wsh (design for safety) regulations -an overview...microsoft powerpoint - overview of dfs...
TRANSCRIPT
WSH (Design for Safety) Regulations
- An Overview -
• Enacted - 10 July 2015
• Come into force – 1 Aug 2016
Commencement
2
� Impetus to Mandate DfS
� WSH (DfS) Regulations
© 2
01
5 A
ll r
igh
ts r
ese
rve
dPresentation Scope
Impetus for DfS
Can such risks posed to maintenance personnel be avoided?
Example of DfS in projects
• Save cost and time to erect scaffolding during maintenance
• Enhanced safety with no need to work at height• Effective long term maintenance
Example of DfS in projects
• Permanent maintenance unit
• Mitigate risk of being hit by passing vehicles
Example of DfS in projects
8
© 2
01
5 A
ll r
igh
ts r
ese
rve
dImpetus to Mandate DfS
Shifting the WSH Intervention Upstream
“We cannot rely solely on downstream regulation and enforcement activities to achieve a
breakthrough in WSH performance. We have to do more upstream rather than only deal with the
risks that materialise downstream.
Presently, developers and designers tend to leave the identification of WSH risks in building
construction and maintenance to the builders and building operators. Performing RM upstream
would mean they have to make a conscious effort to collaborate with relevant experts toidentify WSH risks in their designs and incorporate the necessary risk control solutionsinto them upfront. Builders and facility operators will then have significantly fewer risks to
manage downstream.”
To achieve widespread adoption of DfS
and enable significant progress in
workplace safety, the Government has
decided to mandate DfS, and require
developers to ensure designs are safe to
build.
DPM Tharman Shanmugaratnam
Launch of NWSH Campaign
7 May 2014
Z[
2008 Launch of Guidelines on DfS for Building and Structures
Introduction of the DfS Coordinator Course2010
Introduction of DfS Recognition Scheme2011
Construction Industry Joint Committee (CIJC) pledges support for DfS (non-mandate)2012
1998 Study Trip to UK (Post CDM 94’)
Public developers committed to adopt DfS for new projects
2013
DPM announces mandate of DfS2014
Industry & Public consultations on the proposed WSH (DfS) Regulations
2015 WSH (DfS) Regulations enacted
Highlights of Singapore’s DfS journey
Taskforce on Mandating DfS
10
Contractor
Developer
Centre for Public
Project Mgmt
Developer
DesignerIndustry
rep
Agencies
which
impact
design
Contractor
Consultations with Stakeholders
Focus Group Discussion with Industry
Taskforce meetings
WSH (DfS) Regulations
To foster greater industry ownership amongst Developers and Designers to
manage the WSH risks upstream at the design and planning phase of projects.
Objective
• Collaboration amongst parties in addressing design risks
• Sharing of relevant information with relevant parties
• Competency
Key Features
Stakeholders
• Developers
• Designers
• Contractors
• DfS Professionals
• Owners
WSH (Design for Safety) Regulations
Parts in the Regulations
PART 1 - PRELIMINARY
1. Citation and commencement
2. Definitions
3. Application
PART 2 - DUTIES OF DEVELOPER
4. Design of structure for safety and health of affected persons
5. Developer’s duties in respect of designers and contractors
6. Design-for-safety review meeting
7. Design-for-safety register
8. Delegation of developer’s duties
PART 3 - DUTIES OF DESIGNER AND CONTRACTOR
9. Duties of designer
10. Duties of contractor
PART 4 - MISCELLANEOUS
11. Duty of registered proprietors and subsidiary management corporations
12. Offences
WSH (Design for Safety) Regulations
Note:
(a) Refer to the Planning Act on definition of ‘development’ on what is included or excluded under
‘development’
(a) A development undertaken by a developer in the course of business which
involves construction work with a contract sum of $10 million or more
Apply to
i.e. structures covered in (a) which will undergo modification in future, e.g. extension of bldg
(b) A development to modify a permanent structure (which has a DfS register)
Do not apply to development:
(a) which are not in the course of business (e.g. home owner building his own residence)
(b) where the developer has appointed a designer before 1 August 2016.
WSH (Design for Safety) Regulations
DEVELOPERS
� as far as it is reasonably practicable, ensure all
foreseeable design risks are eliminated
� if not reasonably practicable to eliminate, then ensurethat the design risk must be reduced to as low as reasonably practicable
Eliminate or Reduce
Design Risk
DESIGN
RISK
1) Design risks
2) Competency
3) Time & resources
4) Information
5) DfS Review Meetings
6) DfS Register
WSH (Design for Safety) Regulations
“design risk” - anything that is provided or omitted in the design of a structure that increases the likelihood of a person being injured when constructing, working at or demolishing
the structure;
Example (ommission)
Part of the structure where maintenance need to be carried out have open sides and no barrier,
wall or guard-rail is designed for to prevent person from falling when it is reasonably practicable
to do so.
What is “Reasonably Practicable”?
• It means that the degree of risk in a particular situation can be balanced
against the time, trouble, cost and physical difficulty of taking measures to
avoid the risk.
• An action is considered to be practicable when it is capable of being done.
• Whether it is also reasonable usually takes into account:
– the severity of any injury or harm to health that may occur;
– the degree of risk (or likelihood) of that injury or harm occurring;
– how much is known about the hazard and the ways of eliminating, reducing or
controlling it;
– the availability, suitability and cost of the safeguards.
