work study slides im eee chem 13

Upload: gogana93

Post on 17-Oct-2015

28 views

Category:

Documents


1 download

DESCRIPTION

chemical

TRANSCRIPT

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    1/178

    Productivity

    Ratio between output and input.

    Output : desired

    Input : Man, machine, material, etc.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    2/178

    Concept of Work Content

    BASIC Work Content: is the minimum time

    theoretically required to do a job or operation. This cannot bereduced. This results only if (i) the design and the

    specifications are perfect, (ii) process of manufacture is

    exactly followed and (iii) no loss of working time occurs due

    to any reason.

    The actual time required to complete an operation or job is

    more than the basic time in practical situations. This additional

    portion is called the excess work content.

    The amount of work contained in a given job is referred

    to as work content and is measured in man-hours or machine-hours.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    3/178

    Reasons for Excess Work Content

    A. Work content added due to defects in

    design or specs of a product

    i. Bad design of product

    ii. Lack of standardisation of components

    iii.Incorrect specs & quality standardsiv.Faulty design of components

    B. Work content added due to

    inefficient methods of manufacture

    i. Improper selection of manufacturing

    process/machine

    ii. Wrong selection of tools

    iii.Improper layout of the shop/factory

    iv.Inefficient methods of material handling

    C. Ineffective time added due to

    shortcomings of management

    i. Bad working conditions, ii) frequent prod.

    Interruptions due to breakdown, iii)poor prod.

    planning and control, iv) lack of safety

    measures, v) lack of quality mindedness, vi)

    lack of instruc-tion vii) frequent changes in set-

    ups, viii) lack of performance standards, ix)

    shortage of materials / tools.

    D. Ineffective time added due to reasons

    attributed to workmen

    i. Unauthorised absence from work, ii)substandatd performance, iii) careless-ness in

    working, iv) unnecessary wastage of time /

    idleness.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    4/178

    Productivity

    Productivity of man

    Total timeof operation

    under

    existing

    conditions

    Basic Work Content

    of product and / or

    process

    Work Content added by

    defects in design of

    product or process

    Work Content added by

    inefficient methods of

    operations

    Ineffective Time due tomanagement problems

    Ineffective Time within

    control of workers

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    5/178

    Productivity

    Productivity of man

    Bad design of product

    Lack of standardization

    Incorrect Quality Standards

    Excess Material

    Wrong Machine

    Incorrect Processes operation

    Wrong Tools

    Bad Layout

    Wrong Working method

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    6/178

    ProductivityProductivity of man

    Excessive Product Variety

    Lack of Standardization

    Design Changes

    Wrong / Lack of Planning

    Unavailability of Raw

    Material

    Plant Breakdown

    Bad Plant Condition

    Bad Working Condition

    Accidents

    Absence, Late coming and / or

    Idleness

    Careless Workmanship

    Accidents

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    7/178

    Techniques to reduce Work Content

    A. Mngt technique to reduce work contentdue to product

    i. Product development,

    ii. standardisation,

    iii. value analysis,

    iv. market/consumer research

    B. Mngt technique to reduce work contentdue to process/ methods

    i. process planning ,

    ii. method study

    C. Mngt techniques to reduce ineffectivetime due to shortcomings ofmanagement

    Product standardisation andsimplification, productspecialisation, iii) standardisation of

    components, iv) production planning& control, v) materials control, vi)plant maintenance, vii) safetymeasures and improved workingconditions.

    D. Mngt techniques to reduce ineffectivetime within the control of the workers

    i) sound personnel policies, ii)Operators training, iii) safetytraining, iv) financial incentives.

    The important functions of production management are setting up most

    effective method of performing the operation and control the effective

    utilisation of resources.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    8/178

    Direct means of raising productivityApproach Type of

    Improvement

    Means Cost How quickly

    results be

    achieved?

    Extent of

    improvement

    in

    productivity

    Role of Work

    Study

    Capital

    Investment

    Development

    of new basic

    process or

    fundamental

    improvement

    of exiting one

    Basic or

    Applied

    research,

    pilot plant

    High Generally

    years

    No obvious

    limit

    Method Study to

    improve ease of

    operation and

    maintenance at

    design stage

    CapitalInvestment

    Install moremodern or

    higher

    capacity plant

    or Eqpt. Or

    modernise

    existing plant

    Purchaseprocess

    research

    High Immediatelyafter

    installation

    No obviouslimit

    Method study inPlant Layout and

    to improve ease of

    operation when

    modernising

    BetterManagemen

    t

    Reduction inWork Content

    of the Product

    ProductResearch,

    developme

    nt

    Qlty Mngt

    Method

    study

    valure

    analysis

    Not highcompare

    to (1)

    and (2)

    above.

    Generallymonths

    Limitedofthe same

    order as that

    to be expected

    from later

    Method Study(and its extension

    value analysis) to

    improve design

    for ease of

    production

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    9/178

    Better

    Management

    Reduce work

    content of the

    process

    Process

    research, pilot

    plant, process

    planning,

    Method study,

    value analysis

    Low Immediate Limited, but

    often of a

    high order

    Method study to

    reduce wasted

    effort and time in

    operating the

    process by

    eliminating

    unnecessary

    movement

    Better

    Management

    Reduce

    ineffective

    time (due to

    Management

    or workers)

    Work

    measurement

    Standardisatio

    n, product

    development,

    PPC, material

    control,

    planned

    maintenance,

    personnelpolicy,

    operator

    training,

    incentive

    scheme

    Low May start slowly

    but effect grows

    quickly

    Limited, but

    often of a

    high order

    Work

    Measurement to

    investigate

    existing practice,

    locate ineffective

    time and

    standards of

    performance as a

    basis for: a)

    Planning &Control, b)

    Utilisation of

    Plant, c) Labour

    cost control, d)

    Incentive scheme

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    10/178

    Management approach to deal with Productivity

    To eliminate the excess work content To reduce the ineffective time

    The technique is known as Work Study.

    Work study can be defined as the analyticinvestigation of the methods, conditions andeffectiveness of industrial work and therebythe determination of the ways in whichhuman efforts may most economically beapplied.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    11/178

    Definitions.

    Work Study is primarily concerned withdiscovering the best ways of doing the joband establishing standards based on suchmethods.

    Work study is the technique of Methodstudy and work measurement employed to

    ensure the best possible use of human andmaterial resources in carrying out aspecified activity. -ILO

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    12/178

    WORK STUDY.

    Its a Mgt tool to achieve higher efficiency. Itprovides us a scientific approach to investigate intoforms of work with a view to increase productivity.

    Concerned primarily with manual work Any industry to survive, must use latest technology &

    most efficient method, improvised with a consistentaim of producing best quality goods at lower prices.

    One way to improve is by efficient use of plant,equipment and Labor.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    13/178

    Work Study aims at improving the existing and proposed ways of doing

    work and establishment of standard time for work performance.

    Work Study is the most effective tool to enhance productivity because

    of the fact that it is a straight forward way of increasing the productiveefficiency of the organisation and also considers all the factors

    influencing productivity.

    Work Study comprises of method study and work measurement.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    14/178

    WORK STUDY

    Work study is simply study of work.

    It is analysis of work dividing it into smallerparts followed by rearrangement of these parts

    to give the same effectiveness at a lesser cost. Work study examines both the method and

    duration of the work involved in the process.

    Work study is a powerful tool for simplificationof work Robert Owen, Taylor and Bedeaux gave their contributions to this topic.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    15/178

    Work study and the Worker

    Why workers resist the work study:

    It will change their familiar work methods.

    Many workers resent being timed.

    Fear of being fired.

    Wh i W k S d ?

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    16/178

    What is Work Study? Production system focuses on increasing the efficiency by

    maximizing the output per hour of employee effort.

    The important functions of Production Management are setting upthe most effective method of performing the operations (std.method) and their control for effective utilization of resources.

    Work Study (WS) is one of the most important managementtechniques which is employed to improve the activities inproduction. It provides a scientific approach to investigate into allforms of work, with a view to increase productivity.

    The main objective of WS is to assist the management in the

    optimum use of the human & material resources.

    Main aim of this WS is to finding the best & most efficient way ofusing available resources i.e. men, material, money & machinery.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    17/178

    What is Work Study? It is especially concerned with productivity. To increase

    the productivity from a given quantity of resources.

