authority, may require permits and/or the conditions attached to them to be varied.

Page 46: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Permit Variations(incl. extensions of duration)

• Prior discussion recommended if potentially contentious.

• Application as soon as possible when known that any of the permit conditions may be breached

• If 2 days, or more than 20% of duration left – apply via EToN

• If less than 2 days, or 20% - telephone, then EToN if agreed

Page 47: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Permit Variations (cont’d.)

• The Permit Authority must respond within 2 working days. Otherwise, the variation is deemed to be granted

• Section 74 charges may still be considered, even if extension granted, if ‘reasonable period’ exceeded

• Authority imposed variation – no fee

Page 48: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Early Starts

• When an early start has been agreed after a permit application, the Promoter shall submit an application for a variation to the permit.

• In the case of a Provisional Advance Authorisation, the Promoter will include the revised dates on the permit application.

Page 49: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Application and Response Times

Page 50: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Revocation

• No mechanism, nationally, for formally suspending or postponing

a permit, only for varying or revoking one.

• If need for a revocation due to the promoter failing to comply with

the permit conditions, Authority may use provisions to clear the street

• If promoter wishes to cancel a permit, MUST use the Cancellation Notice provided via EToN.

• No charge for a cancellation Notice.

Page 51: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Transitional Arrangements

• The basic rules of transition will apply on all roads where the permit scheme operates.

• The permit regime will apply to all activities where the administrative processes, such as application for a Permit or Provisional Advance Authorisation, start after the commencement date.

• Activities which are planned to start on site more than one month after the changeover date (for standard, minor and immediate activities) or three months (for major activities) shall operate under the permit scheme.

• Any other activities/works which started under the notices regime will continue under that regime until completion.

Page 52: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Transitional Arrangements

Major

Permit Go Live Date

3 month1 month

Standard,

Minor Immediate

Works raised prior to Go live Date Will be closed as notices only where they do not exceed the Transition windows above.•Standard, Minor and Immediate that start 1 month or more after go live must be re-raised as a Permit•Major that starts in excess of 3 months from the go live date must be re-raised as a Permit

Page 53: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Criminal Offences

• It is a criminal offence for an undertaker or someone acting on its behalf to undertake works without a permit.

• The offence carries a maximum fine of level 5 on the standard scale. The FPN fee is £500, reduced to £300 if paid within 29 calendar days.

• £120 (standard FPN fee) for working in breach of permit conditions. If paid by 29 days then the fee is reduced to £80.

Page 54: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Fixed Penalty Notices (FPNs)• Offer undertaker an opportunity to discharge liability for non-

compliance by paying a penalty amount;

• FPN may not be given more than 91 calendar days after the act of non-compliance (beginning with the day on which the breach is committed);

• Penalty amount is £500 for the offence of working without a permit, discounted to £300 if paid within 29 days;

• For working in breach of a permit condition, the penalty is £120, or a discounted amount of £80 if paid within 29 days;

• If undertaker fails to pay within the required period (36 days), the Authority may bring proceedings in Magistrates’ court.

Page 55: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Permit Fees

Page 56: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Key Performance Indicators

• A key principle and objective of the scheme is that it treats all activities covered by the scheme on an equal basis.

• The present 2007 Permit Regulations provide for both street-works and Highway Authority works.

• In order to show that the Permit Authorities are operating the scheme in a fair and equitable way, the Permit team will generally be separated from the highway scheme design and build activities of the Authority.

Page 57: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Members of the Yorkshire Common Permit Scheme

Phase I

Implementation ??? 2012

•Barnsley MBC

•Doncaster MBC

•Kirklees Council

•Leeds City Council

•Rotherham MBC

•Sheffield City Council

Phase II Implementation

20??

•Bradford MDC

•Calderdale Council

•Wakefield Council

Page 58: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Yorkshire Common Permit Scheme

• Initially Six Authorities ‘go live’ at ??????• Three more may follow later in 2013• Fundamental change in thinking• Only part of the network• Obvious from EToN system• Internal training on details of own systems• Good luck• Work together

Page 59: YCPS Yorkshire Common Permit Scheme For Road Works & Street Works

YCPS

Thank You – Any Questions