WP4 - e-Infrastructure Services - & WP5 - Network Services - achievements. Ramon Diacov o – WP4 Manager (UFRJ) Gilberto Diaz – WP5 Manager (ULA) Final Project Review, 11.10.2012 Brussels (Belgium). Reminder WP4 + WP5 Objectives Achievements & Perspectives WP4 Infrastructure Services - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu

Grid Initiatives for e-Science virtual communities in Europe and Latin America

WP4 - e-Infrastructure Services - &

WP5 - Network Services - achievements

Ramon Diacovo – WP4 Manager (UFRJ)

Gilberto Diaz – WP5 Manager (ULA)

Final Project Review, 11.10.2012

Brussels (Belgium)

Page 2: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu 2

Reminder• WP4 + WP5 Objectives

Achievements & Perspectives• WP4 Infrastructure Services• WP5 Network Services• Sustained e-Infrastructure & Network operation• Handover Status

Conclusions

Outline

2GISELA – Final Project Review - Brussels – 11/10/2012

Page 3: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu

“Ensure the sustainability of the EU-LA e-Infrastructure”

“Establish a powerful e-Infrastructure facility built on the EELA-2 legacy”

• WP4

– Implement the catchall Grid Support Centre (GSC)

– Implement a Grid Operations Centre (GOC)

– Setup and operate the e-Infrastructure following the best practices

recommended by EGI

• WP5

– Implement the Network Support Centre (NSC)

– Deploy Network monitoring tools

– Deploy a ticket system to manage network issues

3

WP4 & WP5 Objectives

GISELA – Final Project Review - Brussels – 11/10/2012

Page 4: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu

• The catchall Grid Support Centre (GSC) has been deployed

• 2 Grid Operation Centres (GOC) are operational (UNAM, Uniandes)

• The e-Infrastructure operation is fully EGI compliant through the adoption of common services and practices, of Operational Level Agreements (OLA) with RCs, etc.

• Experienced Operation Teams (core & RCs) are in place (EELAs + GISELA legacy)

• Baseline Operation tasks ensured routinely– Site integration support

– Prod.vo.eu-eela.eu VO operation

– Resource Centres oversight (monitoring, ticket handling)

– Software deployment as requested by WP3

4

WP4: Achievements

GISELA – Final Project Review - Brussels – 11/10/2012

Page 5: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu

WP4: CPU Cores integration

Number of Cores, basically as committed in the DoW

5

+ 3000 Cores, from Friend Institutions, open to Prod-VO

GISELA – Final Project Review - Brussels – 11/10/2012

Page 6: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu

WP4: RC / Resources situation

CPU, Storage resources by the end of GISELA

•Less RCs than foreseen:– Expectations included former EELA-2 partners that are neither GISELA partners nor third parties– Grouping for cost-effective support

6

WIP

6GISELA – Final Project Review - Brussels – 11/10/2012

Page 7: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu 7

WP4: e-Infrastructure load per RC

Steady usage over the entire reporting period

GISELA – Final Project Review - Brussels – 11/10/2012

Cumulative load per Resource Center (wall-time hours)

Page 8: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu

• Percentage of consumed resources– Considers only the available resources– Depicts fair e-Infrastructure usage

8

Con

su

med

%

WP4: e-Infrastructure Occupancy

GISELA – Final Project Review - Brussels – 11/10/2012

Page 9: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu

Average above the DoW target

9

WP4: e-Infrastructure availability

GISELA – Final Project Review - Brussels – 11/10/2012

Page 10: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu

– 142 total tickets during the 2nd project year– More than 66% solved in 7 days or less

10

WP4: Ticket resolution time

Days to solve

Nu

mb

er of

tickets

GISELA – Final Project Review - Brussels – 11/10/2012

Page 11: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu

• The Network Support Centre (NSC) has been deployed as Partition of the RedCLARA NSC

• A perfSONAR Network platform is operational allowing to monitor inter-RCs network activity. It consists of:

– 5 Measurements Points currently scattered over the region

– A Web-based monitoring tool (MonGISELA) further adopted by the

CLARA Work Group (GT-Mediciones)

• A Ticket System has been installed to handle the network issues

11

WP5: Achievements

11GISELA – Final Project Review - Brussels – 11/10/2012

Page 12: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu 12

perfSONAR Measurements Points

MonGISELA Home Page

Monitoring of network activity between RCs

WP5: Monitoring Infrastructure

12GISELA – Final Project Review - Brussels – 11/10/2012

Page 13: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu 13

• Average delay of 120 milliseconds

• Less than 1% average packet loss

• Average delay of 80 milliseconds

• 3% average packet loss

WP5: Inter-RCs network monitoring

13GISELA – Final Project Review - Brussels – 11/10/2012

Performance assessment of the GISELA’s Network Infrastructure

• Packets delay and packet loss rate (UFRJ - CEDIA)

• Packets delay and packet loss rate (ULA - UFRJ)

Page 14: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu

• Sustainability scheme: Mexico Declaration agreement

– UNAM taking over the prod.vo.eu-eela.eu VO Operation

VOMS, MyProxy, LFC, LB, UI, WMS, AMGA already deployed

The only catch-all VO available for small research groups in LA (thanks to GISELA)

• Handover Status (end of September 2012)

– ROC Operations

Resource Centres handed over to ROC-LA (HEP LA ROC)

IGALC sites that are still active have been/are being handed over

Continuity of RC operation supported by each local Institution

Support still being given by the GSC to ensure the smoothest transition

14GISELA – Final Project Review - Brussels – 11/10/2012

WP4: Sustainability scheme / Handover Status

Page 15: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu

•Sustainability scheme

– Future NSC as a Partition of RedCLARA NSC

– perfSONAR: standard support by RedCLARA

– MonGISELA cared of by RedCLARA & GT-Mediciones

15

WP5: Sustainability scheme

15GISELA – Final Project Review - Brussels – 11/10/2012

Page 16: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu 161616

WP4WP5

WP4 & WP5: e.o. 2012 planning

16GISELA – Final Project Review - Brussels – 11/10/2012

Page 17: WP4 -  e-Infrastructure Services  - &   WP5 -  Network Services  - achievements

www.gisela-grid.eu

• WP4 & WP5 have successfully established Advanced Computing & Network resources for e-Science in Latin America, in legacy of EELA and EELA-2

• The Distributed Computing Infrastructure is constructed from the most natural “building blocks”– Resource Centres in Local Institutions providing computing & storage

resources and their support– One distributed Operation Centre for the Core operations: ROC-LA

merging the GSC and GOC functions– NRENs ensuring all Network services under the federative coordination

of CLARA

• The long-term of the DCI operation and support is granted by– A cost-effective agreement involving UNAM, Uniandes, CEDIA, etc.

– Full EGI compliance

17

Conclusions

17GISELA – Final Project Review - Brussels – 11/10/2012