PAKISTAN’S VISION OF WATERRESOURCES MANAGEMENT
Presented By
Minister for Water and Power
At
Pakistan Development Forum
May 14, 2003
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 2/24
COUNTRY PROFILE
• POPULATION: 141 MILLION
• GEOGRAPHICAL AREA: 796,100 KM2
• IRRIGATED AREA: 36 MILLION ACRES (14.5 MHa)
• ANNUAL WATER AVAILABILITY
(AT RIM STATIONS; POST TARBELA): 143 MAF (175 BCM)
• ANNUAL CANAL WITHDRAWALS: 104 MAF (128 BCM)
• GROUND WATER PUMPAGE: 42 MAF (50 BCM)
• PER CAPITA WATER AVAILABLE (2003): 1200 CUBIC METRE
• AGRICULTURE PRODUCT: 25 % OF GDP
• TOTAL POWER GENERATION
(INSTALLED CAPACITY): 17,942 MW
• HYDROPOWER GENERATION
(INSTALLED CAPACITY) : 5,039 MW
1
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 3/24
RIVERS OF PAKISTAN
INDUS
JHELUM
CHENAB
RAVI
SUTLAJ
BIAS
WESTERN
RIVERS
EASTERN
RIVERS
A F G H
A N I S T A
N
I N D I A
IRAN
2
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 4/24
Indus Basin IrrigationIndus Basin IrrigationIndus Basin IrrigationIndus Basin Irrigation
SystemSystemSystemSystemBarrages 19
Main Canal Commands 45
Link Canals 12
INDIA
IRAN
A F G H
A N I S T
A N
3
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 5/24
IRRIGATION NETWORK OF PAKISTAN
THE IRRIGATION SYSTEM OF PAKISTAN IS THE LARGESTINTEGRATED IRRIGATION NETWORK IN THE WORLD, SERVING 36MILLION ACRES OF CONTIGUOUS CULTIVATED LAND. THE SYSTEM
IS FED BY THE WATERS OF THE INDUS RIVER AND ITSTRIBUTARIES.
SALIENT FEATURES OF IRRIGATION NETWORK
STRUCTURES NO.
MAJOR STORAGE RESERVOIRS 3
(EXISTING LIVE STORAGE 12.7 MAF)SMALL DAMS 80
BARRAGES 19
INTER-RIVER LINK CANALS 12
INDEPENDENT IRRIGATION CANAL COMMANDS 45
4
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 6/24
WATER REQUIREMENT AND AVAILABILITY
121.81
12.26
9.14 %
103.81
Not
Applicable-
Average Surface Water Availability With Additional Storages
Shortfall
% Age
103.81
30.26
22.56 %
103.81
12.61
10.83 %
Average Surface Water Availability
Without Additional StoragesShortfall
% Age
134.07116.42Surface Water Requirements
2025
(MAF)
2000
(MAF)
YearRequirement / Availability
5
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 7/24
ISSUES IN THE WATER SECTOR
• INSTITUTIONAL AND MANAGEMENT ISSUES
• TECHNICAL ISSUES
6
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 8/24
INSTITUTIONAL AND MANAGEMENT ISSUES
• NEED FOR NATIONAL WATER COUNCIL TO OVERSEEINTEGRATED WATER SECTOR PLANNING, DEVELOPMENT AND
MANAGEMENT
• INADEQUATE STAKEHOLDER PARTICIPATION
• LACK OF PUBLIC AWARENESS & DEFICIENT WATERINFORMATION
• LACK OF FINANCIAL SUSTAINABILITY IN WATER SECTOR
SERVICES
• LOW PRIVATE SECTOR INVESTMENT OR PARTICIPATION
7
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 9/24
TECHNICAL ISSUES
• INCREASING DEMAND OF WATER FOR FOOD, FIBRE AND POWER
• COMBINED USE OF SURFACE AND GROUND WATER
• INEFFICIENT USE AND INEQUITABLE DISTRIBUTION OF WATER,ESPECIALLY IN IRRIGATION
• DETERIORATING WATER QUALITY
• INADEQUATE DRINKING WATER SUPPLY AND POOR QUALITY OFSERVICE
• DETERIORATING INFRASTRUCTURE IN THE IRRIGATION AND
DRAINAGE SUB-SECTORS
• ENVIROMENTAL DEGRADATION OF IRRIGATED LANDS
• SAFE DISPOSAL OF SALINE DRAINAGE EFFLUENT TO THE SEA
8
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 10/24
NATIONAL WATER VISION
BY 2025, PAKISTAN SHOULD HAVE ADEQUATE WATER AVAILABLE
THROUGH CONSERVATION, DEVELOPMENT AND GOOD
GOVERNANCE. WATER SUPPLIES SHOULD BE OF GOOD QUALITY,
EQUITABLY DISTRIBUTED AND MEET THE NEEDS OF ALL USERS
THROUGH AN EFFICIENT AND INTEGRATED MANAGEMENT,
INSTITUTIONAL AND LEGAL SYSTEM THAT WOULD ENSURE
SUSTAINABLE UTILIZATION OF THE WATER RESOURCES AND
SUPPORT ECONOMIC AND SOCIAL DEVELOPMENT WITH DUE
CONSIDERATION TO THE ENVIRONMENT, QUALITY OF LIFE,
ECONOMIC VALUE OF RESOURCES, ABILITY TO PAY AND
PARTICIPATION OF ALL STAKEHOLDERS.
