waste heat project at lsil pdd date 05 feb

Upload: rmalegavi5261

Post on 09-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    1/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 1

    CLEAN DEVELOPMENT MECHANISM

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD)

    Version 03 - in effect as of: 28 July 2006

    CONTENTS

    A. General description of project activity

    B. Application of a baseline and monitoring methodology

    C. Duration of the project activity / crediting period

    D. Environmental impacts

    E. Stakeholders comments

    Annexes

    Annex 1: Contact information on participants in the project activity

    Annex 2: Information regarding public funding

    Annex 3: Baseline information

    Annex 4: Monitoring plan

    Appendix: Screen shots of excel sheets.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    2/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 2

    SECTION A. General description of project activity

    A.1. Title of the project activity:>>

    (a) Title of project activity: Waste Heat project at LSIL

    (b) The current version number of document: 1

    (c) The date of the document was completed: 05/02/2010

    A.2. Description of the project activity:

    >>

    Description of project activity

    (1) Purpose of the project activity

    The purpose of project activity is to replace fossil fuel being used in reheating furnace (RHF), Continuoushot dip Galvanising Line (CGL) furnaces and Coiler furnace at Lloyds Steel Industries Limited (LSIL) by

    waste coke oven gas. The details on waste coke oven gas provided in this section.

    The Coke Oven Gas is sourced from joint facility of Uttam Galva Metallics Limited (UGML) and LSIL.

    UGML is being put up with sole intention to supply LSIL their entire finished product Pig Iron. LSIL will

    use the pig iron for manufacturing of their product steel. UGML is within the same industrial facility

    adjoining to LSIL manufacturing area and creating joint facility as they use common utilities like water,

    Nitrogen, Oxygen etc.

    The agreement between UGML and LSIL for creating joint facility where in the entire product of UGML

    is supplied to LSIL and having common utilities including use of coke oven gas by LSIL will be made

    available to DOE during validation process.

    (a) Scenario existing prior to start of the implementation of project activity.

    LSIL is a steel manufacturing company equipped with DR-EAF-Continuous slab caster based steel

    plant of capacity about 600000 tonnes/year of steel. The fossil fuels are presently being fired in the

    following furnaces.

    (a.1) The Reheating Furnace for heating of ladle, turn dish etc uses Furnace oil for firing.

    (a.2) Continuous hot dip galvanising line (CGL) furnaces

    NON OX furnace is direct LPG fired

    RTF furnace is indirect LPG fired

    (a.3) Stecker Mill Coiler furnaceFuel fired is LPG

    The project activity is to replace the fossil fuel being presently used with waste coke oven gas.

    (b) The project scenario.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    3/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 3

    (b.1) LSIL proposes to replace this Reheating furnace (RHF) of capacity of 150 tonnes/hr which uses

    furnace oil as fuel with new Reheating furnace of capacity 300 tonnes/hr which can use Coke Oven Gas

    as fuel. The proposed new facility will result in increased plant of capacity of 1000000 tonnes/year of

    steel.

    (b.2) Continuous hot dip galvanising (CGL) and coiler furnaces which presently use LPG as fuel will

    be modified to use coke oven gas instead of LPG. The modification will involve changing burners and

    control system including piping of coke oven gas.

    LSIL proposes to use only waste coke oven gas in the furnaces thus replacing the furnace oil/LPG

    consumption.

    The waste coke oven gas will be sourced from UGML who are putting 450 m3 blast furnace to produce

    472000 tonnes/month of hot metal and 200000 tonnes/month of metallurgical coke. The coke oven gas is

    obtained as by product during manufacturing of metallurgical coke which is used in blast furnace for

    making hot metal.

    UGML do not have any use for excess coke oven gas after using the coke oven gas in the blast furnace

    and would be letting out into atmosphere after burning.

    LSIL has entered into agreement with UGML to create the joint facility where LSIL will source the

    entire finished product Pig Iron of UGML and common utilities are being used. LSIL will use the waste

    coke oven gas which has the following composition and calorific value as delivered to LSIL at receiving

    point by UGML. The agreement will be made available to DOE during validation.

    Flow rate 12250 Nm3/h

    Temperature 100 deg C

    Pressure 0.95 kg/cm2

    Composition CO 7.5 -9 % CO2 2.0-3.0% H2 55-57 % N2 2-6% CH4 24-26% CnHn 5%Calorific value 16720 kJ/Nm3

    This coke oven gas is fired instead of furnace oil in reheating furnace and coke oven gas will be fired

    instead of LPG in Coiler furnace and CGL furnaces.

