wellheads and casing

102
7/30/2019 Wellheads and Casing http://slidepdf.com/reader/full/wellheads-and-casing 1/102 1 TAMU - Pemex Offshore Drilling Lesson 3 Wellheads and Casing

Upload: omitta-gilbert

Post on 04-Apr-2018

229 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 1/102

1

TAMU - PemexOffshore Drilling 

Lesson 3

Wellheads and Casing

Page 2: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 2/102

2

Wellheads and Casing 

Drilling with a Riser 

Temporary and Permanent Guide Bases

Fracture Gradients

Subsea Cementing

Casing Seals

Drilling Procedures - An Example

Page 3: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 3/102

3

Conventional Riser Drilling

SEAFLOOR

SEA WATERHYDROSTATIC

PRESSURE

   D   E

   P   T   H 

MUD HYDROSTATIC

BOP

FLOATER

DRILLING RISER

CHOKE LINE

Page 4: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 4/102

4

Conventional Riser Drilling- Install 30-in Conductor -

FLOATER

DRILLPIPE

Jet 30-in Conductor to ~ 200 ft below mudline

No riser - “Mud” returns to seafloor  

No annulus - no cementing (in GOM)

~200 30” 

Page 5: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 5/102

5

Conventional Riser Drilling- Install 20-in Conductor

FLOATER

DRILLING RISER

CHOKE LINE

Drill 26-in hole to 1,050 ft below mudline

Riser optional - Mud returns to surface or seafloor 

Run 20-in Conductor to ~ 1,000 ft below mudline

Cement to mudline

D

~1,050

30” 

20” 

Page 6: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 6/102

6

Conventional Riser Drilling  - Install 13 3/8-in Surface Csg.

FLOATER

DRILLING RISER

CHOKE LINE

Run Riser and BOP Stack

Drill 17 1/2-in hole to 4,050 ft BML

Drill with Mud returns to surfaceRun 13 3/8-in Surface Casing

to ~ 4,000 ft below mudline

Cement to mudline

D

BOP

Now, finally, we can close the BOP if necessary

13 3/8” 

Page 7: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 7/1027

Wellheads and Casing 

A subsea wellhead, like a land wellhead:

 Must support the BOP‟s while drilling  Must support the suspended casing

while cementing, and

Must seal off between casing strings

during drilling and production

operations.

Page 8: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 8/1028

Wellheads and Casing, cont. 

In floating drilling, the casing hangers,

casing seals and cementing heads

differ 

from land and platform operationsin the following manner:

Page 9: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 9/1029

Wellheads and Casing 

1. The first and second casing strings

are cemented with returns to the

seabed.2. Casing is run with the last joint made-

up on a casing hanger and

permanently suspended prior tocementing. Mud returns flow

through fluting in the hanger.

Page 10: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 10/10210

Wellheads and Casing 

3. Usually, cementing plugs are

located at the wellhead and

released remotely. Thecementing string from the vessel

to the wellhead is drill pipe.

4. Casing seals are run and set

remotely.

Page 11: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 11/10211

Wellheads and Casing 

5. Special test tools are required for 

remotely testing the casing seals.

6. Wear bushings are essential for 

protecting the wellhead.

Page 12: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 12/10212

Fig.4-10.Typicalsealing

arrangement

for subseawells.

Page 13: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 13/102

13

Page 14: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 14/102

14

Depth BML

240 ft

1,100 ft

4,100 ft

8,600 ft

10,100 ft

Page 15: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 15/102

15

Page 16: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 16/102

16

PermanentGuide

Structure.

Temporary

Guide Base

Page 17: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 17/102

17

Page 18: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 18/102

18

Hole Opener 

TemporaryGuide Base

Utility

Guide Frame

Page 19: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 19/102

19

Procedure for Starting a Well

1. To get the well started, place a heavy

steel template on the seafloor.

Run on drillpipe.2. Four guidelines guide bit, casing, etc to

the right location on the seafloor.

3. Run 36” hole opener (with guide frame)and drill 36” hole to ~240 ft BML 

with returns to the seafloor.

Page 20: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 20/102

20

Procedure for Starting a Well

4. Run 30” casing and cement with returns

to the seafloor. With the 30” casing

also run the permanent guidestructure and the wellhead housing.

(3 & 4 alt.  Sometimes the 30” casing is

 jetted or driven in. - instead of drilling).

5. Drill 26” hole to 1,050 ft below mudline. 

Page 21: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 21/102

21

Procedure for Starting a Well

6. Run 20” conductor casing. 

With the 20” casing, run the high

pressure wellhead. Cement the casing.

