welcome western area power administration1. where did the journey begin? western area power...

26
Western Implementation of FERC Order 890 WELCOME Western Area Power Administration 1

Upload: alison-lyons

Post on 16-Dec-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Western Area Power Administration 1

Western Implementation of FERC Order 890

WELCOME

Western Area Power Administration 2

Where did the journey begin?

Western Implementation of FERC Order 890

Western Area Power Administration 3

FERC Order 890 Timeline

• February 2007 FERC issues Order 890

• December 2007 FERC issues Order 890-A

• June 2007 FERC issues Order 890-B

• March 2009 FERC issues Order 890-C

Western Area Power Administration 4

FERC Order 890 Timeline

• February 2008 Western forms an Order 890 Team

• June 2008 Western forms Tariff Administration Team (TAT) to implement the Tariff.

• June 2009 Western has public customer meeting on proposed Tariff.

• September 2009 Western files new Tariff with FERC

• December 1, 2009 Western implements new Tariff

Western Area Power Administration 5

FERC Order 890 Changes• Unreserved Use

• Reselling/Reassigning of Transmission

• Ancillary Services (Energy & Generator Imbalance)

• Rollover

• Simultaneous Submission Window

• LGI Procedure & Environmental Agreement

• Network Service

• Conditional Firm

Western Area Power Administration

Question: What is unreserved use of transmission service? Use of transmission service that is not reserved or is

in excess of reserved capacity Non-secured reserved capacity or exceeded firm or

non-firm reserved capacity at any point of receipt or delivery

OATT doesn’t specify all circumstances that constitute use of transmission service without a transmission service reservation

DSW will go through Rate process. Unreserved use slides are examples and may change during Rate process.

6

Unreserved use – Schedule 10

Western Area Power Administration 7

Unreserved Use Applies

NO RESERVATION

If Load > than PTP Reservation, Unreserved Use

Applies

Example Scenario - Point to point

1

2 PTP

RESERVATION

Load

Load

Unreserved use

Western Area Power Administration 8

PTP RESERVATION

If Load > than Forecast, Unreserved Use DOES NOT

Apply

3

4 NITS

If Gen > than PTP Reservation, Unreserved Use Applies

Load

Unreserved use

Example Scenario - Excess Generation and Network

Western Area Power Administration 9

Multiple hours in one day

• Daily Firm Point-to-Point Service rate

Multiple days in one

week

• Weekly Firm Point-to-Point Service rate

Multiple weeks in

one month

• Monthly Firm Point-to-Point Service rate

Unreserved use – Frequency & Penalty

Western Area Power Administration 10

Reselling of Transmission

Price of reselling Transmission

Pro Forma FERC 890: Allows for reselling of transmission at “market rate”. Transmission cap rate is no removed, no longer restricted the price a customer can sell transmission.

Western Implementation: Western decided not to adopt this language. The cap will remain in place.

11Western Area Power Administration

Reselling of Transmission

Western’s Role as a Financial Mediator

Pro Forma FERC 890: Requires transmission provider to act as the financing wharehouse for the reseller and third party purchasing the transmission from the reseller.

Western Implementation: Due to Western’s financial authority limitation, we couldn’t perform this function.

12Western Area Power Administration

Reselling of Transmission

New Agreement for Reselling, called Attachment A-1

Pro Forma FERC 890: New Attachment called A-1 was created for the sole purpose of reselling/reassigning of transmission agreements.

Western Implementation: Western will use the new Attachment A-1 for writing reselling and reassignment agreements.

13Western Area Power Administration

Imbalance Services

Energy Imbalance & Generator Imbalance

Pro Forma FERC 890: Implemented new tiers for Energy Imbalance. Created new Schedule for Generator Imbalance

Western Implementation: Western decided Energy Imbalance and Generator Imbalance will be handled through the each Region’s Rate process.

14Western Area Power Administration

Rollover Rights

Change in Rollover Rights

• Existing requirement is a minimum term of one year to have rollover rights. New minimum requirement requires a duration of five years for customer to have the option to exercise rollover rights.

The existing requirement is sixty days notice given to Western. New requirement is one year notification to Western.

15Western Area Power Administration

Rollover Rights

Change in Rollover Rights (Continued)

• The change in rollover rights can be found in Section 2.2 of Western’s new Tariff.