    Workstudy is ageneric term for thetechniquesofmethod study and work measurement. Thesetechniques are used in the examination of human

    workinallitscontexts.Theyleadsystematicallytotheinvestigation of all the factors which affect theefficiencyandeconomyattheworkplaceinordertoaffectimprovement.

    Work Study is the systematic examination of themethods of carrying on activities so as to improve theeffective use of resources and to set up standards ofperformance for the activities being carried out.

    C f W k S d

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    18/178

    Components ofWork Study

    It has threeaspects

    1. More effective use of plant & equipment

    2. More effective use of human effort3. Evaluation of human work

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    19/178

    Work Study - Basic Procedure8 step process

    RECORD

    EXAMINE

    DEVELOP

    MEASURE

    DEFINE

    INSTALL

    MAINTAIN

    SELECT

    Most economical method

    Job or process to be studied

    All details concerning Job using various techniques

    Recorded facts critically by asking questions

    Amount of work involved & set

    standard time to do the job

    New method & standardtime

    New method as a

    standard practice

    New method as

    agreed standard

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    20/178

    Applications of work Study

    Industries: production operations, research and development

    Marketing: sales & distribution.

    Offices: stores & warehouses.

    Material handling

    In designing field

    Building & other construction

    Transport

    Hospital Army

    Agriculture

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    21/178

    Advantages/ Objectives of Work Study

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    22/178

    METHOD STUDY

    Method Study (MS) is the systematic recording and

    critical examination of existing and proposed ways ofdoing work, as a means of developing and applying

    easierand more effective methods and reducing costs.

    MS aims at determining the most effective method of

    performing the job, most logical layout of manufacturing

    facilities, uninterrupted flow of materials throughout the

    organization. It is concerned with reduction of work content

    and establishing the one best way of doing the job.

    MS is a collection of analysis techniques focusing onimproving the effectiveness of man and the machine.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    23/178

    Method Study Methods engineering /work design

    Breakdown of operation into components

    Systematic analysis of each component

    Eliminates un-necessary operations

    It is systematic recording & examination of

    existing methods of doing work and developing

    more effective methods - BSIMS addresses three broad areas:

    1. It is a diagnostic tool (location of faults)

    2. It is a remedial tool (improve situation)

    3. It is a constructive tool (set standards)

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    24/178

    Objectives of Method Study1. Improvement of manufacturing processes and procedures.

    2. Improvement of working conditions.3. Improvement of plant layout and work place layout.

    4. Reducing the human effort and fatigue.

    5. Reducing material handling6. Improvement of plant and equipment design.

    7. Improvement in the utility of material, machines and manpower.

    8. Standardization of method.

    9. Improvement in safety standard.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    25/178

    Method Study

    Method study is the technique of systematicrecording and critical examination of existing and

    proposed ways of doing work and developing an

    easier and economical method.

    Method study examines the way a task (changing theclutch on a car, preparing a flower bed for planting,

    cleaning a hotel room) is done. The industrial

    engineer has an eye on operational efficiencies and

    costs, quality of processes, service reliability, staffsafety etc. Method study techniques are applicable

    from factory/workshop manufacturing to cabin crew

    activities.

    Method Study

    Flow Chart

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    26/178

    Method Study Procedure

    SELECT

    RECORD

    EXAMINE

    DEVELOP

    DEFINE

    INSTALL

    MAINTAIN

    The work which can be studied with economic advantage

    All relevant facts about the job / operation

    The facts critically (purpose, place, sequence,person)

    verify at regular intervals that the improved method is in use

    Plan, arrange and implement the new method as Std.

    method, procedure, layout, equipment, workingconditions, materials, quality, instructions

    A record of improved method,

    under prevailing conditions.

    Reexamine and select the

    best method

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    27/178

    BASIC PROCEDURE FOR METHOD STUDY

    Thebasicprocedureforconductingmethodstudyisasfollows:

    1.Selectthe work to be studied.

    2. Record all facts about the method by directobservation.

    3.Examinethe above facts critically.

    4. Develop the most efficient and economic

    method.5.Definethe new method.

    6.Installthe new method as std. practice

    7.Maintainthe new method by regular checking.

    Method Study

    Flow Chart

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    28/178

    Selecting the work to be studied

    There are three factors that should be kept in mindwhile selecting a job for method study:

    1. Economic or cost-effective considerations.

    2. Technical considerations.

    3. Human considerations.

    1. Economic considerations:

    It is obviously a waste of time to start or continue a

    long investigation if the economic importance ofa job is small.

    Questions that should always be asked are:

    Will it pay to begin a method study of this job? Or

    Will it pay to continue this study?

    BASIC PROCEDURE FOR METHOD STUDY

    Obvious choices for study are:

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    29/178

    Obvious choices for study are:

    A. Keyprofit-generating or costly operations or ones with the largest

    Scrap/waste rates.

    B. Bottlenecks which are holding up other production operations, or

    lengthy operations that consume a great deal of time. C. Operations involving repetitive workusing a great deal of labour

    and ones that are likely to run for a long time.

    D. Movements of material over long distancesbetween workstations,

    those involving the use of a relatively large proportion of labor or

    which require repeated handling of material.

    SelectPossible Results:

    * Increased production rate * Reduced cost

    * Less labor, materials, or equipment * Improved quality

    * Improved safety * Reduced scrap

    * Improved standards of cleanliness

    One of the easiest techniques that can be used to identify key operations aslisted in part (A) is the Pareto analysis (sometimes also referred to as theABC analysis of value analysis).

    The same observation can be extended by saying that among all theoperations in a given plant a small number account for the largest share of

    cost or ofprofit, or the largest percentage ofwaste.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    30/178

    To illustrate the point we will consider the following example.

    Let us assume that a certain enterprise produces 20 different products. Eachof these products generates a certain profit.

    By listing the annual production and profit contribution one obtains theresults shown in table 6.

    The next step consists of rearranging these items in descending order ofimportance according to profit. The result would then appear like the oneshown in table 7.

    From table 7 it can be seen that three products only, listed as A items,

    account for 60 per cent of the profit. These are the most profitable and any improvement in methods of

    producing these particular products would reflect highly on profits. Theywould be a priority for study.

    Products listed under B, which are seven in number, contribute 25 percent of the profit. They could then assume a second importance, while

    products C would command the last priority since their contribution toprofit is minimal. The same type of analysis can be conducted to determine the most costly

    products or processes or the products or processes that yield the highestwaste.

    Those would then become a priority for study by the work study specialist.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    31/178

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    32/178

    St d d Li t f i t t b d h l ti

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    33/178

    1. Product and operation

    2. Person who proposes investigation

    3. Reason for proposal

    4. Suggested limits of investigation

    5. Particulars of the job

    a) How much is produced or handled per week?b) What percentage is this of the total produced or handled in the shop or plant?

    c) How long will the job continue?

    d) Will more or less be required in future?

    e) How many operatives are employed on the joba) Directly

    b) Indirectly

    f) How many operatives are there in each grade and on each rate of pay?

    g) What is the average output per operative (per team) per day?

    h) What is the daily output compared with the output over a shorter period (an hour)?

    i) How is payment made? (team-work, piece work, premium bonus time rate, etc.)

    Standard List of points to be covered when selecting

    a job for Method Study(Sample list which needs to be adapted to individual needs)

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    34/178

    Standard List of points to be covered when selecting a job for Method Study

    (contd.2)

    j) What is the daily output

    a) Of the best operative?

    b) Of the worst operative?

    k) When were production standards set?

    l) Has the job any especially unplesant or injurious features? Is it

    unpopular (a) with workers, (b) with supervisors?

    6. Equipment

    a) What is the approximate cost of plant and equipment?

    b) What is the present machine utilisation Index?

    7. Layout1. Is the existing space allowed fo the job enough?

    2. Is extra space available?

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    35/178

    8. Product

    1. Are the frequent design changes causing modifications?

    2. Can the product be altered for easier manufacture?

    3. What quality is demanded?4. When and how is the product inspected?

    9. What savings or increase in productivity may be expected from a

    method improvement?

    a) Through reduction in the work content of the product or process.

    b) Through better machine utilisation.

    c) Through better utilisation of labour.

