wind farm project development in poland – experience ... · wind farm project development in...
TRANSCRIPT
Wind farm project development in Poland –
experience report from a market participant
Conference „Marktpotential der Offshore-
Windenergie in Polen für deutsche Unternehmen”
Table of Contents
1. CRE – who we are 2. Wind farm project
development in practice – Legal rights (wind farm +
infrastructure) – Wind potential studies – Zoning procedures – Environmental procedures – Grid connection
procedures – Building permit procedures – PPA/CPA topics – Other procedures – Current problems
3. Procedure outlook for offshore wind farms in Poland – Procedures – Where are we? – Problems – Supply chain
– who we are
• Who is CRE
» Mother company established in 1989- active mainly on district heating technology market
» Cibet REenergy established in 2005 to manage renewable energy projects on booming market
• Experience of CRE
» BIOMASS
• Several (number) biomass fired heating plants (biggest 6 MWth)
» WIND
• 30 MW Kamionka wind farm
• Wind farm- development
• Construction supervision
• Technical maintenance
• Ca. 160 MW project pipeline in different development stages
• Due diligence of existing and developing projects
» PV
• Several projects 2-4 MW in development
Acquiring of legal rights
• Subject of legal rights
– Foundation
– Rotor area
– Infrastructure (roads, cables, connection lines)
– Noise impact area?
• Types of legal rights
– Land lease- 29 years due to legal regulations (typical for foundation, roads and internal cables, rotor area)
– Easement (typical connection lines, possibly rotor area)
Acquiring of legal rights
• Discussions with land owners
– Individual approach vs commune approach
• Depending on ownership structure and plot sizes
– Lease fees types (fix vs variable)
• Fixed yearly fee
• Shared risk- fee depending on green/black energy production and energy market prices
– Typical fees
• 5-10 k€ per turbine installed
Wind potential studies
• Timing: when to do – Cost wise optimal moment- after zoning plan – In practice: should be started right after main risk analysis
(feasibility study; discussion with commune, environmental authority and grid operator)
• Importance of wind measurement – in the past mainly for the banks; – now much more important for feasibility studies (due to
potentially lower tariffs)
• Permit procedures – easy procedure for 120 days; – full procedure for unlimited time – mix in practice
Zoning procedures
• Zoning study (Flaechennutzungsplan) - ZS
• Zoning plan (Bebauungsplan) – ZP
• Alternative: building conditions – BC (Bebauungsbedingungen) or Public Aim Investment Site Conditions – PAISC (Vorhaben des Oeffentlichen Zwecks); not possible if any ZP exists on given area – BC/PAISC shorter periods but slightly higher legal
risk of repeal
Zoning procedures
• What is common for which part of infrastructure
– ZS+ZP- wind farm
– BC/PAISC - substation
– LoPAIC- cable line
• Time frame
– ZS: 9-15 months
– ZP: 9-15 months (in some cases can overlap with ZS)
– BC: ca. 2 months (subject to Environmental Decision already issued); however legally not so „strong” as ZS+ZP
Zoning procedures
• Who does what?
– Procedures carried out by Local Government of commune
– Initiative:
• in case of ZS – Government (can also be inspired by Investor)
• in case of ZP - Investor
• in case of BC - Investor
• Who carries the costs and in which form?
– ZS has to be fully financed by the commune
– ZP should be financed by the commune; often developer covers these costs on basis of three-party agreement (government-developer-planning office)
– Various forms of sponsoring for local community are observed as well
• The role of the developer
– Close contact and cooperation with planning office
– Coordination of all tasks
– Close contact with commune increases the efficiency of procuring
Zoning procedures
• Cooperation Investor commune
– Information meetings
– Visits to existing projects
• Cooperation Investor permitting authorities (especially RDOS) due to external evaluation of zoning documents by different authorities
• Public consultations
• Typical combination of ZS & ZP
– Overlapping of the procedures
– Some common documents for both documents
Environmental procedures
• Environmental decision
– Necessary ZP prior to environmental procedure
– Typical timeframe 15 months + (including bird&bats monitoring)
– Lack of precise legal frames for environmental studies esp. Noise (general standards exist but authorities often intepret the standards by themselves), shadow flickering etc.