    Scope of activities include the following installations

    1 New reheating furnace capable of using coke oven gas for firing.

    2 Modification of Coiler furnace for using coke oven gas instead of LPG.

    3 Modification of CGL furnaces for using coke oven gas instead of LPG.

    4 Pipe line to carry gas from gas holder to utility points of approximate length of 3 km.

    Current status of project activity

    1 The new reheating furnace capable of using coke oven gas is received and being installed.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    4/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 4

    2 Piping work from UGML to LSIL utility points will be completed by March 2010.

    3 Commissioning expected by April-June 2010 after the continuous availability of coke oven gas.

    (c)Base line Scenario

    The baseline is the same scenario existing prior to the start of implementation of project activity.

    The base line is fossil fuel i.e. Furnace oil for RHF and LPG for Coiler/CGL furnaces are being fired inpre project scenario and the same scenario of using fossil fuel for firing in furnaces would have been

    continued in the absence of project activity.

    (2) How the project activity reduces GHG emissions

    The project activity reduces CO2 emissions from replacement of fossil fuels used in the furnaces by waste

    coke oven gas which would have been otherwise flared by UGML before letting into atmosphere in theabsence of the project activity and in the project activity LSIL uses this waste coke oven gas in theirfurnaces to provide required heat which would have been otherwise provided by firing fossil fuels like

    furnace oil in reheating furnace and LPG in coiler and CGL furnaces. CO2 emission due to burning of

    fossil fuel is avoided and thus achieves reduction in CO2 emissions.

    In B.3 section it is explained that CO2 emissions due to base line fossil fuel are mainly considered andCH4 and N2O are not considered to be on conservative side in calculating baseline emissions. In A.4.3

    It is also explained that the Furnace oil for RHF and LPG for Coiler/CGL furnaces are being fired in pre

    project scenario and the same are being replaced by WECM coke oven gas.

    .The total CO2 emission reduction for the entire crediting period of 10 years has been calculated as

    1170800 tonne CO2 equivalent.

    (3)The project activity will lead to sustainable development and promote sustainable Industrial growth by

    conserving natural resources and preventing the thermal pollution even though no such statutory

    requirement exists.

    Social benefit to state

    The project activity increases the employment within LSIL for skilled manpower and Professionals.

    Skilled and unskilled labour will gain temporary employment while executing the project.

    India is very deficient in crude oil and major portion of its oil requirements are met by imports. Hence

    saving in the use of fossil fuel like furnace oil and LPG enables the scarce petroleum products to be made

    available to the society for some other uses.

    Economical Benefits to State

    The project involves investment of around 600 million rupees and will involve more than 400 million

    rupees capital equipment purchase. Engineering industry will benefit and provide employment

    opportunity for professionals, skilled and unskilled people.

    The state will generate revenue out of the manufacturing activities supported by the energy generation

    and due to purchase of equipment for execution of project by way of Sales Tax; Excise Duty; Entry Tax

    etc.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    5/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 5

    India is facing shortage of oil leading to import of major requirement of its oil needs which consumes

    valuable foreign exchange leading to petroleum products starvation and hence the project activity enables

    the country to bridge this gap by reduction in demand on petroleum products by company and save

    valuable foreign exchange.

    Environmental Benefit

    The Project activity is waste heat recovery based Project by utilizing waste heat from coke oven gases

    coming from process and thus effectively saving environment of thermal pollution. In the absence of

    project activity coke oven gases would have been flared by UGML leading to thermal pollution. The

    project activity displaces heat from fossil fuel and hence reduces CO2 emission

    A.3. Project participants:

    >>

    Name of the Party Involved (host)

    indicates Host party)

    Private and/or Public entity (ies)

    Project Participant

    ( as applicable)

    Kindly indicate if the party

    involved wishes to be

    Considered as projectparticipant

    (Yes/ No)

    India (host)

    Ministry of Environment and Forest Lloyds Steel Industries Limited

    (Private Entity).

    No

    A.4. Technical description of the project activity:

    A.4.1. Location of the project activity:

    >>

    India

    A.4.1.1. Host Party(ies):>>

    India

    A.4.1.2. Region/State/Province etc.:

    >>

    Maharashtra

    A.4.1.3. City/Town/Community etc.:

    >>

    Bhugano, Taluk Wardha.

    A.4.1.4. Details of physical location, including information allowing the

    unique identification of this project activity (maximum one page):

    >>

    Physical location

    The project activity located at Lloyds Steel Industries Limited, Bhugano, Wardha Taluka & District,

    Maharashtra. Latitude 200 42 4.45, Longitude 780 37 15.24. Nearest Railway station is Bhugano.