17
© 2
01
5 A
ll r
igh
ts r
ese
rve
dWSH (Design for Safety) Regulations
DEVELOPERS
� ensure designers and contractors engaged by developer
are competent to perform their duties
Hire competent
personnel
1) Design risks
2) Competency
3) Time & resources
4) Information
5) DfS Review Meetings
6) DfS Register
WSH (Design for Safety) Regulations
DEVELOPERS
1) Design risks
2) Competency
3) Time & resources
4) Information
5) DfS Review Meetings
6) DfS Register
� Project is planned and managed to ensure
• designers and contractors appointed have
sufficient time and resources to perform their
duties.
Allocate sufficient time and
resources
WSH (Design for Safety) Regulations
DEVELOPERS
1) Design risks
2) Competency
3) Time & resources
4) Information
5) DfS Review Meetings
6) DfS Register
� Provide relevant information to designers and
contractors to enable them to perform the duties.
Provide relevant
information
WSH (Design for Safety) Regulations
DEVELOPERS
1) Design risks
2) Competency
3) Time & resources
4) Information
5) DfS Review Meetings
6) DfS Register
� convene DfS review meetings as are necessary to –
(i) identify all foreseeable design risks in the
project; and
(ii) discuss how each of the foreseeable design
risks can be eliminated or reduced.
� ensure all relevant designers and contractors attend the DfS meetings
DfSREVIEW
MEETINGS
DESIGNERDEVELOPER
CONTRACTORMAIN
CONTRACTOR
WSH (Design for Safety) Regulations
DEVELOPERS
1) Design risks
2) Competency
3) Time & resources
4) Information
5) DfS Review Meetings
6) DfS Register
� keep an updated DfS register
� accessible to designers and contractors appointed
� available for inspection by an inspector
DfSRegister
DfS register contain information and records on –
� DfS review meeting convened; and
� residual design risk in the project.
Information to be used for future maintenance works, Addition & Alteration works, demolition etc.
WSH (Design for Safety) Regulations
DEVELOPERS
Developer may delegate two duties to DfS professional
DfS PROFESSIONAL
5) DfS Review Meetings
6) DfS Register
provide DfS Professional (DP)
• information necessary for
DP to perform these duties
provide developer –
� relevant information on –
� identified design risks; and
� how design risks can be eliminated
or reduced.
� updated copy of DfS register
WSH (Design for Safety) Regulations
DESIGNERS
1) Design Plan
2) Competency
3) Information
Reduce and control
the risk
RISK
Eliminate foreseeable
risk in design
� as far as it is reasonably practicable, design plan must
eliminates foreseeable design risks
� if not reasonably practicable to eliminate, then designer
must propose modification to design plan that reduces
the design risk to as low as reasonably practicable
WSH (Design for Safety) Regulations
DESIGNERS
1) Design Plan
2) Competency
3) Information
� designers appointed by the designer (delegated
designer) must be competent to perform their duties
Hire competent
personnel
WSH (Design for Safety) Regulations
DESIGNERS
1) Design Plan
2) Competency
3) Information
Provide relevant
information
� provide relevant information on the design, construction
or maintenance to person who appointed the designer
� provide delegated designer all relevant informationto enable the delegated designer to perform his duties as a
designer
WSH (Design for Safety) Regulations
CONTRACTORS
1) Competency
2) InformationHire competent
personnel
� designers and subcontractors engaged by the contractor
must be competent to perform their duties
WSH (Design for Safety) Regulations
CONTRACTORS
1) Competency
2) Information
� provide all relevant information to designers and
subcontractors appointed by contractor to enable them
perform their duties
� inform the person who appointed the contractor of any
foreseeable design risk that the contractor knows
Provide relevant
information
WSH (Design for Safety) Regulations
OWNER
� give DfS register to the new owner;
� inform new owner of the nature and purpose of the DfS register.
DfSRegisterWhen structure or building is disposed/sold to new owner
Current owner
� ensure DfS register is made available for inspection by an inspector
New owner
WSH (Design for Safety) Regulations
DEVELOPERS
1) Design risks
2) Competency
3) Time & resources
1) Design Plan
DESIGNERS
2) Competency
3) Information
CONTRACTORS
1) Competency
2) Information
4) Information
DfS PROFESSIONAL
OWNER
DfS register
� available for inspection
� give to new owner
5) DfS Review Meetings
6) DfS Register1) DfS review
meetings
2) DfS Register
3) Information to developer
WSH (Design for Safety) Regulations
Guidelines on DfS
Draft on Revised Guideline for Public
Comment
18 Feb – 18 Mar 2016
Thank You for
your Time
2. In these Regulations, unless the context otherwise requires ––
“design plan” includes drawings, building information modelling, design details, specifications,
materials and bills of quantities (including specifications of articles or substances) relating
to a structure, and calculations prepared for the purpose of a design;
“design risk”, in relation to a structure, means anything present or absent in the design of the
structure that increases the likelihood that an affected person will suffer bodily injury
when constructing, working at or demolishing the structure;
“designer” means the person who prepares a design plan relating to a structure;
“developer” means the person who undertakes a project, and, in relation to the modification of a
subdivided building, includes the subsidiary management corporation of the subdivided
building;
“modify”, in relation to a structure, means to extend, alter, add to or repair the structure;
“prepare”, in relation to a design plan, includes the use or endorsement of a design plan by
another designer, with or without modification;
“residual design risk” means a foreseeable design risk that is not reasonably practicable to
eliminate;
“structure” means any permanent or temporary structure, and a reference to a structure
includes any part of the structure and any product or mechanical or electrical system
intended for the structure;