P a g e | 1

Solar PV Proposal: London Borough of Hounslow

Western International Market

RE:FIT FRAMEWORK

Page 2: Western International Market RE:FIT FRAMEWORKdemocraticservices.hounslow.gov.uk/(S(czobl0450xbqi155ede3ifez... · • Training records, Plant records & weekly inspection checks 3.6

P a g e | 2

Version Control

Document Title : WLA RE:FIT – WIM Solar PV Proposal

File name : RE:FIT Version Control Sheet

Client Name : London Borough of Hounslow

Author(s) Paul Burnett

Date Created : 17th January 2015

Last Updated : 29th January 2015

Last Updated By: Paul Burnett

Revision Control Summary

File Name Release Date Summary of Changes Location of Change Change Impact

WIM Solar PV v1 19/01/2015 1st issue N/A N/A

WIM Solar PV v2 28/01/2015 Financial model

corrected to account

to reflect fluctuations

in financing cost &

capital cost altered to

reflect inclusion of

timers for forklift

charger controls

Section 2.0

Commercial

Appendices –

Business Case

(Project Calculator)

Reduction in

capital cost

Change in

Business Case

WIM Solar PV v3 29/01/15 Inclusion of DC

Battery Storage

Option

Section 2.0

Commercial

Appendices –

Business Case

(Project Calculator)

Increase in capital

cost

Improvement in

system benefits

Improvement in

Business Case

Document Authors

Description Primary Contact Secondary Contact

Name Paul Burnett Lee Podger

Position Group Development Director Head of Energy Services

Address Imtech House, 33-35 Woodthorpe

Road, Ashford, Middlesex, TW15

2RP

1 Deben House, Selsdon Way,

London

Mobile 07825 722318 07767 116 013

E-Mail [email protected] [email protected]

Page 3: Western International Market RE:FIT FRAMEWORKdemocraticservices.hounslow.gov.uk/(S(czobl0450xbqi155ede3ifez... · • Training records, Plant records & weekly inspection checks 3.6

P a g e | 3

1.0 Overview

Imtech have been appointed as an Energy Services Company (ESCo) to all of the London Boroughs within the West London Alliance including the London Borough of Hounslow via the GLA’s Re:Fit Framework. The London Borough of Hounslow has previously identified the Western International Market as an opportunity for the development of Solar Photo Voltaic (PV) panels. Solar PV panels are eco-friendly electric generators. They convert sunlight into electrical energy, have no moving parts, put out zero emissions and require very little maintenance. They generate free electricity and are eligible for government incentives which create not only a sustainable opportunity but an investable one.

Western International Market will be a unique solar PV installation in the UK because of its size and the way the power is distributed to its existing tenants. London Borough of Hounslow currently buys it power from Laser, and this passes through 3 x meters on the site. The tenants have checking meters within their units, which are noted on a monthly base, and the tenants are billed accordingly. With the introduction of a Solar PV system, nothing changes for the tenants as far as billing and cost of electricity. The only thing that changes is where the power comes from as a large proportion will now come via decentralised energy (Solar PV), meaning during the day, it will purchase less power from Laser (currently 10.29 pence per unit). This would mean that London Borough of Hounslow would see savings of £125,968.91 in the first year from the Laser Bill. London Borough of Hounslow would also receive government incentive payments via the Feed In Tariff (FIT) for every unit of power produced from the PV modules, this would be £97,591.03 in the first year. The other big feature for the system will be the use of black framed LG modules that are market leaders in solar PV module production. We have chosen this design based on some key factors:

• Warrantees and guarantees (modules come with 25 years, SMA inverters will

be extended to 20 years)

• Aesthetics (Black framed LG modules)

• Performance (LG modules have an efficiency of 17.1%)

• Breakdown Cover (24H monitoring system installed)

1.1 About Imtech Imtech is one of the UK and Ireland’s largest and most successful broad-based technical services providers. Our 3400 employees deliver high quality solutions for national and international customers through our extensive network of offices. Our low carbon proposition is based on an integrated model that creates solutions to meet the needs of today whilst reducing the demand on the natural environment for tomorrow. Low Carbon Solutions is not a single business unit, its proposition spans the complete organisation and is led by a central specialist development team that draws upon the delivery expertise from across the group. This approach capitalises on the strength in breadth and depth of Imtech UK’s operations and provides a holistic ultra-low carbon technical asset management service.

