world bank document€¦ · report no: 71699 - in restructuring paper on a proposed project...

26
Document of The World Bank Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 IN (BOARD APPROVAL - DECEMBER 5, 2006) TO THE REPUBLIC OF INDIA August 30, 2012 Sustainable Development Department India Country Management Unit South Asia Regional Office This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 07-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

Document of

The World Bank

Report No: 71699 - IN

RESTRUCTURING PAPER

ON A

PROPOSED PROJECT RESTRUCTURING

OF

PUNJAB STATE ROAD SECTOR PROJECT

LOAN 4843 – IN

(BOARD APPROVAL - DECEMBER 5, 2006)

TO THE

REPUBLIC OF INDIA

August 30, 2012

Sustainable Development Department

India Country Management Unit

South Asia Regional Office

This document has a restricted distribution and may be used by recipients only in the

performance of their official duties. Its contents may not otherwise be disclosed without

World Bank authorization

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

CURRENCY EQUIVALENTS

(Exchange Rate Effective - August 23, 2012)

Currency Unit = Indian Rupees

US$ 1.0 = 55.48

Crore = 10 million

ABBREVIATIONS AND ACRONYMS

AC Asphalt Concrete

BoQ Bill of Quantities

CoI Corridor of Impact

DBMOT Design, Build, Maintain, Operate and Transfer

DEA Department of Economic Affairs

DOF Department of Finance

ERR Economic Rate of Return

FIRs First Information Reports

FMRs Financial Monitoring Reports

FWP Forward Works Program

GOI Government of India

GOP Government of Punjab

HDM Highway Design Manual

HLMC High Level Monitoring Committee

IBRD International Bank of Reconstruction and Development

IDA International Development Association

IRI International Roughness Indicator

KPM Key Performance Measures

MDR Major District Roads

MTR Mid-Term Review

NPV Net Present Value

ODR Other District Roads

OPRC Operating and Performance Based Road Contracts

PDO Project Development Objectives

PRBDB Punjab Roads and Bridges Development Board

PPP Public-Private Partnerships

PWD Public Works Department

RAP Resettlement Action Plan

RoW Right of Way

RMF Road Maintenance Fund

RP Restructuring Paper

SH State Highways

VOC Vehicle Operating Costs

Regional Vice President: Isabel M. Guerrero

Country Director: N. Roberto Zagha/Onno Ruhl

Acting Sector Manager / Director: Simon David Ellis/John H. Stein

Task Team Leader: Ben L.J. Eijbergen/Rajesh Rohatgi

Page 3: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

INDIA: PUNJAB STATE ROAD SECTOR PROJECT

RESTRUCTURING PAPER

P090585

TABLE OF CONTENTS

Page

A. SUMMARY ........................................................................................................................... 3

B. PROJECT STATUS .............................................................................................................. 4

C. PROPOSED CHANGES ...................................................................................................... 5

D. APPRAISAL SUMMARY ................................................................................................. 10

ANNEX 1: RESULTS/ MONITORING FRAMEWORK ...................................................... 16

ANNEX 2: OPRC CONTRACTING SYSTEM ........................................................................ 19

ANNEX 3: PROPOSED OPRC NETWORK .......................................................................... 23

Page 4: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

1

INDIA

PUNJAB STATE ROAD SECTOR PROJECT

RESTRUCTURING PAPER

DATA SHEET

Restructuring

Restructuring Type: Level two Last modified on date : 08/30/2012

1. Basic Information Project ID and Name P090585: IN: Punjab State Road Sector Project

Country India

Task Team Leader Benedictus Eijbergen

Sector Manager/Director John Henry Stein

Country Director N. Roberto Zagha

Original Board Approval Date 12/05/2006

Original Closing Date: 06/05/2012

Current Closing Date 09/05/2012

Proposed Closing Date [if applicable] 06/05/2017

EA Category A-Full Assessment

Revised EA Category A-Full Assessment-Full Assessment

EA Completion Date 10/10/2005

Revised EA Completion Date

2. Revised Financing Plan (US$M) Source Original Revised

BORR 83.40 157.30

IBRD 250.00 250.00

Total 333.40 407.30

3. Borrower Organization Department Location

Government of India India

4. Implementing Agency Organization Department Location

Punjab Roads and Bridges

Development Board

India

Page 5: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

2

5. Disbursement Estimates (US$m) Actual amount disbursed as of 08/27/2012 138.78

Fiscal Year Annual Cumulative

2012 0.00 138.78

2013 14.99 153.77

2014 32.82 186.59

2015 23.33 209.92

2016 28.70 238.62

2017 11.38 250.00

Total 250.00

6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N

Does the restructured projects trigger any new safeguard policies? If yes, please select

from the checklist below and update ISDS accordingly before submitting the package.

N

7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes

The project objective is to improve operating conditions of State roads for road users, in a sustainable

way, thus helping to provide the business enabling environment necessary to support Punjab's

economic development strategy.

7b. Revised Project Development Objectives/Outcomes [if applicable]

Page 6: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

3

INDIA: PUNJAB STATE ROAD SECTOR PROJECT

RESTRUCTURING PAPER

A. SUMMARY

1. This paper proposes to extend the loan closing date by five years until June 5,

2017, from the original closing date of June 5, 2012. The reason for seeking the five year

extension is to support Government of Punjab (GOP) in their endeavor to undertake a 10

year network based Output and Performance Based Road Contract (OPRC)1 to improve,

rehabilitate and maintain about 200 km of state road network as part of Road Upgrading,

Rehabilitation and Maintenance component. This network based demonstration project,

based on asset management principles is being implemented for the first time in India and

has the potential of being replicated elsewhere in the country.

