West River Greenway Connector TrailPublic Information Meeting #2 – July 20th 2016
Town of Grand Island
Erie County, New YorkConsultant:
C&S Engineers, Inc.Victor O’Brien, P.E., Project
ManagerTim Hughes, P.E., Project
Principal
![Page 2: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/2.jpg)
![Page 3: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/3.jpg)
Background• Transportation Alternatives Program (TAP)
• Grant application submitted June 2014
• Applicant: Town of Grand Island
• Sponsor: New York State Office of Parks, Recreation & Historic Preservation (Parks)
• Grant approved October 2014
![Page 4: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/4.jpg)
Budget• Total budget $2.5 million (design, construction)
• 64% Federal Funding (TAP Grant)
• 36% State Parks/Regional Funding
![Page 5: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/5.jpg)
Project Objectives• Provide an alternative transportation connection between the
cities of Buffalo and Niagara Falls that will be safer for non-motorized vehicles
• Provide a critical missing link in the Niagara River Greenway Trail system
• Enhance connectivity and improve pedestrian & bicycle safety
• Improve air quality
• Promote health through physical activity
• Construct the entire connector trail
![Page 6: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/6.jpg)
Public Information Meetings
• General public meeting October 6, 2015
• Focus group/stakeholders meetings November 10, 2015• Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway
Commission
• Grand Island Recreation & Conservation Boards
• West River Homeowners Association
![Page 7: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/7.jpg)
Summary of Public Comments
• Concern with guardrail, signs, and other obstructions that would potentially effect view of the river
• Safety concerns–close proximity to 55mph parkway; intersections with side streets
• Convert existing roadway to trail to avoid extra pavement
• Existing & future maintenance concerns with regard to mowing
• Proximity of trail to homes on West Oakfield Road
• Brush clearing and other environmental concerns
• Consider other locations in the town
![Page 8: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/8.jpg)
Three Alternatives Evaluated
1. Construct new 10’ wide trail from Beaver Island State Park to Long Road between the existing parkway and the Niagara River.
2. Identical to alternative 1 except the trail will cross the parkway at Alt Road and use the median and existing snowmobile trail to connect to the Spaulding Trail.
3. Close West River Parkway to vehicular traffic between Long Road and Oakfield Road and reuse existing pavement for trail.
![Page 9: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/9.jpg)
NYSDOT Traffic Volumes
![Page 10: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/10.jpg)
Preferred Alternative-Alternative Three:
Closing the parkway and re-purposing pavement as the new greenway trail.
• Strongly supported by NY State Parks and Town of Grand Island based on analysis.
• Meets all project objectives
• Causes the least environmental impact.
• Is practical, sustainable and park friendly.
• Addresses most safety, access and resident viewshed concerns.
• Minimal impact on maintenance operations/cost.
![Page 11: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/11.jpg)
Comparison of AlternativesAlternatives
Category 1-Off road 2-Off road 3-On parkway
Construction Cost $2.98 million $2.96 million $1.81 million
Wetland Impacts 0.25 acres 0.25 acres 0.23 acres
Tree Removal 20 8 8
Brush/woods Clearing 1.86 acres 2.45 acres 0.24 acres
![Page 12: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/12.jpg)
![Page 13: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/13.jpg)
Typical Trail on Existing Parkway
![Page 14: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/14.jpg)
Section View
![Page 15: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/15.jpg)
Section View
![Page 16: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/16.jpg)
Typical 10’ Wide Paved Trail
![Page 17: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/17.jpg)
Section View
![Page 18: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/18.jpg)
Enlarged View of Transition to Parkway
![Page 19: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/19.jpg)
Enlarged View of Intersection at Fix Road Overlook
![Page 20: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/20.jpg)
Enlarged View of New Parking Area at Love Road Intersection
![Page 21: West River Greenway Connector Trail Presentation · • Buffalo Riverkeeper/Go Bike Buffalo/Niagara River Greenway Commission • Grand Island Recreation & Conservation Boards •](https://reader034.vdocuments.site/reader034/viewer/2022050501/5f93da51411bbd6f7a5e0084/html5/thumbnails/21.jpg)
Next Steps
• NYSDOT Design Approval Fall 2016
• Final Design Spring 2017
• Bid Summer 2017
• Construction Begins Fall 2017
• Construction Complete Summer 2018