Page 4: Western International Market RE:FIT FRAMEWORKdemocraticservices.hounslow.gov.uk/(S(czobl0450xbqi155ede3ifez... · • Training records, Plant records & weekly inspection checks 3.6

P a g e | 4

Imtech became an accredited MCS renewable energy installer back in 2008 and have undertaken a significant amount of Solar installations since then and in 2013 alone Imtech supplied and installed 17,000 Solar PV panels on behalf of their clients, the equivalent of 3 full size football pitches. Imtech’s work streams and business solutions are illustrated below;

Page 5: Western International Market RE:FIT FRAMEWORKdemocraticservices.hounslow.gov.uk/(S(czobl0450xbqi155ede3ifez... · • Training records, Plant records & weekly inspection checks 3.6

P a g e | 5

2.0 Commercial

The total capital cost to design, supply and install the complete solar PV system is £2,050,000 excl VAT. The cost breakdown is as follows;

1. Supply of materials, plant and equipment £1,706,524.00

2. Provision of Labour incl BWIC £211,136.85

3. Project & Site Management £79,369.36

4. Design incl planning and structural £52,949.79

TOTAL:- £2,050,000.00

This price specifically excludes the following;

a) GVA Consultancy Fees (assumed by London Borough of Hounslow)

b) Building Control Fees (assumed by London Borough of Hounslow)

c) CDM Co-ordinator (assumed by London Borough of Hounslow)

d) Assumes site office will be provided free of charge

During recent meetings we have discussed a number of options to increase the amount of energy consumed on site from the panels and therefore reduce the grid export. The provision of timers on the forklift chargers has now been included within this proposal which we estimate that the addition of this item will reduce the currently predicted export to 20%. A final option has now been included within this updated proposal which is the inclusion of the DC Battery Storage product (Solar Ready) and we compare below the business case, which we estimate that the addition of this item will reduce the currently predicted export to 9%.

2.1 Business Case Excl Batt Stor Incl Batt Stor

Payback in Years 11.22 11.20 System Life Benefit £3,412,568 £3,700,604 IRR 8.9% 9.1% Kg Co2 Saved pa 790,824 790,824 See appendices section for detailed analysis (project calculator)

Page 6: Western International Market RE:FIT FRAMEWORKdemocraticservices.hounslow.gov.uk/(S(czobl0450xbqi155ede3ifez... · • Training records, Plant records & weekly inspection checks 3.6

P a g e | 6

3.0 Construction Methodology &

Implementation

3.1 Site location

The works are located on the WIM on both the roof of the Produce and Flower Halls.

With works being undertaken at during the day the site team will utilise the VMU forecourt for materials deliveries, waste away and parking.

If larger areas are required for bulk deliveries this will be agreed with the WIM site management team in advance. Whilst working on site we will set up a set file which will contain the following:

• Site signing in point

• Fire plan

• H&S / RAMS file

• Copies of relevant insurances

• Point of works risk assessments

• Suggestions / Improvements Page

Page 7: Western International Market RE:FIT FRAMEWORKdemocraticservices.hounslow.gov.uk/(S(czobl0450xbqi155ede3ifez... · • Training records, Plant records & weekly inspection checks 3.6

P a g e | 7

We will also leave a first aid box and fire pt on site for the duration of the works at each work location.

Temporary lighting & power, will be provided to allow works to continue in safe manner if required. Once the site is set up it is envisaged that the majority of works will be undertaken during the day, this will include any noisy works and deliveries.

