Why Should An Agency Consider Contractor Prequalification?
The Proper Prequalification Process Benefits of Construction Management Questions
![Page 3: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/3.jpg)
Benefits
Improves Bidder Pool/Requires Experienced Contractors
More Sophisticated Bidders =• Better Questions During Bidding Phase• Reduce Bid Protests• Less Frivolous Change Orders During Construction Phase
The Process Saves Money
![Page 4: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/4.jpg)
Benefits
Avoids Post-Bid Disputes Regarding Responsibility of Low Bidder
More Sophisticated Bidders =• Fewer Unnecessary Pre-Bid Questions• Better Scheduling & Project Management During Construction
Phase• Reduces Risk of Bid Protests
The Process Saves Time
![Page 5: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/5.jpg)
Burdens
Requires Staff/Consultant/Attorney Efforts Up Front Learn Proper Process Improper Process Can Create Challenges Spending Time/Money On Designers/Consultants To
Tailor For Each Process
The Process Costs Money
![Page 6: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/6.jpg)
Burdens
Advanced Planning is Critical Code Allows Parallel Process With Bidding Best Practices Suggests Process Complete
Before Bidding Starts Governing Board Action Recommended
Practice Tip: Process Can Commence Before Design Is Complete
The Process Takes Time
![Page 7: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/7.jpg)
Annual Prequalification By Project Size
Questions1. Does The Agency Do Multiple Projects Within A Certain Bid
Amount?2. Does The Bidding Pool Vary From Project To Project?
No Obligation That All Projects Done Within Time Period Use Prequalified Bidders
![Page 8: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/8.jpg)
Annual Prequalification By Project Type
Questions1. Does The Agency Do Numerous Projects Of Similar Nature?2. Typically, Does Size Of Project Matter?3. What Are The Risk Factors With Specific Project Types?
Typically Used By Large Agencies That Complete Numerous Projects
![Page 9: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/9.jpg)
The CRITICAL Timeline
Analyze Prequalification Packages Perform Independent Due Diligence Check References Evaluate/Score Packages Send Letters To Those Seeking
Prequalification Conduct Administrative Appeals
Hearings Gain Approval Of Final Documents Issue Bid Documents
![Page 10: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/10.jpg)
The CRITICAL Timeline
ReceivePrequalification Package
AdvertisePrequalification Evaluate Packages
Appeals Due
Conduct Appeals Hearing
Advertise Bidding Documents
Allow For Any Further Protest
(Suggested Timeframe *)
(4 Weeks)
(2 Weeks)
(1 Week) (1 Week)
(2 Weeks)
(1 Week)
![Page 11: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/11.jpg)
Drafting Prequalification Package
Three Types Of Questions• “Light-Switch”• Scored• Informational
![Page 12: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/12.jpg)
Drafting Prequalification Package
Establish List Of Project Features What’s Most Important For Project Success?
• Drop Dead Time Limitations?• Community Impact?• Specific Experience Of Prime – Can They Do The Job?