    The plant is located approximately at 6 km from Wardha on Bhugano link road.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    6/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 6

    A.4.2. Category(ies) of project activity:

    >>

    The project activity may be principally categorised in category 04 Manufacturing Industries as per

    Scope of Projects activities enlisted in the list of sectoral scopes and approved base line and monitoring

    methodologies on the website for accreditation of Designated operational Entities.

    The CDM PDD is based on approved methodology ACM0012 version 03.2 and Sectoral scope; 01 & 04EB 51 Consolidated baseline methodology for GHG emission reductions from waste energy recovery

    projects

    A.4.3. Technology to be employed by the project activity:

    1) Description of how the project is environmentally safe and sound technology, and know how transfer.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    7/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 7

    The Reheating Furnace is being imported from Jiangsu Sky run Corporation China which is of proven

    technology and all the technical details for operation of the equipment safely are provided by Jiangsu Sky

    run Corporation. The modifications for Continuous hot dip galvanising line (CGL) furnaces and Coiler

    furnace are being carried out by LSIL with new burners from indigenous suppliers. The technology is

    proven. The installation is under CCOE and hence all approvals will be got from CCOE which ensures

    that the installation is safe and of sound technology.

    2) Purpose of project activity

    The purpose of project activity is to replace fossil fuel being used in reheating furnace (RHF),

    Continuous hot dip Galvanising Line (CGL) furnaces and Coiler furnace at Lloyds Steel Industries

    Limited (LSIL) by waste coke oven gas.

    LSIL proposes to use only waste coke oven gas in the furnaces thus replacing the furnace oil/LPG

    consumption.

    The waste coke oven gas will be sourced from UGML who are putting 450 m3 blast furnace to produce

    472000 tonnes/month of hot metal and 200000 tonnes/month of metallurgical coke. The coke oven gas is

    obtained as by product during manufacturing of metallurgical coke which is used in blast furnace for

    making hot metal.

    UGML do not have any use for excess coke oven gas after using the coke oven gas in the plant and

    would be letting out into atmosphere after flaring.

    LSIL has entered into agreement with UGML to create the joint facility where LSIL will source the

    entire finished product Pig Iron of UGML and common utilities are being used. LSIL will use the waste

    coke oven gas which has the following composition and calorific value as delivered to LSIL at receiving

    point by UGML. The agreement will be made available to DOE during validation.

    Flow rate 12250 Nm3/h

    Temperature 100 deg C

    Pressure 0.95 kg/cm2

    Composition CO 7.5 -9 % CO2 2.0-3.0% H2 55-57 % N2 2-6% CH4 24-26% CnHn 5%

    Calorific value 16720 kJ/Nm3

    This coke oven gas is fired instead of furnace oil in reheating furnace and coke oven gas will be fired

    instead of LPG in Coiler furnace and CGL furnaces.

    (a) The scenario existing before project activity.

    In the present system of steel manufacturing in LSIL is based on DR-EAF-Continuous slab based steel

    plant. The rolling and processing lines include steckel mill, cold rolling mill and galvanising lines. The

    plant is operating with DRI and scrap as major metallic inputs to the EAF.

    The following furnaces are existing presently using fossil fuel

    (a.1) The Reheating Furnace (RHF) for heating of ladle, turn dish etc uses Furnace oil for firing.

    Capacity: 600000 tonnes/year

    Make: MDH

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    8/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 8

    Fuel used: furnace oil

    SpecificFuel consumption: 1380 MJ/tonne based on 3 years averageYear of installation: 1994

    (a.2) Continuous hot dip galvanising line (CGL) furnaces

    NON OX furnace is direct LPG fired

    RTF furnace is indirect LPG fired

    Capacity: 250000 tonnes/year

    Fuel used: LPG

    Specific Fuel consumption: 1210 MJ/tonne based on 3 year average.

    Year of installation: 1995

    (a.3) Coiler furnace

    Fuel fired is LPG

    Capacity: 400000 tonnes/year

    Make: MDHFuel used: LPG

    Specific Fuel consumption: 254 MJ/tonne based on 3 years average.

    Year of installation: 1994

    (b) The project scenario

    (b.1) LSIL proposes to replace this Reheating furnace (RHF) of capacity of 150 tonnes/hr with new

    Reheating furnace of capacity of 300 tonnes/hr which can use both Furnace oil/Coke Oven Gas. The

    proposed facility will result in increased plant of capacity of 100000 tonnes/year of steel from present

    600000 tonnes/year.