Site Hours Our site hours will be:

Day time – 10am till 7pm (tbc)

Weekends – As required, hrs as above.

Night works – No night time works.

Deliverables • Site set up / delineation

• Logistics Plan

• H&S plan

• Fire plan

3.2 Panel Selection When selecting the panel (LG) for this project business cases where run with other panels e.g. Sunpower and Trina. On a production and rate of return basis the LG panel was most desirable for this project.In addition to the above the LG warranties etc are also in line with the lifecycle of the FIT.

• Please refer to appendices for the performance data on each panel type.

Storage Materials will be delivered on a just in time basis and stored either outside the VMU or at a location agreed with the council.

Pallets will then be lifted (by crane) up onto the maintenance gantry to the point of work of each team.

Deliverable • Storage plan / strategy

3.3 Protection of the works With the majority of the works being delivered to site for assembly in their finished state, temporary protection of the works will be kept to a minimum. In the main, protection of the works will be managed by the site delineation barriers and restricted access into the works area.

Deliverable • Zero damage to finished works

Page 8: Western International Market RE:FIT FRAMEWORKdemocraticservices.hounslow.gov.uk/(S(czobl0450xbqi155ede3ifez... · • Training records, Plant records & weekly inspection checks 3.6

P a g e | 8

3.4 Waste away All construction waste will be neatly stored on site and placed in the buildings skips on a daily basis.

Deliverable • Waste receipts & Re use data

3.5 Access to the works / Working at height It is important that all works are accessed in a safe manner.

Access up onto the service gantry’s will be via the existing staircases. Once on the gantry’s access onto the roof will be by way of a scaffold stair. Once on the roof operatives will utilise the existing man safe system.In addition to the above edge protection will be provide to all working areas.

Also training records will be retained on site for any operatives using access equipment e.g PASMA training etc.

Deliverable • Training records, Plant records & weekly inspection checks

3.6 Undertaking the works

Programme We would confirm our programme for these works as 12 weeks with a weeks site set up and decommissioning at either end of the programme (14 weeks in total) comprising: When considering our programme

• Site set up = 1 week.

• Team 1 = 50KW per week for 12 weeks

• Team 2 = 50KW per week for 12 weeks

• Team 3 = 50kw per week for 12 weeks

• Upon completion of the works decommissioning will take week.

The work sequence for each gang will be as follows:

• Mounting

• Panels

• Electrical containment and Cabling

• Site & Mount Invertor

• Visual Inspection

• Final connection

• Test and Commission with DNO connections engineer.

During mobilisation a detailed programme will be produced for each gang in tandem with a pictorial representation which will show weekly productivity targets to be met.

Page 9: Western International Market RE:FIT FRAMEWORKdemocraticservices.hounslow.gov.uk/(S(czobl0450xbqi155ede3ifez... · • Training records, Plant records & weekly inspection checks 3.6

P a g e | 9

Long Lead Items Panels = 6-8 weeks Invertors = 6-8 weeks Mounting systems = 2-3 weeks

Turnaround & approval times We would confirm that we have allowed maximum 1 week duration for all client approvals.

Last Planner

A last planner will be produced on a weekly basis to ensure programme adherence & weekly marked up programmes will be issued.

This will also be done for the manufacture of the panels & invertors, thereby ensuring all parties are kept up to date with progress.

Deliverables • Programme

• Weekly programme updates / lookaheads

• Timely delivery of the project.

3.7 Quality Imtech will develop a project quality plan.In line with our Project Delivery procedure a detailed ITP will be produced for each work activity. As the works are completed the ITP will be reviewed and updated accordingly. The ITPS will be reviewed regularly to ensure adherence to our quality procedures.

Deliverable • Project ITP

3.8 Health & Safety

All works will be undertaken in accordance with the procedures set out within our project H&S plan (see attached draft). All personnel will be inducted, suitably trained, and work in accordance to approved RAMS. Weekly recorded H&S inspections will be undertaken at each location and issued for information.