![Page 13: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/13.jpg)
Drafting Prequalification Package –Sample Language
Similar Construction Projects CompletedPrime Contractors Number Of Public Works Projects With An Engineer’s Estimate Of
$10M Or Greater Number Of Public Works Projects Completed Using State Standards Number Of Projects Completed In Which Company Was Responsible
for Excavating And/Or Placing Fill Material In Excess Of 200,00CY Number Of Cast-In-Place Bridges Completed Per State Standards Number Of Projects In Which Company Was Responsible For
Underground Utility Construction (Water, Sanitary Sewer And Storm Drain Construction) In Excess Of $2M
![Page 14: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/14.jpg)
Analyze Prequalification Packages
Independent Due Diligence Reference Checks Evaluation And Scoring Be Thorough Keep It Objective And Fair
This Is The MOST Important Step/Most Errors By Owners
![Page 15: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/15.jpg)
Dealing With The Unqualified Contractor
Code Requires That Unqualified Contractors Receive Written Notification From Agency Including The Basis For Non-Qualification And Any Supporting Documents
Important To Track Scoring Of Each Contractor To Substantiate Decision
![Page 16: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/16.jpg)
The Administrative Appeals Process
The Best Process (Do It Early!):(Not All Required By Code) Establish Appeals Panel And Gain Governing Board
Approval Establish Appeals Process
• Standard Questions• Standard Scoring
Set Amount Of Time For Hearing Panel Should Promptly Issue Written Ruling
![Page 17: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/17.jpg)
Contractor's Other Remedies
If Contractor Is Deemed Non-Prequalified By The Appeals Panel, It Could:• Appeal To Governing Board• Bring Writ Of Mandate• Potentially Seek Temporary Restraining Order To Stall Bid Process
Arbitration Alternative• New Process/Currently Being Tested• Insures Completion Of Process Before Bidding• Accelerated Process Deters Further Action
![Page 18: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/18.jpg)
Real Life War Story
The Complicated One(Forester Creek Improvements) $19M Estimate $23.5M Actual Bid Amount Project Required Negotiation And
Approval Of Multiple Resource Agencies, Including:• Caltrans• ACOE• SDRWQCB• F&W
Three Distinct Project Components• Bridges• Earth Work• Utilities
Created Experience Requirements For Each Component
![Page 19: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/19.jpg)
Real Life War Story
The Complicated One(Forester Creek Improvements) The Forester Creek Improvement
Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically, Projects Listed Must Demonstrate Your Firm's Experience With:• Large Excavation And Fill Operations• Bridge And Retaining Wall Construction• Water, Sanitary Sewer And Storm Drain
Construction And Relocation• Landscaping And Irrigation Construction• Demolition Of Structures
![Page 20: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/20.jpg)
Real Life War Story
The Complicated One(Forester Creek Improvements)Sample Questions Provide Only Five Projects That Meet
The Requested Requirements Projects Submitted For Review Must
Have A Contract Amount Of No Less Than 60% Of The Engineer's Estimate $17.8M ($19M)
Projects Listed Must Demonstrate That Your Firm's Experience Matches The Work Required To Be Performed In Connection With This Project
![Page 21: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/21.jpg)
Real Life War Story
![Page 22: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/22.jpg)
Real Life War Story
![Page 23: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/23.jpg)
Known Bidder’s Pool
Bidders Will Be Able To Do Project• Residential And Commercial Contractors Bidding Public Work
All "Dirty Laundry" Out In Prequalification Phase Bidders Are Willing To Spend Time/Money To Participate In
Prequalification = Really Want Project And Make Commitment
![Page 24: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/24.jpg)
Optimum Use Of Available Funds Control Of The Scope Of The Work Project Scheduling Optimum Use Of Design And Construction Firms' Skills And Talents Avoidance Of Delays, Changes And Disputes Enhancing Project Design And Construction Quality Optimum Flexibility In Contracting And Procurement
![Page 25: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/25.jpg)
![Page 26: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/26.jpg)
![Page 27: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/27.jpg)
![Page 28: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/28.jpg)
![Page 29: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/29.jpg)
![Page 30: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/30.jpg)
![Page 31: Why Should An Agency Consider Contractor The Proper …€¦ · The Forester Creek Improvement Project Was A Federally Funded Project Using Caltrans Metric Standards. Specifically,](https://reader036.vdocuments.site/reader036/viewer/2022081613/5fb56c4efbc5df0391614b1e/html5/thumbnails/31.jpg)
We serve our clients with honesty, integrity, candor, and objectivity. We assign staff to projects in accordance with their qualifications and commensurate
with the services to be provided. We furnish services consistent with the established and accepted standards of the
profession and with the laws and regulations which govern its practice. We endeavor to avoid conflicts of interest. We will negotiate fairly and openly with our clients in establishing a basis for
compensation. We only make statements that are truthful, and will keep information and records
confidential when appropriate and protect the proprietary interests of our clients and professional colleagues.
We will not discriminate in the performance of our services on the basis of race, religion, national origin, age, disability, or sexual orientation.
We continue to develop professional knowledge and competency, and contribute to the advancement of the construction and program management.
We avoid actions which promote self-interest at the expense of the profession, and will uphold the standards of the construction management profession with honor and dignity.