work study slides im eee chem 13
DESCRIPTION
chemicalTRANSCRIPT
-
5/27/2018 Work Study Slides IM EEE Chem 13
1/178
Productivity
Ratio between output and input.
Output : desired
Input : Man, machine, material, etc.
-
5/27/2018 Work Study Slides IM EEE Chem 13
2/178
Concept of Work Content
BASIC Work Content: is the minimum time
theoretically required to do a job or operation. This cannot bereduced. This results only if (i) the design and the
specifications are perfect, (ii) process of manufacture is
exactly followed and (iii) no loss of working time occurs due
to any reason.
The actual time required to complete an operation or job is
more than the basic time in practical situations. This additional
portion is called the excess work content.
The amount of work contained in a given job is referred
to as work content and is measured in man-hours or machine-hours.
-
5/27/2018 Work Study Slides IM EEE Chem 13
3/178
Reasons for Excess Work Content
A. Work content added due to defects in
design or specs of a product
i. Bad design of product
ii. Lack of standardisation of components
iii.Incorrect specs & quality standardsiv.Faulty design of components
B. Work content added due to
inefficient methods of manufacture
i. Improper selection of manufacturing
process/machine
ii. Wrong selection of tools
iii.Improper layout of the shop/factory
iv.Inefficient methods of material handling
C. Ineffective time added due to
shortcomings of management
i. Bad working conditions, ii) frequent prod.
Interruptions due to breakdown, iii)poor prod.
planning and control, iv) lack of safety
measures, v) lack of quality mindedness, vi)
lack of instruc-tion vii) frequent changes in set-
ups, viii) lack of performance standards, ix)
shortage of materials / tools.
D. Ineffective time added due to reasons
attributed to workmen
i. Unauthorised absence from work, ii)substandatd performance, iii) careless-ness in
working, iv) unnecessary wastage of time /
idleness.
-
5/27/2018 Work Study Slides IM EEE Chem 13
4/178
Productivity
Productivity of man
Total timeof operation
under
existing
conditions
Basic Work Content
of product and / or
process
Work Content added by
defects in design of
product or process
Work Content added by
inefficient methods of
operations
Ineffective Time due tomanagement problems
Ineffective Time within
control of workers
-
5/27/2018 Work Study Slides IM EEE Chem 13
5/178
Productivity
Productivity of man
Bad design of product
Lack of standardization
Incorrect Quality Standards
Excess Material
Wrong Machine
Incorrect Processes operation
Wrong Tools
Bad Layout
Wrong Working method
-
5/27/2018 Work Study Slides IM EEE Chem 13
6/178
ProductivityProductivity of man
Excessive Product Variety
Lack of Standardization
Design Changes
Wrong / Lack of Planning
Unavailability of Raw
Material
Plant Breakdown
Bad Plant Condition
Bad Working Condition
Accidents
Absence, Late coming and / or
Idleness
Careless Workmanship
Accidents
-
5/27/2018 Work Study Slides IM EEE Chem 13
7/178
Techniques to reduce Work Content
A. Mngt technique to reduce work contentdue to product
i. Product development,
ii. standardisation,
iii. value analysis,
iv. market/consumer research
B. Mngt technique to reduce work contentdue to process/ methods
i. process planning ,
ii. method study
C. Mngt techniques to reduce ineffectivetime due to shortcomings ofmanagement
Product standardisation andsimplification, productspecialisation, iii) standardisation of
components, iv) production planning& control, v) materials control, vi)plant maintenance, vii) safetymeasures and improved workingconditions.
D. Mngt techniques to reduce ineffectivetime within the control of the workers
i) sound personnel policies, ii)Operators training, iii) safetytraining, iv) financial incentives.
The important functions of production management are setting up most
effective method of performing the operation and control the effective
utilisation of resources.
-
5/27/2018 Work Study Slides IM EEE Chem 13
8/178
Direct means of raising productivityApproach Type of
Improvement
Means Cost How quickly
results be
achieved?
Extent of
improvement
in
productivity
Role of Work
Study
Capital
Investment
Development
of new basic
process or
fundamental
improvement
of exiting one
Basic or
Applied
research,
pilot plant
High Generally
years
No obvious
limit
Method Study to
improve ease of
operation and
maintenance at
design stage
CapitalInvestment
Install moremodern or
higher
capacity plant
or Eqpt. Or
modernise
existing plant
Purchaseprocess
research
High Immediatelyafter
installation
No obviouslimit
Method study inPlant Layout and
to improve ease of
operation when
modernising
BetterManagemen
t
Reduction inWork Content
of the Product
ProductResearch,
developme
nt
Qlty Mngt
Method
study
valure
analysis
Not highcompare
to (1)
and (2)
above.
Generallymonths
Limitedofthe same
order as that
to be expected
from later
Method Study(and its extension
value analysis) to
improve design
for ease of
production
-
5/27/2018 Work Study Slides IM EEE Chem 13
9/178
Better
Management
Reduce work
content of the
process
Process
research, pilot
plant, process
planning,
Method study,
value analysis
Low Immediate Limited, but
often of a
high order
Method study to
reduce wasted
effort and time in
operating the
process by
eliminating
unnecessary
movement
Better
Management
Reduce
ineffective
time (due to
Management
or workers)
Work
measurement
Standardisatio
n, product
development,
PPC, material
control,
planned
maintenance,
personnelpolicy,
operator
training,
incentive
scheme
Low May start slowly
but effect grows
quickly
Limited, but
often of a
high order
Work
Measurement to
investigate
existing practice,
locate ineffective
time and
standards of
performance as a
basis for: a)
Planning &Control, b)
Utilisation of
Plant, c) Labour
cost control, d)
Incentive scheme
-
5/27/2018 Work Study Slides IM EEE Chem 13
10/178
Management approach to deal with Productivity
To eliminate the excess work content To reduce the ineffective time
The technique is known as Work Study.
Work study can be defined as the analyticinvestigation of the methods, conditions andeffectiveness of industrial work and therebythe determination of the ways in whichhuman efforts may most economically beapplied.
-
5/27/2018 Work Study Slides IM EEE Chem 13
11/178
Definitions.
Work Study is primarily concerned withdiscovering the best ways of doing the joband establishing standards based on suchmethods.
Work study is the technique of Methodstudy and work measurement employed to
ensure the best possible use of human andmaterial resources in carrying out aspecified activity. -ILO
-
5/27/2018 Work Study Slides IM EEE Chem 13
12/178
WORK STUDY.
Its a Mgt tool to achieve higher efficiency. Itprovides us a scientific approach to investigate intoforms of work with a view to increase productivity.
Concerned primarily with manual work Any industry to survive, must use latest technology &
most efficient method, improvised with a consistentaim of producing best quality goods at lower prices.
One way to improve is by efficient use of plant,equipment and Labor.
-
5/27/2018 Work Study Slides IM EEE Chem 13
13/178
Work Study aims at improving the existing and proposed ways of doing
work and establishment of standard time for work performance.
Work Study is the most effective tool to enhance productivity because
of the fact that it is a straight forward way of increasing the productiveefficiency of the organisation and also considers all the factors
influencing productivity.
Work Study comprises of method study and work measurement.
-
5/27/2018 Work Study Slides IM EEE Chem 13
14/178
WORK STUDY
Work study is simply study of work.
It is analysis of work dividing it into smallerparts followed by rearrangement of these parts
to give the same effectiveness at a lesser cost. Work study examines both the method and
duration of the work involved in the process.
Work study is a powerful tool for simplificationof work Robert Owen, Taylor and Bedeaux gave their contributions to this topic.
-
5/27/2018 Work Study Slides IM EEE Chem 13
15/178
Work study and the Worker
Why workers resist the work study:
It will change their familiar work methods.
Many workers resent being timed.
Fear of being fired.
Wh i W k S d ?
-
5/27/2018 Work Study Slides IM EEE Chem 13
16/178
What is Work Study? Production system focuses on increasing the efficiency by
maximizing the output per hour of employee effort.
The important functions of Production Management are setting upthe most effective method of performing the operations (std.method) and their control for effective utilization of resources.
Work Study (WS) is one of the most important managementtechniques which is employed to improve the activities inproduction. It provides a scientific approach to investigate into allforms of work, with a view to increase productivity.
The main objective of WS is to assist the management in the
optimum use of the human & material resources.
Main aim of this WS is to finding the best & most efficient way ofusing available resources i.e. men, material, money & machinery.
-
5/27/2018 Work Study Slides IM EEE Chem 13
17/178
What is Work Study? It is especially concerned with productivity. To increase
the productivity from a given quantity of resources.
Workstudy is ageneric term for thetechniquesofmethod study and work measurement. Thesetechniques are used in the examination of human
workinallitscontexts.Theyleadsystematicallytotheinvestigation of all the factors which affect theefficiencyandeconomyattheworkplaceinordertoaffectimprovement.
Work Study is the systematic examination of themethods of carrying on activities so as to improve theeffective use of resources and to set up standards ofperformance for the activities being carried out.