A designated working site foreman will be retained to manage the site at all times. Welfare will be provided in the existing on site welfare facilities, Whilst the nearest terminal toilet blocks are located close by. Both these facilities will be monitored and cleaned on a regular basis. No changing will be permitted on site. No eating will be permitted on site, other than in the welfare facility provided.

Page 10: Western International Market RE:FIT FRAMEWORKdemocraticservices.hounslow.gov.uk/(S(czobl0450xbqi155ede3ifez... · • Training records, Plant records & weekly inspection checks 3.6

P a g e | 10

Deliverables • RAMS

• Daily briefings

• Training records

• H&S inspections

• Attendance at H&S consultations

• Near miss reporting

• Point / place of works risk assessments

3.9 Environmental Imtech strive to reduce the environmental impact of all works they undertake. Records of all waste generated will be provided.

Deliverables • Waste receipts

• Sustainability records

3.10 Handover and integration

Our Handover manager will liaise closely with our production team & the Imtech and LBH team and will be responsible for the co-ordination & early production of the following Ssep Handover deliverables:

Deliverables

• H&S files

• As built information for each elemental work package

• As built drawings (these will be marked up by the installation teams and

produced by project designer)

• Certification

• Specific Parts Information

• Asset Integration as required

3.11 Training, Familiarisation, & Witness Testing (with the Building

Staff) Whilst the works are being undertaken we will also invite the Building staff to undertake regular training & familiarisation visits as the works progress.

We will also produce a detailed Testing & Commissioning Programme to ensure the building management team are able to witness all relevant witness testing.

3.12 Learning & Feedback Throughout the life of the project learning and feedback will continually underline everything we do.

We will look to record and learn from each activity we undertake and look to improve from this experience.

Page 11: Western International Market RE:FIT FRAMEWORKdemocraticservices.hounslow.gov.uk/(S(czobl0450xbqi155ede3ifez... · • Training records, Plant records & weekly inspection checks 3.6

P a g e | 11

Learning & Feedback will be an agenda item for all team review meetings.

Deliverable • Learning review upon completion of the work

3.13 Risk and Opportunity register

Risks • Working in a live operational area

• Working at heights

• Transportation of heavy loads / logistics

• Working on & around M&E services

• Time – Long lead in items

• Approvals e.g. Planning etc

Opportunities • Value engineering to Reduce cost / programme

• Energy storage = Solar Ready

Deliverables • Risk & Opportunity workshop

• Detailed project risk register

• Updated risk register - Fortnightly

3.14 KPI’S

We have identified the following KPI’s as part of our project delivery strategy

1. Zero incidents or accidents.

2. Undertake weekly health & safety audits.

3. Cost plan adherence.

4. Programme adherence.

5. Quality – Zero snags / defects at the time of handover to the end user.

Deliverables • Review and update of KPI’s in the weekly project review meetings

Page 12: Western International Market RE:FIT FRAMEWORKdemocraticservices.hounslow.gov.uk/(S(czobl0450xbqi155ede3ifez... · • Training records, Plant records & weekly inspection checks 3.6

P a g e | 12

4.0 Clarifications, Assumptions &

Exclusions

• We have made no allowance for asbestos removal, or any works or delays

associated with asbestos.

• We have assumed client approvals will be made within a maximum 1 week

period.

• We have assumed there are adequate M&E loads available.

• We have assumed the roof and gantries alike can take the load of the system

and delivery loads. To be verified by our structural eng.

• No allowance has been made for the ongoing maintenance of the system.

• No allowance has been made for the CDMC role

• System production figures are based on statistical weather data.

• Whilst the panels etc come with performance guarantees we are not able to

guarantee the performance of the weather.

• We have assumed a min of 30day payments.

• Due to the high specialist material content a 60% deposit will be required,

following by another 20% on commencement of the works, and the final 20%

upon completion of the works.