    Standard List of points to be covered when selecting a job for Method Study

    (contd. 3)

    2. Technical or technological considerations:

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    36/178

    gOne of the important considerations is the desire by management to acquiremore advanced technology, i.e. in equipment or in processes.

    Therefore, management may want to computerize its office paperwork or itsinventory system, or to introduce automation in the production operations.

    Before such steps are taken, a method study can point out the most importantneeds of the enterprise in this respect.

    The introduction of new technology should therefore constitute an importantfactor in the choice of methods of work to be investigated.

    Based on the technical knowledge of the process

    Jobs having inconsistent quality, Operations generating lot of scrap, Frequentcomplaint from workers, Extensive paperwork, Repetitive work (automation),

    Hazardous work etc.

    3. Human considerations: Most difficult to foretell, because of mental andemotional nature.

    Certain operations are often a cause of dissatisfaction by workers.

    Select an unpopular job - That may bring on fatigue or monotony or may beunsafe to operate or inconsistent earnings.

    The level of satisfaction should point to a need for method study. In a similarfashion, a choice of a particular job for study may lead to anxiety or ill feeling.

    The suggestion given here is to leave it alone.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    37/178

    2. Record:All the details about the existing method are recorded. This isdone by directly observing the work. Records are useful for BEFORE

    and AFTER comparison to assess effectiveness of proposed method.

    Recording techniques are designed to simplify & standardize recording

    work.

    COMMONLY USED RECORDING TECHNIQUES

    1. Outline Process Charts

    2. Flow Process Chart

    3. Two Handed Process Chart

    4. Multiple Activity Chart

    5. Simo Chart

    6. Flow Diagrams

    7. String Diagrams

    8. Cyclegraph

    9. Chronocyclegraph

    10. Travel Chart

    Man Type

    Material Type

    Equipment Type

    USING TIME SCALE

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    38/178

    Typical Industrial problems and appropriate method study

    technique

    Type of Job Examples Recording Technique

    Complete sequence of

    manufacture

    Manufacture of an electric

    motor from raw material to

    dispatch

    Outline Process Chart

    Flow Process Chart

    Flow Diagram

    Factory Layout: Movement

    of materials

    Movement of diesel engine

    cylinder head through all

    machining operations

    Outline Process Chart

    Flow Process Chart (Mat)

    Flow Diagram

    Travel Chart, Models

    Factory Layout: Movement

    of Workers

    Cooks preparing meals in a

    restaurant kitchen

    Flow Process Chart (Men)

    String diagram

    Travel Chart

    Handling of Materials Putting materials into &

    taking them out of stores

    Flow Process Chart (Mat)

    Flow DiagramString diagram

    Workplace layout Light assembly work on a

    bench

    Flow process Chart (Man)

    Two handed process Chart

    Multiple activity Chart

    Simo Chart, Cyclegraph

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    39/178

    Type of Job Examples Recording Technique

    Automatic machine

    operation

    Assembly line, operator

    looking after semi-automatic lathe

    Multiple activity chart

    Flow Process Chart (Eqpt)

    Movement of operatives at

    work

    Female operatives on short-

    cycle repetition work

    Films, Film analysis,

    Simo Chart

    Memotion photography

    Micromotion analysis

    Typical Industrial problems and appropriate method study technique

    Symbols are used to represent the activities like operation, inspection,

    transport, storage and delay.

    Grouping of activities: Five sets of activities can be grouped in two

    categories

    Those in which something actually happens to the work-piece (it is

    moved, worked upon orexamined)

    Those in which it is not being touched (in storage or in delay)Objective is to maximize proportion of do activities.

    All other activities, however necessary, are considered non-productive

    BASIC PROCEDURE FOR METHOD STUDY

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    40/178

    3. Examine: Critical examination is done by questioning

    technique. This step comes after the method is recorded by

    suitable charts and diagrams. The individual activity is

    examined by putting a number of questions.

    Critical examination is conducted wherein each activity, in turn, being

    subjected to a systematic and progressive series of questions.

    The questioning sequence used follows a well-established pattern

    which examines:

    the PURPOSE for which

    The PLACE at which

    The SEQUENCE in which the activities are undertaken.the PERSON by whom

    the MEANS by which

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    41/178

    PRIMARY QUESTIONS

    In the first stage of the questioning technique, the purpose, place,

    sequence, person and means of every activity recorded are systematically

    questioned, and a reason for each reply is required.

    SECONDARY QUESTIONS

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    42/178

    SECONDARY QUESTIONS

    The secondary questions cover the second stage of the questioning

    technique, during which the answers to the primary questions are

    subjected to further query to determine whether possible alternatives of

    place, sequence, persons and means are practicable and preferred as a

    means of improvement upon the existing method.

    PURPOSEWhat else might be done?

    What should be done?

    PLACEWhere else might be done?

    Where should be done?

    SEQUENCEWhen else might be done?

    When should be done?

    PERSON Who else might be done?Who should be done?

    MEANSHow else might be done?

    How should be done?

    These questions, in the above sequence, must be asked systematically every time

    a method study is undertaken. They are the basis of successful method study.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    43/178

    BASIC PROCEDURE FOR METHOD STUDY

    4. Develop : Answer to the questions will result in thedevelopment of alternatives and of a better method. Develop

    the most efficient and economic method.

    Ex: Sending letters to customers.

    5. Define:Once a complete study of a job has been made and a

    new method is developed, it is necessary to obtain the

    approval of the management before installing it. The work

    study man should prepare a report giving details of the

    existing and proposed methods, reasons for change,

    advantages, limitations, savings expected, tools & equipment

    required etc..

    DEFINING THE IMPROVED METHOD

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    44/178

    DEFINING THE IMPROVED METHOD

    The report should show:

    1. Relative costs in material, labour and overheads of thetwo methods, and savings expected.

    2. The cost of installing the new method, including thecost of new equipment and of re-laying out shopsor working areas

    3. Executive actions required to implement the newmethod.

    It should also give details regarding :

    1. The tools and equipment to be used2. A description of the method

    3. A diagram of the work place layout, jigs/fixtures etc.

    BASIC PROCEDURE FOR METHOD STUDY

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    45/178

    BASIC PROCEDURE FOR METHOD STUDY

    6. Install :This step is the most difficult stage in method study.

    Here the active support of both management and trade union

    is required. Here the work study man requires skill in gettingalong with other people and winning their trust.

    a) Gaining acceptance of the change by the Management

    b) Gaining acceptance of the change by the workers

    c) Maintaining close contact with the progress of the job until satisfiedthat it is running as intended

    7. Maintain:The work study man must see that the new method

    introduced is followed. The workers after some time may slip

    back to the old methods. This should not be allowed. The newmethod may have defects. There may be difficulties also. This

    should be rectified in time by the work study man.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    46/178

    Recording Techniques in

    Method study

    Outline processchart

    Flow process

    chart

    Material type chart

    Machine type chart

    Two -Handed

    process chart

    Using a time scale

    Multiple activity

    chart

    Simo chart

    P.M.T.S. chartMan type chart

    Indicating

    Process

    Sequence

    Diagrams

    indicating

    movements

    String Diagram

    Flow Diagrams

    Travel Chart

    Chrono-cycle

    Graph

    Cycle Graph

    S b l d i Ch t

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    47/178

    OPERATION:A large circle indicates operation. An operation takes place when there

    is a change in physical or chemical characteristics of an object. Occurs when an object is

    intentionally changed in one or more of its characteristics. An assembly or disassembly isalso an operation. When information is given or received or when planning or calculating

    takes place it is also called operation.

    Example: Reducing the diameter of an object in a lathe. Hardening the surface of an

    object by heat treatment. Drilling, Painting, Chemical reaction, Data Entry, Cutting, Sorting,

    etc.

    INSPECTION:A square indicates inspection. Inspection is checking an object for its

    quality, quantity or identifications.

    Example:Checking the diameter of a rod. Examine the quantity or quality, read steam

    gauge on boiler, detect the defectives. Counting the number of products produced. of an

    object by heat treatment.

    Symbols used in Charts

    Symbols used in Charts contd.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    48/178

    Symbols used in Charts contd.

    STORAGE: An equilateral triangle standing on its vertex represents storage. Storage

    takes place when an object is stored and protected against unauthorized removal.