C f W k S d
-
5/27/2018 Work Study Slides IM EEE Chem 13
18/178
Components ofWork Study
It has threeaspects
1. More effective use of plant & equipment
2. More effective use of human effort3. Evaluation of human work
-
5/27/2018 Work Study Slides IM EEE Chem 13
19/178
Work Study - Basic Procedure8 step process
RECORD
EXAMINE
DEVELOP
MEASURE
DEFINE
INSTALL
MAINTAIN
SELECT
Most economical method
Job or process to be studied
All details concerning Job using various techniques
Recorded facts critically by asking questions
Amount of work involved & set
standard time to do the job
New method & standardtime
New method as a
standard practice
New method as
agreed standard
-
5/27/2018 Work Study Slides IM EEE Chem 13
20/178
Applications of work Study
Industries: production operations, research and development
Marketing: sales & distribution.
Offices: stores & warehouses.
Material handling
In designing field
Building & other construction
Transport
Hospital Army
Agriculture
-
5/27/2018 Work Study Slides IM EEE Chem 13
21/178
Advantages/ Objectives of Work Study
-
5/27/2018 Work Study Slides IM EEE Chem 13
22/178
METHOD STUDY
Method Study (MS) is the systematic recording and
critical examination of existing and proposed ways ofdoing work, as a means of developing and applying
easierand more effective methods and reducing costs.
MS aims at determining the most effective method of
performing the job, most logical layout of manufacturing
facilities, uninterrupted flow of materials throughout the
organization. It is concerned with reduction of work content
and establishing the one best way of doing the job.
MS is a collection of analysis techniques focusing onimproving the effectiveness of man and the machine.
-
5/27/2018 Work Study Slides IM EEE Chem 13
23/178
Method Study Methods engineering /work design
Breakdown of operation into components
Systematic analysis of each component
Eliminates un-necessary operations
It is systematic recording & examination of
existing methods of doing work and developing
more effective methods - BSIMS addresses three broad areas:
1. It is a diagnostic tool (location of faults)
2. It is a remedial tool (improve situation)
3. It is a constructive tool (set standards)
-
5/27/2018 Work Study Slides IM EEE Chem 13
24/178
Objectives of Method Study1. Improvement of manufacturing processes and procedures.
2. Improvement of working conditions.3. Improvement of plant layout and work place layout.
4. Reducing the human effort and fatigue.
5. Reducing material handling6. Improvement of plant and equipment design.
7. Improvement in the utility of material, machines and manpower.
8. Standardization of method.
9. Improvement in safety standard.
-
5/27/2018 Work Study Slides IM EEE Chem 13
25/178
Method Study
Method study is the technique of systematicrecording and critical examination of existing and
proposed ways of doing work and developing an
easier and economical method.
Method study examines the way a task (changing theclutch on a car, preparing a flower bed for planting,
cleaning a hotel room) is done. The industrial
engineer has an eye on operational efficiencies and
costs, quality of processes, service reliability, staffsafety etc. Method study techniques are applicable
from factory/workshop manufacturing to cabin crew
activities.
Method Study
Flow Chart
-
5/27/2018 Work Study Slides IM EEE Chem 13
26/178
Method Study Procedure
SELECT
RECORD
EXAMINE
DEVELOP
DEFINE
INSTALL
MAINTAIN
The work which can be studied with economic advantage
All relevant facts about the job / operation
The facts critically (purpose, place, sequence,person)
verify at regular intervals that the improved method is in use
Plan, arrange and implement the new method as Std.
method, procedure, layout, equipment, workingconditions, materials, quality, instructions
A record of improved method,
under prevailing conditions.
Reexamine and select the
best method
-
5/27/2018 Work Study Slides IM EEE Chem 13
27/178
BASIC PROCEDURE FOR METHOD STUDY
Thebasicprocedureforconductingmethodstudyisasfollows:
1.Selectthe work to be studied.
2. Record all facts about the method by directobservation.
3.Examinethe above facts critically.
4. Develop the most efficient and economic
method.5.Definethe new method.
6.Installthe new method as std. practice
7.Maintainthe new method by regular checking.
Method Study
Flow Chart
-
5/27/2018 Work Study Slides IM EEE Chem 13
28/178
Selecting the work to be studied
There are three factors that should be kept in mindwhile selecting a job for method study:
1. Economic or cost-effective considerations.
2. Technical considerations.
3. Human considerations.
1. Economic considerations:
It is obviously a waste of time to start or continue a
long investigation if the economic importance ofa job is small.
Questions that should always be asked are:
Will it pay to begin a method study of this job? Or
Will it pay to continue this study?
BASIC PROCEDURE FOR METHOD STUDY
Obvious choices for study are:
-
5/27/2018 Work Study Slides IM EEE Chem 13
29/178
Obvious choices for study are:
A. Keyprofit-generating or costly operations or ones with the largest
Scrap/waste rates.
B. Bottlenecks which are holding up other production operations, or
lengthy operations that consume a great deal of time. C. Operations involving repetitive workusing a great deal of labour
and ones that are likely to run for a long time.
D. Movements of material over long distancesbetween workstations,
those involving the use of a relatively large proportion of labor or
which require repeated handling of material.
SelectPossible Results:
* Increased production rate * Reduced cost
* Less labor, materials, or equipment * Improved quality
* Improved safety * Reduced scrap
* Improved standards of cleanliness
One of the easiest techniques that can be used to identify key operations aslisted in part (A) is the Pareto analysis (sometimes also referred to as theABC analysis of value analysis).
The same observation can be extended by saying that among all theoperations in a given plant a small number account for the largest share of
cost or ofprofit, or the largest percentage ofwaste.
-
5/27/2018 Work Study Slides IM EEE Chem 13
30/178
To illustrate the point we will consider the following example.
Let us assume that a certain enterprise produces 20 different products. Eachof these products generates a certain profit.
By listing the annual production and profit contribution one obtains theresults shown in table 6.
The next step consists of rearranging these items in descending order ofimportance according to profit. The result would then appear like the oneshown in table 7.
From table 7 it can be seen that three products only, listed as A items,
account for 60 per cent of the profit. These are the most profitable and any improvement in methods of
producing these particular products would reflect highly on profits. Theywould be a priority for study.
Products listed under B, which are seven in number, contribute 25 percent of the profit. They could then assume a second importance, while
products C would command the last priority since their contribution toprofit is minimal. The same type of analysis can be conducted to determine the most costly
products or processes or the products or processes that yield the highestwaste.
Those would then become a priority for study by the work study specialist.
-
5/27/2018 Work Study Slides IM EEE Chem 13
31/178
-
5/27/2018 Work Study Slides IM EEE Chem 13
32/178
St d d Li t f i t t b d h l ti
-
5/27/2018 Work Study Slides IM EEE Chem 13
33/178
1. Product and operation
2. Person who proposes investigation
3. Reason for proposal
4. Suggested limits of investigation
5. Particulars of the job
a) How much is produced or handled per week?b) What percentage is this of the total produced or handled in the shop or plant?
c) How long will the job continue?
d) Will more or less be required in future?
e) How many operatives are employed on the joba) Directly
b) Indirectly
f) How many operatives are there in each grade and on each rate of pay?
g) What is the average output per operative (per team) per day?
h) What is the daily output compared with the output over a shorter period (an hour)?
i) How is payment made? (team-work, piece work, premium bonus time rate, etc.)
Standard List of points to be covered when selecting
a job for Method Study(Sample list which needs to be adapted to individual needs)
-
5/27/2018 Work Study Slides IM EEE Chem 13
34/178
Standard List of points to be covered when selecting a job for Method Study
(contd.2)
j) What is the daily output
a) Of the best operative?
b) Of the worst operative?
k) When were production standards set?
l) Has the job any especially unplesant or injurious features? Is it
unpopular (a) with workers, (b) with supervisors?
6. Equipment
a) What is the approximate cost of plant and equipment?
b) What is the present machine utilisation Index?
7. Layout1. Is the existing space allowed fo the job enough?
2. Is extra space available?
-
5/27/2018 Work Study Slides IM EEE Chem 13
35/178
8. Product
1. Are the frequent design changes causing modifications?
2. Can the product be altered for easier manufacture?
3. What quality is demanded?4. When and how is the product inspected?
9. What savings or increase in productivity may be expected from a
method improvement?
a) Through reduction in the work content of the product or process.
b) Through better machine utilisation.
c) Through better utilisation of labour.
Standard List of points to be covered when selecting a job for Method Study
(contd. 3)
2. Technical or technological considerations:
-
5/27/2018 Work Study Slides IM EEE Chem 13
36/178
gOne of the important considerations is the desire by management to acquiremore advanced technology, i.e. in equipment or in processes.
Therefore, management may want to computerize its office paperwork or itsinventory system, or to introduce automation in the production operations.
Before such steps are taken, a method study can point out the most importantneeds of the enterprise in this respect.
The introduction of new technology should therefore constitute an importantfactor in the choice of methods of work to be investigated.
