win win - norwep · performance, dnv gl has modelled the system taking into account failure rates,...
TRANSCRIPT
DNV GL © 2014
Ungraded
04 November 2015 SAFER, SMARTER, GREENER DNV GL © 2014
Ungraded
1
1st of March 2017
Johan Slätte, Senior Engineer
WIN WIN - Wind-powered water injection – Industry innovation and the development of an «impossible» idea
DNV GL © 2014
Ungraded
04 November 2015
Presentation outline
2
• Introduction to DNV GL
• Background to the WIN WIN JIP
• Brief introduction to Floating Wind
• The innovation project and it’s different phases
• Summary and conclusions
• Q&A
DNV GL © 2016 15 June 2016
Industry consolidation
3
DNV GL © 2016 15 June 2016
MARITIME
SOFTWARE
BUSINESS
ASSURANCE
ENERGY
OIL & GAS
Our vision: global impact for a safe and sustainable future
4
RESEARCH & INNOVATION
DNV GL © 2016 15 June 2016
Leveraging on experience - Offshore wind industry
5
DNV + GL + KEMA + Nobel Denton + Garrad Hassan =
DNV GL Energy
The world’s largest certification and advisory firm in renewable energy
DNV GL © 2016 15 June 2016
A number of facts…
6
DNV GL © 2016 15 June 2016
WIN WIN - Wind-powered water injection Assessing a new concept for water injection, utilizing wind power
7
WIN WIN is a concept for a new generation of oil recovery technology currently being assessed. It comprises a floating wind turbine which supplies power to a water injection process. The concept is a fully stand-alone system that includes pumps and basic water treatment. Our ambition is that WIN WIN will reduce costs, increase flexibility, and reduce emissions.
WIN WIN phase 1 main conclusions
1. Commercially competitive alternative in a range of cases 2. No technical showstoppers identified 3. Technically feasible
DNV GL © 2016 15 June 2016
Background - Inspiration for the WIN WIN project
8
Winter
2013/2014
Idea developed
internally
April 2014
Concept first presented
at OTC with call for a
joint industry project
February 2015
Partnership formed
and project started
May 2016
Project results
presented at OTC
->
Phase 2, pilot
testing and
commercial project
Image: Statoil Image: OTC 20078
Successful operation and deveopments
of floating wind technology
The development of EOR technology /
Tyrihans Raw Seawater injection for EOR
DNV GL © 2016 15 June 2016
WIN WIN (Phase 1) - A joint industry project
9
DNV GL © 2016 15 June 2016
Phase 1 - A recognized industry effort
10
DNV GL © 2016 15 June 2016
Renewable and O&G integration
11
In 2015/2016 assessment
• Statoils Hywind demonstrator, a floating wind turbine located offshore
Stavanger, Norway, has been operating since 2009. In the record year of
2011 it produced 10.1 GWh.
• The potential for moving the test unit to the Valemon platform has been
assessed by statoil.
• Valemon is today supported by power from the Kvitebjørn platform, 10
km away
• From being able to shut down one of the two gas tubines, a reduction
of 11000 tons of CO2 could be a achieved, with associated costs.
DNV GL © 2016 15 June 2016
A brief introduction to floating wind
12
DNV GL © 2016 15 June 2016
Floating wind turbines – Three key philosophies
13
SPAR TLP Semisubmersible
NREL
DNV GL © 2016 15 June 2016
Key milestones for floating wind technology
14
DNV GL © 2016 15 June 2016
Key milestones for floating wind technology
15
2009: Hywind demo – 1st spar buoy
DNV GL © 2016 15 June 2016
Key milestones for floating wind technology
16
2009: Hywind demo – 1st spar buoy
2011: WindFloat demo – 1st semi-sub
DNV GL © 2016 15 June 2016
Key milestones for floating wind technology
17
2009: Hywind demo – 1st spar buoy
2011: WindFloat demo – 1st semi-sub
2012: Kabashima/Goto Spar – 1st concrete/steel
DNV GL © 2016 15 June 2016
Key milestones for floating wind technology
18
2009: Hywind demo – 1st spar buoy
2011: WindFloat demo – 1st semi-sub
2012: Kabashima/Goto Spar – 1st concrete/steel
2012: VolturnUS – 1st concrete semi-sub
DNV GL © 2016 15 June 2016
Key milestones for floating wind technology
19
2009: Hywind demo – 1st spar buoy
2011: WindFloat demo – 1st semi-sub
2012: Kabashima/Goto Spar – 1st concrete/steel
2012: VolturnUS – 1st concrete semi-sub
2013: Compact Semi – 1st turbine connected to:
DNV GL © 2016 15 June 2016
Key milestones for floating wind technology
2012: VolturnUS – 1st concrete semi-sub
2013: Compact Semi – 1st of the Fukushima demonstration unit
2013: Fukushima floating substation – 1st floating substation
