why was spelhaugen station exluded from construction step
TRANSCRIPT
Side 1 av 2 Versjon 1
Marketdialog meeting D18
Tidspunkt:
15.10.2020
Kl.: 09:00-11.00
Sted:
Teams Live meeting
Til:
Potential contractors D18
Procurement team D18,
Bybanen Utbygging
Written by
av by:
Christine S Larsen, Bybanen Utbygging
Present :
Contractors
Potential contractors D18
Procurement team D18 Bybanen Utbygging
Mona Løvås, Project manager D18
Catrine Hatlenes, Construcion Manger D18
Anne Vonli Dagsvik, Contract Manager D18
Daniel Frantzen, Design Manager D18
Cecilie Thiis, Process leader D18
Christine S Larsen, Negotiation leader D18
Summary, questions from the meeting:
Questions
1
Why was Spelhaugen station exluded from Construction Step 4? Answer: This was done due to financial reasons in order to reduce total amount. The end stop is now Oasen in Fyllingsdalen.
2 How many meters in the Kronstad tunel is Pipe Umbrella method Answer: The "arm" is 20 meter, the double part is 30 meter.
3 Will there be a limited number of contractors invited to tender? Answer: Yes this will be limited, but the number of tenders is per now not defined.
Side 2 av 2 Versjon 1
Attached with the minutes of meeting: The Presentation from the meeting.
4 Will there be a tender conference?
Answer: Yes, this will be arranged for the contractors invited to tender.
5 What is the D18 budget? Answer: This will not be informed of per now.
6 For the rig area and the availabilities/limitations, can you elaborate on this ? Answer: The eastern part of the parkinglot at Møllendal kapell is the planned rig area. When Møllendalsbakken 6 (Drevelinbygget) is demolished, there will as well be possibilities for using this ground as rig area. Access to tunel will be from the Kronstad side. There will most probably also be possibilites for access to the construction area at Kunsthøgskolen, but for this sone there will be weight limitation for transport crossing the railway bridge.
7 Will the D18 3DModel be available? Answer: Yes this will be available in the competion documents for the contractors invited to tender.
Bybanen Utbygging (BU)
Market dialog Bybanen byggetrinn 4
D18 Sykkelvei Kronstadtunnelen
Dato: 2020-15-10
Bybanen Utbygging
The procurement team
Project managerMona Løvås
Negotiation leaderChristine Sletten Larsen
Process leaderCecilie Thiis
Construction managerCatrine Hatlenes
Contract managerAnne Vonli Dagsvik
Design managerDaniel Frantzen
Todays goal is not.. …
• to invite for a tender conference
• to give a lesson into deep detail on Bergen Light Rail
Todays goal is to give the market a presentation of the upcoming contract D18 Sykkelvei Kronstadtunnelen for Bergen Light Rail stage 4.
The presentation will be uploaded at the website of Bybanen Utbygging; https://www.hordaland.no/bybanen-utbygging/
Agenda
• Presentation of the Bergen Light Rail project– Overall presentation of the project
– Presentation of construction stage 4
• Presentation of the contract D18
• Progress and procurement
Criteria for success
• Predictability– Segregated tracks
– Priority in all traffic crossings
• Frequency
– Efficient operations
• Availability– Smooth transfers
– Urban adapting
– Open and easy readable system
– Universal design
• Quality– Good design
– Efficient maintenance
Bergen Light Rail is awarded with several prizes
• Worldwide project of the year 2011
• Red Dot Design Award 2011
• Vakre veiers pris 2012
• SRF-prisen 2012
• Kollektivprisen 2012
• BOBY – byutviklingspris 2012
• Bymiljøprisen 2012
• Årets anlegg 2013
• Innovasjonsprisen UU 2015
2010 2011 2012 2013 2014 2015 2016 2017
0
2 000 000
4 000 000
14 000 000
12 000 000
10 000 000
8 000 000
6 000 000
Bybanen 2010-2017
Antall påstigende
Byggetrinn 1 juni 2010
Byggetrinn 2 juni 2013
Byggetrinn 3 august2016
Byggetrinn 3april 2017
Bergen Light Rail – Who are we ?
