wolf minerals

Upload: benchankc

Post on 02-Apr-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Wolf Minerals

    1/22

    INVESTOR PRESENTATION

    JUNE 2013

  • 7/27/2019 Wolf Minerals

    2/22

    Cautionary Statement

    The information contained in this document has been prepared based upon information supplied by Wolf Minerals Limited (the Company).This Document does not constitute an offer or invitation to any person to subscribe for or apply for any securities in the Company.

    While the information contained in this Document has been prepared in good faith, neither the Company nor any of its shareholders,directors, officers, agents, employees or advisers give any representations or warranties (express or implied) as to the accuracy, reliability orcompleteness of the information in this Document, or of any other written or oral information made or to be made available to any interestedparty or its advisers (all such information being referred to as Information) and liability therefore is expressly disclaimed.

    Accordingly, to the full extent permitted by law, neither the Company nor any of its shareholders, directors, officers, agents, employees oradvisers take any responsibility for, or will accept any liability whether direct or indirect, express or implied, contractual, tortious, statutory orotherwise, in respect of, the accuracy or completeness of the Information or for any of the opinions contained in this Document or for anyerrors, omissions or misstatements or for any loss, howsoever arising, from the use of this Document. Neither the issue of this Document norany part of its contents is to be taken as any form of commitment on the part of the Company to proceed with any transaction and the right isreserved to terminate any discussions or negotiations with any person. In no circumstances will the Company be responsible for any costs,losses or expenses incurred in connection with any appraisal or investigation of the Company. In furnishing this Document, the Company doesnot undertake or agree to any obligation to provide the recipient with access to any additional information or to update this Document or tocorrect any inaccuracies in, or omissions from, this Document which may become apparent.

    This Document should not be considered as the giving of investment advice by the Company or any of its shareholders, directors, officers,agents, employees or advisers. Each party to whom this Document is made available must make its own independent assessment of theCompany after making such investigations and taking such advice as may be deemed necessary. In particular, any estimates or projections oropinions contained in this Document necessarily involve significant elements of subjective judgment, analysis and assumptions and eachrecipient should satisfy itself in relation to such matters.

    This Document may include certain statements that may be deemed forward-looking statements. All statements in this discussion, other thanstatements of historical facts, that address future activities and events or developments that the Company expects, are forward-looking

    statements. Although the Company believes the expectations expressed in such forward-looking statements are based on reasonableassumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from thosein the forward-looking statements. The Company, its shareholders, directors, officers, agents, employees or advisers, do not represent,warrant or guarantee, expressly or impliedly, that the information in this Document is complete or accurate. To the maximum extentpermitted by law, the Company disclaims any responsibility to inform any recipient of this Document of any matter that subsequently comesto its notice which may affect any of the information contained in this Document. Factors that could cause actual results to differ materiallyfrom those in forward-looking statements include market prices, continued availability of capital and financing, and general economic, marketor business conditions. Investors are cautioned that any forward-looking statements are not guarantees of future performance and thatactual results or developments may differ materially from those projected in forward-looking statements.

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 2

  • 7/27/2019 Wolf Minerals

    3/22

    Wolf Investment Highlights

    Hemerdon Project - first production expected in 2015

    Planning permissions in place with finance secured to commence construction

    DFS indicates solid EBITDA margins and low operating production costs

    Positive structural market dynamics for tungsten pricing and demand

    Low cost model provides significant leverage to tungsten price upside

    Located in a stable and supportive political environment

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 3

    WORLD CLASS, CONSTRUCTION READY TUNGSTEN AND TIN MINE IN THE UK

  • 7/27/2019 Wolf Minerals

    4/22

    Wolf - Corporate Snapshot

    WOLF MINERALS

    Stock Codes ASX:WLF AIM:WLFEShare Price ASX: A$0.30 AIM: 0.20Issued shares 198.0 MillionUnlisted Options 8.0 MillionMarket Cap ~A$59M ~40M

    Key Management

    MD & CEO Humphrey Hale

    Chairman John Hopkins

    CFO - Richard Lucas

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 4

    SUBSTANTIAL SHAREHOLDERS

    Name Holding Description

    Resource Capital

    Fund V36.4% Mining focused private equity firm.