– Individual approach to each project by local RDOS!
• Bird&bats monitoring
– Commonly min. 1 year pre-construction monitoring
– Commonly 3 year post-construction monitoring
Environmental procedures
• Environmental Impact Assessment
– Complex study describing each element of local environment and assessing investment impact on these elements
– Based on environmental monitoring, calculations and literature
• The role of the developer
– Advisable strong influence on the planning office
– Advisable communication and strong discussion with RDOS due to lack of precise legal frames for studies
– Optimal approach: medium size planning office (not individual scientists) with coordination by the developer
Grid connection procedures
• Procedure and time frame – Max 150 days (specified by Energy Law)
• Pre-conditions for applying – Legal rights to the ground
– Zoning Plan
– Advance payment for connection costs (30 kPLN/MW ca. 7 kEUR/MW)
• Communication with the grid operator – Important contact with operator prior to connection
application due to various connection option
Grid connection procedures
• Negotiations of the grid connection contract
– Connection schedule
• Current problems and outlook for the future
– Big number of „dead” connection contracts blocking new projects
– No new conditions issued since November 2012 due to grid balancing problem
• Do not forget to sign the contract before building permit
Building permit procedures
• Technical design – timing – After grid connection is issued
• Geological survey
• Design documentation for the BP application
• What should be done in advance even if not obligatory for BP application – Extensive foundation planning
– Access roads
– Legal rights for cable routing (is often shifted by developers for near but in practice undefined future)
Building permit procedures
• Grid connection planning – Cable/land line choice
– Connection route
• Telecom line planning – Can be important since not all grid lines are equipped
with fiber optics
• Cooperation and communication with the grid operator – Necessary works to be done by the operator
– Switching off the grid while connecting necessary
PPA/CPA
• 2 yrs ago most typical concept: long term PPA/CPA
• Now: uncertain market of green certificates
• Excessively prolonged Renewable Energy Act and Energy Law Act legislative process
• Change of support system versions- certificates, auctions
• Auction mechanism could provide stability, however no details are known yet.
Other procedures
• Optimization of land usage – Soil classes; new regulations
• Better location on low soil class areas (class IV or lower) • Location on higher soil class areas (class III) above 0,5 ha requires
permission of the Ministry
– Permanent land usage transformation vs access roads to agro areas cost aspect
• Reactive power capabilities – real solutions – Investment approach vs energy usage optimizing incl.
Penalty fees
• Renewable energy generation license – Normally a formal aspect, but – Cannot be forgotten
Current problems
• Legislative problems
– Renewable Energy Act and Energy Law Act in preparation since 2 years- changing conceptions from green certificates to auctions
– Presidential initiative - Landscape Act in preparation
– MP’s proposition of moratorium for all wind farm projects
Off-shore in Poland- procedures
• Zoning - Location Decision for artificial islands refection issued by Ministry of infrastructure; valid for 30 years
• Environmental Decision- Issued by local RDOS itself instead of local government
• Grid connection conditions- issued only by transmission grid operator (PSE) instead of distribution grid operators
• Building permit- issued by voivodeship governor instead of district governor
Off-shore in Poland- where are we
• 20 Location Decisions issued
• 2 grid connection conditions issued: – Baltica 3- 1045,5 MW (PGE)
– Baltyk Srodkowy 3- 1200 MW (Kulczyk Investments)
– First connections 2019 earliest
• No Environmental Decisions issued so far- projects on environmental impact assessment stage
Off-shore in Poland- problems
• Natura 2000 areas along major part of Polish coast
• Grid connection- no new connection conditions issued for wind energy since November 2012
• No framework for PPA preparation?
Off-shore in Poland- supply chain
• Production of turbines’ masts
• Production of turbine blades
• Jack-up barges from polish shipyards
• Production of grid connection cables
Thank You for Your attention
Vielen Dank fuer Ihre Aufmerksamkeit
Fragen? Gerne!
Marcin Kaniewski [email protected] Office phone: +48 22 57 39 733
CIBET Reenergy Sp. z o.o. Al. Krakowska 197; 02-180 Warszawa POLAND Phone: +48 22 57 39 733; [email protected]