    Example:Raw material in the store room, finished products inventory, archived documents.

    DELAY: A large capital letter D indicates delay. This is also called as temporary

    storage. Delay occurs when an object or operator is waiting for the next activity. Occurswhen the immediate performance or the next planned action does not take place.

    Example:An operator waiting to get a tool in the stores. Work pieces stocked near the

    machine before the next operation. Work In Process inventory waiting to be processed,

    Employee waiting for an elevator, Waiting for accumulation of a certain quantity for

    packaging

    TRANSPORTATION:An arrow indicates transport. This refers to the movement of an

    object or operator or equipment from one place to another. When the movement takes

    place during an operation, it is not called transport.Example:Moving the material by a trolley Operator going to the stores to get some tool,

    Using elevator, carrying, moving with material handling devices

    .

    ASME Standard Symbols

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    49/178

    y

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    50/178

    Why Charts?

    It gives a complete picture of what is being done andhelps to understand the facts and its relationship to oneanother.

    Details on the chart must be obtained from directobservation. Should not be from memory.

    Neatness and accuracy is important.

    Increased value if following is included:

    1. Product, equipment details (code#, drawing#)

    2. Job or process being carried out

    3. Location and time (date) of the study

    4. Observers name

    5. Chart reference number

    (A) MACRO MOTION CHARTS

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    51/178

    (A) MACRO MOTION CHARTS

    1.Operation Process Chart

    Also called Outline process chart

    Birds eye view of whole process

    Records only major activities and inspections

    Uses only two symbols i.e. operations & inspection

    Constructed by placing symbols one below another

    Uses

    Visualize sequence of operations & inspections in process

    Know where operations selected fits into the entire

    process

    OPERATION PROCESS / OUTLINE PROCESS Chart:

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    52/178

    OPERATION PROCESS / OUTLINE PROCESS Chart:Example : Manufacture of Electric Motor

    1

    4

    7

    Conventions followed in

    preparing the chart

    1. Write title at the top of the chart.

    2. Begin the chart from the right handside top corner.

    3. Represent the main component at

    the right extreme.

    4. Represent the sequence of

    operations and inspections by their

    symbols. Connect them by vertical

    flow lines.5. Record the brief description of the

    activity to the right side of the

    symbols.

    6. Note down the time for each activity

    to the left of the symbol.

    7. Number all operations in one serial

    order. Start from the right hand top(from number 1).

    8. Similarly number all inspections in

    another serial order (starting from 1).

    9. Continue numbering, till the entry of

    the second component.

    10. Show the entry of purchased parts

    by horizontal lines.

    4

    7 11114

    4

    Record- Example

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    53/178

    Outline Chart

    Face, turn, cut

    Face opposite end

    Dimension and finish

    Straddle mill four flats

    Remove burr

    Final inspection of machining

    Degreasing

    Cadmium plating

    Final check

    Face both sides

    Drill hole

    Final check

    Assemble and drill

    Turn shank

    Remove chip

    Dimensions

    Degreasing

    Cadmium plating

    Final check

    Fit stop pin

    Final check

    Switch Rotor

    Ex: Outline process chart of Plywood manufacture

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    54/178

    Ex: Outline process chart of Plywood manufacture

    Record- Example

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    55/178

    Outline Chart

    2. Flow Process Chart

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    56/178

    A flow process chart is a graphical representation of the sequence of all the

    activities (operation, inspection, transport, delay and storage) taking place in a

    process.

    It is the detail version of outline process chart recording all the events.

    Process chart symbols are used here to represent the activities.

    Gives sequence of flow of work.

    Constructed same as operation process chart

    Three types1. Material type

    (records how the material is handled or treated).

    2. Man type

    (records what the worker does).

    3. Equipment type

    (records how the equipment or machine is used).

    Uses Reduce idle time and delays

    Reduce distance travelled

    Reduce production cycle time

    To relocate inspection stages

    1. The details must be obtained by directobservationcharts must not be based

    on memory.2. All the facts must be correctly recorded.

    3. No assumptions should be made.

    4. Make it easy for future reference.

    5. All charts must have the following details:

    (a) Name of the product, material orequipment that is observed.

    (b) Starting point and ending point.

    (c) The location where the activities takeplace.

    (d) The chart reference number, sheetnumber and number of total sheets.

    (e) Key to the symbols used must bestated.

    Ex: Machine/ Equipment Flow Process Chart: Biscuit Making

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    57/178

    Ex: Machine/ Equipment Flow Process Chart: Biscuit Making

    Flow Process Chart - Example

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    58/178

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    59/178

    Distance in

    meter

    Symbol Process description

    10 Move to cabinet

    - Get loaf of bread

    - Remove two slices of bread

    - Lay slices on table top

    - Close loaf of bread

    - Replace loaf on shelf

    - Open butter

    - Spread butter on top slice- Inspect sandwich

    - Move to serving area

    10 Serve sandwich

    Ex: Process chart for making a Cheese Sandwich

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    60/178

    Ex: Flow Process ChartEmergency ward

    1 X Enter emergency room, approach patient window2 X Sit down and fill out patient history

    3 X Nurse escorts patient to ER triage room

    4 X Nurse inspects injury

    5 X Return to waiting room

    6 X Wait for available bed

    7 X Go to ER bed

    8 X Wait for doctor

    9 X Doctor inspects injury and questions patient

    10 X Nurse takes patient to radiology

    11 X Technician x-rays patient12 X Return to bed in ER

    13 X Wait for doctor to return

    14 X Doctor provides diagnosis and advice

    15 X Return to emergency entrance area

    16 X Check out

    17 X Walk to pharmacy

    18 X Pick up prescription

    19 X Leave the building

    0.50 1510.0 -

    0.75 40

    3.00 -

    0.75 40

    1.00 -

    1.00 60

    4.00 -

    5.00 -

    2.00 200

    3.00 -2.00 200

    3.00 -

    2.00 -

    1.00 60

    4.00 -

    2.00 180

    4.00 -

    1.00 20

    Process: Emergency room admission

    Subject: Ankle in jury pat ient

    Beginning: Enter emergency roomEnding: Leave hospi ta l

    Stepno.

    Time(min)

    Distance

    (ft)

    Summary

    Number

    of stepsActivity

    Time

    (min)

    Distance

    (ft)

    Step description

    Insert Step

    Append Step

    Remove Step

    Transport 9 11 815

    Operation 5 23

    Inspect 2 8

    Store

    Delay 3 8

    3.Two Handed Process Chart

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    61/178

    It is the process chart in which the activities of two hands of the operator are

    recorded.

    Motions of both hands of worker are Right hand-Left hand chart recorded

    independently.

    It shows whether the two hands of the operator are idle or moving in relation to

    one another, in a timescale.

    It is generally used for repetitive operations.

    Confined to work carried out at a single workplace Visualize complete sequence of activities in repetitive task

    Study work station layout

    Operation:Represents the activitiesgrasp, position, use, releaseetc. of a tool, component or material.

    Transport:Represents the movement of the hand or limb to or from the work or a tool or material.

    Delay:Refers to the time when the hand or limb is idle.

    Storage (Hold):The term holdis used here instead of storage to refer to the time when the work is held byhand.

    The activityinspectionby hand is considered as an operation. Hence, the symbol for inspection is not usedin this

    chart. Two-handed process chart can be used for assembly, machining and clerical jobs.

    Ex: Two-Handed Process Chart

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    62/178

    Ex: Two Handed Process Chart

    Summary of the number of each activity can be tabulated at the bottom of the chart. The chart is first drawn for the existing method.

    This chart is analyzed and if it is found that one hand is over loaded than the other, modification are done in the layout of the

    workplace or in the sequence of activities. Then a new chart is made for the proposed cycle. This assists in finding a better method of

    performing the task and to train the operator in the preferred method.

    1. Provide all

    information about

    the job in the chart.2. Study the operation

    cycle a few times

    before starting to

    record.

    3. Record one hand

    at a time.

    4. First record theactivities of the

    hand which starts

    the work first.

    5. Do not combine the

    different activities

    like operations,

    transport etc.

