4.0 PROJECT PLANNING: WORK BREAKDOWN STRUCTURE (WBS) 1.0 METHANE ENTRAPMENT 1.1 PROJECT PLANNING 1.1.1 Create Project Plan 1.1.2 Submit Project Plan 1.1.3 Project Plan Approval 1.2 MARKET RESEARCH 1.2.1 Focus Groups 1.2.2 Surveys 1.2.3 Research Analysis 1.2.4 Market Research Findings 1.3 MARKETING 1.3.1 Marketing Strategy 1.3.2 Marketing Plan 1.4 PROJECT SETUP 1.4.1 Hire Human Resources 1.4.2 Technical Planning 1.4.3 Purchase Materials 1.4.4 Technical Supervision 1.4.4 Setup Done 1.5 PROJECT MANAGEMENT 1.5.1 Project Start Activity 1.5.2 Project Coordinatio n 1.5.3 Project Controlling 1.5.4 Project Marketing 1.5.5 Project Closure 1.5.6 Project End 1.6 PRODUCTION 1.6.1 Production Start 1.6.2 Collecting Raw Materials 1.6.3 Processsing Raw Materials 1.6.4 Producing Biogas 1.6.5 Producing Biogas Energy 1.6.6 Production Finish 1.7 TERMINATION 1.7.1 Organizatio n Meeting 1.7.2 Financial Report 1.7.3 Appoint Termination Manager 1.7.4 Prepare Final Report 1.7.5 Project Closure

Upload: amir-firdaus

Post on 10-Apr-2016

4 views

Category:

Documents


0 download

DESCRIPTION

.

TRANSCRIPT

Page 1: WBS n Milestone

4.0 PROJECT PLANNING: WORK BREAKDOWN STRUCTURE (WBS)

1.0 METHANE ENTRAPMENT

1.1 PROJECT PLANNING

1.1.1 Create Project Plan

1.1.2 Submit Project Plan

1.1.3 Project Plan Approval

1.2 MARKET RESEARCH

1.2.1 Focus Groups

1.2.2 Surveys

1.2.3 Research Analysis

1.2.4 Market Research Findings

1.3 MARKETING

1.3.1 Marketing Strategy

1.3.2 Marketing Plan

1.4 PROJECT SETUP

1.4.1 Hire Human

Resources

1.4.2 Technical Planning

1.4.3 Purchase Materials

1.4.4 Technical Supervision

1.4.4 Setup Done

1.5 PROJECT MANAGEMENT

1.5.1 Project Start Activity

1.5.2 Project Coordination

1.5.3 Project Controlling

1.5.4 Project Marketing

1.5.5 Project Closure

1.5.6 Project End

1.6 PRODUCTION

1.6.1 Production Start

1.6.2 Collecting Raw Materials

1.6.3 Processsing Raw Materials

1.6.4 Producing Biogas

1.6.5 Producing Biogas Energy

1.6.6 Production

Finish

1.7 TERMINATION

1.7.1 Organization

Meeting

1.7.2 Financial Report

1.7.3 Appoint Termination

Manager

1.7.4 Prepare Final Report

1.7.5 Project Closure

Page 2: WBS n Milestone

4.1 PROJECT MILESTONETask Duration Predecessors Description Assigned To

1.1 Project Planning

1.1.1 Create Project Plan

1.1.2 Submit Project Plan

1.1.3 Project Plan Approval

2 weeks

1 week

1 week-

Formal task before start project.

Eg: Company proposal

Chief Executive Officer

Board of Directors

1.2 Market Research

1.2.1 Focus Groups

1.2.2 Surveys

1.2.3 Research Analysis

1.2.4 Market Research

Findings

1 week

2 weeks

4 weeks

1 week-

To check on the market

availability

R&D

Researcher

Chemist

Marketing Manager

1.3 Marketing

1.3.1 Marketing Strategy

1.3.2 Marketing Plan2 weeks

2 weeksa,b Involved all the marketing

strategy and budgeting needed

Marketing Manager

Sales & Promotional Team

Page 3: WBS n Milestone

1.4 Project Setup

1.4.1 Hire Human

Resources

1.4.2 Technical Planning

1.4.3 Purchase Materials

1.4.4 Technical Supervision

1.4.4 Setup Done

1 month

2 months

6 months

3 months

6 monthsc, a Installment of all equipments.

Chief Executive Officer

Operational and Production Head

Finance Manager

Head of Technical Unit

Plant Engineer

Mechanical Engineer

1.5 Project Management

1.5.1 Project Start Activity

1.5.2 Project Coordination

1.5.3 Project Controlling

1.5.4 Project Marketing

1.5.5 Project Closure

1.5.6 Project End96 c, d

Project initiation process until

project closure.

Operational and Production Head

Chief Executive Officer

Operational and Production Head

Marketing Manager

Board of Directors

Page 4: WBS n Milestone

1.6 Production

1.6.1 Collecting Raw

Materials

1.6.2 Processing Raw

Materials

1.6.3 Producing Biogas

1.6.4 Producing Biogas

Energy

1.6.5 Production Finish

84 dStarting the production of the

project. The generation of

electricity from methane.

Plant Manager 1 & 2

Head of Technical Unit

Plant Engineer

Mechanical Engineer

1.7 Termination

1.7.1 Organization Meeting

1.7.2 Financial Report

1.7.3 Appoint Termination

Manager

1.7.4 Prepare Final Report

1.7.5 Project Closure

1 month

3 months1 month

2 months

5 months

e, fProject closure due to several

aspects.

Board of Directors

Finance Manager

Chief Executive Officer

Accountant

Operational and Production Head