    TTI (NZ) Limited

    19.9%

    Wholly owned subsidiary of Todd Corporation Limited, a major private NZ

    based company with a diversified portfolio of business interests.

    Traxys Projects LP 9.3%Global leader in financing, marketing, distribution and financial services for the

    mining, metals and minerals industries.

    0

    500

    1,000

    1,500

    2,000

    0.15

    0.20

    0.25

    0.30

    0.35

    0.40 SHARE PRICE (ASX:WLF)

    ASX:WLF - Share Pricing -Volume ASX:WLF - Share Pricing

  • 7/27/2019 Wolf Minerals

    5/22

    Tungsten Positive Structural

    Market Dynamics

    Critical for industrial development due to its uniqueproperties (melting point / hardness) and limitedsubstitutability

    Considered a strategic metal in US, EU and China

    Used in manufacture of hard metals (cementedcarbines), steels/alloys and mill products

    Ammonium Para Tungstate (APT) is the most tradedof the tungsten products current price US$365**

    Product prices quoted in metric tonne units or mtu(1 mtu = 10kg)

    OVERVIEW

    China a net importer in 2012

    China holds 60% of known tungsten reserves (USGS)

    and accounts for +50%* of demand and +80%* ofsupply

    New capacity required to meet Western demand

    Forecast demand growth of 6-7% to 2016*

    Hemerdon in full production will produce less than3% of total forecast demand in 2016

    PRIMARY TUNGSTEN DEMAND

    5

    0

    10000

    20000

    30000

    40000

    50000

    60000

    70000

    80000

    90000

    100000

    1989

    1990

    1991

    1992

    1993

    1994

    1995

    1996

    1997

    1998

    1999

    2000

    2001

    2002

    2003

    2004

    2005

    2006

    2007

    2008

    2009

    2010

    2011

    2012

    2013

    2014

    2015

    2016

    FORECAST TUNGSTEN DEMAND

    1989 TO 2016*

    *Source: ITIA: Roskill forecast

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE

    *Source: Roskill research

    **EU APT price US$365 (Metal Pages)

  • 7/27/2019 Wolf Minerals

    6/22

    Hemerdon Project

    Large, high quality reserve base

    26.7mt @ 0.19%W03 (tungsten) and 0.03%Sn(tin) of proven and probable reserves

    Low cash cost of US$105/mtu*

    DFS confirms a robust low cost project

    A$212M in funding to commence construction

    Permitted to 2021 with potential to extend

    Stable UK location with existing infrastructure

    EPC contract in line with DFS

    Production expected in 2015

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 6

    *After tin credits

  • 7/27/2019 Wolf Minerals

    7/22

  • 7/27/2019 Wolf Minerals

    8/22

    Hemerdon - Construction Ready

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 8

    CURRENT FOCUSCOMPLETED ONGOING

    A$212 Million

    Funding packageto commenceconstructioncompleted

    Binding Offtakeagreementscompleted

    DFScompleted

    Planningpermission

    secured

    Water permitsapproved

    EPC Contractorappointed

    NEXT STEPS

    Appoint Senior staff and continue landpurchases

    Commence detailed design andprocurement of the plant and

    infrastructure Secure remaining environmental approvals

    Planning Funding2013

    Construction2014

    Commissioning2015

    Production

    2016Increase Mine

    Life

  • 7/27/2019 Wolf Minerals

    9/22

  • 7/27/2019 Wolf Minerals

    10/22

    EPC Contract in line with DFS

    The 75 million (A$110.6 million) contract is belowthe DFS estimate of ~77 million

    Completion includes commissioning the plant &performing a throughput test

    Fixed delivery period of 105 weeks from formal

    commencement date

    Globally experienced firm with a solid history ofexecuting projects on time and in budget

