widewater /wagner/nine mile point private sewer installations

21
Widewater/Wagner/Nine Mile Point Private Sewer Installations Municipal District of Lesser Slave River No. 124 1

Upload: tyler-mejia

Post on 04-Jan-2016

25 views

Category:

Documents


0 download

DESCRIPTION

Widewater /Wagner/Nine Mile Point Private Sewer Installations. Municipal District of Lesser Slave River No. 124. The Final LINK. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

1

Widewater/Wagner/Nine Mile Point Private Sewer

Installations

Municipal District of Lesser Slave River No. 124

Page 2: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

2

The installations of grinder pumps and lines from residences on private property to M.D. collection lines is the final link in finishing a project commenced in 2004.

This is the final stage of a $21.3 million project to bring rural sewage collection and treatment to the Southshore communities of Canyon Creek, Widewater, Wagner and Nine Mile Point

THE FINAL LINK

Page 3: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

3

AREAS SERVICED

Page 4: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

4

Where Are We At?The Municipal District is in the final stages of completing the collector lines and service connections (CCs) to hamlet lots. This work will be completed by July.

The Municipal District has tendered to secure a contractor to do the private property installations for homeowners and plans to award the tender by June 15, 2010.

The Municipal District is currently reviewing the tenders received.

Page 5: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

5

THE SCHEDULEThe project is anticipated to start on July 5th

with completion by September 2011.Minimum expectations were identified in the

tender with respect to completing the services in Widewater/Wagner/Nine Mile Point so works are finished by September 2011

Page 6: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

6

Construction Schedule25 installations by August 15, 2010 in

western Widewater90 installations by November 15, 2010 in

central Widewater to 2nd Street.135 installations by September 2011 from 2nd

Street in Widewater, through Wagner, to Nine Mile Point (and beyond)

Upon award, the contractor may give the M.D. a revised schedule that may result in work being completed sooner.

Page 7: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

7

ONSITE PROPERTY COST

Upon tender award, specific property cost estimates can be prepared.

We will provide you with this estimate once known.

However, a projection might look like this.

Page 8: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

8

Estimated Average Homeowner CostCOMPONENT TYPICAL PROJECTED

COSTBASIS OF ESTIMATE

Station Supply $ 4,380.00 Average supply cost 2004 through 2006, as per quote from Environment One.

Station Installation and Tie-In

$4,000.00 Projected typical installation and tie-in cost based on competitive tenders.

Service Line Supply and Installation (Property line to Station)

$3,640.00 Projected typical costs for up to a 100 meter service line.

Total $12,020.00 Projected typical cost per lot.

Page 9: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

9

What Does the Service Look Like?

Page 10: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

10

How Does the System Work Anyway?Wastewater from your residence flows by

gravity into the installed tank.At a certain capacity in the tank, the grinder

pump sends your wastewater to the M.D. collector line.

The wastewater moves under low pressure to the lift station by the Widewater Fire Hall.

The lift station then pushes this wastewater at a higher pressure to the Canyon Creek Wastewater Treatment Facility for treatment and return to the environment.

Page 11: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

11

Financing the Installation

Like the residents in Canyon Creek who installed services on their property previously, the Municipal District, through its financier, the Alberta Capital Finance Authority will provide Widewater/Wagner/Nine Mile Point residents with favorable, set rate financing over twenty years.

Currently these rates are 4.586% but the rates in effect are those when the M.D. secures the money.

Page 12: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

12

Not Using the Endorsed ContractorTo be consistent with the financing offered to

those previously, if you choose to use a contractor other than the endorsed contractor of the M.D., the installation cost is ineligible for financing.

One exception to this is for additional electrical costs by your own electrician – if you choose to use your own electrician.

Page 13: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

13

I Don’t Want This SystemIf your property is serviceable by this

wastewater system, you are required to hook-up to it under M.D. legislation (Bylaw 2003-08).

Page 14: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

14

Exceptions for Mandatory Hook-upThere are two exceptions to hook-up that

have been historically honoured during this project:

Properties that do not have municipal water service (though they are permitted to hook-up)

Properties with new, nonfailing, systems with approved Building Codes Permits – have been allowed to operate for 5 years from the date of installation approval.

Page 15: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

15

Economic Hardship

The Municipal District has the means to address, in strict confidence, cases where a citizen may simply not be able to afford the cost of the system, even with financing.

Public health and the environment is the priority.

Page 16: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

16

What is the Game Plan?The M.D. will award the private installations

contract by June 15, 2010Eligible residents will be sent a letter that:

Provides an initial estimate based on contracted costs of the M.D. endorsed contractor

Asks if they want to use the M.D. endorsed contractor or their own contractor/self

Asks if they want to take advantage of financing offered by the Municipal District

Page 17: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

17

Then What?Assuming you want the endorsed contractor, a

final estimate will be prepared as their may be some adjustments you want addressed with respect to your property (different siting than proposed).

Note: The costs associated with your installation are your costs. Modifications may increase your costs.

Upon installation completion, M.D. staff will verify the installation and commission it in service.

Page 18: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

18

Payment & Repayment AgreementsAssuming you want to take advantage of M.D.

financing:An agreement will be prepared based on the

final estimate subject to adjustment to actual costs.

The agreement shall be executed prior to any construction taking place by the contractor.

If you are not using a repayment agreement, but using the endorsed contractor, you will have to pay the cost upfront.

Page 19: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

19

Warranty, Parts, & RepairsThe warranty is one year from the date your

system is commissioned.Currently the M.D. has parts in stock but it is

working with local vendors/plumbers to service the market.

One local company has been qualified to service the grinder pumps and it is suspected others will follow suit.

Page 20: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

20

What About My Old Septic System?It can be decommissioned if you wish as you

won’t have a need for it.It can remain as there is an option in the

contract to install a valve to change from your existing system to your new system.

You may want to do a final pump out of your existing tank.

Page 21: Widewater /Wagner/Nine Mile Point  Private Sewer  Installations

21

Technical & Other QuestionsM.D. Council, staff and representative(s) from

the M.D.’s project engineering firm are here to answer your questions.