NOTE:  The 26” hole may be drilled with

returns to the seafloor, or with returns

to the surface using the marine riser.

Note the guide posts on the permanent

guide structure. These are for the BOP stack

Page 22: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 22/102

22

Fig. 4-5. Estimated Fracture gradients at

100 ft below seabed (Santa Barbara Channel).

Page 23: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 23/102

23

Fracture gradient at

100 ft. below seabed

(Santa BarbaraChannel). 

Why drill with returns to the seafloor? 

With this low fracture gradient it is difficult to

drill with returns to the surface.

No shallow gas would be expected at this

depth below the mudline. 

Page 24: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 24/102

24

Fig. 4-5. Estimated Fracture gradients at

1000 ft below seabed (Santa Barbara Channel).

Drill with Diverter to theSurface Casing Point

Page 25: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 25/102

25

ShallowGas

Blowout

Gasreduces

buoyancy!

Page 26: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 26/102

26

Typical specific gravity variations in ablowout boil have increasing effect nearer 

the water‟s surface. 

Fortunately for a semi-submersible, therig‟s primary flotation members are

situated below the zones where specific

gravity has been reduced the most.

Gas in theWater Column

Page 27: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 27/102

27

Page 28: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 28/102

28

If there is sufficient length to the mooringsystem cables/ chains, the rig will be

pushed off location and out of harm‟s way.

However, the plume can also cause the rig

to list, which reduces its freeboard and

makes it more susceptible to capsizing.

Gas in theWater Column

Page 29: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 29/102

29

Increasing the water depth reduces

the total overburden gradient and

consequently the formation fracturegradient. This can be expressed as:

ppobf  gF)gg(g

Fracture Gradients in Deep Water

Page 30: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 30/102

30

Where:

ratiostressvertical / horizontalF

psi/ftgradient,pressureoverburdeng

psi/ftgradient,pressureformationg

psi/ftgradient,fractureg

ob

p

ppobf  gF)gg(g

Page 31: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 31/102

31

For offshore drilling:

)ddd(p4335.0d44.0d

1g FKBf KB

ob

3f 

F

KB

g/cmdensity,bulk formation 

ftwater,theaboveflowlineof heightd

ftdepth,waterd

ftbushing,kellythefrommeasureddepthd

Where:

f  

Page 32: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 32/102

32

0.44 d is the overburden due to water,

or simply the hydrostatic pressure at theseafloor.

(dKB - d - dF) is merely the penetrationinto the seafloor.

)ddd(p4335.0d44.0d

1

g FKBf KB

ob

f  

Page 33: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 33/102

33

Formation bulk density vs. horizontal to verticalstress ratios for the Santa Barbara Channel.

Get  f fromdensity log.

Get F  fromthis plot.

Calculate gf 

Get gp

Page 34: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 34/102

34

Fig. 4-7. An example of onshore andoffshore fracture gradients.

Page 35: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 35/102

35

Cumulative average (BML)

formation bulk density

= 5.3 * (TVDBML)0.1356

e.g.  = 5.3 * (3,000)0.1356 = 15.70 lb/gal

J. W. Barker and T. D. Woods“Estimating Shallow Below Mudline Deepwater 

Gulf of Mexico Fracture Gradients” Presented at the 1997 Houston AADE Chapter 

 Annual Technical Forum, April 2-3, 1997. 

Page 36: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 36/102

36

 At 1,000 ft below mudline, avg. OB. Density,

= 5.3 * (TVDBML)0.1356

gob = 5.3 * (1,000)0.1356 = 13.52 lb/gal

gf = 0.9 * ob = 12.17 lb/gal = 0.663 psi/ft

gp = 0.8 * ob  = 10.82 lb/gal = 0.563 psi/ft

NOTE: These are gradients relative to

the mudline!

J. W. Barker and T. D. Woods cont’d 

Page 37: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 37/102

37

 At 1,000 ft below mudline, in 1,500 ft water:

Total overburden = 0.44 * 1,500

+ 0.052 * 13.52 * 1,000 psi 

gob = 1,363/2,500 psi/ft = 10.48 lb/gal !! 

pf = 0.44 *1,500 + 0.052 * 12.17 * 1,000 psi

gf = 1,293/2,500 psi/ft = 9.94 lb/gal 

gp = 0.44 * 1,500 +0.052 * 10.82 * 1,000 psi= 1,223/2,500 psi/ft = 9.40 lb/gal 

NOTE: These are gradients relative to SURFACE!

