Page 1: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

XTRA POWER ENERGY SYSTEMS

BREAKING THE BOTTLENECK

Lean Consulting Alireza Almaleki Faith Kaplan Brian Chipman Amandeep Sekhon

Page 2: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Agenda Clarification

Analysis

Recommendation

Implementation

Risks

Page 3: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

• Demand exceeds supply •  Supply chain needs

reconfiguring Key

Issues

•  Switch suppliers to solve bottleneck

•  Incentivize DLSP to manage and support open face battery system

Solution

Clarify Analyze Implement Risks Lean Consulting

Page 4: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Clarify Analyze Implement Risks Lean Consulting

Where is the Bottleneck? Customers

return batteries

Retailer stores batteries

Battery pick-up and return

to plant

Ship retailers new and

refurbished batteries

Page 5: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Clarify Analyze Implement Risks Lean Consulting

Strengths

Robust supply chain

Dynamic distribution network

Strong retailer relationships

Challenges

Market demand outstrips supply

Retailer dissatisfaction affects customer purchases

Threats

Fluctuating commodity pricing

Foreign exchange rate

Opportunities

New revenue stream

Partnerships

XTRA

Page 6: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Clarify Analyze Implement Risks Lean Consulting

Efficient logistics Revenue Feasibility

Criteria for Success

Page 7: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Clarify Analyze Implement Risks Lean Consulting

Alternatives

Work with Cretto to address bottleneck

Replace Galaxy Electrical with Haley Power

Replace Avani International and Cretto with DLSP and Dolphin Power

Replace all existing suppliers with DLSP, Dolphin Power, and Haley Power

Page 8: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Advantages Disadvantages

Lose market share

Demand exceeds supply

Retailer dissatisfaction

Same cost

Maintain trusted relationship

Work with Cretto

Clarify Analyze Implement Risks Lean Consulting

Page 9: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Replace Galaxy with Haley Power

Clarify Analyze Implement Risks Lean Consulting

Advantages Disadvantages

Supplier trust

Bottleneck remains

Increased costs

Larger lead producer

Shorten lead time by 2 days

Page 10: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Replace Cretto and Avani

Clarify Analyze Implement Risks Lean Consulting

Advantages Disadvantages

Supplier trust

Supplier bargaining power

Increased costs

Happier retailers

Solves bottleneck

Page 11: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Change All Suppliers

Clarify Analyze Implement Risks Lean Consulting

Advantages Disadvantages

Resolves bottleneck

Meet increased battery demand

Happy retailers

Supplier trust

HR issues

Page 12: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Clarify Analyze Implement Risks Lean Consulting

OK, Good, Better, Best Status Quo Change Lead

Supplier Change Transportation and Lead Suppliers

Change All Suppliers

Efficient Logistics

Revenue

Feasibility

Page 13: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

•  Demand exceeds supply •  Supply chain needs

reconfiguring Key

Issues

•  Switch suppliers to solve bottleneck

•  Incentivize DLSP to manage and support open face battery system

Solution

Clarify Analyze Implement Risks Lean Consulting

Page 14: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Clarify Analyze Implement Risks Lean Consulting

Implementation

Bottleneck solution

Partnership agreement

Retailer solutions

Page 15: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Clarify Analyze Implement Risks Lean Consulting

Bottleneck Solution

• DLSP • Dolphin Power

New partnership

• Down from 12 to 6 days

• Aligns with production

Lead Time •  Replace with

superior product

Avanti

Page 16: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Partnership Agreement

Concern with commitment in production chain

Tie success of reconditioned batteries to DLSP

Connect DLSP to XTRA Power Auto Industries

Clarify Analyze Implement Risks Lean Consulting

Page 17: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Retailer Solutions

Retailer Satisfaction

• Reimburse key retailers • B2B marketing • Retailer training • Relationship management

Clarify Analyze Implement Risks Lean Consulting

Page 18: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Key Performance Indicators

Turnaround

•  6 day production cycle

Sustainability

•  Eliminate waste

•  Increase battery recycling to 10%

Customer Satisfaction

•  Increase customer interaction to monthly

•  Feedback surveys

Clarify Analyze Implement Risks Lean Consulting

Page 19: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Human Resources

Staffing Increase

•  Maintain optimum staff levels

•  Local reps for local customers

Training

•  Align with lean corporate culture

•  Training best practices

•  Reduce training to 1 from 3 months

Performance

•  Supervision until confidence

•  Quality assurance

•  Feedback survey - quarterly

Clarify Analyze Implement Risks Lean Consulting

Page 20: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Operations

Standardization

•  suppliers to reduce production time: 6 to 5 days

•  Company wide efficiencies

Optimization

•  Limit in-house waste

Sharpen the Saw

•  Examine production for optimization

•  Off-site training

Clarify Analyze Implement Risks Lean Consulting

Page 21: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Clarify Analyze Implement Risks Lean Consulting

Marketing

Outdoor

•  Increase brand awareness and quality

Point of Purchase

•  Promote XTRA batteries

•  Highlight reconditioned batteries

B2B

•  Contests •  Incentivize

sellers to maximize sales

Page 22: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Timeline Months 0  to  3 3  to  6 6  to  12 12  to  18 18  to  24 24  to  32 32  to  40

PartnershipAgreementMaintenance

MarketingB  TO  BB  TO  CRetailerTraining

HRHireTrainQA

OperationsStandarizeEfficencies

QA

Phase  1 Phase  2 Phase  3

Clarify Analyze Implement Risks Lean Consulting

Page 23: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Revenue Projections

Clarify Analyze Implement Risks Lean Consulting

INR in Millions   2013   2014   2015   2016  

Heat shielded   89.9   105   135   160  

Open shielded   126   140   170   200  

Recondition   17   22   27   40  

Others   125   135   155   165  

Total   360   402   487   560  

Page 24: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Cost

Clarify Analyze Implement Risks Lean Consulting

INR  in  Millions   2013   2014   2015   2016  Raw material   89   99   110   130  Packaging   8   11   13   15  Logistics   95   120   145   175  Direct Costs   193   230   268   320  

OVERHEADS  Employee salary   41   46   51   56  Utilities   37   42   44   47  Marketing   0.7   1.5   1.5   1.5  Total Overheads   78   89   96   104  

Page 25: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Income Statement

Clarify Analyze Implement Risks Lean Consulting

INR  in  Millions   2013   2014   2015   2016  

Revenue   360   402   487   560  

Direct costs   193   230   268   320  

Overhead costs   78   89   96   104  

N. Profit   89   83   123   136  

Page 26: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Clarify Analyze Implement Risks Lean Consulting

0

100

200

300

400

500

600

1 2 3 4

Revenue N. Profit Linear (Revenue)

Page 27: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

Risks •  Scale up supply of batteries •  Improve pick-up times of open-shield

batteries

Dissatisfied retailers

•  Link Dolphin Power and Xtra Auto to ensure mutual sustainable success

Supplier bargaining power

•  Buy forward and futures Foreign exchange

Clarify Analyze Implement Risks Lean Consulting

Page 28: XTRA POWER ENERGY SYSTEMS · 2015-10-19 · XTRA POWER ENERGY SYSTEMS BREAKING THE BOTTLENECK Lean Consulting Alireza ... Recommendation Implementation Risks • Demand exceeds supply

• Demand exceeds supply •  Supply chain needs

reconfiguring Key

Issues

•  Switch Suppliers to solve bottleneck

•  Incentivize DLSP to manage and support open face battery system

Solution

Clarify Analyze Implement Risks Lean Consulting