Page 13: Western International Market RE:FIT FRAMEWORKdemocraticservices.hounslow.gov.uk/(S(czobl0450xbqi155ede3ifez... · • Training records, Plant records & weekly inspection checks 3.6

P a g e | 13

Appendices

• Business Case (Project Calculator)

• LG Panel Specification

• LG Panel Guarantee

• Inverter Specification

• Panel Layout Sketch

Page 14: Western International Market RE:FIT FRAMEWORKdemocraticservices.hounslow.gov.uk/(S(czobl0450xbqi155ede3ifez... · • Training records, Plant records & weekly inspection checks 3.6

Customer Name

Address Hayes Road

Southall

UB2 5XJ

Ub2 5FB

11

Array 2 Array 3

85 0 Assumed annual rate of Inflation 3% Pay Back Time in Years 11.20 Discount Factor 3.50%

7 0 Annual increase in energy cost 8% System Life Benefit £3,700,604.55 NPV £1,764,472.92

1 1 Percentage of export 9% IRR (Investment Return) 9.1%

Percentage of self consumption 91%

3000 2 Annual Drop in System efficiency 0.7%

280 0 Imported electricity cost p/kWh 10.29

6.38

915 0 Fit Export Rate p/kWh 4.77

840.00 0.00 Total Size of system (kW) 1680.00 1529640.00

Year Saving on Electricity

UsedExport FIT Revenue Financing Cost Cumulative Net Cashflow Accumulated Benefit NPV Factor

-2,050,000.00

1 1529640.00 kWh p/kWh 10.29 p/kWh £143,289.64 p/kWh £6,566.74 -£144,240 -£1,946,792.79 £103,207.21 98%

2 1518932.52 kWh p/kWh 11.12 p/kWh £153,669.54 p/kWh £6,716.40 -£144,240 -£1,830,831.93 £219,168.07 95%

3 1508299.99 kWh 6.77 p/kWh 12.01 p/kWh £164,801.36 p/kWh £6,869.47 -£144,240 -£1,701,311.39 £348,688.61 92%

4 1497741.89 kWh 6.97 p/kWh 12.97 p/kWh £176,739.57 p/kWh £7,026.02 -£144,240 -£1,557,369.45 £492,630.55 89%

5 1487257.70 kWh 7.18 p/kWh 14.00 p/kWh £189,542.59 p/kWh £7,186.15 -£144,240 -£1,398,084.73 £651,915.27 86%

6 1476846.90 kWh 7.40 p/kWh 15.13 p/kWh £203,273.05 p/kWh £7,349.92 -£144,240 -£1,222,471.88 £827,528.12 83%

7 1466508.97 kWh 7.62 p/kWh 16.34 p/kWh £217,998.15 p/kWh £7,517.42 -£144,240 -£1,029,477.07 £1,020,522.93 80%

8 1456243.40 kWh 7.85 p/kWh 17.64 p/kWh £233,789.94 p/kWh £7,688.74 -£144,240 -£817,973.07 £1,232,026.93 77%

9 1446049.70 kWh 8.08 p/kWh 19.05 p/kWh £250,725.68 p/kWh £7,863.97 -£144,240 -£586,753.99 £1,463,246.01 75%

10 1435927.35 kWh 8.32 p/kWh 20.58 p/kWh £268,888.25 p/kWh £8,043.19 -£144,240 -£334,529.66 £1,715,470.34 72%

11 1425875.86 kWh 8.57 p/kWh 22.22 p/kWh £288,366.51 p/kWh £8,226.50 -£144,240 -£59,919.60 £1,990,080.40 70%

12 1415894.73 kWh 8.83 p/kWh 24.00 p/kWh £309,255.78 p/kWh £8,413.98 -£144,240 £238,553.45 £2,288,553.45 67%

13 1405983.47 kWh 9.10 p/kWh 25.92 p/kWh £331,658.27 p/kWh £8,605.73 -£144,240 £562,470.49 £2,612,470.49 65%