    (b.2) Existing Continuous hot dip galvanising (CGL) and coiler furnaces will be modified to use coke

    oven gas instead of LPG. The capacity of each furnace remains unchanged.

    The Coke Oven gas which is a by product during manufacturing of metallurgical coke from coal which is

    used in blast furnace to produce pig iron and excess coke oven gas after the use in coke ovens is a waste

    gas which has to be let out to atmosphere and the waste coke oven gas has the following composition and

    flow rate as delivered to receiving point of LSIL by UGML

    Flow rate 12250 Nm3/h

    Temperature 100 deg C

    Pressure 0.95 kg/cm2

    Composition CO 7.5 -9 % CO2 2.0-3.0% H2 55-57 % N2 2-6% CH4 24-26% CnHn 5%

    Calorific value 16720 kJ/Nm3

    UGML does not have any use for this excess coke oven gas in their process after their requirements aremet in coke oven batteries and have to let out into atmosphere after burning in the absence of project

    activity.

    The project activity will comprise the following scope of activities

    Main equipment

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    9/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 9

    1 The pipe line from this gas tank to utility points of approximately 3 km.

    2 The new reheating furnace.

    The new reheating furnace (RHF) has the following specifications:

    Make: Jiangsu Sky run Corporation

    Capacity: 1 Million tones/year

    Charging: cold/hotFuel used: Coke Oven Gas

    Specific Fuel consumption: 1.3 GJ/tonne based on manufacturer specifications for coke oven gas

    1.35 GJ/tonne for furnace oil based on manufacturer specification for

    Furnace oil.Fuel consumed = 9000 Nm3/hr

    3 Coiler furnace and CGL furnaces modification in burner system to make them suitable for coke ovengas firing. Make of burners is M/S Continental Thermal Engineers, Chennai, India.

    Coiler furnace:

    Capacity: 400000 tonnes/year

    Fuel used: Coke Oven Gas

    Specific Fuel consumption: 1210 MJ/tonne based on 3 year average

    Fuel Consumption: 500 Nm3/hr of coke oven gas.

    CGL furnaces

    Capacity: 250000 tonnes/year

    Fuel used: Coke Oven Gas

    Fuel Consumption: 2550 Nm3/hr of coke oven gas.

    The fuel consumption being monitored by electronic meters.

    (c) Base line Scenario

    The baseline is the same scenario existing prior to the start of implementation of project activity.

    The base line is fossil fuel i.e. Furnace oil for RHF and LPG for Coiler/CGL are being been fired in preproject scenario and the same scenario of using fossil fuel for firing in furnaces would have been

    continued in the absence of project activity as it is business as usual scenario.

    c. a) Age and average life time of equipment

    LSIL is a steel manufacturing company equipped with DR-EAF-Continuous slab caster based steel plantof capacity about 600000 tonnes/year of steel. The fossil fuels are presently being fired in the following

    furnaces.

    1 The Reheating Furnace (RHF) for heating of ladle, turn dish etc uses Furnace oil for firing.

    Capacity: 600000 tonnes/year

    2 Continuous hot dip galvanising line (CGL) furnaces fuel used is LPG. Capacity 250000 tonnes/year

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    10/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 10

    3 Coiler furnace, Fuel fired is LPG, Capacity: 400000 tonnes/year

    Fuel consumption and production from furnace are monitored.

    Normal life of steel mill equipment is 30 years as observed in industry. Reheating furnace is new. CGL

    furnace and coiler furnace are approximately 16 years in operation. Expected balance life for these

    furnaces is about 14 years.

    c.b) how emission reductions are achieved.

    The project activity reduces CO2 emissions from replacement of fossil fuels used in the furnaces by

    Waste coke oven gas would have been otherwise flared by UGML before letting into atmosphere in the

    absence of the project activity and in the project activity LSIL uses this waste coke oven gas in their

    furnaces to provide required heat which would have been otherwise provided by firing fossil fuels like

    furnace oil in reheating furnace and LPG in coiler and CGL furnaces. CO2 emission due to burning of

    fossil fuel is avoided and thus achieves reduction in CO2 emissions.

    c.c) Heat energy generated in the project activity.

    The Coke Oven gas which is a by product during manufacturing of metallurgical coke from coal which is

    used in blast furnace to produce pig iron and excess coke oven gas after the use in coke ovens is a waste

    gas which has to be let out to atmosphere and the waste coke oven gas has the following composition and

    flow rate as delivered to receiving point of LSIL by UGML

    Flow rate 12250 Nm3/h

    Temperature 100 deg C

    Pressure 0.95 kg/cm2

    Composition CO 7.5 -9 % CO2 2.0-3.0% H2 55-57 % N2 2-6% CH4 24-26% CnHn 5%

    Calorific value 16720 kJ/Nm3

    UGML does not have any use for this excess coke oven gas in their process after their requirements are

    met in coke oven batteries and have to let out into atmosphere after burning in the absence of project

    activity.