9
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 11/24
POLICY PLANNINGFOR THE NATIONAL WATER VISION
• WAPDA VISION 2025
• NATIONAL WATER POLICY
• NATIONAL WATER RESOURCES STRATEGY
10
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 12/24
OBJECTIVES OF VISION 2025
• TO PREVENT THE WATER SHORTAGES IN THE FUTURE
• TO COMPENSATE/ADJUST FOR THE PREDICTED CLIMATICCHANGES
• TO PROTECT THE AGRICULTURE SECTOR FROM DROUGHTS
• TO INCREASE RESERVOIR CAPACITIES LOST DUE TO SILTATION AND DEVELOP NEW STORAGES TO CATER FOR FUTURE NEEDS
• TO DEVELOP 16,000 MW OF HYDROPOWER FOR PROVIDING CHEAPELECTRICITY TO CONSUMERS
• TO INVEST US $ 33 BILLION IN NEXT 22 YEARS TO ACHIEVE THE
ABOVE VISION 11
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 13/24
ON GOING WATER SECTOR PROJECTS
174,492268.43,259,1065.64Total:
Dec. 200717,947-412,400-Rainee Canal
June 200732,450-713,000-Kachhi Canal
June 200730,467-1,530,000-Greater Thal Canal
March2006
2,0921319,9200.08Satpara Dam
June 20051,000-25,0000.02Sabakzai Dam
June 20099,30058362,5001.20Kurram Tangi Dam
June 20065,860-33,2000.30Mirani Dam
Sept 200612,82317.4163,0861.14Gomal Zam Dam
June 200762,553180-2.90Mangla Dam Raising
Project
CompletionDate
Cost
(RsMillion)
Installed
Capacity(MW)
Irrigable Area
(Acres)
Storage
(MAF)
Name of Project
12
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 14/24
ON GOING HYDRO POWER PROJECTS
June 20048,8401,450Ghazi BarothaHydropower Project
53,1171,975Total:
June 200613,54796Jinnah Barrage HydroProject
June 20067,035106Golen Gol Hydro PowerProject
June 20079,754130Duber Khawar Hydro
Power Project
June 20068,578121 Allai Khawar Hydro
Power Project
June 20065,36372Khan Khawar Hydro
Power Project
CompletionDate
Cost
(Rs Million)
Installed
Capacity(MW)
Name of Project
13
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 15/24
IMPACT OF ONGOING PROJECTS
THE ONGOING WATER AND POWER SECTOR PROJECTS
WILL PROVIDE
1) ADDITIONAL STORAGES OF 5.64 MAF, AND
2) IRRIGATE ADDITIONAL 3.26 MILLION ACRES OF LAND
AND PROVIDE EXTRA 2,443 MW OF HYDROPOWER
14
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 16/24
PROSPECTIVE IRRIGATION
INFRASTRUCTURE PROJECTS
88,2314,988,661Total:
-
159,073
285,652
956,936
2,430,000
175,000
482,000
340,000
160,000
Area to be
Irrigated (Acres)
-do-1,000Balochistan Small IrrigationSchemes
-do-2,332Patfeeder Canal Extension
-do-19,200Chashma Right Bank Canal 1st
Lift
-do-6,208North West Canal Remodelling
Project
-do-37,701Sehwan Barrage Complex
-do-7,003Shakargarh Canal Irrigation
System
-do-3,618Cholistan Project – 1
-do-9,019Dajal Canal Extension Project
Beyond 20052,150Jalalpur Canal Project
Tentative
Start Date
Cost
(Rs Million)
Name of Project
15
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 17/24
PROSPECTIVE STORAGE PROJECTS
11,70031.59Total:
-do-7400.67Munda Dam
3.60
15.52
6.10
5.70
Storage(MAF)
-
4,000
3,600
3,360
InstalledCapacity (MW)
-do- Akhori Dam
Feasibility
Study
Skardu Dam
Ready forConstructionKalabagh Dam
Feasibility
Study
Basha Dam
StatusName of Project
16
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 18/24
PROSPECTIVE HYDROPOWER PROJECTS
906,0188,914Total
PC-I Approved84,502963Neelum Jhelum Hydropower
-do-10,556120Taunsa Hydropower