    Example of a Two-Handed Process Chart:

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    63/178

    p(Cutting Glass Tubes)

    Example of a Two-Handed Process Chart:

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    64/178

    p(Cutting Glass Tubes)

    Ex: Two-handed process Chart

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    65/178

    Ex: Left-Hand-Right-Hand Chart

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    66/178

    Ex: Left Hand Right Hand Chart

    Standard format of a Two-handed process f lowchart

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    67/178

    Standard format of a Two handed process flowchart

    E l f T h d d fl h t

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    68/178

    Example of a Two-handed process flowchart

    F ixing Screw on a Assembly

    Example of a Two-handed process flowchar t

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    69/178

    p p

    F ixing Screw on a Assembly

    Example of a Two-handed process flowchart

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    70/178

    4 Multiple Activity Chart or Man machine Chart

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    71/178

    4. Multiple Activity Chart or Man-machine Chart A man-machine/ Multiple Activity Chart chart is a chart in which the activities of

    more than one worker or machine are recorded.

    Activities are recorded on a common time scale to show the inter-relationship.

    It is used when a worker operates a number of machines at a time. It is also

    used when a number of workers jointly do a job. (Determine no. of machines

    handled by one operator).

    The chart shows the idle time of the worker or machine during the process.(Study idle time)

    Work load is evenly distributed among the workers or machines by this the idle

    time of worker or machine is reduced. Multiple activity chart is very useful in

    planning team work in production or maintenance. (Determine no. of operators

    required). Only two symbols are used in man-machine/ Multiple Activity Chart :

    Working Idle

    Purpose of Multiple Activity Chart

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    72/178

    Purpose of Multiple Activity Chart

    To detect the idle time on machine and workers (The chart shows the exacttime relationship between the working cycle of the person and operating

    cycle of the machine).

    To optimize work distribution between workers and machines.

    To decide number of workers in a group.

    To balance the work team

    To examine the activities. It is used for recording the complex movements of material or men.

    Used to find out the most economical route.

    Application ofMultiple Activity Chart:

    Planning team work. Plant repair & maintenance.

    Job construction.

    It is used to check whether the work station is correctly located.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    73/178

    Example of Multiple Activity Chart:Facing & Centering Operations

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    74/178

    Time Operator Machine 1Washer

    Machine 2Dryer

    # Sec Load clothes & detergent in

    machine 1

    Being loaded Idle

    Idle Run Idle

    - Remove clothes from machine 1 Being unloaded Idle

    - Load clothes into machine 2 Idle Being loaded

    - Load clothes & detergent into

    machine 1

    Being loaded Run

    - Idle Run Run

    - Remove clothes from machine 2 Idle Being unloaded

    - Hang clothes Idle Idle

    Multiple activity chart for doing three loads of laundry

    Ex: Worker-Machine Chart for a Gourmet Coffee Store

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    75/178

    Diagrams

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    76/178

    Diagrams

    Diagrams gives pictorial view of the layout of workplace on which

    locations of different equipment, machines etc. are indicated.

    The movement of subject(man or machine) is then indicated on the

    diagram by a line or a string.

    The diagram are valuable in highlighting the movement so the analystcan take steps to simplify or reduce it so as to obtain saving in time.

    The most commonly used method study diagrams are:

    o Flow diagram

    o String diagramo Travel chart

    o Cyclegraph and Chronocyclegraph

    Types of LAYOUT

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    77/178

    FOUR MAJOR TYPES OF LAYOUT:

    (A) layout by FIXED position, material to be processed dont

    travel round the plant but stays in one place. When product is

    bulky, heavy and only few units are made (Ship Building,

    Aircraft construction, Manufacture of large Diesel engines)

    (B) layout by PROCESS, Operations of the same nature are

    grouped together. Cutting in garment industry, stitching inanother area. This is mostly chosen where great many products

    share the same machine.

    (C) Layout by PRODUCT, or LINE layout (Mass production) all

    m/c & equipment necessary is set in the same area and in the

    sequence of manufacturing process.

    (D) layout by GROUP. Group production methods.

    Types of LAYOUT

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    78/178

    1 Flow diagram

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    79/178

    1.Flow diagram

    Drawing of working area & showing location of various activities

    Shows the route followed and selects the optimum one Study different layout and selecting optimum one

    Study traffic and frequency over different routes

    Procedure :

    Layout of workplace is drawn to scale

    Relative positions of the m/c tools, storage & inspection benches are

    marked on the scale

    Path followed by the subject under study is tracked by drawing lines

    Each movement is serially numbered & indicated by arrow for direction

    Different colors are used to denote different types of movements

    Flow diagram

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    80/178

    Its a top view of the work area correctly indicating the positions of

    machining and other locations affecting the movement of subject.

    Therefor it gives on-the-spot observation of the paths of movement

    of product sometimes using symbols of process charts.

    80

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    81/1782. String diagram

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    82/178

    Scale layout drawing

    Length of a string is used to record extent & pattern of movements of a

    worker within a limited area.

    Movements difficult to trace on flow diagram can be shown Shows the route followed and selects the optimum one

    Study different layout and selecting optimum one

    Study traffic and frequency over different routes

    Procedure :

    A Layout of workplace is drawn to scale

    Pins are fixed into boards to mark locations of workstations

    Pins are also driven at turning points of the routes A measured length of thread is taken to trace the movements

    The distance covered by object is obtained by measuring the remaining

    part of the thread and subtracting it from original length

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    83/178

    START

    END

    83

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    84/178

    DRILL+CUT

    FOLD

    RIVET

    MARK

    IQC

    STACK

    OQC

    SHEETMETAL

    STAR

    END

    START

    END

    Comparison

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    85/178

    SHEET METALCHECK = 10 ft

    CHECKCUT = 12 ft

    CUTDRILL = 9 ft

    DRILLFOLD = 10 ft FOLDRIVET = 10 ft

    RIVETCHECK = 14 ft

    CHECKSTACK = 12 ft

    TOTAL = 67 ft

    SHEET METALIQC = 2.8 ft.

    IQCMARK = 5 ft.

    MARKDRILL &CUT= 6ft

    DRILL &CUTFOLD = 6ft.

    FOLDRIVET = 5 ft.

    RIVETOQC = 5 ft.

    TOTAL = 30 ft.

    Comparison

    Scale 1cm = 2feet

    Before After

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    86/178

    86

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    87/178

    87

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    88/178

    88

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    89/178

    89

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    90/178

    90

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    91/178

    91

    CLASSIFICATION OF MOVEMENTS

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    92/178

    Class Pivot Body member(s) moved

    1 Knuckle Finger

    2 Wrist Hand and Finger

    3 Elbow Forearm, hand and fingers

    4 Shoulder Upper arm, forearm, hand and

    fingers

    5 Trunk Torso, Upper arm, forearm, hand and

    fingers

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    93/178

    93

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    94/178

    94

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    95/178

    95

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    96/178

    96

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    97/178

    97

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    98/178

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    99/178

    99

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    100/178

    100

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    101/178

    101

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    102/178

    102

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    103/178

    103

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    104/178

    104

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    105/178

    105

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    106/178

    106

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    107/178

    107

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    108/178

    108

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    109/178

    109

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    110/178

    110

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    111/178

    111

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    112/178

    112

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    113/178

    113

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    114/178

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    115/178

    Improve Productivity, Reduce Costs, Improve Profits

    Work Measurement:

    Work measurement is the application of a set of techniques

    designed to establish the quantum of work to be done in a given

    time for a qualified worker to carry out specified jobs, under

    specified conditions at a defined level of performance.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    116/178

    We have seen how total time to manufacture a product is

    increased by: adding undesirable features to product,

    bad operation of the processes, and

    ineffective time added because of worker andmanagement.

    All this leads to decreased productivity.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    117/178

    Time Study/ Work Measurement

    Work measurement is identified as a scientificmethod of fixing standard of production orstandard time for a given job.

    To manage, one must measure first.

    Work measurement means the application of aset of techniques intended to establish the

    i. Amount of work to be done by an operator

    ii. At a given time

    iii. Under a specific condition and

    iv. At defined level of performance.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    118/178

    Work measurement (WM) is concerned with investigating,

    reducing and eliminating ineffective time, whatever may

    be the cause.

    WM is the means of measuring the time taken in the

    performance of an operation or series of operations in such

    a way that the ineffective time is shown up and can be

    separated out.

    In practice,proving existence of the ineffective time is the

    most difficult task.