    The heat generated using coke oven gas is calculated as follows:

    Heat from coke oven gas: 12250 x 4000 x 4.18 = 2.0482 x 10 8 kilojoules/hr

    Heat produced by coke oven gas /year = 17942.2 x 10 8 kilojoules/year.

    The use in furnaces expected as follows:

    S No Description ReheatingFurnace

    CGLfurnaces

    CoilerFurnace

    Referencedocument

    1 Production

    capacity

    tonnes/year

    1000000 250000 400000 Manufacturer

    specifications

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    11/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 11

    2 Base line

    fuel

    Furnace

    oil

    LPG LPG

    3 Specificheat

    requirement

    MJ/tonne

    1350 1210 254 Manufacturerspecification

    for RHF and

    for CGL/Coiler

    furnaces

    3 years average

    4 Heat

    provided by

    coke oven

    gas MJ

    13.5 X 108

    3.025X

    108

    1.016X

    108

    5 HG j y 17.541 X 108MJ/Year

    A.4.4. Estimated amount of emission reductions over the chosen crediting period:Years Annual estimation of emission

    reductions in tonnes of CO2eq

    2010 117028

    2011 117028

    2012 117028

    2013 117028

    2014 117028

    2015 117028

    2016 117028

    2017 117028

    2018 117028

    2019 117028Total estimated reductions

    (tonnes CO2 e)1170280

    Total number of crediting years 10

    Annual average over the

    crediting period of estimated

    reductions (tonnes CO2 e)

    117028

    A.4.5. Public funding of the project activity:

    >> No public funding from parties included in Annex-I is available for the project activity. No ODA

    funds are used in project activity.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    12/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 12

    SECTION B. Application of a baseline and monitoring methodology

    B.1. Title and reference of the approved baseline and monitoring methodology applied to the

    project activity:

    >>

    Title of approved methodology: Consolidated baseline methodology for GHG emission reduction from

    energy recovery projects

    Methodology No &Version : ACM 0012, Version 03.2, Sectoral Scope: 1&4 EB 51.

    Other methodologies ACM 0012

    draws upon : 1 Tool for the demonstration and assessment of additionality

    (Version 05.2) EB 39.

    B.2. Justification of the choice of the methodology and why it is applicable to the project

    activity:

    >>

    The methodology sets out two types of project activity.

    Type 1 All the waste energy in identified WECM stream, that will be utilized in the project activity, is, or

    would be flared or released to atmosphere in the absence of project activity at the existing or new facility.

    The waste energy is an energy source for

    . Cogeneration or

    . Generation of electricity or

    . Direct use as process heat source or

    .For generation of heat in element process (e.g. steam, hot water, hot oil, hot air) or

    . For generation of mechanical energy

    The project activity is for direct use as process heat source in furnaces and hence falls in type1 category

    direct use as process heat source. The identified WECM is excess waste coke oven gas.

    The methodology lists out following applicable conditions

    Applicable conditions of Methodology How the project activity meets the conditionsIf project activity is based on use of waste pressure

    to generate electricity, electricity generated using

    waste gas pressure should be measurable

    Not applicable as project activity is for direct use as

    process heat source.

    Energy generated in the project activity may be

    used within the industrial facility or exported

    outside the industrial facility

    The project activity generates heat for use in

    furnaces from WECM and the generated heat is

    used within the industrial facility. UGML has no

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    13/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 13

    use for excess WECM after using in coke oven

    batteries, WECM is being sourced to LSIL as an

    energy source as per agreement to form jointindustrial facility.

    The electricity generated in the project activity may

    be exported to grid

    Not applicable as the project activity is for direct

    use of WECM as process heat source

    Energy in the project activity can be generated by

    the owner of the industrial facility producing waste

    gas/heat or by a third party (e.g.ESCO) within the

    industrial facility.

    Energy in the form of heat is being generated and

    used by LSIL within the same industrial facility.

    UGML has no use for excess WECM after using in

    coke oven batteries, WECM is being sourced to

    LSIL as an energy source as per agreement to form

    joint industrial facility.

    Regulations do not constrain the industrial facility

    generating waste energy from using the fossil fuels

    being used prior to the implementation of project

    activity

    Regulations do not constrain UGML generating

    waste energy from using the fossil fuels being used

    prior to the implementation of project activity.