Based on the technical knowledge of the process
Jobs having inconsistent quality, Operations generating lot of scrap, Frequentcomplaint from workers, Extensive paperwork, Repetitive work (automation),
Hazardous work etc.
3. Human considerations: Most difficult to foretell, because of mental andemotional nature.
Certain operations are often a cause of dissatisfaction by workers.
Select an unpopular job - That may bring on fatigue or monotony or may beunsafe to operate or inconsistent earnings.
The level of satisfaction should point to a need for method study. In a similarfashion, a choice of a particular job for study may lead to anxiety or ill feeling.
The suggestion given here is to leave it alone.
-
5/27/2018 Work Study Slides IM EEE Chem 13
37/178
2. Record:All the details about the existing method are recorded. This isdone by directly observing the work. Records are useful for BEFORE
and AFTER comparison to assess effectiveness of proposed method.
Recording techniques are designed to simplify & standardize recording
work.
COMMONLY USED RECORDING TECHNIQUES
1. Outline Process Charts
2. Flow Process Chart
3. Two Handed Process Chart
4. Multiple Activity Chart
5. Simo Chart
6. Flow Diagrams
7. String Diagrams
8. Cyclegraph
9. Chronocyclegraph
10. Travel Chart
Man Type
Material Type
Equipment Type
USING TIME SCALE
-
5/27/2018 Work Study Slides IM EEE Chem 13
38/178
Typical Industrial problems and appropriate method study
technique
Type of Job Examples Recording Technique
Complete sequence of
manufacture
Manufacture of an electric
motor from raw material to
dispatch
Outline Process Chart
Flow Process Chart
Flow Diagram
Factory Layout: Movement
of materials
Movement of diesel engine
cylinder head through all
machining operations
Outline Process Chart
Flow Process Chart (Mat)
Flow Diagram
Travel Chart, Models
Factory Layout: Movement
of Workers
Cooks preparing meals in a
restaurant kitchen
Flow Process Chart (Men)
String diagram
Travel Chart
Handling of Materials Putting materials into &
taking them out of stores
Flow Process Chart (Mat)
Flow DiagramString diagram
Workplace layout Light assembly work on a
bench
Flow process Chart (Man)
Two handed process Chart
Multiple activity Chart
Simo Chart, Cyclegraph
-
5/27/2018 Work Study Slides IM EEE Chem 13
39/178
Type of Job Examples Recording Technique
Automatic machine
operation
Assembly line, operator
looking after semi-automatic lathe
Multiple activity chart
Flow Process Chart (Eqpt)
Movement of operatives at
work
Female operatives on short-
cycle repetition work
Films, Film analysis,
Simo Chart
Memotion photography
Micromotion analysis
Typical Industrial problems and appropriate method study technique
Symbols are used to represent the activities like operation, inspection,
transport, storage and delay.
Grouping of activities: Five sets of activities can be grouped in two
categories
Those in which something actually happens to the work-piece (it is
moved, worked upon orexamined)
Those in which it is not being touched (in storage or in delay)Objective is to maximize proportion of do activities.
All other activities, however necessary, are considered non-productive
BASIC PROCEDURE FOR METHOD STUDY
-
5/27/2018 Work Study Slides IM EEE Chem 13
40/178
3. Examine: Critical examination is done by questioning
technique. This step comes after the method is recorded by
suitable charts and diagrams. The individual activity is
examined by putting a number of questions.
Critical examination is conducted wherein each activity, in turn, being
subjected to a systematic and progressive series of questions.
The questioning sequence used follows a well-established pattern
which examines:
the PURPOSE for which
The PLACE at which
The SEQUENCE in which the activities are undertaken.the PERSON by whom
the MEANS by which
-
5/27/2018 Work Study Slides IM EEE Chem 13
41/178
PRIMARY QUESTIONS
In the first stage of the questioning technique, the purpose, place,
sequence, person and means of every activity recorded are systematically
questioned, and a reason for each reply is required.
SECONDARY QUESTIONS
-
5/27/2018 Work Study Slides IM EEE Chem 13
42/178
SECONDARY QUESTIONS
The secondary questions cover the second stage of the questioning
technique, during which the answers to the primary questions are
subjected to further query to determine whether possible alternatives of
place, sequence, persons and means are practicable and preferred as a
means of improvement upon the existing method.
PURPOSEWhat else might be done?
What should be done?
PLACEWhere else might be done?
Where should be done?
SEQUENCEWhen else might be done?
When should be done?
PERSON Who else might be done?Who should be done?
MEANSHow else might be done?
How should be done?
These questions, in the above sequence, must be asked systematically every time
a method study is undertaken. They are the basis of successful method study.
-
5/27/2018 Work Study Slides IM EEE Chem 13
43/178
BASIC PROCEDURE FOR METHOD STUDY
4. Develop : Answer to the questions will result in thedevelopment of alternatives and of a better method. Develop
the most efficient and economic method.
Ex: Sending letters to customers.
5. Define:Once a complete study of a job has been made and a
new method is developed, it is necessary to obtain the
approval of the management before installing it. The work
study man should prepare a report giving details of the
existing and proposed methods, reasons for change,
advantages, limitations, savings expected, tools & equipment
required etc..
DEFINING THE IMPROVED METHOD
-
5/27/2018 Work Study Slides IM EEE Chem 13
44/178
DEFINING THE IMPROVED METHOD
The report should show:
1. Relative costs in material, labour and overheads of thetwo methods, and savings expected.
2. The cost of installing the new method, including thecost of new equipment and of re-laying out shopsor working areas
3. Executive actions required to implement the newmethod.
It should also give details regarding :
1. The tools and equipment to be used2. A description of the method
3. A diagram of the work place layout, jigs/fixtures etc.
BASIC PROCEDURE FOR METHOD STUDY
-
5/27/2018 Work Study Slides IM EEE Chem 13
45/178
BASIC PROCEDURE FOR METHOD STUDY
6. Install :This step is the most difficult stage in method study.
Here the active support of both management and trade union
is required. Here the work study man requires skill in gettingalong with other people and winning their trust.
a) Gaining acceptance of the change by the Management
b) Gaining acceptance of the change by the workers
c) Maintaining close contact with the progress of the job until satisfiedthat it is running as intended
7. Maintain:The work study man must see that the new method
introduced is followed. The workers after some time may slip
back to the old methods. This should not be allowed. The newmethod may have defects. There may be difficulties also. This
should be rectified in time by the work study man.
-
5/27/2018 Work Study Slides IM EEE Chem 13
46/178
Recording Techniques in
Method study
Outline processchart
Flow process
chart
Material type chart
Machine type chart
Two -Handed
process chart
Using a time scale
Multiple activity
chart
Simo chart
P.M.T.S. chartMan type chart
Indicating
Process
Sequence
Diagrams
indicating
movements
String Diagram
Flow Diagrams
Travel Chart
Chrono-cycle
Graph
Cycle Graph
S b l d i Ch t
-
5/27/2018 Work Study Slides IM EEE Chem 13
47/178
OPERATION:A large circle indicates operation. An operation takes place when there
is a change in physical or chemical characteristics of an object. Occurs when an object is
intentionally changed in one or more of its characteristics. An assembly or disassembly isalso an operation. When information is given or received or when planning or calculating
takes place it is also called operation.
Example: Reducing the diameter of an object in a lathe. Hardening the surface of an
object by heat treatment. Drilling, Painting, Chemical reaction, Data Entry, Cutting, Sorting,
etc.
INSPECTION:A square indicates inspection. Inspection is checking an object for its
quality, quantity or identifications.
Example:Checking the diameter of a rod. Examine the quantity or quality, read steam
gauge on boiler, detect the defectives. Counting the number of products produced. of an
object by heat treatment.
Symbols used in Charts
Symbols used in Charts contd.
-
5/27/2018 Work Study Slides IM EEE Chem 13
48/178
Symbols used in Charts contd.
STORAGE: An equilateral triangle standing on its vertex represents storage. Storage
takes place when an object is stored and protected against unauthorized removal.
Example:Raw material in the store room, finished products inventory, archived documents.
DELAY: A large capital letter D indicates delay. This is also called as temporary
storage. Delay occurs when an object or operator is waiting for the next activity. Occurswhen the immediate performance or the next planned action does not take place.
Example:An operator waiting to get a tool in the stores. Work pieces stocked near the
machine before the next operation. Work In Process inventory waiting to be processed,
Employee waiting for an elevator, Waiting for accumulation of a certain quantity for
packaging
TRANSPORTATION:An arrow indicates transport. This refers to the movement of an
object or operator or equipment from one place to another. When the movement takes
place during an operation, it is not called transport.Example:Moving the material by a trolley Operator going to the stores to get some tool,
Using elevator, carrying, moving with material handling devices
.
ASME Standard Symbols
-
5/27/2018 Work Study Slides IM EEE Chem 13
49/178
y
-
5/27/2018 Work Study Slides IM EEE Chem 13
50/178
Why Charts?