J. W. Barker and T. D. Woods cont’d 

Page 38: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 38/102

38

Fracture gradient equation:g =

Poisson‟s 

Ratio

from Text

Ben A. Eaton and Travis L. Eaton“Fracture Gradient Prediction for the new

generation” World Oil, October 1997, pp. 93-100. 

ppobf  gF)gg(g

D

p

1D

p

D

S

D

F

 

 

 

 

g

g

 

 

 

 

Page 39: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 39/102

39

Fig. 4-8. Plot of a leak-off test.

Page 40: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 40/102

40

Mud Weight 9.5 PPGCasing 13 inchesSet to 3,340 ft-KB

Frac. Grad. = ?

Fracture Gradient Calculation 

Fracture Pressure = 0.052 * 9.5 * 3,340 + 650= 2,300 psig

Frac. Grad. = 2,300/3,340 = 0.6886 psi/ft= 0.6886/0.052 = 13.24 ppg

Page 41: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 41/102

41

BOPs

Casing

Drillpipe

Leak-Off Test 

Page 42: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 42/102

42

Fig. 4-9.

Sub-seacementing

system.

Page 43: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 43/102

43

Fig.4-10.Typical

sealingarrangement for subsea

wells.

Page 44: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 44/102

44

Metal-to-Metal Casing Annulus Seal 

Assures maximum seal over 

extended periods, even in high-

pressure holes Eliminates dependence on seal

materials that deteriorate or “cold

flow”. 

Available on systems up to 15,000

psi pressure integrity.

1 Actuating force is transferred to the

Page 45: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 45/102

45

Upper MetalSeal Lips

Resilient

CompressionElement

Lower MetalSeal Lips

1. Actuating force is transferred to the2. Resilient compression element

which expands, forcing the3. Metal seal lips into contact

with the surface of the4. Wellhead housing and the5. Casing hanger

Page 46: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 46/102

46

Casing Hanger and Pack-offAssembly 

Single trip installation

The pack-off seal assembly is runsimultaneously with the casing hanger 

body. All operations - installing the casing

hanger, cementing the casing string and

actuating and testing the pack-off seal areperformed in a single trip of the running

string. 

Page 47: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 47/102

47

Large Flow-By Areas 

Large flow-by areas can handle most

drilling fluid applications with a minimal

drop in pressure.

Deep 2" wide flow-by slots in the casing

hanger body, and ample porting through

the pack-off nut assembly, provide clear passage for cuttings and mudcake

without plugging.

Page 48: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 48/102

48

Liquid Compressibility 

The volume required to compress a liquid

is defined by the equation: 

Where:

Vi = volume of system, bbl

Cp = compressibility = 3 * 10-6 per psi for water = 6 * 10-6 per psi for mud

DP = test pressure, psi

DV = Vi * Cp *  P 

Page 49: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 49/102

49

Seal Test - Example

Water depth = 500 ft (all depths are KB)

Casing string = 13 3/8” OD 

Volume of system above the seal = 11 bblTest pressure = 3,000 psi

Test fluid = water 

Previous casing string = 20”, J-55, 94.0 lb/ftPrevious casing seat = 1,500 ft KB

Cement top = 996 ft

Page 50: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 50/102

50

Seal Test - Example

V = 11 bbl

500 „ KB Mud Line

996‟ 20”

1,500‟ 

13 3/8” 

4,000 ft

Page 51: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 51/102

51

With no leak, the system will require

DV = 3 * 10-6 * 11 * 3,000 = 0.1 bbl water 

to reach test pressure.

If the seal leaks, the volume will be more,but how much more?

Page 52: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 52/102

52

Obviously, 0.1 bbl would be difficult to

measure. The annular volume between the

seal and the cement is

(996 - 500) ft * 0.1815 bbl/ft = 90 bbl of mud

Now, 

DV = 6*10-6 * 90 DP + 3*10-6 * 11 DP bbl

= ( 5.4 * 10-4

+ 3.3*10-5

) DP bbl= ( 5.73 * 10-4 ) DP bbl

What should the maximum pressure be?

?

Page 53: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 53/102

53

Pressure in the annulus must always be

less than the collapse pressure of the inner 

casing, and less than the internal yield of the outer casing.

This will depend on both volume andpressure. Table 4-2 shows the relationship

for four grades of casing.

 Also, the internal yield of the 20-inch casing 

is reached at 2,110 psi when V = 1.24 bbl. 