2. The OPRC was envisioned early on in the project implementation, but being a

new and innovative contracting system, a significant amount of time was spent on

awareness raising and capacity building of Government of Punjab, PRBDB officials and

local construction industry representatives. Furthermore, the feasibility study of OPRC

suggested a different road network than the identified corridors during the project

preparation, which resulted in additional efforts and time for data collection and

feasibility study of the proposed OPRC network. Also, the preparation and finalization of

the customized bidding documents, taking into account the innovative principles of

OPRC, did not follow a standard process and as a result more time was needed to

complete and come to an agreement. All these factors contributed to delay and the

bidding of the OPRC contract could only be commenced in January 2012 i.e. about six

months before the original loan closing.

3. The proposed 5 year extension would ensure Bank’s support to GOP for initial 5

years of OPRC implementation both in terms of finances and capacity building of the

implementing agency.

4. In addition, the proposed restructuring includes changes to (i) results monitoring

framework; (ii) scope of project components; (iii) applicability of January 2011 version

of Procurement Guidelines and Consultant Guidelines; (iv) changes in Project Costs and;

(v) corresponding changes to legal amendments including dropping of covenants related

to Road Maintenance Fund.

5. The proposed project restructuring entails no change to the Project Development

Objectives (PDO) which is “to improve operating conditions of State Roads for road

users, in a sustainable way, thus helping to provide the business enabling environment

necessary to support Punjab’s economic development strategy”. There are no changes to

1 OPRC is a new and innovative contracting philosophy focused on specifying the contractor’s outputs and

performance needed to achieve the enhanced performance of a road network. It avoids wherever possible,

specifying or measuring the contractor’s inputs, leaving the choice of how the work is undertaken up to the

contractor.

Page 7: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

4

the project implementation and disbursement arrangements or to the loan amount. No

additional safeguard policy is expected to be triggered due to the proposed restructuring.

6. In order to review and appraise the five year loan extension request by GOP,

endorsed by the Department of Economic Affairs, Government of India, an interim

extension of three months until September 5, 2012 had been approved by the Bank in

June 2012.

B. PROJECT STATUS

Project Data and Performance

Key Project Data Current Ratings and Flags

Board Date Dec 05, 2006 Development Objectives Moderately Satisfactory

Closing Date Sep 05, 2012 Implementation Progress Moderately Satisfactory

Project Age 68 months Problem Flags Legal Covenant

% Disbursed 55.5%

7. The Project has two components– (i) Road Upgrading, Rehabilitation and

Maintenance; and (ii) Institutional Strengthening.

8. The Punjab State Road Sector Project was approved in 2006 and since its

effectiveness in 2007, the project is performing (moderately) satisfactorily. All civil

works, envisaged under the Phase I of the project stand completed since 2009 and most of

the activities, envisaged under the Institutional Strengthening components are in advance

stages of completion and their outputs/recommendations are being reviewed by the GOP

for adoption/implementation. Bids for Phase II Civil Works (OPRC) have also been

received and the evaluation has been completed by GOP. The Bank is currently

reviewing the Bid Evaluation Report.

9. Since January 31, 2008 the project had been in non-compliance with legal

covenants associated with the partial implementation of the Road Maintenance Fund and

insufficient allocation of a seed amount of US$25m through the state budget. The prime

intention for keeping these covenants was to ensure sustainability of investments and

improved maintenance of existing road network. However, during the project

implementation, GoP decided not to operationalize the Road Fund further and continue to

fund maintenance under their state’s budget head. The result was convincing – there was

a substantial reduction of poor road network from about 50 percent in 2006-07 to 4

percent in 2011 in the state.

10. The Project impact is being monitored through improvements in key performance

indicators relating to (i) Average Core Network Speed; (ii) Reduction in VOC; (iii)

number of fatal accidents; (iv) User Satisfaction and; (v) Efficiency of Road Agency

(PRBDB). All indicators have shown improvement from start of the project and the

current status demonstrates that most of the indicators have substantially met the end-of-

Page 8: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

5

project targets, indicating that the project has strong likelihood of continuing to achieve

its development objective. Please refer to Annex 1 for Result Monitoring Framework.

C. PROPOSED CHANGES

Summary:

11. Following changes are proposed

Scope of Project Components – (i) Road Upgrading, Rehabilitation and

Maintenance component; and (ii) Institutional Strengthening component

Results Monitoring Framework/Indicators

Applicability of January 2011 version of Procurement Guidelines and Consultant

Guidelines

Changes in Project Costs

Extension of loan closing date by five year from original loan closing until June 5,

2017

Corresponding amendments to legal agreements including dropping of covenants

related to Road Maintenance Fund.

12. There are no changes in the PDO, institutional/ implementation arrangements,

financial plan and disbursement arrangements. No additional safeguard policy is expected

to be triggered due to the proposed restructuring.

13. The proposed changes will ensure the project continues to meet the Project

Development Objective.

Change in the Scope of Component 1: Road Upgrading, Rehabilitation and

Maintenance

14. Introduction of OPRC. Under Phase II, the project envisaged (i) about 210 km of

up-gradation, about 40 km of rehabilitation; (ii) improvement of about 40 accident black-

spots and; (iii) maintenance through performance-based and regular contracting methods.

However, during the project implementation, the Bank and GOP agreed to undertake

improvement of about 200 km of state road network through innovative OPRC

contracting method to facilitate building the state’s capacity in asset management and

drop the initial identified corridors. The selection of the OPRC network was based on a

comprehensive feasibility study. Annex 4 shows the map of the OPRC network. The

following table presents a list of roads to be dropped from the project and the proposed

network to be improved under OPRC.