It gives a complete picture of what is being done andhelps to understand the facts and its relationship to oneanother.
Details on the chart must be obtained from directobservation. Should not be from memory.
Neatness and accuracy is important.
Increased value if following is included:
1. Product, equipment details (code#, drawing#)
2. Job or process being carried out
3. Location and time (date) of the study
4. Observers name
5. Chart reference number
(A) MACRO MOTION CHARTS
-
5/27/2018 Work Study Slides IM EEE Chem 13
51/178
(A) MACRO MOTION CHARTS
1.Operation Process Chart
Also called Outline process chart
Birds eye view of whole process
Records only major activities and inspections
Uses only two symbols i.e. operations & inspection
Constructed by placing symbols one below another
Uses
Visualize sequence of operations & inspections in process
Know where operations selected fits into the entire
process
OPERATION PROCESS / OUTLINE PROCESS Chart:
-
5/27/2018 Work Study Slides IM EEE Chem 13
52/178
OPERATION PROCESS / OUTLINE PROCESS Chart:Example : Manufacture of Electric Motor
1
4
7
Conventions followed in
preparing the chart
1. Write title at the top of the chart.
2. Begin the chart from the right handside top corner.
3. Represent the main component at
the right extreme.
4. Represent the sequence of
operations and inspections by their
symbols. Connect them by vertical
flow lines.5. Record the brief description of the
activity to the right side of the
symbols.
6. Note down the time for each activity
to the left of the symbol.
7. Number all operations in one serial
order. Start from the right hand top(from number 1).
8. Similarly number all inspections in
another serial order (starting from 1).
9. Continue numbering, till the entry of
the second component.
10. Show the entry of purchased parts
by horizontal lines.
4
7 11114
4
Record- Example
-
5/27/2018 Work Study Slides IM EEE Chem 13
53/178
Outline Chart
Face, turn, cut
Face opposite end
Dimension and finish
Straddle mill four flats
Remove burr
Final inspection of machining
Degreasing
Cadmium plating
Final check
Face both sides
Drill hole
Final check
Assemble and drill
Turn shank
Remove chip
Dimensions
Degreasing
Cadmium plating
Final check
Fit stop pin
Final check
Switch Rotor
Ex: Outline process chart of Plywood manufacture
-
5/27/2018 Work Study Slides IM EEE Chem 13
54/178
Ex: Outline process chart of Plywood manufacture
Record- Example
-
5/27/2018 Work Study Slides IM EEE Chem 13
55/178
Outline Chart
2. Flow Process Chart
-
5/27/2018 Work Study Slides IM EEE Chem 13
56/178
A flow process chart is a graphical representation of the sequence of all the
activities (operation, inspection, transport, delay and storage) taking place in a
process.
It is the detail version of outline process chart recording all the events.
Process chart symbols are used here to represent the activities.
Gives sequence of flow of work.
Constructed same as operation process chart
Three types1. Material type
(records how the material is handled or treated).
2. Man type
(records what the worker does).
3. Equipment type
(records how the equipment or machine is used).
Uses Reduce idle time and delays
Reduce distance travelled
Reduce production cycle time
To relocate inspection stages
1. The details must be obtained by directobservationcharts must not be based
on memory.2. All the facts must be correctly recorded.
3. No assumptions should be made.
4. Make it easy for future reference.
5. All charts must have the following details:
(a) Name of the product, material orequipment that is observed.
(b) Starting point and ending point.
(c) The location where the activities takeplace.
(d) The chart reference number, sheetnumber and number of total sheets.
(e) Key to the symbols used must bestated.
Ex: Machine/ Equipment Flow Process Chart: Biscuit Making
-
5/27/2018 Work Study Slides IM EEE Chem 13
57/178
Ex: Machine/ Equipment Flow Process Chart: Biscuit Making
Flow Process Chart - Example
-
5/27/2018 Work Study Slides IM EEE Chem 13
58/178
-
5/27/2018 Work Study Slides IM EEE Chem 13
59/178
Distance in
meter
Symbol Process description
10 Move to cabinet
- Get loaf of bread
- Remove two slices of bread
- Lay slices on table top
- Close loaf of bread
- Replace loaf on shelf
- Open butter
- Spread butter on top slice- Inspect sandwich
- Move to serving area
10 Serve sandwich
Ex: Process chart for making a Cheese Sandwich
-
5/27/2018 Work Study Slides IM EEE Chem 13
60/178
Ex: Flow Process ChartEmergency ward
1 X Enter emergency room, approach patient window2 X Sit down and fill out patient history
3 X Nurse escorts patient to ER triage room
4 X Nurse inspects injury
5 X Return to waiting room
6 X Wait for available bed
7 X Go to ER bed
8 X Wait for doctor
9 X Doctor inspects injury and questions patient
10 X Nurse takes patient to radiology
11 X Technician x-rays patient12 X Return to bed in ER
13 X Wait for doctor to return
14 X Doctor provides diagnosis and advice
15 X Return to emergency entrance area
16 X Check out
17 X Walk to pharmacy
18 X Pick up prescription
19 X Leave the building
0.50 1510.0 -
0.75 40
3.00 -
0.75 40
1.00 -
1.00 60
4.00 -
5.00 -
2.00 200
3.00 -2.00 200
3.00 -
2.00 -
1.00 60
4.00 -
2.00 180
4.00 -
1.00 20
Process: Emergency room admission
Subject: Ankle in jury pat ient
Beginning: Enter emergency roomEnding: Leave hospi ta l
Stepno.
Time(min)
Distance
(ft)
Summary
Number
of stepsActivity
Time
(min)
Distance
(ft)
Step description
Insert Step
Append Step
Remove Step
Transport 9 11 815
Operation 5 23
Inspect 2 8
Store
Delay 3 8
3.Two Handed Process Chart
-
5/27/2018 Work Study Slides IM EEE Chem 13
61/178
It is the process chart in which the activities of two hands of the operator are
recorded.
Motions of both hands of worker are Right hand-Left hand chart recorded
independently.
It shows whether the two hands of the operator are idle or moving in relation to
one another, in a timescale.
It is generally used for repetitive operations.
Confined to work carried out at a single workplace Visualize complete sequence of activities in repetitive task
Study work station layout
Operation:Represents the activitiesgrasp, position, use, releaseetc. of a tool, component or material.
Transport:Represents the movement of the hand or limb to or from the work or a tool or material.
Delay:Refers to the time when the hand or limb is idle.
Storage (Hold):The term holdis used here instead of storage to refer to the time when the work is held byhand.
The activityinspectionby hand is considered as an operation. Hence, the symbol for inspection is not usedin this
chart. Two-handed process chart can be used for assembly, machining and clerical jobs.
Ex: Two-Handed Process Chart
-
5/27/2018 Work Study Slides IM EEE Chem 13
62/178
Ex: Two Handed Process Chart
Summary of the number of each activity can be tabulated at the bottom of the chart. The chart is first drawn for the existing method.
This chart is analyzed and if it is found that one hand is over loaded than the other, modification are done in the layout of the
workplace or in the sequence of activities. Then a new chart is made for the proposed cycle. This assists in finding a better method of
performing the task and to train the operator in the preferred method.
1. Provide all
information about
the job in the chart.2. Study the operation
cycle a few times
before starting to
record.
3. Record one hand
at a time.
4. First record theactivities of the
hand which starts
the work first.
5. Do not combine the
different activities
like operations,
transport etc.
Example of a Two-Handed Process Chart:
-
5/27/2018 Work Study Slides IM EEE Chem 13
63/178
p(Cutting Glass Tubes)
Example of a Two-Handed Process Chart:
-
5/27/2018 Work Study Slides IM EEE Chem 13
64/178
p(Cutting Glass Tubes)
Ex: Two-handed process Chart
-
5/27/2018 Work Study Slides IM EEE Chem 13
65/178
Ex: Left-Hand-Right-Hand Chart
-
5/27/2018 Work Study Slides IM EEE Chem 13
66/178
Ex: Left Hand Right Hand Chart
Standard format of a Two-handed process f lowchart
-
5/27/2018 Work Study Slides IM EEE Chem 13
67/178
Standard format of a Two handed process flowchart
E l f T h d d fl h t
-
5/27/2018 Work Study Slides IM EEE Chem 13
68/178
Example of a Two-handed process flowchart
F ixing Screw on a Assembly
Example of a Two-handed process flowchar t
-
5/27/2018 Work Study Slides IM EEE Chem 13
69/178
p p
F ixing Screw on a Assembly
Example of a Two-handed process flowchart
-
5/27/2018 Work Study Slides IM EEE Chem 13
70/178
4 Multiple Activity Chart or Man machine Chart
-
5/27/2018 Work Study Slides IM EEE Chem 13
71/178
4. Multiple Activity Chart or Man-machine Chart A man-machine/ Multiple Activity Chart chart is a chart in which the activities of
more than one worker or machine are recorded.
Activities are recorded on a common time scale to show the inter-relationship.