    The methodology covers both new and existing

    facilities. For existing facilities, the methodology

    applies to existing capacity, as well as to planned

    increases in capacity during the crediting period. Ifcapacity expansion is planned, the added capacity

    must be treated as a new facility.

    LSIL is existing plant. The production capacity of

    RHF is being expanded to 1 million tonne of

    steel/year from 0.6 million tonne of steel/year

    before the project activity by replacing the old RHFwhich uses fossil fuel with new Chinese make

    RHF. Hence it is treated as new facility. CGL

    furnaces and coiler furnace are being modified and

    hence they are existing facility.

    The emission reductions are claimed by generator

    of energy using waste gas/heat

    The CDM credits will be claimed only by LSIL

    who generate process heat using waste coke oven

    gas.

    In case the energy is exported to other facilities anagreement is signed by the energy generation plant

    with recipient plants that emission reductions

    would not be claimed by recipient plants for using

    a zero emission source

    Not applicable as process heat generated will beused for captive consumption only.

    For those facilities and recipients included in the

    project boundary, which prior to the

    implementation of project activity generated energy

    on site, the credits can be claimed for a minimum

    of the following periods

    . The remaining life time of equipments currently

    being used.

    . Credit period

    LSIL is replacing the present RHF with new RHF

    with increased capacity and hence can be treated as

    new facility.

    Normal life of steel mill equipment is 30 years as

    observed in industry. CGL furnace and coilerfurnace are approximately 16 years in operation.

    Expected balance life for these furnaces is about 14

    years.

    The PDD has been developed for fixed crediting

    period of ten years.

    Waste gas that is released under abnormal

    operation of the plant shall not be accounted.

    The PDD does not take into consideration any

    waste gas released under abnormal conditions

    Cogeneration is from combined heat and power and

    not Combined cycle mode of electricity generation

    The project activity is for process heat generation

    only.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    14/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 14

    The waste energy utilized in project activity was

    flared or released into the atmosphere in the

    absence of project activity. This shall be proven byeither one of the following

    1 By direct measurements of energy content

    2 Energy balance

    3 Energy bills

    4 Process plant manufacturers original

    specifications

    5 On site checks by DOE

    Coke oven Gas used in project activity is surplus

    after providing for internal use of UGML. UGML

    has no further use in the process and would haveflared through chimney in the absence of the

    project activity. The same can be proven from site

    checks by DOE.

    The project activity meets the applicability conditions set out in approved methodology

    The other conditions of methodology are met by the following steps

    1. The base line calculations for CO2 emission reduction are in line with approved methodology andare calculated using CEA data provided in CO2 data base Version 5.0 November 2009 available in CEA

    web site www.cea.nic.in.

    2. By successful operation of project activity, the project activity will be able to displace/ substitute

    electricity of grid with an emission reduction of 117028 tCO2/annum (Ref. Section- B 6.3).

    3. The project activity adds no additional GHG emission.

    Hence it is concluded that the project activity meets the conditions set out in selected approved

    methodology.

    B.3. Description of the sources and gases included in the project boundary:

    >>

    In line with methodology, the project activity is for the recovery of waste heat from coke oven gases for

    generation of process heat for direct use as heat in furnaces.

    In the base line scenario, the heat would have other wise been generated by fossil fuel like furnace oil and

    LPG.

    In line with methodology the project boundary comprises of the RHF, CGL and Coiler Furnaces, piping

    for coke oven gas

    As per the approved methodology the geographical extent project boundary shall include the following:

    1 The industrial facility where waste energy is generated (coke oven gas), that is, UGML

    Project activity has no control over waste gas quantity and quality like flow and temperature. , Gas holder

    is provided by UGML for temporary storage.

    2 The facility where process heat in element process/steam/electricity are generated (generator of process

    heat/steam/electricity). Equipment providing auxiliary heat to the waste heat recovery process shall be

    included within the project boundary:

    That is the actual project activity comprises of burning coke oven gas in furnaces where project

    participant has full Control.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    15/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 15

    3 The facility/s where the process heat in element process/steam/electricity is used (the recipient plant(s)

    and /or grid where electricity is exported. Not applicable as the project activity is for providing in house

    requirement of direct heat to furnaces.

    Schematic for project boundary is as below.

    316720 Kj/Nm

    100C

    20.95 kg/Cm

    Approximate pipe line : 3 km

    312250 Nm /hr

    PROJECT ACTIVITY BOUNDARY

    LSIL

    POINT OFRECEIVING

    3

    RHF

    9000 m /hr

    3500 m /hr

    32550 m /hr

    COILER FURNACE

    CGL 1 & 2

    Table 1: Summary of gases and sources included in the project boundary, justification explanation where

    gases and sources are not included.