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 10

    GR ENGINEERING SERVICES (GRES) APPOINTED AS EPC CONTRACTOR

    RECENTLY COMPLETED PROJECTS

    CBH Resources Limited

    Broken Hill Operations

    Rasp Project $76M

    750,000 tpa Lead Zinc

    Processing Plant

    (Design and Construct)

    Catalpa Resources Ltd

    Edna May Gold Project

    $52M

    2.8 Mtpa Gold Process

    Plant & Infrastructure

    (Design and Construct)

    Western Areas NL

    Cosmic Boy Nickel Project

    $35M

    250,000 tpa Nickel

    Sulphide Process Plant

    (Design and Construct)

  • 7/27/2019 Wolf Minerals

    11/22

    Offtake Agreements completed

    Confirms saleability of tungsten concentrate

    Provides partial guarantee for Senior debt of 75m

    Total contracted quantity equal to 80% of scheduledproduction on a 5 year term

    Market pricing with no cap or floor

    Suitable for German government guarantee

    Global Tungsten &Powders (Plansee)

    Wolfram Bergbau undHutten (Sandvik)

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 11

    TOP TIER OFFTAKE PARTNERS

  • 7/27/2019 Wolf Minerals

    12/22

    Optimise and Increase Mine Life

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 12

    POTENTIAL DEVELOPMENT OPTIONS WITH FRESH PLANNING PERMISSIONS

    Current DFS is limited only by existing planningpermission

    Lateral and vertical pit expansion

    Potential for underground expansion

    Opportunity to steepen the ultimate pit wallsresulting in an increase in mineable reserve.

    Mineralisation is open at depth to 400m and alongstrike providing the opportunity to expand pit designfurther and extend mine life by many years.

  • 7/27/2019 Wolf Minerals

    13/22

    Next Steps

    Provide site access to EPC contractor

    Secure remaining environmental approvals

    Commence detailed design and procurement ofplant and infrastructure

    Appoint Senior staff and continue land purchases

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 13

  • 7/27/2019 Wolf Minerals

    14/22

    Wolf Summary

    High quality, open pit 3Mtpa construction ready tungsten and tin project in the UK

    EPC contract secured in line with DFS estimates

    Financing from top tier investors to commence construction and offtake agreements

    Low cost model provides significant leverage to tungsten price upside

    2015 production schedule in line with projected forecast increase in Western tungsten demand

    Fourth largest tungsten deposit globally with significant future development options

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 14

  • 7/27/2019 Wolf Minerals

    15/22

    APPENDICES

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE

  • 7/27/2019 Wolf Minerals

    16/22

    Competent Persons

    Statement

    The information in this report relates to Exploration Results, Mineral Resources or Ore reserves is based oninformation compiled by Mr. H. Hale BSc. (Hons), MAIG. Mr. Hale has sufficient experience that is relevant tothe style of deposit under consideration and to the activity which he is undertaking to qualify as CompetentPerson as defined in the 2004 Edition of the Australasian Code for Reporting of Exploration Results, MineralResources and Ore reserves. Mr. Hale consents to the inclusion in the report of the matters based on thisinformation in the form and context in which it appears.

    The information in the report to which this statement is attached that relates to Exploration Results andMineral Resources is based on information compiled by Phil Jankowski, who is a Member of the AustralasianInstitute of Mining and Metallurgy. Phil Jankowski is a full-time employee of SRK Consulting (Australasia) PtyLtd (SRK), and has sufficient experience which is relevant to the style of mineralisation and type of depositunder consideration and to the activity which he is undertaking to qualify as a Competent Person as defined inthe 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and OreReserves. Phil Jankowski consents to the inclusion in the report of the matters based on his information in theform and context in which it appears.