It is used when a worker operates a number of machines at a time. It is also
used when a number of workers jointly do a job. (Determine no. of machines
handled by one operator).
The chart shows the idle time of the worker or machine during the process.(Study idle time)
Work load is evenly distributed among the workers or machines by this the idle
time of worker or machine is reduced. Multiple activity chart is very useful in
planning team work in production or maintenance. (Determine no. of operators
required). Only two symbols are used in man-machine/ Multiple Activity Chart :
Working Idle
Purpose of Multiple Activity Chart
-
5/27/2018 Work Study Slides IM EEE Chem 13
72/178
Purpose of Multiple Activity Chart
To detect the idle time on machine and workers (The chart shows the exacttime relationship between the working cycle of the person and operating
cycle of the machine).
To optimize work distribution between workers and machines.
To decide number of workers in a group.
To balance the work team
To examine the activities. It is used for recording the complex movements of material or men.
Used to find out the most economical route.
Application ofMultiple Activity Chart:
Planning team work. Plant repair & maintenance.
Job construction.
It is used to check whether the work station is correctly located.
-
5/27/2018 Work Study Slides IM EEE Chem 13
73/178
Example of Multiple Activity Chart:Facing & Centering Operations
-
5/27/2018 Work Study Slides IM EEE Chem 13
74/178
Time Operator Machine 1Washer
Machine 2Dryer
# Sec Load clothes & detergent in
machine 1
Being loaded Idle
Idle Run Idle
- Remove clothes from machine 1 Being unloaded Idle
- Load clothes into machine 2 Idle Being loaded
- Load clothes & detergent into
machine 1
Being loaded Run
- Idle Run Run
- Remove clothes from machine 2 Idle Being unloaded
- Hang clothes Idle Idle
Multiple activity chart for doing three loads of laundry
Ex: Worker-Machine Chart for a Gourmet Coffee Store
-
5/27/2018 Work Study Slides IM EEE Chem 13
75/178
Diagrams
-
5/27/2018 Work Study Slides IM EEE Chem 13
76/178
Diagrams
Diagrams gives pictorial view of the layout of workplace on which
locations of different equipment, machines etc. are indicated.
The movement of subject(man or machine) is then indicated on the
diagram by a line or a string.
The diagram are valuable in highlighting the movement so the analystcan take steps to simplify or reduce it so as to obtain saving in time.
The most commonly used method study diagrams are:
o Flow diagram
o String diagramo Travel chart
o Cyclegraph and Chronocyclegraph
Types of LAYOUT
-
5/27/2018 Work Study Slides IM EEE Chem 13
77/178
FOUR MAJOR TYPES OF LAYOUT:
(A) layout by FIXED position, material to be processed dont
travel round the plant but stays in one place. When product is
bulky, heavy and only few units are made (Ship Building,
Aircraft construction, Manufacture of large Diesel engines)
(B) layout by PROCESS, Operations of the same nature are
grouped together. Cutting in garment industry, stitching inanother area. This is mostly chosen where great many products
share the same machine.
(C) Layout by PRODUCT, or LINE layout (Mass production) all
m/c & equipment necessary is set in the same area and in the
sequence of manufacturing process.
(D) layout by GROUP. Group production methods.
Types of LAYOUT
-
5/27/2018 Work Study Slides IM EEE Chem 13
78/178
1 Flow diagram
-
5/27/2018 Work Study Slides IM EEE Chem 13
79/178
1.Flow diagram
Drawing of working area & showing location of various activities
Shows the route followed and selects the optimum one Study different layout and selecting optimum one
Study traffic and frequency over different routes
Procedure :
Layout of workplace is drawn to scale
Relative positions of the m/c tools, storage & inspection benches are
marked on the scale
Path followed by the subject under study is tracked by drawing lines
Each movement is serially numbered & indicated by arrow for direction
Different colors are used to denote different types of movements
Flow diagram
-
5/27/2018 Work Study Slides IM EEE Chem 13
80/178
Its a top view of the work area correctly indicating the positions of
machining and other locations affecting the movement of subject.
Therefor it gives on-the-spot observation of the paths of movement
of product sometimes using symbols of process charts.
80
-
5/27/2018 Work Study Slides IM EEE Chem 13
81/1782. String diagram
-
5/27/2018 Work Study Slides IM EEE Chem 13
82/178
Scale layout drawing
Length of a string is used to record extent & pattern of movements of a
worker within a limited area.
Movements difficult to trace on flow diagram can be shown Shows the route followed and selects the optimum one
Study different layout and selecting optimum one
Study traffic and frequency over different routes
Procedure :
A Layout of workplace is drawn to scale
Pins are fixed into boards to mark locations of workstations
Pins are also driven at turning points of the routes A measured length of thread is taken to trace the movements
The distance covered by object is obtained by measuring the remaining
part of the thread and subtracting it from original length
-
5/27/2018 Work Study Slides IM EEE Chem 13
83/178
START
END
83
-
5/27/2018 Work Study Slides IM EEE Chem 13
84/178
DRILL+CUT
FOLD
RIVET
MARK
IQC
STACK
OQC
SHEETMETAL
STAR
END
START
END
Comparison
-
5/27/2018 Work Study Slides IM EEE Chem 13
85/178
SHEET METALCHECK = 10 ft
CHECKCUT = 12 ft
CUTDRILL = 9 ft
DRILLFOLD = 10 ft FOLDRIVET = 10 ft
RIVETCHECK = 14 ft
CHECKSTACK = 12 ft
TOTAL = 67 ft
SHEET METALIQC = 2.8 ft.
IQCMARK = 5 ft.
MARKDRILL &CUT= 6ft
DRILL &CUTFOLD = 6ft.
FOLDRIVET = 5 ft.
RIVETOQC = 5 ft.
TOTAL = 30 ft.
Comparison
Scale 1cm = 2feet
Before After
-
5/27/2018 Work Study Slides IM EEE Chem 13
86/178
86
-
5/27/2018 Work Study Slides IM EEE Chem 13
87/178
87
-
5/27/2018 Work Study Slides IM EEE Chem 13
88/178
88
-
5/27/2018 Work Study Slides IM EEE Chem 13
89/178
89
-
5/27/2018 Work Study Slides IM EEE Chem 13
90/178
90
-
5/27/2018 Work Study Slides IM EEE Chem 13
91/178
91
CLASSIFICATION OF MOVEMENTS
-
5/27/2018 Work Study Slides IM EEE Chem 13
92/178
Class Pivot Body member(s) moved
1 Knuckle Finger
2 Wrist Hand and Finger
3 Elbow Forearm, hand and fingers
4 Shoulder Upper arm, forearm, hand and
fingers
5 Trunk Torso, Upper arm, forearm, hand and
fingers
-
5/27/2018 Work Study Slides IM EEE Chem 13
93/178
93
-
5/27/2018 Work Study Slides IM EEE Chem 13
94/178
94
-
5/27/2018 Work Study Slides IM EEE Chem 13
95/178
95
-
5/27/2018 Work Study Slides IM EEE Chem 13
96/178
96
-
5/27/2018 Work Study Slides IM EEE Chem 13
97/178
97
-
5/27/2018 Work Study Slides IM EEE Chem 13
98/178
-
5/27/2018 Work Study Slides IM EEE Chem 13
99/178
99
-
5/27/2018 Work Study Slides IM EEE Chem 13
100/178
100
-
5/27/2018 Work Study Slides IM EEE Chem 13
101/178
101
-
5/27/2018 Work Study Slides IM EEE Chem 13
102/178
102
-
5/27/2018 Work Study Slides IM EEE Chem 13
103/178
103
-
5/27/2018 Work Study Slides IM EEE Chem 13
104/178
104
-
5/27/2018 Work Study Slides IM EEE Chem 13
105/178
105
-
5/27/2018 Work Study Slides IM EEE Chem 13
106/178
106
-
5/27/2018 Work Study Slides IM EEE Chem 13
107/178
107
-
5/27/2018 Work Study Slides IM EEE Chem 13
108/178
108
-
5/27/2018 Work Study Slides IM EEE Chem 13
109/178
109
-
5/27/2018 Work Study Slides IM EEE Chem 13
110/178
110
-
5/27/2018 Work Study Slides IM EEE Chem 13
111/178
111
-
5/27/2018 Work Study Slides IM EEE Chem 13
112/178
112
-
5/27/2018 Work Study Slides IM EEE Chem 13
113/178
113
-
5/27/2018 Work Study Slides IM EEE Chem 13
114/178
-
5/27/2018 Work Study Slides IM EEE Chem 13
115/178
Improve Productivity, Reduce Costs, Improve Profits
Work Measurement:
Work measurement is the application of a set of techniques
designed to establish the quantum of work to be done in a given
time for a qualified worker to carry out specified jobs, under
specified conditions at a defined level of performance.
-
5/27/2018 Work Study Slides IM EEE Chem 13
116/178
We have seen how total time to manufacture a product is
increased by: adding undesirable features to product,
bad operation of the processes, and
ineffective time added because of worker andmanagement.
