![Page 1: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/1.jpg)
West Seattle and BallardLink Extensions
Northwest Seaport Alliance and Port of Seattle | 4.3.18
Item No.: 5A_SuppDate of Meeting: April 3, 2018
![Page 2: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/2.jpg)
System expansion
![Page 3: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/3.jpg)
System expansion
soundtransit.org/system
Sound Transit’s system expansion means every few years new light rail, bus rapid transit and commuter rail stations open throughout the region, providing fast,reliable alternatives to congested roads.
![Page 4: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/4.jpg)
By 2040: 116+ miles | 80+ stations | 16 cities connected
Regional light rail expansion
![Page 5: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/5.jpg)
New approach toproject development
Enhance commitment to partnership, community engagement, collaboration, transparency and accountability
Apply innovative ideas and lessons learned to streamline project delivery
![Page 6: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/6.jpg)
West Seattle and Ballard Link Extensions
![Page 7: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/7.jpg)
• Identifies mode, corridor, station areas
• Informs cost, schedule, operating needs
Representative project
![Page 8: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/8.jpg)
28
Project Flyover
Take a bird's-eye view tour of the representative project.
View Video:https://vimeo.com/255646896
![Page 9: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/9.jpg)
West Seattle project timeline
PUBLIC INVOLVEMENT PUBLIC INVOLVEMENT
Conversations withproperty owners
Groundbreaking
Construction updatesand mitigation
Safety education
Testing and pre-operations
PUBLIC INVOLVEMENT
Final route design
Final station designs
Procure and commission station and public art
Obtain land use and construction permits
PLANNING DESIGN CONSTRUCTION2017–2022 2022–2025 2025–2030
START OFSERVICE
2016Alternatives development
Board identifies preferred alternative
Draft Environmental Impact Statement
Final Environmental Impact Statement
Board selects projectto be built
Federal Record of Decision
2030
![Page 10: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/10.jpg)
Ballard project timeline
PUBLIC INVOLVEMENT PUBLIC INVOLVEMENT
Conversations withproperty owners
Groundbreaking
Construction updatesand mitigation
Safety education
Testing and pre-operations
PUBLIC INVOLVEMENT
Final route design
Final station designs
Procure and commission station and public art
Obtain land use and construction permits
PLANNING DESIGN CONSTRUCTION2017–2022 2023–2026 2027–2035
START OFSERVICE
Alternatives development
Board identifies preferred alternative
Draft Environmental Impact Statement
Final Environmental Impact Statement
Board selects projectto be built
Federal Record of Decision
20352016
![Page 11: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/11.jpg)
Alternatives development process
![Page 12: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/12.jpg)
PUBLIC INVOLVEMENT
PLANNING DESIG2016 2019–2022
Draft Environmental Impact Statement
Final Environmental Impact Statement
Board selects project to be built
Federal Record of Decision
2017–2019Alternatives development
Board identifies preferred alternative
![Page 13: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/13.jpg)
PUBLIC INVOLVEMENT PUBLIC INVOLVEMENTPUBLIC INVOLVEMENT
Alternatives development process
LEVEL 1Alternatives development
LEVEL 2Alternatives development
LEVEL 3Alternatives development
PREFERRED ALTERNATIVE*
Conduct early scoping
Study ST3 representative project and alternatives
Screen alternatives
Early-2018 Mid-2018 Late-2018 / Early-2019 Early-2019
Technical analysis
Refine and screen alternatives
Refine and screen alternatives
Conduct Environmental Impact Statement(EIS) scoping
*The Sound Transit Board identifies preferred alternatives and other alternatives to study.
![Page 14: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/14.jpg)
Community engagement and collaboration
![Page 15: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/15.jpg)
What we heard during early scoping
![Page 16: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/16.jpg)
Highlights
• 700+ people attended threepublic meetings
• 5,000+ visited online open house
• 8 agencies and Muckleshoot Tribe participated in agency meeting
• 2,800+ total comments received via meetings and other methods
• All comments will be captured in Early Scoping Summary Report
16
![Page 17: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/17.jpg)
West Seattle/ Duwamish
SODO
Downtown
Interbay/Ballard
17ST3 Representative project
![Page 18: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/18.jpg)
West Seattle/Duwamish 18
Tunnel in West Seattle
Route through golf course
= early scoping comments
Terminal station location
Minimize neighborhood disruption
Accommodate future extension
Alternate routes to Duwamish crossingAlternate routes
in West SeattleConsolidate
stations
SODO interim transfer
Preserve industrial operations
![Page 19: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/19.jpg)
SODO 19
Fully grade separate LRT
Minimize cut-and-cover construction impacts
along 5th Ave. S
Place Stadium Station on both lines
= early scoping comments
E3 busway utilization
![Page 20: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/20.jpg)
Downtown 20
Move Midtown Station to First Hill
= early scoping comments
Move Denny Station east
Space stations farther apart
Connect to renovated arena
Consolidate stations
Ensure good connections
between stations
Ensure good connections
between stations
![Page 21: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/21.jpg)
Interbay/Ballard 21
Shift Ballard station westUse 20th Ave W
Tunnel in Ballard
Tunnel or fixed bridge (avoid movable)
Smith Cove Station locations
Accommodate future extensions
Alternate routes in Interbay/Ballard
Terminal station location
= early scoping comments
Avoid Elliott and 15th avenues
Preserve industrial and maritime operations incl. Fishermen’s Terminal
![Page 22: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/22.jpg)
Interagency coordination
![Page 23: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/23.jpg)
23
Agency coordination
![Page 24: West Seattle and Ballard Link Extensions...West Seattle and Ballard Link Extensions Northwest Seaport Alliance and Port of Seattle | 4.3.18 Item No.: 5A_Supp Date of Meeting: April](https://reader035.vdocuments.site/reader035/viewer/2022071022/5fd6f9ffb0d2905c29183d0c/html5/thumbnails/24.jpg)
24
Agency coordination• Monthly Interagency Group meetings
• Upcoming Agency Workshops on stations (March/April) and water crossings
• Planning summer Station Charrettes
• Regular meetings to discuss key concerns (impacts to facilities, freight/maritime interests)