14 1396141.58 kWh 9.37 p/kWh 28.00 p/kWh £355,683.60 p/kWh £8,801.86 -£144,240 £913,523.67 £2,963,523.67 63%

15 1386368.59 kWh 9.65 p/kWh 30.24 p/kWh £381,449.32 p/kWh £9,002.45 -£144,240 £1,293,524.27 £3,343,524.27 61%

16 1376664.01 kWh 9.94 p/kWh 32.65 p/kWh £409,081.51 p/kWh £9,207.62 -£144,240 £1,704,411.28 £3,754,411.28 59%

17 1367027.36 kWh 10.24 p/kWh 35.27 p/kWh £438,715.37 p/kWh £9,417.46 -£144,240 £2,148,260.53 £4,198,260.53 57%

18 1357458.17 kWh 10.55 p/kWh 38.09 p/kWh £470,495.91 p/kWh £9,632.08 -£144,240 £2,627,294.56 £4,677,294.56 55%

19 1347955.96 kWh 10.86 p/kWh 41.14 p/kWh £504,578.64 p/kWh £9,851.60 -£144,240 £3,143,893.13 £5,193,893.13 53%

20 1338520.27 kWh 11.19 p/kWh 44.43 p/kWh £541,130.31 p/kWh £10,076.11 -£144,240 £3,700,604.55 £5,750,604.55 51%

28641338.44

NPV

-£1,913,592.92

£110,128.80

£118,846.88

£127,613.35

£136,440.27

£145,339.74

£154,323.96

£163,405.23

£172,595.99

£181,908.78

£191,356.30

£200,951.43

£210,707.22

£220,636.92

£230,753.99

£241,072.12

£251,605.26

£262,367.63

£273,373.70

£284,638.28

kWh/annum Fit Rate (Inc Inflation) Fit Annual Income

£103,207.21

Cost of Electricity

£97,591.03

£109,230.09

£111,719.44

£351,053.17

6.80

7.00

£115,960.87

£129,520.54

£143,941.94

£99,815.13

Savings and Income

6.04

6.22

CO 2 Emissions

Metric Tonnes of C02 Saved Per Year

Solar PV System Price (Exc Vat)

Roof Orientation

Roof Pitch

Shading Factor (SF)

Feed in Tariff (Band)

Number of Panels

Size of Panels (Watts)

Irradiance Zone

Irradiance Level

Array size kWp

790.82

790823.88

2,050,000.00£

Fit Rate p/kWh

£380,000.60

£159,284.73

£175,612.85

£192,994.81

£211,504.00

£231,219.08

£298,473.05

£323,917.04

Financial Analysis

£516,598.57

£556,711.42

£143,146.24

£146,408.55

£149,745.20

4.77

4.91

£252,224.33

£274,610.06

£127,893.24

£130,807.93

£133,789.04

£136,838.09

£139,956.63

£114,265.53

£116,869.64

£119,533.10

£122,257.26

£125,043.50

£102,089.92

£104,416.55

6.41

6.60

5.06

The performance of solar PV systems is impossible to predict with certainty due to the variability in the amount of solar radiation (sunlight) from location to location and from year to year. This estimate is based on upon the government's standard assessment procedure for energy rating of buildings (SAP) and is given as guidance only. It should not be considered as a

guarantee of performance.

Inverter

SAP Details

Predicted System Output kWh / Year

1

906

>250 - 5mw

Sap calculations for PV Solar system

6.38

6.57

95

7

1

Kilograms CO2 saved Per Year

3000

280

840.00

Export Fit Rate (Inc

Inflation)

Array 1

7.88

8.12

£479,034.03

£410,887.01

£443,849.25

8.36

7.65

5.87

Project Reference

Option 1:

LG 280 S1C-G3

Solar Edge

Modules

14/11/2014Date

WIM

£106,796.20

7.22

7.43

5.21

5.37

5.53

5.70

Energy Rating Data