Page 9: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

6

Table 1: Phase II- Roads to be dropped from the project

SN Description of the Section Length (Km)

Phase II – Upgrading

1 Nakodar – Phillaur (MDR - 48) 35.6

2 Kapurthala-Nakodar (MDR – 48) 31.3

3 Handiaya – Harisinghwala (SH – 13) 38.2

4 A – Dehlon 9.50

5 Jalandhar – Kapurthala (MDR – 52) 13.8

6 Mansa – Sardulgarh (SH-13) 44.7

7 Jaitu - Bajakhana - Bhagta - Salabatpura - distt. Boundary (MDR – 43) 38.7

Phase II – Rehabilitation

1 Sahnewal – A 7.0

2 Harisinghwala – Mansa (SH – 13) 7.3

3 Barnala – Handiaya (SH-13) 3.5

4 Doraha – NH-95 (ODR) 24.0

Total Road Length 253.6

Table 2: Phase II - Proposed roads to be included (OPRC)

SN Description of the Section Length (Km)

S1 Sangrur-Sunam: (MDR21) 11.3

S2 Bhawanigarh - Sunam - Bhikhi – SH13 Intersection – Kotshamir:

(SH12A)

106.1

S3 Barnala – Mansa: (SH13) 7.3

S4 Mansa - Talwandi Sabo (upto intersection with B8) :(ODR9) 25.0

S5 Dhanaula – Bhikhi: (MDR14) 25.3

B8 Bathinda - Kotshamir - Talwandi Sabo (up to intersection with S4):

(SH17)

28.6

Total Road Length 203.6

15. Construction of Dehlon Bypass In Ludhiana-Malerkotla-Sangrur road corridor,

improved under the phase I of the project, about 4 km of the section passes through a

congested stretch of village Dehlon. As per geometric design and road safety aspects, the

road needed to be widened on the left hand side, which necessitated acquiring land of two

religious committees and two private owners. However, the title of the land occupied by

religious committees was not clear and commercial establishments were built by both on

the outer edge of the property, facing the road. These shops are being operated by 57

tenants (non titleholders) for the last 40 years, who would have been displaced due to the

acquisition, affecting their livelihood.

16. As per the Resettlement and Rehabilitation Policy (R&R Policy) adopted by the

project, if a minimum of 20 project displaced families (PDFs) affected in a continuous

stretch of 5 Km opts for assisted resettlement, the project will develop a resettlement site.

Therefore, it was agreed by tenants and religious committees that the tenants will be

accommodated in newly constructed shops within their premises. As per this proposal, a

tripartite agreement was signed by the PRBDB and both religious committees on August

22, 2007. However both the committees refused to honor the agreement, claiming that

more than 75 percent of the tenants are defaulters, who were not paying rent for the last

Page 10: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

7

15 years. PRBDB then explored the option of resettling them on a common village land

on the right hand side of the road. However, this option could not be implemented as the

proposed resettlement site is under the No Construction Zone as per the Punjab Regional

and Town Planning and Development Act, 1995 of schedule roads. Therefore, it was

agreed that widening in this section will be restricted to the available clear space to

minimize the adverse social impact; and feasibility of construction of a bypass would be

explored instead.

17. It is therefore proposed to include construction of the said bypass of about 3km

length with an estimated cost of US$15million in the project. The alignment has been

finalized, socio-environmental assessment has been completed and the land acquisition

process is in the advance stages.

18. Intervention to provide structural adequacy to Kharar-Banur-Tepla Corridor.

This corridor, improved under the project in phase I, has observed a higher increase in

traffic volumes than estimated during the pavement design, which has led to pavement

failures at many places. As part of ongoing pavement engineering investigations, the

Central Road Research of India (CRRI) has recommended to provide additional

pavement crust on this corridor to maintain adequate structural adequacy of the created

asset and to ensure its sustainability. It is therefore proposed to fund this work under the

project, which will include pavement overlay of about 22 km with an estimated cost of

US$3million.

19. Road Safety Enhancements and Black Spot improvements works A total of 347

accident black spots were identified throughout the state, out of which about 90 have

already been addressed, instead of only 40 envisaged during the project. It is proposed to

include road safety enhancement and accident black spot improvement works on the

remaining state road network to improve road safety situation of the state with an

estimated cost of US$12 million.

Change in the Scope of Component 2: Institutional Strengthening

20. Removal of support to Road Maintenance Fund During the project preparation

more than 50 percent of the state road network was in poor condition and it was agreed

that to address this issue, the Road Maintenance Fund, which was already established

legally at that time, would be made operational by providing technical assistance through

the project. It was envisaged that a secretariat would be established and the maintenance

would be financed through the Road Maintenance Fund. Simultaneously, the state would

also explore additional revenue streams. However, this could not be achieved and GOP

decided not to operationalize the Road Maintenance Fund and establish its secretariat.

Despite this, the state was able to improve the condition of state roads with its own

budgetary support and centrally sponsored schemes, resulting in substantial reduction of

poor road network from about 50 percent in 2006-07 to 4 percent in 2011.

21. Furthermore, the GOP has recently constituted a High Level Monitoring

Committee (HLMC) under the chairmanship of Chief Secretary, Punjab to monitor

allocation of maintenance budget in the state. The Secretary Public Works has constituted

Page 11: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

8

a technical committee to serve as the secretariat to the HLMC and to prepare a draft

proposal for undertaking a road maintenance program. A provision of US$60 million has

also been kept under the approved budget for the year 2012-13 for the maintenance of

state roads, which include roads covered under the project. In addition, proposed OPRC

contracts also have the potential of being replicated across the state network, resulting in

proper upkeep of its network governed by better asset management principles.

22. The overall improvement in condition of state road assets and developments

mentioned above, indicate state’s commitments to ensure maintenance and sustainability

of project investments. In view of the above, it is proposed to drop the technical

assistance to operationalize the Road Maintenance Fund and associated legal covenants.

23. Removal of support to PPP Transactions. All PPP Infrastructure projects are

being developed and managed by the Punjab Infrastructure Development Board (PIDB)

and are not under the mandate of the project implementing agency PRBDB. Therefore,

this activity is proposed to be removed from the project scope. However, in order to

undertake a comprehensive policy planning of the transport sector as a whole, a study

entitled Integrated Transport Policy and Strategy and Strategic Investment Plan

(Transport Sector Master Plan) was undertaken during the project. The final report has

been submitted by the consultants, which is being reviewed by the Government.

24. Removal of support to computerize Traffic Fine Collection System This activity is

being undertaken by the State Police Department and hence is proposed to be dropped.

