![Page 1: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/1.jpg)
Jason Kelly, PEConstruction Project ManagerOBEC Consulting Engineers
Accelerated Bridge Construction of the West Humbug Creek Bridge
Western Bridge Engineers SeminarReno, Nevada | September 9, 2015
![Page 2: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/2.jpg)
Presentation Overview
• Project Background• Alternatives• Design• Construction• Lessons Learned
![Page 3: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/3.jpg)
• ADT is 6,500, 11% trucks• NHS Route• Main route from
Portland to Seaside with limited detour options
• 16 miles east of Seaside• High seasonal variability
in traffic and directional imbalance!
Project Background: Location and Usage
![Page 4: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/4.jpg)
Project Background
• Project History– US26 at MP 16.28, built in 1934– 59-foot-long, three-span, timber bridge, supported on pedestals
on sandstone
![Page 5: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/5.jpg)
• 2010 Sufficiency Rating: 53%• Scour Critical Bridge
– In July 2007, scour repairs were performed on the footing at bent 2 and became undermined almost immediately
• Timber Girders with reinforced concrete deck
• 24-foot roadway width • RF = 1.2
Project Background: Considerations for Replacement
![Page 6: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/6.jpg)
Project Background: Project Team
• ODOT – Ken Kohl, PE (PM)– Craig Shike, PE
(Bridge Ops & Standards)– Tanarat Potisuk, PE
(Concrete Standards)
• OBEC Design Team – Bob Goodrich, PE (PM)– Andy Howe, PE (EOR)
• General Contractor– Oregon State Bridge– HP Civil (Sub)– Axis Crane (Sub)
• Precast Fabricators– Knife River (Deck Panels)– RB Johnson (Girders, Pile Caps,
Impact Panels)
![Page 7: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/7.jpg)
Project Background
• FHWA Innovative Bridge Research and Deployment (IBRD) Program. Grant awarded of $400,000.
• Building off of the Burnt River Project & Salt Creek Viaduct V-E.
![Page 8: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/8.jpg)
Presentation Overview
• Project Background• Alternatives• Design• Construction• Lessons Learned
![Page 9: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/9.jpg)
• Adjacent wetlands/waters• Cultural site• Old growth trees
• Narrow right-of-way• Summer in-water work
window
Alternatives: Site Constraints
![Page 10: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/10.jpg)
Alternatives: Traditional Methods
• Detour/Diversion
• Closure
• Staging/ABC
![Page 11: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/11.jpg)
Alternatives: ABC Methods
• Sliding– Not practical given R/W, wetlands, etc.
• SPMT’s– Require extended (hours)
full closure, requires access from below
• Prefabricated/Preassembly– Prefabricated concrete elements
Post tensioned with closure pours– Burnt River Bridge
![Page 12: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/12.jpg)
Alternatives: Staging + ABC
![Page 13: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/13.jpg)
Presentation Overview
• Project Background• Alternatives• Design• Construction• Lessons Learned
![Page 14: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/14.jpg)
• Prebored Piling- (7) HP 12x74 per bent- Installed with CFA
• Precast/PT Caps- (5) 1 3/8-inch threaded Rod
Design: Foundation
![Page 15: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/15.jpg)
• (7) 36-inch Deck Bulb-T• Steel Plate Diaphragms
Design: Superstructure
![Page 16: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/16.jpg)
• (18) Interior Panels- 8’ x 23’
• (4) Exterior Panels- 2.5’ x 23’
• Longitudinally Post Tensioned - (4) strands per tendon, 20
tendons• 1-inch A307 Leveling rods• Match Cast • Class 6000 flowable
concrete for build-up
Design: Deck
![Page 17: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/17.jpg)
Presentation Overview
• Project Background• Alternatives• Design• Construction• Lessons Learned
![Page 18: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/18.jpg)
Construction
![Page 19: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/19.jpg)
• Stage 1- Constructed Roadway Widening- Installed 10 of 14 piling (4 pile ahead
of schedule)- June 2nd-27th (4 weeks, per contract)
• Stage 2 Phase 1 and 2- Removed existing west-bound half of
bridge & installed new west-bound half - July 27th-August 1st (1 week ahead of
schedule)
• Stage 3 Phase 1- Completed remaining 4 piling- Excavated Swales- August 3rd-5th (1.5 weeks ahead of
schedule)
• Stage 3 Phase 2- Remove remaining bridge- Installed east-bound half of bridge- August 10th-15th (1.5 weeks ahead
of schedule)
• 10 additional days to complete, 8 days with flaggers - Landscaping- Punch list- Rip Rap Removal per Permit- Swale Construction- Extra Work
• Total of 43 days on-site
Construction: Schedule
![Page 20: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/20.jpg)
Presentation Overview
• Project Background• Alternatives• Design• Construction• Lessons Learned
![Page 21: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/21.jpg)
• Reduce CIP concrete whenever possible– Foundation closure pours– Beam pedestals (Contractor elected to eliminate)– Deck buildup, blockouts, and closure pour– Pile Blockouts (Contractor reduced with CMP sleeve)
• Specify a minimum numberof concrete mix designs– Class 6000 Flowable for Deck– Class 3300 for Foundation
• Better to be too high than too low?
Lessons Learned
![Page 22: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/22.jpg)
• PT Ducts for threaded rods– CMP vs PVC
Lessons Learned
![Page 23: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/23.jpg)
• QA/QC of Precast Elements– Dimensional issues– Concrete Strength– Different precast suppliers
• Finish• Width » Consider Impact Panel CP
Lessons Learned
![Page 24: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/24.jpg)
Lessons Learned
• Consider closure pour for impact panels down center line consistent with bridge deck– Alleviate difficulty with splicing tie rods on the crown– Allow for adjustment in width to match bridge
• Misc. Items: Removal of leveling bolts, edge girder forms instead of foam
![Page 25: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/25.jpg)
Traffic In Design
• Verify Traffic Count Data- 72⁰F = 6,000 ADT in summer- What does 100⁰F yield?
• Coordinate with other projects- Days vs. nights- Consecutive schedules- Consolidating traffic
• Advanced Warning Devices- PCMS- Regional VMS’
Traffic In Construction
• Learn Traffic Patterns- Peak Flows
• Flagger Education- Unbalanced Queues
• Coordination with adjacent projects
• Public Information- Press Releases
Lessons Learned
![Page 26: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/26.jpg)
Summary
• Prefabricated/Preassembly ABC is a viable option– Closure Pours vs. PT & Match Cast
• Strive for tight tolerances on precast elements• Be mindful of traffic data
![Page 27: Western Bridge Engineers Seminar - etouches · PDF fileJason Kelly, PE. Construction Project Manager. OBEC Consulting Engineers. Accelerated Bridge Construction . of the . West Humbug](https://reader030.vdocuments.site/reader030/viewer/2022012923/5abbedc47f8b9a321b8d6f17/html5/thumbnails/27.jpg)
Questions