    After existence is proved, nature and extent is easy to see!

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    119/178

    WM is also used to set standard times to carry out the

    work, so that any ineffective time is not included later. Any addition to the standard time would show up as excess

    time and thus can be brought to attention.

    Since, standard times are set for all the activities through

    WM, it has earnedbad reputation amongst workers. Major reason for that has been the initial focus of the WM

    methods, which essentially targeted only the worker

    controllable ineffective times.

    Management controllable ineffective times were ignoredtraditionally.

    f k

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    120/178

    Use of Work Measurement

    1. Assessment of manpower requirements

    2. Planning

    3. Estimation of Production costs

    4. Cost reduction and cost control

    5. Improved methods

    6. Basis for Incentives

    7. Comparing alternative methods

    8. Standard data9. Performance appraisal

    10. Training needs assessment

    Work Measurement

    Work Measurement (WM) is the application of

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    121/178

    Work Measurement (WM) is the application oftechniques designed to establish the time for a qualified

    worker to carry out a specified job at a defined level ofperformance. (British Standard Glossary of Terms in Work Study)

    The purpose of WM is to reveal the nature & extent of ineffective time so that action can be taken to reveal the

    eliminate it and then set standards of performance.

    Two critical issues in work study:

    1. Method study should precede the work measurement,

    always.2. Elimination of management controllable ineffective time

    should precede the elimination of the ineffective time within

    the control of the workers.

    To reduce the amount of ineffective time

    PURPOSE OF WORK MEASUREMENT

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    122/178

    Provides management with a means of identifying the causes of

    ineffective time.

    1. To find ineffective time in a process2. To set standard for output level

    3. To plan workforce needs

    4. To evaluate workers performance

    5. To determine available capacity

    6. To determine price or cost of product7. To compare work methods

    8. To facilitate operations schedules

    9. To establish wage incentive schemes

    10. Training of new employees

    11. Checking employee progressGeneral criteria where WM can be applied for measurable jobs:1. Work should be identifiable in terms of No. of units a worker performed,

    2. Work should be performed in a reasonably consistent manner, and

    3. There should be considerable volume of work to justify performing the study.

    Use of Work Measurement:

    1. Assessment of manpowerrequirements

    2. Planning

    3. Estimation of Production

    costs

    4. Cost reduction and cost

    control

    5. Improved methods

    6. Basis for Incentives

    7. Comparing alternative

    methods

    8. Standard data

    9. Performance appraisal

    10. Training needs assessment

    THE TECHNIQUES OF WORK MEASUREMENT

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    123/178

    1. Stop-watch time study

    2. Work sampling

    3. Predetermined time standards(PTS)

    4. Standard Data

    The choice of technique depends on:

    The level of details desired and The nature of work itself

    Direct observationalmethods

    Indirect

    methods

    Steps in Work Measurement

    Select the job to be timed (B l k i i i j b j b i h f l

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    124/178

    Selectthe job to be timed (Bottleneck operations, repetitive jobs, jobs with great amount of manuallabour, frequent overtime, new job/component, if cost of operation is high, introduce/revise incentive scheme etc)

    Standardise the method of working; Select OperatorRecordall the relevant data relating to the circumstances in which the work is

    being done, the method and the elements of activity in them

    Examinethe recorded data and the detailed breakdown critically to ensure that

    the most effective method and motions are being used and that unproductive and

    foreign elements are separated from productive elements

    Measurethe quantity of work involved in each element, in terms of time, using

    the appropriate work measurement techniques

    Compilethe standard time for the operation which will include time

    allowances to cover relaxation, personal needs, contingencies, etc.

    Defineprecisely the series of activities and methods of operations for which the

    time has been compiled and issue the time as standard for the activities and

    methods specified.

    TIME STUDY

    Basic Steps

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    125/178

    1. Obtaining and recording all available information about the job,

    operator and the surrounding conditions likely to affect theexecution of the work

    2. Recording the complete description of the method, breaking

    down the operation into 'elements'

    3. Measuring with a stopwatch and recording the time taken bythe operator to perform each 'element' of the operation.

    4. Assessing the rating

    5. Extending observed time to 'basic times'

    6. Determining the allowances to be made over and above the basictime for the operation

    7. Determining the 'standard time' for the operation.

    Time StudyTime Study is the application of WM technique to establish time

    for a QUALIFIED WORKER to carry out a SPECIFIED TASK

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    126/178

    for a QUALIFIED WORKER to carry out a SPECIFIED TASK

    under SPECIFIED CONDITIONS and at the DEFINED LEVEL

    OF PERFORMANCE. How much time one should take to reach Wgl Stn?

    * Breaking into the work elements * Time for each work element

    * Rate of performance

    * Time of similar work elements should be compared to keep the standard time

    constant

    * Study a number of cycles instead of one or two

    * Extreme values to be discarded

    To separate productive & non-productive time

    To assess rating of the worker

    To identify different types of elements & to

    measure their timings

    To determine fatigue allowance

    To prepare detailed work specifications

    To fix Std. time for repetitive elements

    Each element should have definite beginning & end

    Element should be as short as possible to be conveniently

    timed (0.04 min)

    Manual & M/c elements should be separately timed

    Constant separate from variable

    Occasional & foreign to be timed separately

    Steps in Work Measurement (Contd.)

    Di id th j b i t l t Th di i i f

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    127/178

    Divide the job into elements. The division ofjobs is necessary for the following reasons.

    1. Provide better understanding.

    2. Break the study into manageable size.

    3. Workers efficiency thorough out job.

    4. Distinguish between various parts.5. Isolate man and machines.

    Time the elements. Stop watch is generally used in thesystem. Either of continuous or Fly-back method is used for

    recording time.

    Ex: Dividing Drilling into elements1. Selecting the work piece and

    placing it in jig.2. Tightening the screw3. Advancing the drill towards

    the work piece4. Drilling5. Withdrawing the drill from the

    operation6. Loosening the screw7. Removing piece from jig8. Removing the chips

    The number ofcycles to be timed. There should besufficient readings to get reasonably accurate results It depends

    Steps in Work Measurement (Contd.)

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    128/178

    sufficient readings to get reasonably accurate results. It dependson

    1. Variation in times of element.2. Degree of accuracy required.

    3. Prescribed level of confidence.

    Rating ofoperator.RATING is gauging and comparing the

    pace or the performance of a worker against a STD performancelevel set by the TS Engineer.

    Objective rating. Here emphasis is laid on speed anddifficulty experienced in performing a job. At first operator is rated

    on normal speed and movement. Then other factors are

    considered. (based on (i) the amount of body used (ii) foot movement involved (iii) eye-hand coordination(iv) weight moved or lifted (v) handling requirements etc.).

    Allowances.

    Amount of work that can be produced by a qualified employee when working

    t l d ff ti l tili i hi ti h k i t t i t d b

    A FAIR DAY'S WORK

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    129/178

    at normal pace and effectively utilizing his time where work is not restricted by

    process limitations.

    Qualified Worker is one who is accepted as having the necessary physical

    attributes, who possesses the required intelligence and education, and has

    acquired the necessary skill and knowledge to carry out the work in hand to

    satisfactory standards of safety, quantity and quality. (Choose the operator

    among many doing the job under study).

    It is the rate of output which qualified workers will naturally achieve

    without over-exertion as an average over the working day or shift,provided that they know and adhere to the specified method and

    provided that they are motivated to apply themselves to their work.STANDARD RATING

    Rating is the assessment of the worker's rate of working relative to the

    observers' concept of the rate corresponding to standard pace.

    STANDARD PERFORMANCE

    FACTORS AFFECTING RATE OF WORKING

    (outside the control of worker)

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    130/178

    ( )

    1. Variation in the quality of materials used

    2. Changes in the operating efficiency of the equipment

    3. Changes in climatic and surrounding conditions of operation.

    FACTORS WITHIN THE CONTROL OF WORKER

    a. Acceptable variations in the quality of the product

    b. Variations due to his ability

    c. Variations due to his attitude

    Thus, rarely the time taken to perform an element of operation by the operator is

    constant from piece to piece of the job. Therefore, enough cycles are to be timed to

    get representative time of each element.

    No. of Observations required, = (()

    Ifaccuracy level required is 10% the co-eff is 20; for5% it is 40; for2.5% it is 80.