All this leads to decreased productivity.
-
5/27/2018 Work Study Slides IM EEE Chem 13
117/178
Time Study/ Work Measurement
Work measurement is identified as a scientificmethod of fixing standard of production orstandard time for a given job.
To manage, one must measure first.
Work measurement means the application of aset of techniques intended to establish the
i. Amount of work to be done by an operator
ii. At a given time
iii. Under a specific condition and
iv. At defined level of performance.
-
5/27/2018 Work Study Slides IM EEE Chem 13
118/178
Work measurement (WM) is concerned with investigating,
reducing and eliminating ineffective time, whatever may
be the cause.
WM is the means of measuring the time taken in the
performance of an operation or series of operations in such
a way that the ineffective time is shown up and can be
separated out.
In practice,proving existence of the ineffective time is the
most difficult task.
After existence is proved, nature and extent is easy to see!
-
5/27/2018 Work Study Slides IM EEE Chem 13
119/178
WM is also used to set standard times to carry out the
work, so that any ineffective time is not included later. Any addition to the standard time would show up as excess
time and thus can be brought to attention.
Since, standard times are set for all the activities through
WM, it has earnedbad reputation amongst workers. Major reason for that has been the initial focus of the WM
methods, which essentially targeted only the worker
controllable ineffective times.
Management controllable ineffective times were ignoredtraditionally.
f k
-
5/27/2018 Work Study Slides IM EEE Chem 13
120/178
Use of Work Measurement
1. Assessment of manpower requirements
2. Planning
3. Estimation of Production costs
4. Cost reduction and cost control
5. Improved methods
6. Basis for Incentives
7. Comparing alternative methods
8. Standard data9. Performance appraisal
10. Training needs assessment
Work Measurement
Work Measurement (WM) is the application of
-
5/27/2018 Work Study Slides IM EEE Chem 13
121/178
Work Measurement (WM) is the application oftechniques designed to establish the time for a qualified
worker to carry out a specified job at a defined level ofperformance. (British Standard Glossary of Terms in Work Study)
The purpose of WM is to reveal the nature & extent of ineffective time so that action can be taken to reveal the
eliminate it and then set standards of performance.
Two critical issues in work study:
1. Method study should precede the work measurement,
always.2. Elimination of management controllable ineffective time
should precede the elimination of the ineffective time within
the control of the workers.
To reduce the amount of ineffective time
PURPOSE OF WORK MEASUREMENT
-
5/27/2018 Work Study Slides IM EEE Chem 13
122/178
Provides management with a means of identifying the causes of
ineffective time.
1. To find ineffective time in a process2. To set standard for output level
3. To plan workforce needs
4. To evaluate workers performance
5. To determine available capacity
6. To determine price or cost of product7. To compare work methods
8. To facilitate operations schedules
9. To establish wage incentive schemes
10. Training of new employees
11. Checking employee progressGeneral criteria where WM can be applied for measurable jobs:1. Work should be identifiable in terms of No. of units a worker performed,
2. Work should be performed in a reasonably consistent manner, and
3. There should be considerable volume of work to justify performing the study.
Use of Work Measurement:
1. Assessment of manpowerrequirements
2. Planning
3. Estimation of Production
costs
4. Cost reduction and cost
control
5. Improved methods
6. Basis for Incentives
7. Comparing alternative
methods
8. Standard data
9. Performance appraisal
10. Training needs assessment
THE TECHNIQUES OF WORK MEASUREMENT
-
5/27/2018 Work Study Slides IM EEE Chem 13
123/178
1. Stop-watch time study
2. Work sampling
3. Predetermined time standards(PTS)
4. Standard Data
The choice of technique depends on:
The level of details desired and The nature of work itself
Direct observationalmethods
Indirect
methods
Steps in Work Measurement
Select the job to be timed (B l k i i i j b j b i h f l
-
5/27/2018 Work Study Slides IM EEE Chem 13
124/178
Selectthe job to be timed (Bottleneck operations, repetitive jobs, jobs with great amount of manuallabour, frequent overtime, new job/component, if cost of operation is high, introduce/revise incentive scheme etc)
Standardise the method of working; Select OperatorRecordall the relevant data relating to the circumstances in which the work is
being done, the method and the elements of activity in them
Examinethe recorded data and the detailed breakdown critically to ensure that
the most effective method and motions are being used and that unproductive and
foreign elements are separated from productive elements
Measurethe quantity of work involved in each element, in terms of time, using
the appropriate work measurement techniques
Compilethe standard time for the operation which will include time
allowances to cover relaxation, personal needs, contingencies, etc.
Defineprecisely the series of activities and methods of operations for which the
time has been compiled and issue the time as standard for the activities and
methods specified.
TIME STUDY
Basic Steps
-
5/27/2018 Work Study Slides IM EEE Chem 13
125/178
1. Obtaining and recording all available information about the job,
operator and the surrounding conditions likely to affect theexecution of the work
2. Recording the complete description of the method, breaking
down the operation into 'elements'
3. Measuring with a stopwatch and recording the time taken bythe operator to perform each 'element' of the operation.
4. Assessing the rating
5. Extending observed time to 'basic times'
6. Determining the allowances to be made over and above the basictime for the operation
7. Determining the 'standard time' for the operation.
Time StudyTime Study is the application of WM technique to establish time
for a QUALIFIED WORKER to carry out a SPECIFIED TASK
-
5/27/2018 Work Study Slides IM EEE Chem 13
126/178
for a QUALIFIED WORKER to carry out a SPECIFIED TASK
under SPECIFIED CONDITIONS and at the DEFINED LEVEL
OF PERFORMANCE. How much time one should take to reach Wgl Stn?
* Breaking into the work elements * Time for each work element
* Rate of performance
* Time of similar work elements should be compared to keep the standard time
constant
* Study a number of cycles instead of one or two
* Extreme values to be discarded
To separate productive & non-productive time
To assess rating of the worker
To identify different types of elements & to
measure their timings
To determine fatigue allowance
To prepare detailed work specifications
To fix Std. time for repetitive elements
Each element should have definite beginning & end
Element should be as short as possible to be conveniently
timed (0.04 min)
Manual & M/c elements should be separately timed
Constant separate from variable
Occasional & foreign to be timed separately
Steps in Work Measurement (Contd.)
Di id th j b i t l t Th di i i f
-
5/27/2018 Work Study Slides IM EEE Chem 13
127/178
Divide the job into elements. The division ofjobs is necessary for the following reasons.
1. Provide better understanding.
2. Break the study into manageable size.
3. Workers efficiency thorough out job.
4. Distinguish between various parts.5. Isolate man and machines.
Time the elements. Stop watch is generally used in thesystem. Either of continuous or Fly-back method is used for
recording time.
Ex: Dividing Drilling into elements1. Selecting the work piece and
placing it in jig.2. Tightening the screw3. Advancing the drill towards
the work piece4. Drilling5. Withdrawing the drill from the
operation6. Loosening the screw7. Removing piece from jig8. Removing the chips
The number ofcycles to be timed. There should besufficient readings to get reasonably accurate results It depends
Steps in Work Measurement (Contd.)
-
5/27/2018 Work Study Slides IM EEE Chem 13
128/178
sufficient readings to get reasonably accurate results. It dependson
1. Variation in times of element.2. Degree of accuracy required.
3. Prescribed level of confidence.
Rating ofoperator.RATING is gauging and comparing the
pace or the performance of a worker against a STD performancelevel set by the TS Engineer.
Objective rating. Here emphasis is laid on speed anddifficulty experienced in performing a job. At first operator is rated
on normal speed and movement. Then other factors are
considered. (based on (i) the amount of body used (ii) foot movement involved (iii) eye-hand coordination(iv) weight moved or lifted (v) handling requirements etc.).
Allowances.
Amount of work that can be produced by a qualified employee when working
t l d ff ti l tili i hi ti h k i t t i t d b
A FAIR DAY'S WORK
-
5/27/2018 Work Study Slides IM EEE Chem 13
129/178
at normal pace and effectively utilizing his time where work is not restricted by
process limitations.
Qualified Worker is one who is accepted as having the necessary physical
attributes, who possesses the required intelligence and education, and has
acquired the necessary skill and knowledge to carry out the work in hand to
satisfactory standards of safety, quantity and quality. (Choose the operator
among many doing the job under study).
It is the rate of output which qualified workers will naturally achieve
without over-exertion as an average over the working day or shift,provided that they know and adhere to the specified method and
provided that they are motivated to apply themselves to their work.STANDARD RATING
Rating is the assessment of the worker's rate of working relative to the
observers' concept of the rate corresponding to standard pace.
STANDARD PERFORMANCE
FACTORS AFFECTING RATE OF WORKING
(outside the control of worker)
-
5/27/2018 Work Study Slides IM EEE Chem 13
130/178
( )
1. Variation in the quality of materials used
2. Changes in the operating efficiency of the equipment
3. Changes in climatic and surrounding conditions of operation.
FACTORS WITHIN THE CONTROL OF WORKER
a. Acceptable variations in the quality of the product
b. Variations due to his ability
c. Variations due to his attitude
Thus, rarely the time taken to perform an element of operation by the operator is
constant from piece to piece of the job. Therefore, enough cycles are to be timed to
get representative time of each element.