• We are a public developer working on behalf of the County Council of Vestland and the members in Byvekstavtalen (City growth agreement)
• We are given the authorization to develop and manage the strategies for procurement and execution of theconstruction works.
• We are responsible for the engineering, procurement,construction and handover to the owner and maintainer of the infrastructure.
Bergen Light Rail & the contractors
Contractors are of a high importance to us:
• They are the ones executing the construction
• It is paramount that the contractors fully understands their tasks and scope of work
• Contractors must have the correct and needed competence and ability to execute
• In Bergen Light Rail we depend on having high skilled entrepreneurs and contractors
Bergen Light Rail – we are …
• a professional and demanding client
– Only the good contractors are allowed to work with us
• a client with a high competition focus and ability to create a competition in the market. Targets are:
– Contractors of good quality
– Reduction of uncertainty in the market
– Gain the "correct price"
Recieve the order
Procurement Building HandoverEngineering
D14 Mindemyren
D12 Ado Kronstad
BU delstrekninger
D11 Sentrum
Existing line (grey)Sentrum – Airport.(approx. 20 km)
D15 Løvstakk tunnelen
D19 Buss terminal
D16 Fyllingsdalen
D18 Sykkelvei Kronstadtunnelen
Building stage 4 contains:
• Prepared zoning plan agreed in Bergen City Council June 21st 2017
• Approx. 10 km of railway from Kaigaten(in City centre) to Oasen (inFyllingsdalen) - Approx. 5 km of distance in open air, 5 km of tunnel
– Travel time approx 20 minutes
– Good development of urban areas and the Haukeland UniversityHospital.
– New connection between Fyllingsdalen and Bergensdalen
– New paths for walking and bicycling
• 8 new stops + 2 common stops with Line 1 (Kaigaten and Nonneseter)
Cut april-18
Progress highlights
• Approved zoning plan
• KS2 process
• Startup Procurement Main contracts
• Startup Building Main contracts
• Startup Technical contracts
• Test driving
June 21st 2017
Sept. 2017
Feb. 2018
Dec. 2018
Autumn 2019
Winter 2022
What does «Green construction of light rail» mean ?
Bergen Light Rail wants constructive green contractors
• Requirements to renewable energy (80%)
• Requirements to electrical vehicles for transporting workers
• Requirements to more low emission concrete where applicable
• Encourage to use electrical construction machinery
• CEEQUAL-certification
Summary - Scope of work
1) Demolition of Møllendalsbakken 6 2) Dismantling/removal of old bridge north of Kronstadtunnelen3) 100 meters concrete culvert for railway4) 60 meters mountain tunnel for railway5) Ventilation and emergency lighting for railway6) Escape route from the railway tunnel7) Expansion of bridge in Møllendalsbakken. 8) Rebuilding and expanding old Kronstad tunnel (railway) to a pedestrian and bicycle tunnel. 9) Establishing an additional exit for pedestrians in the northern end of the PB-tunnel, through soil under
Møllendal cemetery. The method chosen is «Pipe Umbrella».10) Pedestrian and bicycle path11) Renewal and upgrade of Water and sewage, new water pipeline and new drainage between Kronstad and Fløen12) Protected cultural monuments
Summary
• Interphase towards other contracts in BT4
• Public agencies such as BKK, water & sewage dep., Norwegian road administration among others
• Bane NOR (national railway infrastructure)
• - specified time for connecting new tracks to excisting tracks (des 2022)
• Neighbours, public schools, cemetery, medical hospital
• Limited access to construction site
• Urban construction site
• Traffic
• Pedestrians
• Kindergarden/Day care
D18 - Progress
Estimated Progress Purchase D18
AnnouncementDeadline Qualification
November/December 2020Minimum 30 days afterannouncement
Deadline for tender March 2021
Contract award June 2021
Startup August 2021 (some preliminary work in June)
Procurement
• Qualification requirements
– ESPD-form
– Documentation for fulfilment of qualification requirement to be submitted together with the application
• Award Criteria
– Total price
– Comprehension of the assignment
And finally
• Please read the competition documents carefully and submit the application for qualification and tender according to the given guidelines.
• Use the opportunity to ask questions if something is unclear
• Start uploading documents in TendSign (the procurement tool) well in advance of the deadline