Work Plan Development
Steve RobinsonHighway Utility Engineer, INDOT
June 11, 2015
![Page 2: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/2.jpg)
2
Outline Learning objectives –why work
plan? Top five reasons why a work plan is
important What are the recent updates?
Target date, signing first or second page, emergency contact, pre-construction & post construction activity, etc.
Work plan development (Process): preparation, review, revision & approval.
Practical exercise
![Page 3: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/3.jpg)
Why is a work plan Important?1. Because it is the law!
he 105 IAC 13-3-3 (b) (1): A work plan shall be
submitted whether or not any facility relocations are required.
It is not a matter of opinion or an option, it is the LAW.
Utilities are obligated to submit their work plans to accommodate a highway improvement project.
![Page 4: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/4.jpg)
Why is a work plan Important ?2. Because it focuses on deliverables:
Target out of conflict date.
Pre-construction schedule.
Construction schedule.
Relocation drawing.
Cost estimate
Proof of property interest.
![Page 5: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/5.jpg)
Why is a work plan Important?3. Because it is a signed
commitment/contract
A work plan is a signed commitment by a utility to accurately relocate its facilities on schedule.
Projects are let based on information obtained from utility work plans.
A utility may be held accountable, for utility related delay claims.
![Page 6: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/6.jpg)
Why is a work plan Important4. No Surprises during construction:
Work plan is a major tool to avoid surprises during construction.
The utility team shall demonstrate due diligence in reviewing & approving work plans.
Last chance before construction stage!
![Page 7: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/7.jpg)
Why is a work plan Important?5: Because we use the work plan as an
input:
Utility risk management report.
Gantt chart.
Utility special provision.
Utility coordination certificate.
![Page 8: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/8.jpg)
A tool for resolution of scheduling and location conflicts
![Page 9: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/9.jpg)
Preamble 105 IAC-13-2-19: Work plan is defined as a
plan of the utility to carry out facility relocation to accommodate an improvement project.
Use preliminary final project plan (Stage 3/90%).
Prepare and send letter Request Work Plan.
Use the most recent work plan template. Go to the INDOT website.
![Page 10: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/10.jpg)
When is a work plan due? Sixty (60) days for a minor project; and
One hundred twenty (120) days for a major project.
An additional thirty (30) days will be allowed to furnish the work plan if coordination is required with another utility or utilities.
If a work plan is not received on time: contact the authorized representative and notify the oversight agent.
![Page 11: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/11.jpg)
11
Work plan revision Non compatible work plans shall be returned
to the utility immediately.
The utility shall submit a revised work plan within 30 days.
If the revised work plan is not compatible, the UC will prepare an alternate work plan.
The utility shall accept/make changes to the alternate plan within 30 days.
![Page 12: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/12.jpg)
12
Section 1: General Information
![Page 13: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/13.jpg)
13
General info……cont’d
![Page 14: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/14.jpg)
14
General info……cont’d
![Page 15: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/15.jpg)
15
Section 2: Location info.
![Page 16: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/16.jpg)
16
Section 3 & 4 Property interest & Work in
contract
![Page 17: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/17.jpg)
17
Section 5: Pre-construction
![Page 18: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/18.jpg)
18
Section 6: Construction
![Page 19: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/19.jpg)
19
Section 7, 8, & 9: Attachments
$500,000.00 (Not Reimbursable)
![Page 20: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/20.jpg)
20
Work Plan Review Ensure each work plan is
compatible with: INDOT permit requirements The project plans The construction schedule Other utility relocation work plans
Ensure the relocation scheme and cost for compensable work is reasonable
![Page 21: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/21.jpg)
21
Section 10 & 11: Approval
![Page 22: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/22.jpg)
22
Work Plan Approval Letter Relocation permit to occupy public
right-of-way.
Notice to proceed with preconstruction activities.
In rare cases a notice to proceed with construction activities.
![Page 23: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/23.jpg)
23
Work plan addendums: Addendums can either be INDOT initiated or
utility initiated.
A utility shall submit a revised work plan with a new cost estimate (if reimbursable).
The utility coordinator shall review the addendum; and send it to the approval of the oversight agent.
If an addendum is issued during construction, a copy shall be sent to the construction engineer.
![Page 24: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/24.jpg)
24
Work Plan Addendum Letter What is the change of work.
What is the cost.
Who is paying for it.
What is the impact on construction schedule.
Revise exhibits to executed agreements, if reimbursable.
![Page 25: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/25.jpg)
Letter AWP Addendum No payment for additional work
without prior approval.
Any change of work needs an approved work plan addendum.
![Page 26: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/26.jpg)
26
Notice to Proceed Does the work of the utility depend on
the schedule(s) of other utilities?
Are all the parcels needed by the utility acquired, ROE obtained?
Is the right-of-way cleared from trees & other obstructions, staked?
Does the work of the utility depend on the INDOT contractor?
![Page 27: Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015](https://reader035.vdocuments.site/reader035/viewer/2022062516/56649d7e5503460f94a61c39/html5/thumbnails/27.jpg)
27Questions?
Questions?