-do-15,720219Naran (NWFP)
-do-15,960222 Azad Pattan (Jhelum River)
-do-161,3401500Bunji Hydropower (NA)
-do-153,9601043Thakot Hydropower (NA)
-do-10,020139Chokothi (Jhelum River)
84
1172
2712
740
Installed
Capacity
(MW)
-do-6,600Matiltan (NWFP)
-do-178,080Pattan Hydropower (N.A)
F.S. in Hand186,420Dasu Hydropower (N.A)
F.S. Completed82,860Kohala Hydropower (AJK)
StatusCost
(Rs Million)
Name of Project
17
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 19/24
NATIONAL WATER POLICY
A NATIONAL WATER POLICY HAS RECENTLY BEEN PREPARED AND ISBEING PROCESSED FOR APPROVAL OF THE GOVERNMENT.OBJECTIVES OF THE POLICY ARE:
• ACCESS TO POTABLE WATER SUPPLY FOR ALL
• ADEQUATE QUANTITY OF WATER FOR FINANCIALLY SUSTAINABLE
IRRIGATED AGRICULTURE TO MEET FOOD AND FIBRE
REQUIREMENTS
• WATER FOR INDUSTRY TO SUPPORT HIGH ECONOMIC
DEVELOPMENT
• BALANCED AND EQUITABLE USE OF WATER TO MEET THE NEEDS OF
ALL USERS
• IMPROVED ENVIRONMENT THROUGH BETTER WATER QUALITY
• REDUCTION IN DRAINAGE EFFLUENT AS FAR AS POSSIBLE AND ITS
SAFE DISPOSAL TO SEA
18
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 20/24
WATER RESOURCES STRATEGY
A NATIONAL WATER RESOURCES STRATEGY HAS BEEN PREPARED
WHICH IS CURRENTLY UNDER APPROVAL OF THE GOVERNMENT.
ELEMENTS OF STRATEGY ARE:
• TO PROVIDE UPDATED COMPREHENSIVE WATER SECTOR STRATEGY
UPTO YEAR 2025 FOR GUIDANCE ON INVESTMENT PLANNING ANDMANAGEMENT OF WATER SECTOR. ALSO EVOLVE MEDIUM TERM
INVESTMENT PLAN UPTO YEAR 2011
• TO DEVELOP SPECIFIC INVESTMENT PROPOSALS RESPONSIVE TO THE
NATIONAL DEVELOPMENT PROGRAMME
19
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 21/24
WATER RESOURCES SECTOR STRATEGY - COST
TOTAL
FLOOD PROTECTION
ENVIRONMENTHYDROPOWER
IRRIGATION AND DRAINAGE
INDUSTRIAL WATER SUPPLY ANDPOLLUTION CONTROL
RURAL WATER SUPPLY ANDSANITATION
URBAN WATER SUPPLY ANDSANITATION
WATER RESOURCES DEVELOPMENT
SUB-SECTOR
33,622
418
1134,500
11,099
253
2,173
5,066
10,000
COST($ US MILLION)
20
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 22/24
Thank You
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 23/24
INSTITUTIONAL REFORMS
MASSIVE INSTITUTIONAL REFORMS IN THE WATER SECTOR AREBEING UNDERTAKEN TO ENSURE GOOD GOVERNANCE, EFFICIENTMANAGEMENT AND SUSTAINABILITY OF THE EXISTING
IRRIGATION AND DRAINAGE INFRASTRUCTURE. TO MEET THISOBJECTIVE, FOLLOWING MEGA PROJECTS ARE UNDER EXECUTION.
• NATIONAL DRAINAGE PROGRAMME
• RIGHT BANK OUTFALL DRAIN
• IRRIGATION SYSTEMS REHABLITATION AND LINING OFIRRIGATION CHANNELS IN PROVINCES
• MODERNIZATION OF BARRAGES
7/23/2019 Water Mgmt
http://slidepdf.com/reader/full/water-mgmt 24/24
INSTITUTIONAL REFORMS UNDER NATIONAL
DRAINAGE PROGRAMME
OBJECTIVES: (1) GOOD GOVERNANCE
(2) DEVOLUTION OF POWERS TO GROSS ROOT
LEVEL(3) INCREASE OPERATIONAL EFFICIENCY OFPROVINCIAL IRRIGATION DEPARTMENTS
(4) ENSURE FINANCIAL SUSTAINABILITY
REFORMS: (1) TRANSFORMATION OF PIDs INTO
AUTONOMOUS PIDAs(2) FORMATION OF FINANCIALLY SELF-
ACCOUNTING AREA WATER BOARDS (AWBS)
(3) ESTABILISHMENT OF SELF-SUSTAININGFARMERS ORGANIZATION (FOS) FOR
OPERATION AND MANAGEMENT OF THEIRRIGATION AND DRAINAGE SYSTEM
BENEFITS: PIDAS SHALL BECOME SELF-FINANCING WITHIN A
PERIOD OF 7-10 YEARS AND SHALL NOT REQUIRE
GOVERNMENT SUBSIDIES TO FINANCE THEIR O&M IN
FUTURE