Changes in Results Monitoring Framework and Indicators

25. The project has already completed its intended implementation period and most of

the indicators have met their targets as monitored and reported during 2011. It is now

proposed to revise the Results Monitoring Framework for the proposed extended project

period. The current and proposed result monitoring framework is attached in Annex 1.

Changes in Project Costs

26. The proposed changes would results in increase to project costs by about US$71

million. The Bank loan would remain as US$250 million and the additional amount

would be contributed by the Government of Punjab. The original and revised project

costs are given below.

Page 12: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

9

Table 3: Project Costs (US$M) Components/Activities Original Proposed

A. Component 1 - Road Development 310.4 388.8

- Road Upgrading 221.5 109.6

- Rehabilitation 66.9 65.7

- Maintenance and Other works 22 15.3

- OPRC - 168.2

- Dehlon Bypass - 15.0

- Additional crust for increasing the structural

adequacy of pavement structure on UG1

- 3.0

- Road Safety enhancements and Black Spot

Improvements

- 12.0

B. Component 2 - Institutional Strengthening 11 12.3

Incremental Operating Cost 12 6.2

Total Project Cost 333.4 407.3

Front-end Fee 0 0

Sub-Total 333.4 407.3

Note: For Expenditure already incurred exchange rate of Rs. 45.64/US$ has been taken and for the future

works exchange rate has been taken as Rs. 50/US$.

Applicability of January 2011 version of Procurement Guidelines and Consultant

Guidelines

27. Additional procurement activities which may be undertaken following the

proposed restructuring and extension of loan would include- (i) Procurement of

monitoring consultants for OPRC work; (ii) Construction of Dehlon Bypass; (iii) Works

to provide structural adequacy to Kharar-Banur-Tepla Corridor; and (iv) Road Safety

Enhancements and Black Spot improvements works. For these additional procurement

activities and those that may further be agreed to during the extended period of the

project, Bank’s current Guidelines “Procurement of Goods, Works, and Non-Consulting

Services under IBRD Loans, and IDA Credits and Grants by World Bank Borrowers”,

January 2011 and “Selection and Employment of Consultants under IBRD Loans and

IDA Credits and Grants by World Bank Borrowers”, January, 2011 will be applicable.

The Procurement Plan would be updated to reflect additional procurement activities.

Loan Closing date Extension

28. In order to utilize the un-disbursed funds (US$111 million) under the project;

undertake additional activities; and to ensure technical support and handholding of the

GOP for at least first five years of the 10 year OPRC contract, it is proposed to extend the

loan by five year (from original loan closing) until June 5, 2017.

Amendments to Legal Agreements

29. In order to reflect changes described above, legal agreements are proposed to be

amended including dropping of following covenants associated with the Road

Maintenance Fund:

Page 13: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

10

Establish and fully operationalize, satisfactory to the Bank, the Road Maintenance

Fund and its secretariat by January 31, 2008.

Take all necessary steps to ensure that from fiscal year 2007-08 to 2011-12, that it

disburses to the Road Maintenance Fund, through its Finance Department, at least

twenty five million Dollars (US$25,000,000) each fiscal year, for the purpose of

the maintenance of plan roads.

Carry out and furnish to the Bank, annual reviews of the Road Maintenance Fund,

under term of reference satisfactory to the Bank, commencing April 30, 2008.

Commencing March 31, 2009, prepare and furnish to the Project Implementing

Entity an annual report of the road maintenance fund, including its audited

financial statements and a summary of the PRBDB’s decisions. This report shall

be provided to the Project Implementing Entity no later than nine months

following the end of the preceding year.

Commencing January 31, 2009 and on January 31 of each year thereafter during

the period of Project Implementation, shall prepare and submit to the Project

Implementing Entity an annual maintenance program to be financed from the

Road Maintenance Fund

D. APPRAISAL SUMMARY

Economic and financial analysis

30. To examine the whole-of-life benefits that are likely to accrue as a result of the

implementation of the OPRC philosophy and a comparison of the anticipated pavement

and surfacing treatments before and after implementation has been undertaken.

31. The historical pavement management practices have seen regular interventions in

terms of pavement rehabilitation and resurfacing works, typically around 8 to 12 years

and 4 to 6 years respectively. Design and construction practices have perhaps contributed

to these short pavement lives. If current practices continue, traffic growth will put further

pressure on these pavement lives.

32. With the implementation of the OPRC concept it is expected that the combination

of robust pavement design solutions along with rigorous quality assurance and auditing

will result in significant increase in the lifecycles for these assets. The expected average

life for rehabilitated pavements under the OPRC are likely to be in the order of 20+ years

and with resurfacing required every 8 to 12 years respectively. While the initial

rehabilitation under OPRC will involve a significant increase in the depth of the

pavement, future treatments are only expected to involve 50 mm – 70 mm overlays and

the milling and replacement of 100 to 500mm of the AC as the next rehabilitation.

33. The network was modeled under these two scenarios in HDM to assess the user

benefits of the proposed approach over a 20 year planning horizon and then tested the

Page 14: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

11

sensitivity of both our cost and intervention period assumptions. The analysis assumes a

7.5 percent traffic growth.

34. The modeling indicates a very good economic return in terms of both Internal

Rate of Return and Net Present Value.

Economic Rate of Return (ERR) of the introduction of OPRC

35. If the frequency of the current strategy of treatments stays the same with cycles of

resurfacing at 5 years and rehabilitation at 10 years the model indicates that the

introduction of OPRC offers an ERR of 20 percent. However, if the frequency of

interventions changes, as mentioned in paragraph 32, under the increased loading to 4

and 8 years respectively, the ERR increases to 32 percent.

Net Present Value (NPV) of the introduction of OPRC

36. The table below shows the sensitivity to tendered prices. The analysis has been

undertaken at a discount rate of 12 percent.

