This document describes the procedures to be followed and parameters required to successfully carry our welding on storage tank on towerTRANSCRIPT
Welding procedure specification
WELDING PROCEDURE SPECIFICATION
PROJECT : FABRICATION & ERECTION OF 30,000 LITRES ON 16M TOWER
PROCEDURE NO: WPS - 008SUPPORTING PQR N O :
CLIENT: DANTATA & SAWOELOCATION : KADUNA
CONTRACTOR: AREWA METAL CONTAINER (ARMECO) LTD.
CODES / APPLICABLE STANDARDS : ISO 15614-1
MATERIAL SPECIFICATION: ASTM A 36 (GRADE 43A)
JOINT DESIGN :SQUARE GROOVE BUTT JOINT WITHOUT BACKING
WELDING PROCESS : SHIELDED METAL ARC WELDING (SMAW)
ELECTRODE CLASSIFICATION: E6013 (AWS A5.1)
WELDING PROCEDURECOMPLETE JOINT PENETRATION GROOVE WELD
TEST METAL THICKNESS5MM
THICKNESS RANGE QUALIFIED: 2.5MM 6.5MM
WELD SEQUENCE ELECTRODE MANUFACTURER / SIZEDIAMETERAMPERAGEARC VOLTAGE
SINGLE PASSOERLIKON 350MM3.25MM100-140A22-28V
HOT PASS / SECOND PASSN/AN/AN/AN/A
OTHER PASSES / CAPPINGN/AN/AN/AN/A
OTHER ELECTRICAL CHARACTERISTICS CURRENT: 3 PHASE AC TRANSFER MODE: METAL ARC
WELDING POSITION FLAT, HORIZONTAL, VERTICAL, (1G,2G,3G)
VERTICAL PROGRESSION DOWN
TIME LAPSE BETWEEN END OF ROOT RUN AND START OF SECOND PASSN/A
TIME LAPSE BETWEEN END OF SECOND PASS AND START OF OTHER PASSESN/A
MAXIMUM TIME BETWEEN COMMENCEMENT AND COMPLETION OF WELD N/A
TYPE OF LINE UP CLAMP : NONE
REMOVAL OF LINE UP : N/A
CLEANING : WIRE BRUSHING
MINIMUM PRE-HEAT TEMPERATURENONE
TYPE OF HEATER TO BE USED N/A
MAXIMUM INTER-PASS TEMPERATURE: N/A
STRESS RELIEF PEENING
SHIELDING GAS N/ A
SPEED OF TRAVEL 78MM/MN
TEST ASSESSMENT: VISUAL, PENETRANT TEST & TENSILE TEST.
PREPARED BY HQA/QCCHECKED BYGM GENERAL SERVICESAPPROVED BYGM OPERATIONS