    Source Gas Included? Justification /

    ExplanationCO2 Excluded Not

    applicable.

    CH4 Excluded Not

    applicable.

    Electricity generation, grid or captive source.

    N2O Excluded Not

    applicable.

    CO2 Included Main

    emission

    source

    CH4 Excluded Excluded for

    simplification.

    This is

    conservative.

    Fossil fuel consumption in furnace for thermal energy

    N2O Excluded Excluded for

    simplification.

    This is

    conservative.

    Baseline

    Fossil fuel consumption in cogeneration plantCO2 Excluded Not

    applicable.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    16/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 16

    CH4 Excluded Not

    applicable.

    N2O Excluded Notapplicable.

    CO2 Excluded Not

    applicable.

    CH4 Excluded Not

    applicable.

    Base line emissions from generation of steam used in the flaring

    if any.

    N2O Excluded Not

    applicable.

    CO2 Excluded Not

    applicable as

    No extra fuel

    or support

    fossil fuel

    is fired.

    Supplemental fossil fuel consumption

    at project plant

    N2O Excluded Not

    applicable

    CO2 Excluded Not

    applicable as

    No

    supplemental

    electricity

    consumed

    CH4 Excluded Not

    applicable

    Supplemental electricity consumption

    at project plant

    N2O Excluded Not

    applicable

    CO2 Excluded Not

    applicable as

    No captive

    electricity is

    consumed

    CH4 Excluded Not

    applicable

    Electricity import to replace captive electricity which was generated

    gas in absence of project activity

    N2O Excluded Not

    applicable

    CO2 Excluded Not applicable

    as waste gas

    cleaning not

    requiredCH4 Excluded Not applicable

    ProjectActivity

    Project emissions from cleaning of gas

    N2O Excluded Not applicab

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    17/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 17

    B.4. Description of how the baseline scenario is identified and description of the identified

    baseline scenario:

    >> Identification of baseline scenario.

    The baseline scenario is identified as the most plausible scenario among all realistic and credible

    alternatives.

    Realistic and credible alternatives should be determined for:

    . Waste energy use in the absence of the project activity.

    . Heat generation in the absence of the project activity.

    While determining the baseline scenario the project participant shall identify the realistic and

    credible alternatives to the project activity, which would provide output equivalent to combined output of

    all the sub systems in the project scenario. Therefore the alternatives should provide the same heat output

    as in the project activity and should include the alternate use of the waste gas heat utilised in the projectactivity.

    The project Participant shall exclude baseline options that:

    . do not comply with legal or regulatory requirements or

    . depend on fuels that are not available on the site.

    The project participant is required to provide evidence and supporting documents to exclude

    baseline options that meet the above mentioned criteria. The methodology provides 4 steps to

    to determine baseline.

    Step 1: Define the most possible baseline scenario for the generation of heat and electricity using

    baseline options and combinations.

    The baseline candidates should be considered for following facilities.. For the industrial facility where the waste energy (coke oven gas) is generated UGML and

    . For the facility where the energy is produced and consumed i.e.LSIL; and

    Hence Baseline study has been carried for project proponent LSIL and UGML.

    Baseline

    options

    Realistic and credible

    alternative

    LSIL UGML

    W1 WECM is directly vented to

    atmosphere without

    incineration

    Not applicable. Not applicable.

    W2 WECM is released after

    incineration or waste heat isreleased to atmosphere or

    Waste gas pressure energy is

    not utilized.

    Not applicable. Applicable. UGML who

    generate waste gaseswould have flared the

    waste gases before

    releasing to atmosphere in

    the absence of project

    activity as UGML does

    not have any use of the

    excess waste gases.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    18/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 18

    W3 Waste energy is sold as an

    energy source.

    Not applicable. Not applicable. UGML

    has no use for excess

    WECM after using incoke oven batteries,

    WECM is being sourced

    to LSIL as an energy

    source as per agreement to

    form joint industrial

    facility.

    W4 Waste energy is used for

    meeting energy demand.

    Not applicable as WECM

    is not generated by LSIL.

    Not applicable.

    UGML does not have any

    further use of WECM and

    UGML will send waste

    gases to atmosphere after

    flaring in the absence ofproject activity.

    W5 A portion of waste gas

    produced at the facility is

    captured and used for captive

    electricity generation while

    the rest of the waste gas

    produced at the facility is

    vented/flared.

    Not applicable. Not applicable as no

    electricity is generated

    using waste gas.