    Where, N = actual No. ofobservations taken in pilot study.

    And x = each observed

    elemental time

    R ti f t

    SCALES OF

    RATING

    100-133

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    131/178

    Rating factor

    The figure 100 represents standard performance.

    If the operator is apparently performing with less effective

    speed, than the assigned factor is less than 100.

    If, on the other hand, the effective rate of working is abovestandard, the operator gets a factor above hundred.

    Essential idea being:

    Observed time x Rating = Constant

    60-80

    75-100

    0-100

    Performance Rating

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    132/178

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    133/178

    (this 100 is Standard rating)

    10. Calculating standard time of the job

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    134/178

    Constituents of Standard TimeBasic constituents of Standard Timeare:

    Elemental times (Observed

    times)

    Compensation for the

    difference in operatives pace ofperformance and standard

    performance.

    Relaxation allowance

    Interference and Contingency

    allowances

    Policy allowance

    Normal Time

    Total

    Allowance

    Standard

    Time

    Relaxation

    Allowance

    Policy

    Allowance

    Interference

    Allowance

    Contingency

    Allowance

    Fatigue

    Allowance

    Personal

    Needs

    Allowance

    Standard Time

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    135/178

    Normal or Basic Time of elements of the job when

    added, gives BASIC TIME of the job. Becausenobody can work continuously some additional time

    (given as allowances) is required to be added to

    Basic Time to arrive at Standard Time.

    Standard Time is calculated by taking the NormalTime and adding allowances for Personal Needs,

    Fatigue, Contingency, Interference etc.

    = Observed Time

    Or

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    136/178

    =

    Performance Rating

    The expression of ten used in practice for Standard Time is:

    = Normal Time ( 1 + )

    Some times the allowances are allowed to be applied to the total work

    period, then

    =

    ( )

    Illustrated Examples

    An industrial operation consists of Ele Observe Performan Normal or

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    137/178

    An industrial operation consists of

    FIVE elements with following

    observed times and the performance

    ratings:

    Assuming rest and personalallowances as 15% and contingency

    allowance as 2% of the basic time,

    calculate standard time per piece.

    Element Observed

    Time (Min.)

    Performance

    Rating (%)

    A 0.20 85

    B 0.08 80

    C 0.50 90

    D 0.12 85

    E 0.10 80

    me

    nt

    d Time

    (Min.)

    ce Rating

    (%)

    Normal or

    Basic Time

    (Min)

    A 0.20 85

    B 0.08 80 0.064

    C 0.50 90 0.450

    D 0.12 85 0.102

    E 0.10 80 0.080

    0.866

    Standard Time computation of an ordinary manual operation:An operator working on a Pillar Drill performed the following elements for which the

    observed times and ratings are given hereunder:

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    138/178

    (i)Calculate normal time of each element and normal time of the job,

    (ii) Also calculate standard time of the job.

    Element

    Code

    Element Description Obseved

    Time

    Rating Relaxation

    allowance

    A Position job into a drill jig 0.20 80 11%

    B Switch on the M/c & lower drill 0.008 100 11%

    C Drill hole 2.20 90 13%

    D Raise drill and switch off M/c 0.05 80 11%

    E Remove job from jig 0.10 110 11%

    Element

    Code

    Element Description Obsd

    Time

    Rating Relaxa

    allowan

    Work content/

    Std time

    A Position job into a drill jig 0.20 80 11% 0.1776

    B Switch on the M/c & lower drill 0.008 100 11% 0.0888

    C Drill hole 2.20 90 13% 2.2374

    D Raise drill and switch off M/c 0.05 80 11% 0.0444

    E Remove job from jig 0.10 110 11% 0.1221

    Standard Time of the Job 2.6703 min

    A cylindrical grinding operation involves elements detailed below along with theirrelated data:

    Elemen

    t code

    Element description Obsrd

    time

    Rati

    ng

    Remark Assuming rest & personal allowance as

    13% and contingency allowance as 2%,

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    139/178

    A Pickup job &tighten carrier

    0.2 90 --

    B Position untilbetween centres 0.05 80 --

    C Advance wheel tojob

    0.03 100 --

    D Grindto size 0.78 100 --

    E Spark off 0.06 100 --

    F Withdraw wheel toclear job

    0.05 100 --

    G Measure 0.02 85 Once in5 pieces

    H Release job frombetween cetres

    0.06 80 --

    I Loosen carrier &keep the job aside

    0.10 90 --

    J Dress wheel 0.04 90 Once in20 jobs

    3% a d co ge cy a o a ce as %,

    calculate standard time of the job.

    Solution:

    Eleme

    nt

    Obsd

    time

    rating Norm

    al

    time

    freq NT/

    cycle

    Tota

    l

    Allo

    Work

    content

    / cycle

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    140/178

    w

    A 0.20 90 0.18 1 0.18 15% 0.207

    B 0.05 80 0.04 1 0.04 15% 0.046

    C 0.03 100 0.03 1 0.03 15% 0.0345

    D 0.78 100 0.78 1 0.78 15% 0.897

    E 0.06 100 0.06 1 0.06 15% 0.069

    F 0.05 100 0.50 1 0.05 15% 0.0575

    G 0.20 85 0.17 1/5 0.034 15% 0.0391

    H 0.06 80 0.048 1 0.048 15% 0.0552

    I 0.10 90 0.09 1 0.09 15% 0.1035

    J 0.40 90 0.36 1/20 0.018 15% 0.0207

    1.330 1.5295

    Standard time computation when Stop Watch

    readings are given:

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    141/178

    A time study was conducted on a job consisting of three

    elements. The stop watch readings of the first five cycles using

    cumulative timing method are given below:

    The rating factors were estimated at 80, 100, 110 for the threeelements respectively (on the rating scale of 100 corresponding to

    normal performance). The allowance for personal needs, rest etc.

    amount to 12%. Calculate the standard time for the job.

    ELEME

    NT

    STOP WATCH READINGS in hundredth of a minute

    1 2 3 4 5

    A 10 73 139 203 266

    B 25 88 155 218 280

    C 64 128 193 257 320

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    142/178

    Eleme

    nt

    Elemental Individual time

    (centiminutes)

    Ave. time of

    elements

    (Min)

    Rating Normal

    (or

    Basic)

    time

    Allowances Work

    Content

    1 2 3 4 5

    A 10 09 11 10 09 0.098 80 0.0784 12% 0.0878

    B 15 15 16 15 14 0.150 100 0.1500 12% 0.1680

    C 39 40 38 39 40 0.392 110 0.4312 12% 0.4829

    0.7387

    Uses of time standards

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    143/178

    To provide information on which the planning and

    scheduling of production can be based, including theplant and labor requirements for carrying out the program

    of work and utilization of resources.

    To provide information on which estimates for tenders,

    selling prices and delivery promises can be based. To set standards of machine utilization and labor

    performance which can be used for incentive scheme.

    To provide information for labor-cost control and to

    enable standard costs to be fixed and maintained.

    Work /Activity Sampling

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    144/178

    For long cycle operations and for activities where Time Study

    is not possible, Work Sampling is applied. Ex. Office work,supervisory work, activities in stores etc.

    The second common technique for measuring a job is called

    Work Sampling. It involves observing a portion or sample of

    work activity and based on the findings of this sample,statements can be made about the activity.

    The time it takes to make an observation depends on what is

    being observed. Many a times only a glance is needed todetermine the activity and majority of studies require only

    several seconds of observation.

    Work Sampling

    W k S li i t h i i hi h l b f

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    145/178

    Work Sampling is a technique in which a large number of

    instantaneous observations are made over a period of time of a

    group of machine, processes or people. Work sampling is a

    method of finding the percentage occurrence of a certain activity

    by statistical sampling and random observations.

    Each observation records what is happening at that instant and the

    percentage of observations recorded for a particular activity or

    delay is a measure of thepercentage of time during which that

    activity or delay occurs. (Also known as Activity Sampling, RatioDelay Study,

    ObservationRatio Study, SnapReading Method and Random Observation Method)

    Work sampling is a method of finding the percentage occurrence of a certainactivity by statistical sampling and random observations.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    146/178

    Work sampling is the process of making sufficient random observations of anoperators activities to determine the relative amount of time the operatorspends on the various activities associated with the job.