20
2009: Hywind demo – 1st spar buoy
2011: WindFloat demo – 1st semi-sub
2012: Kabashima/Goto Spar – 1st concrete/steel
DNV GL © 2016 15 June 2016
…and then, in 2015
21
Source: Windpower Monthly
DNV GL © 2016 15 June 2016
Looking forward, the first small projects are soon here
WindFloat Atlantic
27.5 MW off Portugal’s coast
30 m€ in funding from NER300
Operation aimed for 2018
22
Hywind Scotland
30 MW off Peterhead in Scotland
Financed by ROCs
In operation from 2017
Image: http://www.macartney.com/ Image: Statoil
DNV GL © 2016 15 June 2016
Summary – Floating wind
Floating wind offers a potential to reach the high energy yield
sites
Technology is developing
Leveraging on the knowledge and competence from O&G
Costs are coming down – The first arrays (several units) are to
be commissioned in 2017-2019
Potential to support O&G / other applications – Business cases
Leading to the WIN WIN JIP
23
Image: Knut Ronold, DNV GL
DNV GL © 2016 15 June 2016
WIN WIN – Integration of floating wind with O&G
24
DNV GL © 2016 15 June 2016 25
Is oil recovery affected by variable
injection rates?
Will the wind-powered system
function in an off-grid environment?
Technical
Can WIN WIN inject the required
volumes of water?
Functional
How much does it cost?
Is it competitive with conventional
technology?
Commercial
DNV GL © 2016 15 June 2016 26
III. Connected to platform II.Stand-alone system
with subsea equipment
I. Stand-alone system with
topside equipment
Concept options and functions
I. Standalone system with key equipment (pump, water treatment system) integrated with the floating structure
(‘Topside’)
II. Standalone system with key equipment subsea (pump, water treatment system)
III. Concept option I or II with power cable to production platform (i.e. system is not standalone)
DNV GL © 2016 15 June 2016
Use case and system specifications
27
Geographic location: North Sea
Water depth [m]: 200
Distance from production host [km]: 30
Reservoir conditions: 1 template, 2 injection wells, normal injectivity with
specified injectivity index
Target injection rate [bbl/d]: 44 000
Maximum injection rate [bbl/day]: 81 000
Maximum pump discharge pressure [bar]: 130
Water treatment requirements: Water filtration / chemical injection
DNV GL © 2016 15 June 2016
Different alternatives: Conventional vs. WIN WIN
28
Wind powered water injection (WIN WIN)
6 MW wind turbines and 2x2 MW pump
Autonomous system, injection through riser
Zero CO2 emission
Average 44.000 barrels of water injected per day
Conventional Gas Turbine System
3 MW gas turbine located on platform
Subsea flowline between platform and injection well
16.500 tonnes annual CO2 emission per well
Average 44.000 barrels of water injected per day
DNV GL © 2016 15 June 2016
The system
29
DNV GL © 2016 15 June 2016
The base case configuration and its functionality
30
1. A standard wind turbine is mounted to a floating foundation. This foundation also serves as a platform for the water injection system.
2. An electrical micro grid enables controlled start-up and shut-down of the system, and ensures that power demand matches power supply during operation. A battery bank ensures power to critical safety and communication functions during periods of no wind.
3. Communication with the host platform is enabled through satellite communication. A conventional control umbilical can also be used.
4. The system uses sea water, which is pumped topside using lift pumps.
5. The sea water is filtered down to 50 micron using a vertical disc filter with backwashing capability.
6. The water is treated with chemicals. Chemicals are stored on board in vessels, and refilled during other maintenance activities on the platform.
7. Water is injected into the reservoir by injection pumps.
DNV GL © 2016 15 June 2016
Performance of WIN WIN
The WIN WIN concept has shown that it can
meet the demands in relation to set
requirements
Key performance issues addressed in the project
include delivering required injection volumes,
understanding overall availability as well as
investigating start-stop cycles and downtime.
For the use case considered and others, WIN
WIN exceeds target injection rates over time.
Injection volumes over time have been simulated
based on realistic wind-data for the use case,
showing that volumes exceed target rate, despite
some periods of low wind.
