Page 1: Weekly Construction Newsletter September 1st, 2017 Asphalt ... · September 1st, 2017 . Left: Greenhouse roof is installed, operable shade curtains being hung. Workers preparing supports
benf
Text Box
CURRENT NEWS High School Mounting of markerboards and smartboards were completed. Furniture was delivered and installed. All flooring was installed. All new HVAC equipment is currently running and going through the commissioning process.The new student parking lot is paved and will be ready to go for school on Tuesday. Greenhouse polycarbonate panel installation has begun as well has interior mechanical work. Headhouse masonry work is nearing completion in preparation for trusses next week. Foundation work for the Agility Center addition is continuing. Middle School Furniture and wall-mounted boards were delivered and installed. Paint touch-up was completed and doors were installed. District Office Painting of main rooms is nearing completion, painting of hallway areas will start shortly. The ceiling grid has been installed in preparation for MEP finish work.
benf
Image
benf
Line
benf
Line
benf
Image
benf
Text Box
Weekly Construction Newsletter September 1st, 2017
TimO
Text Box
Asphalt paving taking place early morning on Friday
TimO
Text Box
A new business classroom to be ready for students on Tuesday
TimO
Image
TimO
Image
Page 2: Weekly Construction Newsletter September 1st, 2017 Asphalt ... · September 1st, 2017 . Left: Greenhouse roof is installed, operable shade curtains being hung. Workers preparing supports
benf
Image
benf
Line
benf
Line
benf
Image
benf
Text Box
September 1st, 2017
TimO
Text Box
Left: Greenhouse roof is installed, operable shade curtains being hung
TimO
Text Box
Workers preparing supports for the water piping for the new roof chiller
TimO
Text Box
Above: In the background the new student parking lot is being paved, in the foreground the new Agility Center foundation is shaping up
TimO
Image
TimO
Image
Page 3: Weekly Construction Newsletter September 1st, 2017 Asphalt ... · September 1st, 2017 . Left: Greenhouse roof is installed, operable shade curtains being hung. Workers preparing supports
benf
Line
benf
Line
benf
Image
benf
Text Box
September 1st, 2017
TimO
Text Box
Asphalt paving taking place early morning on Friday
TimO
Text Box
The Agility Center concrete pad formed and poured in the same day. Each pad is 4' deep and contains approximately 15 cubic yards of concrete