Table 4: Sensitivity of NPV Analysis to Cost Rates

Basic of Cost rates NPV [Million USD]

Status quo Resurfacing/ Rehab Cycles

4 and 8 years 5 and 10 years

Base Rate US$44.20 US$23.70

Base Rate +25 % US$23.20 US$2.70

Base Rate -25 % US$65.30 US$44.70

37. As can be seen, even with a 25 percent increase in the tendered rates the project

still delivers a positive albeit marginal NPV.

38. It has been assessed that this project generates benefits to many stakeholders, and

an excellent return on the investments. The identified benefits include:

39. Benefits to Road Agency

Improved management of the asset

A doubling of pavement and surfacing lives which in turn will result in much

lower cost going forward

Development of staff

Informed sharing of risk

Introduction of consistent service levels i.e. a focus on the performance of the

network

Competitive rates

40. Benefits of road users

Reduced delays

More planned work and less reactive work

Page 15: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

12

Smoother roads

Safer roads

41. Benefits to Contracting Industry

Long term view to network health

Stable long term work i.e. staff development, innovation payback period,

increased efficiencies and reduced costs

Rewards for good performance

Technical

42. OPRC is an innovative contracting philosophy focused on specifying the

contractor’s outputs and performance needed to achieve the enhanced performance of a

road network. It avoids wherever possible, specifying or measuring the contractor’s

inputs, leaving the choice of how the work is undertaken up to the contractor. The

duration of proposed OPRC contract is 10 year. Please refer to Annex 2 for details.

43. Network Selection: The entire state road network was reviewed in detail by

undertaking numerous visual inspections, geotechnical investigations, pavement

deflections surveys and traffic data collection. The final set of corridors to be undertaken

in OPRC was then arrived bases on following key factors:

Length of network to make best utilization of contracting entity’s resources;

Connectivity to ensure efficient maintenance operations;

Mix of road types;

Indicative work load (and hence cash flow) to provide a meaningful level of

input; and

Risk, which should be neither too high or too low

44. Proposed scope of OPRC: Contract Scope includes both works and services.

The work includes:

i. Improvement Works - widening of Road Section S2 (Bhawanigarh - Sunam -

Mansa - Kot Shamir) from the existing 7.0m nominal width to 10.0m and S4

from existing 5.5m nominal width to 10.0m including all required drainage,

safety and intersection improvements.

ii. Rehabilitation, Resurfacing and associated routine drainage maintenance works -

The road proposed to be improved under the rehabilitation category are S1

(Sangrur-Sunam), S2 (Bhawanigarh-Sunam, Mansa, Kot Shamir), S3 (Barnala

Mansa), S5 (Dhanaula – Bhikhi) and B4 (Bathinda - Kotshamir - Talwandi Sabo)

with a total length of 74.78 km. The intent of rehabilitation contract is to have all

pavements within the network rehabilitated once during the term of the contract.

iii. Other potential capital improvement works not included or intended in the

conceptual designs and not included in the bidding documents but identified

afterwards which have the potential to significantly benefit road users and/or the

Page 16: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

13

Employer over the life of the asset. This also includes the works undertaken to

comply with Environmental and Social Framework (Section VI Part 2B). At the

sole discretion of the Employer such additional improvement works would be

undertaken as a variation to the contract.

iv. All network performance works and associated activities such as pavement

surfacing, shoulder and drainage maintenance, routine bridge and minor structure

maintenance, sign maintenance, pavement marking, raised reflectorized pavement

marker and marker post maintenance.

v. Vegetation control, rubbish and litter removal (except those sections where

already some department / agency has the responsibility to do so, mostly in built

up sections under the jurisdiction of local bodies (such as Municipal Corporation,

Municipal Council, Nagar Panchayat, Gram Panchayat etc.),accident damage

reporting and emergency works as required.

vi. Providing appropriate resources to respond to all unplanned incidents which can

cause obstruction to the normal flow of traffic on the road (e.g. Road accident,

flooding, oil spillages, etc.).

vii. Structural repairs to bridges and large culverts required to maintain or re-store

overall structural integrity of its major components are excluded from scope.

The scope of Services under OPRC includes:

i. Maintaining the Contract Area.

ii. Delivering the Contractor’s obligations under the Contract.

iii. Proactive compliance of conformance measurement and performance systems,

and achieving the Performance requirements.

iv. Contractor‘s self-monitoring and reporting the contract conformance requirements

and performance.

v. Assisting the Employer and Project Manager with the development and

implementation of a Ten Year Forward Works Program (10 year FWP), and

associated maintenance management strategy for the contract‘s roads.

Environment

45. The restructuring of the project has no incremental or additional adverse

environmental impacts. The use of Output and Performance Based Road Contracting

system (OPRC) requires the Contracting Entity to undertake screening, conduct impact

assessment, formulate the environmental management plan and subsequently undertake

its implementation. The preparation of an Environmental Management Plan (EMP) has to

be adequate and commensurate to the scale of civil works proposed during various stages

of the contract. On the other hand, the Employer (PRBDB) through a monitoring

consultant would enforce the contract by verifying compliance with the agreed service

levels, including the conformity to all applicable environmental legislation and

regulations.

Page 17: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

14

46. To ensure a sustained environmental performance for OPRC contracts, an

Environment and Social Management Framework (ESMF), including a set of codes of

practice has been prepared and integrated into the bidding document. These define a

minimum level of environmental process, mitigation and performance standards that the

contracting entity requires to meet under the project.

Social Safeguards

47. No additional safeguard policy is expected to be triggered due to the proposed

restructuring and there are no changes in the implementation arrangements. It is

anticipated that the majority of the required interventions under the OPRC will not

require land acquisition. However, land acquisition may be required where there is a need

for geometric improvement. The policy may be invoked when any road is required to be

cleared of any encumbrance including private land acquisition before being considered

for up-gradation, rehabilitation and maintenance under the OPRC contract. The

Contractor will prepare a Resettlement Action Plan (RAP), adequate and commensurate

to the scale of resettlement and rehabilitation involved in the project. PRBDB will be

responsible for implementation of RAP to provide the Corridor of Impact (CoI) required

for actual construction, free of all encumbrances to the Contractor. RAP will be

implemented only after approval of the Bank and PRBDB/PWD. In case of new

encroachment or re-encroachment of cleared Right of Way (RoW) that takes place post

contract award, the Employer will pay the compensation and/or resettlement assistance as

per the agreed R&R policy framework of Punjab State Road Sector Project. The

responsibility of monitoring and reporting re-encroachment shall be the responsibility of

the Contractor. The overall supervision and monitoring will be undertaken by

PRBDB/PWD.

