  • Willis Island Building Rectification

    Environmental Plan for Contractors

  • Willis Island Building Rectification Environmental Plan for Contractors

    Published by the Bureau of Meteorology 2013

    Commonwealth of Australia 2012 This work is copyright. Apart from any use as permitted under the Copyright Act 1968, no part may be reproduced without prior written permission from the Bureau of Meteorology. Requests and inquiries concerning reproduction and rights should be addressed to the Publishing Unit, Bureau of Meteorology, GPO Box 1289, Melbourne 3001. Requests for reproduction of material from the Bureau website should be addressed to AMDISS, Bureau of Meteorology, at the same address.

  • Willis Island Building Rectification Environmental Plan for Contractors

    i

    Revision history

    Date Version Description Author

    06-03-2013 V1.0 Approved D Aylward & S Arblaster

    Release history

    Date Version Status Audience Approval

    06/03/2013 V1.0 Approved External As per release signatories

    Document management register

    Document File reference

    25/008002 Construction Building Rectification Willis Island QLD

    Review Status

    Reviewer Date Reviewed Version Reviewed

    Project Manager Orion Law 17-02-2013 V0.1, V0.2 & V0.3

    Contractor Representative - GHD 20-02-2013 V0.2

    Release Signatories

    Approval Name Signature Date

    Project Manager Orion Law

    Manager WHS&E Sue Allen

  • Willis Island Building Rectification Environmental Plan for Contractors

    ii

    Contact details

    Darryl Aylward

    ES Section Planning Coordinator

    Bureau of Meteorology

    GPO Box 1289 MELBOURNE VIC 3001

    Phone: 96694672

    Email: [email protected]

    Sarah Arblaster

    Environmental & Sustainability Executive Officer

    Bureau of Meteorology

    GPO Box 1289 MELBOURNE VIC 3001

    Phone: 03 9616 8420

    Email: [email protected]

    mailto:[email protected]:[email protected]

  • Willis Island Building Rectification Environmental Plan for Contractors

    iii

    Contents

    1 Background ................................................................................................................... 1

    1.1 Scope ................................................................................................................ 1

    2 Funding ......................................................................................................................... 1

    2.1 Funding Codes for Willis island Site ................................................................... 1

    3 Location ........................................................................................................................ 2

    3.1 Lease ................................................................................................................. 2 3.2 Local Authority ................................................................................................... 2 3.3 Site Location ...................................................................................................... 3 3.4 Location Notes ................................................................................................... 4

    4 Schedule of Works ........................................................................................................ 5

    5 Nature of Project ........................................................................................................... 5

    5.1 Plant & Hand Held Tools .................................................................................... 5 5.2 Noise / Dust ....................................................................................................... 6 5.3 Transport ........................................................................................................... 6 5.4 Fuel / Chemicals ................................................................................................ 6

    6 Environmental Issues .................................................................................................... 7

    6.1 Matters of National Significance within 10 km radius of Willis Island .................. 7 6.2 Listed Threatened Species, Migratory Species & Marine Species ..................... 7 6.3 Existing Flora ................................................................................................... 11 6.4 Invasive Species .............................................................................................. 11 6.5 Breading Cycles .............................................................................................. 12 6.6 Environmental Objectives and Targets ............................................................ 13 6.7 Control Measures ............................................................................................ 21 6.8 Contact Phone Numbers .................................................................................. 34

    7 Appendix Flora & Fauna ........................................................................................... 35

    8 Appendix Legal Register .......................................................................................... 57

    8.1 Purpose & scope ............................................................................................. 57 8.2 Legal and Other Requirements Register .......................................................... 59 8.3 Other Environmental Obligations ..................................................................... 65

    9 References .................................................................................................................. 67

    9.1 Published ......................................................................................................... 67 9.2 Unpublished ..................................................................................................... 67 9.3 Websites Viewed ............................................................................................. 67

    10 Definitions ................................................................................................................... 69

    10.1 Significant impact ............................................................................................. 69

  • Willis Island Building Rectification Environmental Plan for Contractors

    iv

    List of Figures & Tables

    Figure 1: Willis Island Location................................................................................................. 2

    Figure 2: Willis Island - General Layout .................................................................................... 3

    Figure 3: Willis Island Site Layout showing work area .............................................................. 4

    Table 1: Yearly Species Breeding Chart .................................................................................. 12

    Table 2: Environmental aspects and impacts identified with projects works as per Appendix ... 13

  • Willis Island Building Rectification Environmental Plan for Contractors

    1

    1 Background

    Cyclone Yasi resulted in the services from the Willis Island Meteorological facility being

    significantly disrupted and unsuitable for human habitation. The Willis Island Restoration Project

    was initiated in 2009. The project objective was to restore the islands meteorological and

    habitation support services and to have the facility operational before end October 2011. The

    project scope also included addressing previously identified issues and improving sustainability

    and robustness against future severe weather events.

    The Willis Island Restoration project was run over two phases, Phase 1A & Phase 1B, each

    phase being a separate package of work. A third phase has been proposed and is awaiting

    approval.

    Phase 1A was planned as an interim solution, in which minimal restoration was completed to

    make the island and facility safe for reoccupation by Bureau staff and to restore the Upper Air and

    Visual Observations programs.

    Phase 1B of the Willis Island Restoration Project was to complete all works to restore the facility to

    full operations, address existing issues and improve the robustness and efficiency of the islands

    habitation support and operational systems.

    The Architectural/Engineering consultant for this project was GHD. The Phase 1B works

    contractor was Hutchinson Builders.

    The radar was restored on 24th October 2011 in line with the planned schedule. Data was

    available internally for forecasting purposes. Due to operational staff being removed from the

    island during the works, the data was not broadcast on the external web until normal operations

    resumed in early December.

    Some scheduled restoration work was not completed prior to restoration of the radar, and will be

    addressed by this project.

    For more information, refer to the Willis Island Restoration Project Phase 1B: End of Stage &

    Project Review Report.

    1.1 Scope

    The scope of this document is the completion of agreed rectification work to the Willis Island

    Met Office.

    2 Funding

    Funding arrangements for this project have yet to be determined.

    2.1 Funding Codes for Willis island Site

    Funding codes for this project have yet to be allocated.

  • Willis Island Building Rectification Environmental Plan for Contractors

    2

    3 Location

    The Coral Sea