    The major goal of work sampling is to determine how long, or how much ofthe work day, is spent on specific types of work.

    Work sampling may identify the fact that certain operators spend a largeportion of their time waiting for work, or performing paperwork tasks, or evenperforming activities that are not included in their job descriptions.

    One of the basic foundations of statistical sampling theory is the concept thatthe larger the sample size, the results will be more accurate.

    In work sampling, a sufficient number of observations must be made to be surethat the results accurately summarize the work performed. There are statisticalformulas to help determine how many observations should be made.

    Number of observations in Work Sampling One of the basic foundations of statistical sampling theory is the

    concept that the larger the sample size, the results will be more

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    147/178

    p g paccurate.

    In work sampling, a sufficient number of observations must be madeto be sure that the results accurately summarize the work performed.There are statistical formulas to help determine how manyobservations should be made.

    For 95 % accuracy (confidence level)

    Sp = 2 { p (1p) / N }

    Sp is significance level, p is extent of the phenomenon (problem) being

    observed in a pilot studyexpressed as decimals, and N is totalnumber of observations.

    N is then divided into number of machines, days, operators, etc.

    A few words about sampling

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    148/178

    Sampling is mainly based on probability. Probability has been defined asthe degree to which an event is likely to occur.

    A simple and often-mentioned example that illustrates the point is that oftossing a coin.

    The law of probability says that we are likely to have 50 heads and 50 tailsin every 100 tosses of the coin. The greater the number of tosses, the morechance we have of arriving at a ratio of 50 heads to 50 tails.

    The size of the sample is therefore important, and we can express ourconfidence in whether or not the sample is representative by using a certainconfidence level.

    Establishing confidence levels

    Let us go back to our previous example and toss five coins at a time, andthen record the number of times we have heads and the number of times wehave tails for each toss of these five coins. Let us then repeat this operation100 times.

    Using Work Sampling

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    149/178

    Make tours of observations on representative of normal

    working days

    Tours should be carried out in random intervals, random

    numbers could be generated to decide on the order

    Familiarity of the observer with the process is not critical,

    though beneficial.

    CONDUCTING A STUDY

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    150/178

    It is recommended that a uniform procedure should be

    followed to perform a work sampling study is to

    1. Establish the Purpose

    First, the objective of the study should be established. Worksampling can be used to determine an overall perspective onthe work done.

    2. Identify the Subjects

    Second, the people performing the task must be identified, i.e.general office work is being studied with the objective of determining overall productivity.

    3. Identify the Measure of Output

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    151/178

    The third step in making the study is the identification of the

    measure of the output produced or the types of activities performedon the jobs being studied. This step is especially important if theobjective of the study is to measure productivity with the intent of

    setting a standard.

    4. Establish a Time Period

    Fourth, the time period during which the study will be conductedmust be established. Starting and stopping points for the study must

    be defined as well.

    5. Define the Activities

    This step involves defining the activities that are performed by thepeople under study. For example, the definition used in a machineutilization study, including only the categories of working, idle, and

    idle-mechanical breakdown.

    6. Determine the Number of Observations Needed

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    152/178

    After the work elements are defined, the number of observations for

    the desired accuracy at the desired confidence level must bedetermined. If a reasonable guess cannot be made, then a trial studyof perhaps 20 to 40 observations should be made to get an estimate.

    7. Schedule the Observations

    Once the number of required observations has been determined,either from appropriate statistical calculations or from tables, and theactual observations must be scheduled. Typically, the analyst willassign an equal number of observations each day during the course ofthe study. For example, if 800 observations are required and 20 workdays are established as an appropriate observation time, 40

    observations should be recorded each day. A random number table can be used to establish the random times foreach observation.

    8. Inform the Personnel Involved

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    153/178

    Before the study is actually performed, the personnelinvolved should be informed about the objective of the studyand the methodology that will be employed.

    9. Record the Raw Data

    The next is the actual recording of the raw data. Althoughthis recording can be performed by anyone, it is desirablethat a trained analyst be employed.

    It is also very important that the observations be made atexactly the same location every time.

    10. Summarize the Data After the data have been collected, they must be

    summarized.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    154/178

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    155/178

    To make things easier, it is more convenient to speak of a 95 per cent confidence level than of a95.45 per cent confidence level.

    To achieve this we can change our calculations and obtain: 95 per cent confidence level or 95 per cent of the area under the curve = 1.96 p

    99 per cent confidence level or 99 per cent of the area under the curve = 2.58 p

    99.9 per cent confidence level or 99.9 per cent of the area under the curve = 3.3 p

    In this case we can say that if we take a large sample at random we can be confident that in 95per cent of the cases our observations will fall within 1.96 p

    Number of Samples

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    156/178

    Number of Samples

    Confidence interval

    Probability that true

    proportion will fall

    within confidence interval

    p- e p+ ep

    e= zp(1 - p)

    n

    Number of Samples

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    157/178

    Number of Samples

    n= p(1 - p) z 2

    e

    DesiredConfidence (%) z

    90 1.65

    95 1.96

    96 2.05

    97 2.1798 2.33

    99 2.58

    n = required sample size

    p = estimate of proportion time an activity takes place

    z = number of standard deviations for desired confidence

    e = maximum error allowable

    Determination of sample size

    As well as defining the confidence level for our observations we have to decide onthe margin of error that we can allow for these observations.

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    158/178

    Let us look at our example about the productive time and the idle time of the

    machines in a factory. There are two methods of determining the sample size thatwould be appropriate for this example:

    the statistical method and the nomogram method.

    Statistical method. The formula used in this method is:

    Let us assume that some 100 observations were carried out as a preliminarystudy and at random, and that these showed the machine to be idle in 25 percent of the cases (p = 25) and to be working 75 per cent of the time (q = 75).

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    159/178

    We thus have approximate values for p and q; in order now to determine thevalue of n.

    Let us choose a confidence level of 95 per cent with a 10 per cent margin of error (that is, we are confident that in 95 per cent of the cases our estimateswill be 10 per cent of the real value).

    E = z p Since E= 10

    And Z = 1.96

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    160/178

    Nomogram methodAn easier way to

    determine sample size is to

    read off

    the number of observations

    needed directlyfrom a nomogram

    such as the one reproduced

    in figure 91.

    Making random observations

    To ensure that our observations are in fact made at random, we can use a

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    161/178

    To ensure that our observations are in fact made at random, we can use arandom table such as the one in table 12.

    Various types of random table exist, and these can be used in different ways. Inour case let us assume that we shall carry out our observations during a dayshift of eight hours, from 7 a.m. to 3 p.m. An eight-hour day has 480 minutes.These may be divided into 48 ten-minute periods.

    We can start by choosing any number at random from our table, for example

    by closing our eyes and placing a pencil point somewhere on the table. Let usassume that in this case we pick, by simple chance, the number 11 which is inthe second block, fourth column, fourth row (table 12).

    We now choose any number between 1 and 10. Assume that we choose thenumber 2; we now go down the column picking out every second reading andnoting it down, as shown below (if we had chosen the number 3, we should pick

    out every third figure, and so on).

    11 38 45 87 68 20 11 26 49 05

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    162/178

    Looking at these numbers, we find that we have to discard 87, 68 and 49 because theyare too high (since we have only 48 ten-minute periods, any number above 48 has to bediscarded).

    Similarly, the second 11 will also have to be discarded since it is a number that hasalready been picked out. We therefore have to continue with our readings to replace thef i i i i

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    163/178

    four numbers we have discarded. Using the same method, that is choosing every secondnumber after the last one (05), we now have 14 15 47 22

    These four numbers are within the desired range and have not appeared before. Ourfinal selection may now be arranged numerically and the times of observationthroughout the eight-hour day worked out. Thus our smallest number (05) representsthe fifth ten-minute period after the work began at 7 a.m. Thus our first observation willbe at 7.50 a.m., and so on (table 13).

    Example: Conducting the study

    Determining the scope of the study. Before making our actual observations, it is

    important that we decide on the objective of our work sampling.

    Th i l t bj ti i th t f d t i i h th i hi i idl

  • 5/27/2018 Work Study Slides IM EEE Chem 13

    164/178

    The simplest objective is that of determining whether a given machine is idle or

    working. In