48. Affected persons will be consulted and provided opportunities to participate in

planning and implementing resettlement programs during the course of the contract. The

Contractor will display and provide complete information to the local community on (i)

plans and range of proposed activities; (ii) measures adopted to reduce the inconvenience

including traffic management; and (iii) proposed intervention for emergency works at

least three (3) days in advance of the work commencing. The contractor will give

sufficient time to allow individuals to relocate. An external agency will be engaged to

monitor and evaluate implementation of RAP.

49. The proposed by-pass of 2.8 km of 45 meters Right of Way at Dehlon will require

approximately 38 acres of irrigated land (125 plots), two houses and two boring wells to

be acquired for which Resettlement action plan will be prepared in accordance with the

Bank’s Operational Policy on Involuntary Resettlement.

Risk

50. Contractual Mechanisms and agreed Compliance Framework are made available

in the OPRC contract to manage the risk of the client with respect to non-completion of

work and non-compliance by the contractor with the required Road User Service and

Page 18: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

15

Comfort and Key Performance Measures2. Even minor breaches in KPM will usually

attract an agreed level of payment reduction and is aligned with the reduction in road user

comfort and/or safety that has resulted.

2 KPMs are measurable asset condition parameters that will be used to define the required service level

targets required to be achieved.

Page 19: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

16

Annex 1: Results/ Monitoring Framework

INDIA: PUNJAB STATE ROAD SECTOR PROJECT

RESTRUCTURING PAPER

(a) Results/ Monitoring Framework till Year 5 of the project

Target Values3 Data Collection and Reporting

YR1

(2008)

YR2

(2009)

YR3

(2010)

YR4

(2011)

YR5

(2012)

Project Outcome Indicators Baseline (T)

(T)

(T)

(T) (A) (T)

Frequency and

Reports

Data Collection

Instruments

Responsibility

for Data

Collection

Average Network Speed (kmph) 33.5 NA NA 39 43 45 MTR and end-

of-

implementation

PRBDB Report

Surveys PRBDB

Reduction in VOC (%) 0% NA NA 6% 19%4 20% MTR and end-

of-

implementation

PRBDB Report

Surveys PRBDB

Maintain number of fatal

accidents

2655 2655 2655 2655 2655 26425 2655 Aide memoire,

every six

months

First

Information

Reports (FIRs)

Police/ PRBDB/

Bank

User Satisfaction 61.11%

(Baseline

survey

undertak

en in

2009)

NA NA NA NA 63.33% User satisfaction

Survey Report,

every two year

Survey PWD/ PRBDB

Efficiency of Road Agency

(PWD, PRBDB)

60.27%

(Baseline

survey

undertak

en in

2009)

NA NA NA NA 63.27% User

Satisfaction

Survey Report,

every two year

Survey PWD/ PRBDB

Results Indicators for Each

Component

3Target Values have been compared with initial target values and actual results achieved till date.

4 19 percent reduction in VOC achieved on improved road and 8 percent reduction achieved on entire state road network.

5 The number of fatalities i.e. 2,655 pertains to year 2003, for year 2006 the fatalities were 3,060. For the calendar year 2011 (up to Sept) the fatalities were 2,462.

Page 20: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

17

Target Values3 Data Collection and Reporting

YR1

(2008)

YR2

(2009)

YR3

(2010)

YR4

(2011)

YR5

(2012)

Project Outcome Indicators Baseline (T)

(T)

(T)

(T) (A) (T)

Frequency and

Reports

Data Collection

Instruments

Responsibility

for Data

Collection

Component 1: About 1050 km

of roads rehabilitated, resurfaced

and maintained

To be

undertak

en YR1

550 km 640 km

(Phase I

works

complet

e)

Monthly

Construction

Supervision

Reports;

Quarterly

FRMs, Aide

Memoire (every

6 months)

Certification of

Quantities by

the Engineer

Construction

Supervision

Consultant;

PRBDB

Reduction in IRI (m/ km) 6.9 5.3 2.6

m/Km

PRBDB’s

Annual Report,

Yearly

Roughness and

Condition

Surveys

PRBDB

Reduction in network in poor

and bad condition from 52% to

10%

52% 25% 4% PRBDB’s

Annual Report,

yearly

Roughness and

Condition

Surveys

PRBDB

Component 2: Routine and

periodic maintenance fully

funded during the project period;

training program

INR 750

mn

2200 mn -

Once a year

Quarterly

reports by DOF,

Implementation

Support Mission

DOF/ PRBDB/

Bank

About 250 km of roads

maintained through performance

based contracts

0 Annual Aide

Memoire

Implementation

Support Mission

(every six

months)

PWD/ PRBDB/

Bank

Department wide

computerization and use of

integrated systems for planning,

management, financial

accounting, monitoring

Partial Full

Computeriza

tion

Not yet

done

As per

implementation

schedule

- PWD/ PRBBDB

Page 21: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

18

(b) Proposed Results/ Monitoring Framework for extended term

Target Values Data Collection and Reporting

Project Outcome Indicators Baseline

YR6

(2013)

YR7

(2014)

YR8

(2015)

YR9

(2016)

YR10

(2017)

Frequency and

Reports

Data Collection

Instruments

Responsibility for

Data Collection

Average Network Speed (kmph) 33.5 46 48 MTR and end-of-

implementation

PRBDB Report

Surveys PRBDB

Maintain VOC (%) 0% 20% 20% MTR and end-of-

implementation

PRBDB Report

Surveys PRBDB

Reduction in number of fatal accidents 2655 2522 2390 Aide memoire, every

six months

First Information

Reports (FIRs)