• Section 2.2 is applicable when FERC accepts Western’s Attachment P (Planning Process), until then the current sixty day notice will be applied.

• When Western’s Attachment P is accepted by FERC a business practice will be posted explaining how Western will handle Agreements that expire within one year.

16Western Area Power Administration

Simultaneous Submission Window

What is Simultaneous Submission Window?

• FERC Order 890 required TPs who set a “no earlier than” time limit for TSRs to treat all received within a specified period of time as having been received simultaneously.

• New provision can be found in Section 13.2.

17Western Area Power Administration

Simultaneous Submission WindowWestern implementation of Simultaneous Submission Window

• Only applicable to short term firm point-to-point. Non-Firm, Hourly-Secondary, and long-term requests will have the same evaluation process.

• Western will treat all applicable requests received within five minutes of window opening as having the same queue time.

• If there’s not enough capacity to accommodate the requests, Western will implement a lottery to allocate the capacity.

18Western Area Power Administration

Simultaneous Submission WindowLottery implementation

• Western will implement the lottery giving priority to requests in the following order:

A. Service Increment• In order Monthly, Weekly, Daily, and Hourly

B. Duration of the requestC. Pre-Confirmation

• Request that are preconfirmed will have priority over non-preconfirmed requests.

• Pre-Confirmation D. Price

19Western Area Power Administration

Large Generation Interconnection Procedure & Environmental StudiesChanges to Large Generation Interconnection

Procedure

• Within 15 calendar days of providing a system impact study report, an environmental review agreement will be provided to the customer.

• Environmental review agreement must be executed and funded by the customer within 30 calendar days .

• If agreement isn’t executed and funded with the required time, the interconnection request will be deemed withdrawn.

20Western Area Power Administration

Network Transmission Service

Changes to Network Transmission Service.

•Attestation of resources is required.

• Minimum term of designating a network resource (DNR).

• Requirements of DNR

• If agreement isn’t executed and funded with the required time, the interconnection request will be deemed withdrawn.

21Western Area Power Administration

Network Transmission Service

Requirements of Designated Network Resources.

• Resource must be owned, leased, or customer purchases non-interruptible power under executed contracts.

• DSW, CRSP, RMR, and SNR will not require purchases from a specific generating unit.

For off-system resources, Customer is required to obtain and demonstrate to Western it either has or is in the process of obtaining firm transmission from the point where the Customer takes delivery.

22Western Area Power Administration

Network Transmission Service

Requirements of Designated Network Resources

• For Day-Ahead and Real-Time purchases, Western will reserve the capacity for the length of those purchases.

• Network Resources currently listed in Network Agreements will remain “Grandfathered”, until expiration of the Network Resource, expiration of the Network Agreement, or Resource is undesignated.

23Western Area Power Administration

Conditional Firm Transmission ServiceWhat is Conditional Firm?

Modified form of long-term firm PtP service that includes less-than-firm service in a defined number of hours of the year or during defined system conditions. (OATT Section 15.4)

No separate queueThe service can be curtailed solely for reliability

reasons during the defined system conditions or defined number of hours.

Western will offer either option (considerations)NERC Priority 6 during “conditional” periods

24Western Area Power Administration

Conditional Firm Transmission ServiceConditional Firm Bridge Product

For customers supporting the construction of upgrades, the planning redispatch or conditional firm options will serve as a bridge until upgrades are constructed to remedy the congested transmission facilities.

For these customers, the TP must offer planning redispatch or conditional firm service until the time when the upgrades are constructed. The conditions or redispatch applicable to this period must be specified in the service agreement and are not subject to change.

25Western Area Power Administration

Conditional Firm Transmission ServiceConditional Firm

Western retains the right to perform a biennial assessment of the conditions to reassess the conditions.

A customer taking conditional firm service will be first in the queue for transmission service if a non-conditional firm service stops taking service.

26Western Area Power Administration

Contact Information

For questions regarding implementation of Order 890, please contact the TAT member for your Region:

CRSP: Dave Shelton – (801) 524-4012DSWR: John Steward – (602) 605-2774RMR: Raymond Vojdani – (970) 461-7379SNR: Ira Witherspoon – (916) 353-4659UGPR: Steve Sanders – (406) 247-7436