Page 54: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 54/102

54

Page 55: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 55/102

55

Plug fortesting

casing seal

to fullworking

pressure.

Page 56: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 56/102

56

Test Procedure

1. Set seal

2. Land test plug in wellhead,

sealing off below the seal3. Displace mud with water for test

4. Close pipe rams

5. Pump slowly down the choke line,preferably in stages, to protect the

casing in case of leaks

Page 57: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 57/102

57

Test Evaluation

During the test, if the wellhead system

being tested will not sustain test

pressure, several possible causesshould be considered:

1. Leak in the surface manifold2. Leak in the test plug (detected by

returns through the drillpipe)

Page 58: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 58/102

58

Test Evaluation, cont.

3. Leak in the casing seal

4. Leak in the BOPs5. Leak in the hydraulic wellhead

connector  

Page 59: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 59/102

59

When the well does not sustain

pressure, it is obvious that there is a

problem.

There is also a problem if the well

takes too much fluid to reach testpressure, just as we have discussed. 

Test Evaluation, cont.

Page 60: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 60/102

60

Drilling Proceduresfrom a floater

 Install 30” Structural Csg. 

 Install 20” Conductor  

 Install 13 3/8” Surface Casing 

etc.

D illi P d

Page 61: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 61/102

61

Drilling ProceduresTentative Hole and Casing Sizes

 8 1/2” Pilot Hole to 180‟ BML 

 26”x36” Hole Opener to 180‟ BMLInstall 30” Structural Csg. 

 8 1/2” Pilot Hole to 1040‟ BML 

 17 1/2” Pilot Hole to 1040‟ BML  17 1/2”x26” Under reamer to 1040‟

Install 20” Conductor  

Drilling Procedures

Page 62: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 62/102

62

Drilling ProceduresTentative Hole and Casing Sizes

 12 1/4” Pilot Hole to 3,830‟ BML 

 12 1/4”x17 1/2” Hole Opener to 3,830‟ BMLInstall 13 3/8” Surface Csg. 

 12 1/4” Hole to TD (8,530‟ BML)Install 9 5/8” Production Csg. 

 8 1/2” Hole if Required 7” ContingencyLiner 

Page 63: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 63/102

63

General Rules 

1. Do not change the tension on the

anchor lines until the 30” casing

has been run and cemented.

2. Have all the 30” casing and all of the

wellhead equipment on board

prior to spudding.

3. There will be an SLM prior to any

logging or coring run.

Page 64: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 64/102

64

General Rules 

4. All casing strings will be strapped

and drifted prior to running.

5. Casing will not be run until thehole is in the best possible

condition and a trouble free

wiper trip can be made.6. Cement densities will be

monitored with a mud balance.

G l R l

Page 65: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 65/102

65

General Rules 

7. The rig will be moved 50‟ off location

whenever the riser is being run or 

pulled.

8. No smoking or open flames arepermitted on deck whenever the

riser is connected to the well.

9. Welding permits (authorized by thedrilling supervisor and tool pusher)

will be required at all times.

Page 66: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 66/102

66

General Rules 

10. Coring will be at the the discretion of the

well site geologist, but only after 

approval from the task force Manager and the Exploration Coordinator.

11. All information concerning the well will

be kept strictly confidential. Anydiscussions will be held in a secure

area in the quarters or on the rig.

Page 67: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 67/102

67

General Rules 

11. Confidentiality - cont‟d. 

Only contractors with “a need to

know” will be allowed access to wellinformation.

12. All personnel on board and all visitors

will be instructed with the necessaryenvironmental and safety films and

instructions.

Page 68: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 68/102

68

General Rules 

13. No one will be allowed on the

helicopters, work boats, or drilling

vessel without the proper authorization or identification.

14. The rotary table must be positioned

within a 200 foot radius of theproposed location.

G l R l

Page 69: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 69/102

69

General RulesAnchoring 

1. Place anchors on sea floor 5800‟ from

the desired final location.

2. Anchor lines should be equally

deployed around the rig with an

angular spacing of 45 degreesbetween adjacent lines.

General Rules

Page 70: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 70/102

70

General RulesAnchoring 

3. Pull in opposing lines to set anchors.

 An indicated line tension of 125

kips is necessary for the anchor toreceive any load.

4. A tension level of 440-460 kips

should be reached before 600‟ of line is taken in with the rig

remaining stationary.

General Rules

Page 71: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 71/102

71

General RulesAnchoring 

5. If a line tension of 440-460 kips has

not been reached before 800‟-

1000‟ of line has been retrieved,

then it may be necessary to use

piggy-back anchors.