No. of Observations required, = (()
Ifaccuracy level required is 10% the co-eff is 20; for5% it is 40; for2.5% it is 80.
Where, N = actual No. ofobservations taken in pilot study.
And x = each observed
elemental time
R ti f t
SCALES OF
RATING
100-133
-
5/27/2018 Work Study Slides IM EEE Chem 13
131/178
Rating factor
The figure 100 represents standard performance.
If the operator is apparently performing with less effective
speed, than the assigned factor is less than 100.
If, on the other hand, the effective rate of working is abovestandard, the operator gets a factor above hundred.
Essential idea being:
Observed time x Rating = Constant
60-80
75-100
0-100
Performance Rating
-
5/27/2018 Work Study Slides IM EEE Chem 13
132/178
-
5/27/2018 Work Study Slides IM EEE Chem 13
133/178
(this 100 is Standard rating)
10. Calculating standard time of the job
-
5/27/2018 Work Study Slides IM EEE Chem 13
134/178
Constituents of Standard TimeBasic constituents of Standard Timeare:
Elemental times (Observed
times)
Compensation for the
difference in operatives pace ofperformance and standard
performance.
Relaxation allowance
Interference and Contingency
allowances
Policy allowance
Normal Time
Total
Allowance
Standard
Time
Relaxation
Allowance
Policy
Allowance
Interference
Allowance
Contingency
Allowance
Fatigue
Allowance
Personal
Needs
Allowance
Standard Time
-
5/27/2018 Work Study Slides IM EEE Chem 13
135/178
Normal or Basic Time of elements of the job when
added, gives BASIC TIME of the job. Becausenobody can work continuously some additional time
(given as allowances) is required to be added to
Basic Time to arrive at Standard Time.
Standard Time is calculated by taking the NormalTime and adding allowances for Personal Needs,
Fatigue, Contingency, Interference etc.
= Observed Time
Or
-
5/27/2018 Work Study Slides IM EEE Chem 13
136/178
=
Performance Rating
The expression of ten used in practice for Standard Time is:
= Normal Time ( 1 + )
Some times the allowances are allowed to be applied to the total work
period, then
=
( )
Illustrated Examples
An industrial operation consists of Ele Observe Performan Normal or
-
5/27/2018 Work Study Slides IM EEE Chem 13
137/178
An industrial operation consists of
FIVE elements with following
observed times and the performance
ratings:
Assuming rest and personalallowances as 15% and contingency
allowance as 2% of the basic time,
calculate standard time per piece.
Element Observed
Time (Min.)
Performance
Rating (%)
A 0.20 85
B 0.08 80
C 0.50 90
D 0.12 85
E 0.10 80
me
nt
d Time
(Min.)
ce Rating
(%)
Normal or
Basic Time
(Min)
A 0.20 85
B 0.08 80 0.064
C 0.50 90 0.450
D 0.12 85 0.102
E 0.10 80 0.080
0.866
Standard Time computation of an ordinary manual operation:An operator working on a Pillar Drill performed the following elements for which the
observed times and ratings are given hereunder:
-
5/27/2018 Work Study Slides IM EEE Chem 13
138/178
(i)Calculate normal time of each element and normal time of the job,
(ii) Also calculate standard time of the job.
Element
Code
Element Description Obseved
Time
Rating Relaxation
allowance
A Position job into a drill jig 0.20 80 11%
B Switch on the M/c & lower drill 0.008 100 11%
C Drill hole 2.20 90 13%
D Raise drill and switch off M/c 0.05 80 11%
E Remove job from jig 0.10 110 11%
Element
Code
Element Description Obsd
Time
Rating Relaxa
allowan
Work content/
Std time
A Position job into a drill jig 0.20 80 11% 0.1776
B Switch on the M/c & lower drill 0.008 100 11% 0.0888
C Drill hole 2.20 90 13% 2.2374
D Raise drill and switch off M/c 0.05 80 11% 0.0444
E Remove job from jig 0.10 110 11% 0.1221
Standard Time of the Job 2.6703 min
A cylindrical grinding operation involves elements detailed below along with theirrelated data:
Elemen
t code
Element description Obsrd
time
Rati
ng
Remark Assuming rest & personal allowance as
13% and contingency allowance as 2%,
-
5/27/2018 Work Study Slides IM EEE Chem 13
139/178
A Pickup job &tighten carrier
0.2 90 --
B Position untilbetween centres 0.05 80 --
C Advance wheel tojob
0.03 100 --
D Grindto size 0.78 100 --
E Spark off 0.06 100 --
F Withdraw wheel toclear job
0.05 100 --
G Measure 0.02 85 Once in5 pieces
H Release job frombetween cetres
0.06 80 --
I Loosen carrier &keep the job aside
0.10 90 --
J Dress wheel 0.04 90 Once in20 jobs
3% a d co ge cy a o a ce as %,
calculate standard time of the job.
Solution:
Eleme
nt
Obsd
time
rating Norm
al
time
freq NT/
cycle
Tota
l
Allo
Work
content
/ cycle
-
5/27/2018 Work Study Slides IM EEE Chem 13
140/178
w
A 0.20 90 0.18 1 0.18 15% 0.207
B 0.05 80 0.04 1 0.04 15% 0.046
C 0.03 100 0.03 1 0.03 15% 0.0345
D 0.78 100 0.78 1 0.78 15% 0.897
E 0.06 100 0.06 1 0.06 15% 0.069
F 0.05 100 0.50 1 0.05 15% 0.0575
G 0.20 85 0.17 1/5 0.034 15% 0.0391
H 0.06 80 0.048 1 0.048 15% 0.0552
I 0.10 90 0.09 1 0.09 15% 0.1035
J 0.40 90 0.36 1/20 0.018 15% 0.0207
1.330 1.5295
Standard time computation when Stop Watch
readings are given:
-
5/27/2018 Work Study Slides IM EEE Chem 13
141/178
A time study was conducted on a job consisting of three
elements. The stop watch readings of the first five cycles using
cumulative timing method are given below:
The rating factors were estimated at 80, 100, 110 for the threeelements respectively (on the rating scale of 100 corresponding to
normal performance). The allowance for personal needs, rest etc.
amount to 12%. Calculate the standard time for the job.
ELEME
NT
STOP WATCH READINGS in hundredth of a minute
1 2 3 4 5
A 10 73 139 203 266
B 25 88 155 218 280
C 64 128 193 257 320
-
5/27/2018 Work Study Slides IM EEE Chem 13
142/178
Eleme
nt
Elemental Individual time
(centiminutes)
Ave. time of
elements
(Min)
Rating Normal
(or
Basic)
time
Allowances Work
Content
1 2 3 4 5
A 10 09 11 10 09 0.098 80 0.0784 12% 0.0878
B 15 15 16 15 14 0.150 100 0.1500 12% 0.1680
C 39 40 38 39 40 0.392 110 0.4312 12% 0.4829
0.7387
Uses of time standards
-
5/27/2018 Work Study Slides IM EEE Chem 13
143/178
To provide information on which the planning and
scheduling of production can be based, including theplant and labor requirements for carrying out the program
of work and utilization of resources.
To provide information on which estimates for tenders,
selling prices and delivery promises can be based. To set standards of machine utilization and labor
performance which can be used for incentive scheme.
To provide information for labor-cost control and to
enable standard costs to be fixed and maintained.
Work /Activity Sampling
-
5/27/2018 Work Study Slides IM EEE Chem 13
144/178
For long cycle operations and for activities where Time Study
is not possible, Work Sampling is applied. Ex. Office work,supervisory work, activities in stores etc.
The second common technique for measuring a job is called
Work Sampling. It involves observing a portion or sample of
work activity and based on the findings of this sample,statements can be made about the activity.
The time it takes to make an observation depends on what is
being observed. Many a times only a glance is needed todetermine the activity and majority of studies require only
several seconds of observation.
Work Sampling
W k S li i t h i i hi h l b f
-
5/27/2018 Work Study Slides IM EEE Chem 13
145/178
Work Sampling is a technique in which a large number of
instantaneous observations are made over a period of time of a
group of machine, processes or people. Work sampling is a
method of finding the percentage occurrence of a certain activity
by statistical sampling and random observations.
Each observation records what is happening at that instant and the
percentage of observations recorded for a particular activity or
delay is a measure of thepercentage of time during which that
activity or delay occurs. (Also known as Activity Sampling, RatioDelay Study,
ObservationRatio Study, SnapReading Method and Random Observation Method)
Work sampling is a method of finding the percentage occurrence of a certainactivity by statistical sampling and random observations.
-
5/27/2018 Work Study Slides IM EEE Chem 13
146/178
Work sampling is the process of making sufficient random observations of anoperators activities to determine the relative amount of time the operatorspends on the various activities associated with the job.