Police/ PRBDB/

Bank

Increase in User Satisfaction 61.11% 64% 67% User satisfaction

Survey Report, every

two year

Survey PWD/ PRBDB

Improvement in efficiency of Road

Agency (PWD, PRBDB)

60.27% 63% 65% User Satisfaction

Survey Report, every

two year

Survey PWD/ PRBDB

Results Indicators for Each

Component

Component 1: Total km of roads

improved and rehabilitated under the

project w.e.f. YR 6

0 km 27km 82km 136km 161km 166km Monthly

Construction

Supervision Reports;

Quarterly FRMs,

Aide Memoire (every

6 months)

Certification of

Quantities by the

Engineer

Construction

Supervision

Consultant; PRBDB

Maintain IRI (m/ km) 6.9/km 2.6/

km

2.6/km PRBDB’s Annual

Report, Yearly

Roughness and

Condition Surveys

PRBDB

Maintain poor and bad network

condition @ 4%

52% 4% 4% PRBDB’s Annual

Report, yearly

Roughness and

Condition Surveys

PRBDB

Component 2: Department wide

computerization and use of integrated

systems for planning, management,

financial accounting, monitoring

Vendor

on-

board

Pilot

testing

Final Roll-

out to the

entire

department

As per

implementation

schedule

- PWD/ PRBBDB

Page 22: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

19

Annex 2: OPRC Contracting System

INDIA: PUNJAB STATE ROAD SECTOR PROJECT

RESTRUCTURING PAPER

1. Basic Concept of Road Asset Management with OPRC. Output- and Performance-based

contracting for Roads is designed to increase the efficiency and effectiveness of road asset

management and maintenance. It should ensure that the physical condition of the roads under contract

is adequate for the needs of road users, over the entire period of the contract which is normally several

years. This type of contract significantly expands the role of the private sector, from the simple

execution of works to the management and conservation of road assets.

2. In traditional road construction and maintenance contracts, the Contractor is responsible for the

execution of works which are normally defined by the Road Administration or the Employer, and the

Contractor is paid on the basis of unit prices for different work items, i.e. a contract based on “inputs”

to the works. The results of traditional road contracts are in many cases less-than-optimal. The problem

is that the Contractor has the wrong incentive, which is to carry out the maximum amount of works, in

order to maximize his turnover and profits. Even if the work is carried out according to plan and

considerable money is spent, the overall service quality for the road user depends on the quality of the

design given to the Contractor who is not accountable for it. In many cases the roads do not last as long

as they should because of deficiencies in the original design, aggravated by inadequate maintenance.

3. The OPRC as a model for road asset management is similar to Design, Build, Maintain,

Operate and Transfer (DBMOT) model of contracts which addresses the issue of inadequate

incentives. During the bidding process, contractors compete among each other by essentially proposing

fixed lump-sum prices for bringing the road to a certain service level and then maintaining it at that

level for a relatively long period. It is important to understand that contractors are not paid directly for

“inputs” or physical works (which they will undoubtedly have to carry out), but for achieving specified

Service Levels, i.e., the Rehabilitation of the road to pre-defined standards, the maintenance service of

ensuring certain Service Levels on the roads under contract, and specific improvements, all represented

in outputs or outcomes, expressed in Service-Levels criteria. A lump-sum periodic remuneration paid

to the Contractor will cover all physical and non-physical services provided by the Contractor, except

for unforeseen emergency works which are remunerated separately. In order to be entitled to these

periodic payments, the Contractor must ensure that the roads under contract comply with the Service

Levels which have been specified in the bidding document. It is possible that during some months he

will have to carry out a rather large amount of physical works in order to comply with the required

Service Levels and very little work during other months. However, his periodic payment remains the

same as long as the required Service Levels are complied with.

4. A fundamental feature of the OPRC is that the “Contractor” must not necessarily be a

traditional works contractor, but can be any type of firm or business venture “Contractor” having the

necessary technical, managerial and financial capacity to fulfill the contract. In any case, the contractor

is responsible for designing and carrying out the works, services and actions he believes are necessary

in order to achieve and maintain the Service Levels stated in the contract. The Service Levels are

defined from a road user‘s perspective and from a “strength of the pavement” point of view and may

include factors such as, riding comfort, safety features, residual strength of pavement, etc. If the

Page 23: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

20

Service Level is not achieved in any given month, the payment for that month may be reduced or even

suspended.

5. Under the OPRC, the Contractor has a strong financial incentive to be both efficient and

effective whenever he undertakes work. In order to maximize profits, he must reduce his activities to

the smallest possible volume of well designed interventions, which nevertheless ensure that pre-

defined indicators of Service Level are achieved and maintained over time. This type of contract makes

it necessary for the Contractor to have a good management capacity. Here, “management” means the

capability to define, optimize and carry out on a timely basis the physical interventions which are

needed in the short, medium and long term, in order to guarantee that the roads remain above the

agreed Service Levels. In other words, within the contract limitations and those required to comply

with local legislation, technical and performance specifications and environmental and social

regulations, the Contractor is entitled to independently define (within the limits indicated in the

schedule of payment): (i) what to do, (ii) where to do it, (iii) how to do it, and (iv) when to do it. The

role of the Road Administration and of the Employer is to enforce the contract by verifying compliance

with the agreed Service Levels and with all applicable legislation and regulations. The Contractor will

be responsible for the detailed design of the rehabilitation and other consequent phases included in the

life-span of the project (the Contractor is not entitled to any payment for the design). The Design

Standards and specifications shall be recommended by the Project Manager and meet at least the

minimum specified design standards The bidder can propose higher standards if it serves better his

optimal Programming for the project designed for 10 years period.

6. The project managing triangle is composed of the Employer, Contractor and the Project

Manager from the Monitoring Consultant.