    The Ore Reserve estimate is based on work completed by Mr Quinton de Klerk, who is a Member of theAustralasian Institute of Mining and Metallurgy. Mr de Klerk is a full time employee of Cube Consulting and hassufficient experience which is relevant to the activity which he is undertaking to qualify as a Competent Personas defined in the 2004 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resourcesand Ore Reserves. Mr de Klerk consents to the inclusion in the report of the matters based on his informationin the form and context in which it appears.

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 16

  • 7/27/2019 Wolf Minerals

    17/22

    Hemerdon Mineral and

    Ore Reserves

    ORE

    RESERVESPROVEN PROBABLE TOTAL

    Mt WO3 % Sn % Mt WO3 % Sn % Mt WO3 % Sn %

    Granite 18.9 0.18 0.03 2.4 0.18 0.03 21.3 0.18 0.03

    Soft Granite 4.6 0.19 0.03 0.9 0.21 0.03 5.5 0.21 0.03

    Total 23.5 0.19 0.03 3.2 0.19 0.03 26.7 0.19 0.03

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 17

    MINERAL RESOURCES TONNAGE (MT) WO3 GRADE (%) SN GRADE (%)Measured 76.8 0.15 0.02Indicated 40.3 0.13 0.02Measured and Indicated 117.1 0.14 0.02Inferred 284.2 0.13 0.02Measured, Indicated & Inferred 401.4 0.13 0.02

    Tables reported at a cutoff grade of 0.063% WO3

  • 7/27/2019 Wolf Minerals

    18/22

    DFS Headline Outcomes

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 18

    RESULT UNITS BASE CASE UPPER CASE

    APT Price** US$/mtu 360 415

    Operating Period Yrs 9.25 9.25

    Annual Throughput Mtpa 3 3

    Tungsten Production mtu/pa 345,000 345,000

    Tin Production t/pa 462 462

    Average Cash Cost* US$/mtu 105 105

    CAPEX M 104 104

    Operating SurplusM

    338 424

    EBITDA M 29 37

    Project NPV

    (post tax ungeared)

    M74M 114M

    IRR % 21% 26%

    Payback Years 3.25 2.75

    *After tin credits

    **EU APT Price 7/3/13 US$365 (Metal Pages)

  • 7/27/2019 Wolf Minerals

    19/22

    Capital and Operating Costs

    CAPITAL COST ESTIMATES

    ITEM 000s

    Process plant 65,366

    Infrastructure 8,491

    Land purchases 10,548

    Owners costs 10,403

    Contingency 9,314

    Total 104,122

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 19

    OPERATING COST ESTIMATES

    ITEM US$ /mtu

    Mining 66.99Processing 53.10

    General Administration (Inc. marketing & royalties) 15.52

    C1 Cash Cost for operating period 122

    Total Cash cost (After tin credits) 105.18

  • 7/27/2019 Wolf Minerals

    20/22

  • 7/27/2019 Wolf Minerals

    21/22

    DFS Data Sources

    STUDY AREA CONSULTANTS

    Mineral resources and Geology SRK Consulting Perth

    Ore Reserves and Mining Plan Cube Consulting Perth

    Mining Cost Estimates Cutback Consulting

    Hydrogeology Aquaterra

    Client Metallurgical Representative Coffey Mining

    Metallurgical Testwork Ammtec managed by GR Engineering Services

    Process Plant Design GR Engineering Services

    Plant Capital GR Engineering Services

    Plant Operating Costs GR Engineering Services

    Treatment and Refining Traxys

    Infrastructure and Services GR Engineering ServicesEnvironmental MRH Associates

    Tailings and Storage Facilities Coffey Mining

    Planning and permitting Mineral Planning Associates UK

    Archaeological Groundwork Archaeology Ltd

    Geological Consultant Richard Scrivener

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 21

  • 7/27/2019 Wolf Minerals

    22/22

    FOR FURTHER INFORMATION:Humphrey Hale - Managing Director

    P: +61 8 6364 3776

    E: [email protected]

    W: www.wolfminerals.com.au

    WOLF Minerals UK Tungsten ASX:WLF |AIM:WLFE 22