6. The following Western KDC planoutlines the mooring procedure.

Page 72: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 72/102

72

Page 73: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 73/102

73

Shallow Gas Plan 

 After the rig is properly anchored the

following steps will be followed as

there is a potential for shallow gas in

this area:

Page 74: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 74/102

74

Shallow Gas Plan 

1. Leave mooring line pawls or stoppels

unset until the 20” casing has been

set and cemented.

2. Mooring winches will be manned while

the 8 1/2” pilot holes for the 30” and20” casings are being drilled. 

Shallow Gas Plan

Page 75: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 75/102

75

Shallow Gas Plan 

3. Mooring winches will be manned

while the 8 1/2” pilot holes for the

30” and 20” casings are being

opened up or under-reamed.

4. The moonpool and seafloor will be

observed for gas bubbles until the20” casing is set and cemented. 

36” H l Pl

Page 76: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 76/102

76

36” Hole Plan 

1. Premix 600 barrels of 11.5 ppg kill mud

prior to spudding the well.

2. PU and TIH with an 8 1/2” bit, 6 - 6 1/2”

drill collars, 6 jts of 5” Hevi-Wate drill

pipe, and sufficient 5” drill pipe. 

36” H l Pl

Page 77: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 77/102

77

36” Hole Plan 

3. Tag bottom with the pilot bit, and

note and report the following:

a. RKB to water level

b. RKB to mud line

c. Water depthd. Time of day (tide allowance)

36” Hole Plan

Page 78: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 78/102

78

36” Hole Plan 

4. Lower TV camera, and observe bit

entering guide base. Retrieve

universal guide frame back to surface.

5. Upon spudding, space out drill string with

pup joints so that it will not be

necessary to pull the bit above theguide base to make the first

connection.

Page 79: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 79/102

79

36” Hole Plan 

6. Drill an 8 1/2” hole to +/- 30‟ below

the setting depth of the 30”

casing (estimated at 180‟ BML).

Circulate returns to the sea floor,

and monitor returns with the

TV camera.

36” H l Pl

Page 80: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 80/102

80

36” Hole Plan 

7. If there are no problems with shallow

gas, pull out of hole, PU 26” bit and

36” hole opener, 6-9 1/2” DC‟s, 6 jts5” Hevi-Wate DP, and sufficient 5” DP. 

Drill 36” hole to set 150‟ (4 joints) of 30” OD structural casing.

36” H l Pl

Page 81: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 81/102

81

36” Hole Plan 

Drill with sea water as follows:

a. Circulate viscous sweeps as

required to clean the hole.b. Survey hole at 30‟, 60‟, and

150‟ BML. 

c. At TD of 36” hole, displacehole to the mud line with

viscous mud.

Page 82: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 82/102

82

36” Hole Plan 

Drill with sea water cont.:

d. Make a wiper trip.e. Circulate the hole to the mud

line with viscous mud.

f. Penetration rate should notexceed 100 ft/hr overall.

36” H l Pl

Page 83: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 83/102

83

36” Hole Plan 

8. Run 30” structural casing per procedure. 

9. If there are problems with shallow gas,

displace the 8 1/2” hole with kill mud

until the gas stops or the hole is full of 

kill mud.

Monitor returns with the TV camera for 

evidence of gas or flow, and if after 

one hour the hole is stable, proceed

as in steps 7 and 8.

36” H l Pl

Page 84: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 84/102

84

36” Hole Plan 

10. If the kill mud in step 9 does notstabilize the well and it appears that

heavier mud will not stabilize the well

or will break down the formation, thenprepare to cement.

Mix and pump, sufficient 15.8 ppg

cement slurry to circulate cement tothe mud line, and monitor returns for 

gas with the TV camera.

36” H l Pl

Page 85: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 85/102

85

36” Hole Plan 

10. Make sure that the hole is stable

POH with BHA

Retrieve TGB

Move rig as required

26” H l Pl

Page 86: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 86/102

86

26” Hole Plan 

1. Have 600 barrels of 11.5 ppg kill mud

prior to drilling out below the 30” 

casing.

2. PU and TIH with an 8 1/2” bit, 9-6 1/2” 

DC‟s, 9 jts of 5” Hevi-Wate DP, andsufficient 5” DP.

26” Hole Plan

Page 87: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 87/102

87

26” Hole Plan 

3. Drill an 8 1/2” hole to +/- 40‟ below the

setting depth of the 20” casing

(estimated at 1040‟ BML).