The major goal of work sampling is to determine how long, or how much ofthe work day, is spent on specific types of work.
Work sampling may identify the fact that certain operators spend a largeportion of their time waiting for work, or performing paperwork tasks, or evenperforming activities that are not included in their job descriptions.
One of the basic foundations of statistical sampling theory is the concept thatthe larger the sample size, the results will be more accurate.
In work sampling, a sufficient number of observations must be made to be surethat the results accurately summarize the work performed. There are statisticalformulas to help determine how many observations should be made.
Number of observations in Work Sampling One of the basic foundations of statistical sampling theory is the
concept that the larger the sample size, the results will be more
-
5/27/2018 Work Study Slides IM EEE Chem 13
147/178
p g paccurate.
In work sampling, a sufficient number of observations must be madeto be sure that the results accurately summarize the work performed.There are statistical formulas to help determine how manyobservations should be made.
For 95 % accuracy (confidence level)
Sp = 2 { p (1p) / N }
Sp is significance level, p is extent of the phenomenon (problem) being
observed in a pilot studyexpressed as decimals, and N is totalnumber of observations.
N is then divided into number of machines, days, operators, etc.
A few words about sampling
-
5/27/2018 Work Study Slides IM EEE Chem 13
148/178
Sampling is mainly based on probability. Probability has been defined asthe degree to which an event is likely to occur.
A simple and often-mentioned example that illustrates the point is that oftossing a coin.
The law of probability says that we are likely to have 50 heads and 50 tailsin every 100 tosses of the coin. The greater the number of tosses, the morechance we have of arriving at a ratio of 50 heads to 50 tails.
The size of the sample is therefore important, and we can express ourconfidence in whether or not the sample is representative by using a certainconfidence level.
Establishing confidence levels
Let us go back to our previous example and toss five coins at a time, andthen record the number of times we have heads and the number of times wehave tails for each toss of these five coins. Let us then repeat this operation100 times.
Using Work Sampling
-
5/27/2018 Work Study Slides IM EEE Chem 13
149/178
Make tours of observations on representative of normal
working days
Tours should be carried out in random intervals, random
numbers could be generated to decide on the order
Familiarity of the observer with the process is not critical,
though beneficial.
CONDUCTING A STUDY
-
5/27/2018 Work Study Slides IM EEE Chem 13
150/178
It is recommended that a uniform procedure should be
followed to perform a work sampling study is to
1. Establish the Purpose
First, the objective of the study should be established. Worksampling can be used to determine an overall perspective onthe work done.
2. Identify the Subjects
Second, the people performing the task must be identified, i.e.general office work is being studied with the objective of determining overall productivity.
3. Identify the Measure of Output
-
5/27/2018 Work Study Slides IM EEE Chem 13
151/178
The third step in making the study is the identification of the
measure of the output produced or the types of activities performedon the jobs being studied. This step is especially important if theobjective of the study is to measure productivity with the intent of
setting a standard.
4. Establish a Time Period
Fourth, the time period during which the study will be conductedmust be established. Starting and stopping points for the study must
be defined as well.
5. Define the Activities
This step involves defining the activities that are performed by thepeople under study. For example, the definition used in a machineutilization study, including only the categories of working, idle, and
idle-mechanical breakdown.
6. Determine the Number of Observations Needed
-
5/27/2018 Work Study Slides IM EEE Chem 13
152/178
After the work elements are defined, the number of observations for
the desired accuracy at the desired confidence level must bedetermined. If a reasonable guess cannot be made, then a trial studyof perhaps 20 to 40 observations should be made to get an estimate.
7. Schedule the Observations
Once the number of required observations has been determined,either from appropriate statistical calculations or from tables, and theactual observations must be scheduled. Typically, the analyst willassign an equal number of observations each day during the course ofthe study. For example, if 800 observations are required and 20 workdays are established as an appropriate observation time, 40
observations should be recorded each day. A random number table can be used to establish the random times foreach observation.
8. Inform the Personnel Involved
-
5/27/2018 Work Study Slides IM EEE Chem 13
153/178
Before the study is actually performed, the personnelinvolved should be informed about the objective of the studyand the methodology that will be employed.
9. Record the Raw Data
The next is the actual recording of the raw data. Althoughthis recording can be performed by anyone, it is desirablethat a trained analyst be employed.
It is also very important that the observations be made atexactly the same location every time.
10. Summarize the Data After the data have been collected, they must be
summarized.
-
5/27/2018 Work Study Slides IM EEE Chem 13
154/178
-
5/27/2018 Work Study Slides IM EEE Chem 13
155/178
To make things easier, it is more convenient to speak of a 95 per cent confidence level than of a95.45 per cent confidence level.
To achieve this we can change our calculations and obtain: 95 per cent confidence level or 95 per cent of the area under the curve = 1.96 p
99 per cent confidence level or 99 per cent of the area under the curve = 2.58 p
99.9 per cent confidence level or 99.9 per cent of the area under the curve = 3.3 p
In this case we can say that if we take a large sample at random we can be confident that in 95per cent of the cases our observations will fall within 1.96 p
Number of Samples
-
5/27/2018 Work Study Slides IM EEE Chem 13
156/178
Number of Samples
Confidence interval
Probability that true
proportion will fall
within confidence interval
p- e p+ ep
e= zp(1 - p)
n
Number of Samples
-
5/27/2018 Work Study Slides IM EEE Chem 13
157/178
Number of Samples
n= p(1 - p) z 2
e
DesiredConfidence (%) z
90 1.65
95 1.96
96 2.05
97 2.1798 2.33
99 2.58
n = required sample size
p = estimate of proportion time an activity takes place
z = number of standard deviations for desired confidence
e = maximum error allowable
Determination of sample size
As well as defining the confidence level for our observations we have to decide onthe margin of error that we can allow for these observations.
-
5/27/2018 Work Study Slides IM EEE Chem 13
158/178
Let us look at our example about the productive time and the idle time of the
machines in a factory. There are two methods of determining the sample size thatwould be appropriate for this example:
the statistical method and the nomogram method.
Statistical method. The formula used in this method is:
Let us assume that some 100 observations were carried out as a preliminarystudy and at random, and that these showed the machine to be idle in 25 percent of the cases (p = 25) and to be working 75 per cent of the time (q = 75).
-
5/27/2018 Work Study Slides IM EEE Chem 13
159/178
We thus have approximate values for p and q; in order now to determine thevalue of n.
Let us choose a confidence level of 95 per cent with a 10 per cent margin of error (that is, we are confident that in 95 per cent of the cases our estimateswill be 10 per cent of the real value).
E = z p Since E= 10
And Z = 1.96
-
5/27/2018 Work Study Slides IM EEE Chem 13
160/178
Nomogram methodAn easier way to
determine sample size is to
read off
the number of observations
needed directlyfrom a nomogram
such as the one reproduced
in figure 91.
Making random observations
To ensure that our observations are in fact made at random, we can use a
-
5/27/2018 Work Study Slides IM EEE Chem 13
161/178
To ensure that our observations are in fact made at random, we can use arandom table such as the one in table 12.
Various types of random table exist, and these can be used in different ways. Inour case let us assume that we shall carry out our observations during a dayshift of eight hours, from 7 a.m. to 3 p.m. An eight-hour day has 480 minutes.These may be divided into 48 ten-minute periods.
We can start by choosing any number at random from our table, for example
by closing our eyes and placing a pencil point somewhere on the table. Let usassume that in this case we pick, by simple chance, the number 11 which is inthe second block, fourth column, fourth row (table 12).
We now choose any number between 1 and 10. Assume that we choose thenumber 2; we now go down the column picking out every second reading andnoting it down, as shown below (if we had chosen the number 3, we should pick
out every third figure, and so on).
11 38 45 87 68 20 11 26 49 05
-
5/27/2018 Work Study Slides IM EEE Chem 13
162/178
Looking at these numbers, we find that we have to discard 87, 68 and 49 because theyare too high (since we have only 48 ten-minute periods, any number above 48 has to bediscarded).
Similarly, the second 11 will also have to be discarded since it is a number that hasalready been picked out. We therefore have to continue with our readings to replace thef i i i i
-
5/27/2018 Work Study Slides IM EEE Chem 13
163/178
four numbers we have discarded. Using the same method, that is choosing every secondnumber after the last one (05), we now have 14 15 47 22
These four numbers are within the desired range and have not appeared before. Ourfinal selection may now be arranged numerically and the times of observationthroughout the eight-hour day worked out. Thus our smallest number (05) representsthe fifth ten-minute period after the work began at 7 a.m. Thus our first observation willbe at 7.50 a.m., and so on (table 13).
Example: Conducting the study
Determining the scope of the study. Before making our actual observations, it is
important that we decide on the objective of our work sampling.
Th i l t bj ti i th t f d t i i h th i hi i idl
-
5/27/2018 Work Study Slides IM EEE Chem 13
164/178
The simplest objective is that of determining whether a given machine is idle or
working. In