7. Maintaining a road network includes both routine and periodic tasks. Routine Maintenance

consists of many different tasks frequently necessary to maintain the function of the road (such as

pothole repairs, cleaning of drainage, sealing of cracks, cutting of vegetation, etc.). Periodic

Maintenance consists of predictable and more costly measures of a less frequent nature designed to

avoid road degradation (such as grading, drainage work, resurfacing, asphaltic concrete overlays, etc.).

Intelligent management, the timeliness of interventions and the adequacy of technical solutions are

critical. It is expected that the use of private specialized firms under output- and performance-based

contracts will unleash significant efficiency gains, and stimulate innovation in comparison with

traditional road administration practices.

8. Minimum road conditions and Service Levels are defined through output and performance

measures, and these are used under the OPRC to define and measure the desired performance of the

Contractor. In the OPRC, the defined performance measures are thus the accepted minimum thresholds

for the quality levels of the roads for which the Contractor is responsible.

9. The performance criteria should ideally cover all aspects of the contract and take account of the

fact that different sub-areas within the contract area might require different Service Levels. Criteria can

be defined at three levels (although simpler contracts will not use all of the criteria identified below):

(a) Road User Service and Comfort measures, which can be expressed in terms such as:

Road Roughness

Road and lane width

Page 24: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

21

Rutting

Skid resistance

Vegetation control

Visibility of road signs and markings

Availability of each lane-km for use by traffic

Response times to rectify defects that compromise the safety of road users

Attendance at road accidents

Drainage off the pavement (standing water is dangerous for road users)

(b) Road Durability measures, which can be expressed in terms such as:

Longitudinal profile

Pavement strength

The extent of repairs permissible before a more extensive periodic maintenance treatment is

required

Degree of sedimentation in drainage facilities

(c) Management Performance Measures, which define the information the Employer requires both

to govern the asset during the term of the contract, and to facilitate the next tender round.

Requirements should include:

Delivery of regular progress reports to the Road Controlling Authority

Inventory updates and other data sharing requirements

Maintenance history (so subsequent tenders can price the work).

10. Together the performance measures define the minimum acceptable Service Level for the

particular road. In setting the measures various criteria (both technical and practical) need to be

carefully considered, such as (i) traffic volume and composition, (ii) urban vs. rural roads (iii) flat,

hilly or mountainous terrain, (iv) sub-grade quality and type, (v) quality of available construction

materials, (vi) capacity of available contractors, (vii) any environmental constraints, such as protected

areas, parks, forest reserves, etc. However, probably the most important criterion is the question of

what Service Level can be afforded and economically justified for the road in question.

11. Under the terms of the contract, the Contractor will also be responsible for the continuous

monitoring and control of road conditions and Service Levels for all roads or road sections included in

the contract. This will not only be necessary to fulfill the contract requirements, but it is an activity

which will provide him with the information needed to be able (i) to know the degree of his own

compliance with Service Level requirements, and (ii) to define and plan, in a timely fashion, all

physical interventions required to ensure that service quality indicators never fall below the indicated

thresholds. Under the OPRC model, the Contractor will not receive instructions from the Employer

concerning the type and volume of road maintenance works to be carried out. Instead, all initiative

rests with the Contractor who must do whatever is necessary and efficient to achieve the quality levels

required. This concept is expected to lead not only to significant efficiency gains, as mentioned earlier,

but also to technological innovation.

Page 25: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

22

12. The beneficiaries of the new concept are expected to be the road users, the Road

Administration, and the contractors or other private sector enterprises. In a wider sense, future

generations will be able to benefit from a better preservation of past investments in roads. Road users

will be able to know the Service Level they can expect in return for the payments they make for the use

of the infrastructure (tolls, tariffs, user fees, taxes, etc.). The Road Administrations should benefit by

obtaining better overall road conditions at the same levels of expenditure. For contractors and other

private sector enterprises, the new type of contracts should open up new business opportunities, in

which longer contract periods provide a more stable business environment, and for the establishment

of true Public-Private Partnership relations. However, it may be the future generations who will

perhaps benefit most, since they will not have to pay for the reconstruction of roads destroyed because

of a lack of maintenance today.

13. Output- and Performance-based Road Contracts as the model for road asset management

transfers a significant burden of risk onto the contractor. It is important that this burden is both

equitable and within the capacity of the industry. The contract defines the risk profile carried by the

contractor arising from storm events, legislation changes, changes in traffic volumes, and roadside

development.

14. Some emergency works should always be foreseen. Those are meant to remedy unexpected

damage which occurs as a result of extraordinary natural phenomena, and which affect the normal use

of the road network, or the safety and security of the users. For emergency works, the contract limits

the responsibility of the Contractor, establishing that the Employer will approve execution of services

and separate remuneration based on specific amounts proposed by the Contractor for each case, on the

basis of volume of works estimated at each time and on unit prices included in the bid and in the

contract.

15. The agreed periodic payment for maintenance works and services will be made to the

Contractor if he has complied, during the month for which the payment is to be made, with the agreed

Service Levels on the road network under contract. Together with his Periodic Payment Report, the

Contractor will report the result of his own evaluation of compliance with the required Service Levels,

based on his own monitoring system which is mandatory. His statement will then be verified by the

Employer or his representative (supervision/monitoring consultant) through inspections. If the Service

Levels are not met, payments are reduced, based on a schedule given in the contract, payments may

even be suspended, and the contract cancelled, if the contractor fails during an extended period to

achieve certain minimum thresholds values of Service Levels. The contract describes the formulas

used to calculate payment reduction and potential contract suspensions.

Page 26: World Bank Document€¦ · Report No: 71699 - IN RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF PUNJAB STATE ROAD SECTOR PROJECT LOAN 4843 – IN (BOARD APPROVAL - DECEMBER

23

Annex 3: Proposed OPRC Network

INDIA: PUNJAB STATE ROAD SECTOR PROJECT

RESTRUCTURING PAPER

Legend:

Improvement Works (Widening)

Resurfacing and Rehabilitation