31
DNV GL © 2016 15 June 2016
Commercial - CAPEX
Total CAPEX for the use case configuration with
process equipment located topside comes to around
75 MEUR.
The wind structure and marine operations and
logistics are the two main CAPEX drivers, together
contributing to more than 50% of CAPEX costs.
The pump system and development costs are also
significant in the overall investment.
32
DNV GL © 2016 15 June 2016
Commercial - OPEX
To achieve a realistic estimate of the O&M cost and
performance, DNV GL has modelled the system taking into
account failure rates, repair times and wind and wave data.
The resulting annual average operation and maintenance
costs are on the order of 4,7 MEUR.
Key drivers include parts, chemicals, and vessel costs.
Increased reliability of the system would positively influence
maintenance frequency and scope, in particular for
unscheduled maintenance, reducing operational
expenditures.
33
DNV GL © 2016 15 June 2016
The use case costs have been compared with a
conventional alternative where water injection is
accomplished with a flowline from the host.
While WIN WIN has higher operational
expenditures compared to a conventional
alternative, the significantly lower capital
expenditure means that it comes out comparable
in 20 year life-cycle comparison.
WIN WIN is therefore a commercially competitive
alternative in a range of cases, and especially
when host platform capacity is limited or injection
wells are located far away.
34
WIN WIN is cost-competitive for suitable fields
DNV GL © 2016 15 June 2016
Develop the WIN WIN concept along four pathways Validate, Innovate, Recommend and Explore
35
WIN WIN Phase 2 –Work Packages (WP)
A. Validate
Detailed assessment of pump type, performance and reliability
A.2
Electrical system
validation
A.1
B. Innovate
Detailed technology
assessment of water
treatment systems
Identify and assess
opportunities to
improve reliability and
reduce OPEX
B.3 B.4
C. Recommend
Development of
guideline for design
and operation of WIN
WIN
C.5
D. Explore
Identify other applications where wind power could
prove a cost-effective solution for the oil and gas industry
D.6
DNV GL © 2016 15 June 2016
WIN WIN - Wind-powered water injection Fruitful collaboration between the wind and oil industries
36
DNV GL © 2016 15 June 2016
SAFER, SMARTER, GREENER
www.dnvgl.com
Thank you
37
Johan Slätte
+ 47 917 38 338
DNV GL © 2016 15 June 2016
WIN WIN meets performance targets
38
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
In
jecte
d V
olu
me (
bb
l/d
)
Injected Volume Loss due to Equipment Failure Loss due to wind variation Injection Target
DNV GL © 2016 15 June 2016
WIN WIN is cost-competitive for suitable fields
39
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
WIN WIN Alternative
Leveli
zed
co
st
of
wate
r in
jecti
on
[EU
R/
bb
l]
Wells
Decommissioning
OPEX
CAPEX
Lifecycle cost per barrel of water, WIN WIN vs alternative, EUR*
*Only includes difference in well cost, full well cost not included. Assumed oil:water ratio of 1:20
$3
saved per barrel of oil
17 000 tCO2
Avoided per year
DNV GL © 2016 15 June 2016
An innovation project now entering a second Phase
40
In the phase 1 of the WIN WIN project a technical and commercial feasibility assessment was conducted with successful results. DNV GL and its joint industry partners have now started a phase 2 to drive the concept further towards commercialization by maturing the technical solutions, reducing uncertainty and cost, and enhancing performance.
The objective for Phase 2 is to develop the WIN WIN concept towards commercialization. The project will overall on the four following pathways:
Phase 2 - Objectives Phase 1 - Benefits
Feasible: The concept is, to a large extent, based on commercially
off-the shelf components and systems. Many of the remaining parts
are already undergoing full-scale testing.
Effective: WIN WIN meets performance requirements for a wide
range of injection volumes and several reservoir types.
Competitive: The concept can be cost-competitive, especially
when the host platform capacity is limited or the injection well is
located far away.
Emission: Potential to reduce emissions, reduce carbon tax, from
reduced need of operating gas turbines.
Flexible: The inherent flexibility of the WIN WIN concept means
that more water injection locations can be targeted through easy
relocation, regardless of distance to platform.
Innovative: Building on the strength of two industries, oil and gas
joins forces with wind to achieve something greater together, also
enabling a faster commercialization of floating wind turbine
technology
Validate: Build confidence and reduce uncertainty in the technical
solution developed in Phase 1
Innovate: Improve performance and competitiveness
Recommend: Develop guidelines for the design and operation of
WIN WIN
Explore: Identify other applications where wind power can provide
a cost effective solution