Circulate returns to the rig shakers, and

monitor returns for indications of gas or 

flow.

26” Hole Plan

Page 88: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 88/102

88

26” Hole Plan 

4. Displace the hole with viscous

spud mud, make a wiper trip,displace the hole with viscous

spud mud, POH, and log well

as required.

26” Hole Plan

Page 89: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 89/102

89

26 Hole Plan 

5. If there are no problems with shallow

gas, pull the riser, PU & TIH with a

17 1/2” bit, 26” hole opener, monel

DC, 6-9 1/2” DC‟s, 6-8” DC‟s, 9 jts 5” 

Hevi-Wate DP, 26” stabilizer at 60‟,

qand sufficient 5” DP.

Drill a 26” hole to set 1040‟ of 20” OD

conductor casing as follows:

26” Hole Plan

Page 90: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 90/102

90

26” Hole Plan 

a. Circulate viscous pills as

required to clean the hole.

b. Circulate returns to the sea floor with sea water.

c. Maintain inclination at less than

three degrees.

d. Spot viscous mud at TD of 26”

hole.

Page 91: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 91/102

91

26” Hole Plan 

e. Make a wiper trip.

f. Spot viscous mud as required.

g. Drop multishot and POH.

6. Run 20” OD conductor casing and

cement per procedure.

26” H l Pl

Page 92: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 92/102

92

26” Hole Plan 

7. If there are problems with shallow gas in

Step 5, circulate the hole with viscous

spud mud and slowly increase theweight until the flow has stopped or 

until the active system is depleted.

If the flow continues, pump the killmud at the maximum rate until the

active system is depleted.

26” Hole Plan 

Page 93: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 93/102

93

7. (Cont.) Then pump sea water at themaximum rate until the hole bridges.

8. If the flow rate is significant, and the hole

will not bridge, prepare to move the rig.Cement the hole to just below the sea

floor with 15.8 ppg cement. POH with

the BHA. Cut or shoot the 30” casing,and pull the TGB and PGB. Move rig

as required.

26” Hole Plan

Page 94: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 94/102

94

26 Hole Plan 

9. If the gas in step 7 depletes or the

density is sufficient to control the

well, then casing can be run or the

well can be drilled ahead.

10. Drill 8 1/2” hole to +/- 40‟ below the

setting depth of the 20” casing

(estimated at 1040‟ BML).

26” H l Pl

Page 95: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 95/102

95

26” Hole Plan 

11. Circulate and condition for logs. Pull out

of hole, and log well per procedure.

12. PU & TIH with 17 1/2” bit, Monel DC, 6-9

1/2” DC‟s, stabilizers at 60‟ amd 90‟, 6-8”

DC‟s, jars, 9 jts 5” Hevi-Wate DP.

26” Hole Plan

Page 96: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 96/102

96

13. Drill a 17 1/2” hole to sufficient depth

to set 1040‟ of 20” conductor casing.

Drop multishot, and POH.

14. PU & TIH with 17 1/2” bit and 26”

underreamer, 6-9 1/2” drill collars, 6-  8” drill collars, 9 jts 5” Hevi-Wate DP,

and 26” stabilizer at 60‟.

26 Hole Plan 

Page 97: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 97/102

97

15. Underream to sufficient depth to set

1040‟ of 20” conductor casing.

16. Circulate and condition the hole for 

casing. Care must be taken to have a

balanced mud weight all the wayaround with no heavy slugs.

26” Hole Plan 

26” Hole Plan

Page 98: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 98/102

98

17. Displace hole from TD to the sea floor 

with sufficient weight mud to balance

the hydrostatic when the riser is

removed.

 Again, care must be taken to have a

balanced mud weight while displacing,

and the riser may have to be voidedwith sea water as the heavier mud is

circulated.

26 Hole Plan 

26” Hole Plan

Page 99: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 99/102

99

18. POH, run the 20” casing and 18 3/4” - 

10,000 psi wellhead housing, and

cement per procedure.

19. If there is evidence that the hole

cannot be drilled deeper safely in

step 9, the well will be underreamedat the depth reached in step 9 and

20” casing will be set.

26 Hole Plan 

Page 100: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 100/102

100

20. It will then be determined whether 

future casing settings need to be

changed.

etc. etc. etc.

26” Hole Plan 

Page 101: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 101/102

101

Page 102: Wellheads and Casing

7/30/2019 Wellheads and Casing

http://slidepdf.com/reader/full/wellheads-and-casing 102/102