    UGML which generates

    WECM uses part of

    WECM to generate heat

    in their facility. UGML

    would have flared WECM

    in the absence of project

    activity at LSIL.

    Surplus WECM is

    sourced to LSIL which isa part of joint industrial

    facility as energy i.e heat

    source for their furnaces

    in the process. LSIL is the

    project proponent as LSIL

    is sourcing and using

    WECM to generate heat

    in the furnaces in steel

    making process as per

    agreement to form joint

    industrial facility.

    W6 All the waste gas produced at

    the industrial facility is

    captured and used for export

    electricity generation

    Not applicable. Not applicable as no

    electricity is generated

    from waste gas.

    UGML which generates

    WECM uses part of

    WECM to generate heat

    in their facility. UGML

    would have flared WECM

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    19/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 19

    in the absence of project

    activity at LSIL.

    Surplus WECM issourced to LSIL which is

    a part of joint industrial

    facility as energy i.e heat

    source for their furnaces

    in the process. LSIL is the

    project proponent as LSIL

    is sourcing and using

    WECM to generate heat

    in the furnaces in steel

    making process.

    H1 Proposed project activity not

    undertaken as a CDM

    activity.

    LSIL has incurred losses

    when the steel industry

    faced acute recession afew years back. The

    company has accumulated

    losses and is under BIFR

    (Board of Industrial and

    Financial Restructure)

    with debt restructuring of

    liabilities. Hence the

    company faces the

    financial barrier due to the

    non availability of fresh

    funds to carry out

    expansion activities both

    from financial institutesand equity market.

    Hence LSIL promoters

    had to arrange privately

    raised loans to undertake

    the project activity. These

    loans carry higher rate of

    interests compared to

    institutional loans. In the

    absence of CDM benefits

    the project activity could

    not be implemented as

    CDM benefits enable the

    promoters to convinceprivate lenders on

    viability of the project

    activity.

    Not applicable as UGML

    does not have any further

    use of WECM.

    H2 On site or off-site

    existing/new fossil fuel fired

    cogeneration plant

    Not applicable as

    presently only fossil fuel

    is being used currently to

    Not applicable.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    20/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 20

    provide heat in the

    process. LSIL does not

    have any cogenerationplant based on fossil fuel.

    H3 On site or off-site

    existing/new renewable

    energy based cogeneration

    plant

    Not applicable as LSIL do

    not have any cogeneration

    plant based renewable

    energy.

    Not applicable.

    H4 An existing or new fossil fuel

    based furnaces.

    Applicable. Presently

    only fossil fuel is used to

    provide heat in the

    process. LSIL will

    continue to use fossil fuel

    in the absence of project

    activity.

    Not applicable.

    H5 An existing or newrenewable or other waste

    energy based existing

    furnaces

    Not applicable aspresently only fossil fuel

    is used to provide heat in

    the process.

    Not applicable.

    H6 Any other source such as

    district heat

    No such heat source is

    available

    Not applicable.

    H7 Other heat generation

    technologies (e.g heat pumps

    or solar energy)

    No such alternative source

    is available or feasible as

    the steel making process is

    energy intensive and direct

    use of large amount of heat

    is required in concentrated

    fashion.

    Not applicable.

    H8 Steam/process heatgeneration from waste

    energy, but with lower

    efficiency.

    Not applicable as WECMavailable has to be used

    with maximum efficiency

    as WECM quantity is

    limited.

    Not applicable.

    H9 Cogeneration with waste

    energy but a lower

    efficiency.

    Not applicable as the

    project activity is not for

    cogeneration.

    Not applicable.

    Step 2: Identify the fuel for the baseline choice of energy source taking into account the national

    and/or sectoral policies as applicable

    The base line is fossil fuel (Furnace oil for RHF furnace and LPG for Coiler and CGL furnaces) as the

    fossil fuel being used as energy source from the inception of the manufacturing facilities. There is no

    shortage of furnace oil or LPG as the same are available on demand from the refineries. The refineries use

    both indigenous and imported crude oil to generate the fossil fuels.

    STEP 3:

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    21/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 21

    Step 2 and/or Step 3 of the latest approved version of the Tool for the demonstration and

    assessment of additionality shall be usedto identify the most plausible baseline scenarios by

    eliminating non feasible options

    Section B.5 covers the stepwise demonstration of additionality as per the Tool for the demonstration

    and assessment of additionality version 05.2 EB 39 . We have demonstrated the additionality based on

    step 3.

    STEP 4: If more than one credible and plausible alternative scenario remain, the alternative with

    the lowest base line emissions shall be considered as the most likely baseline scenario.

    Project scenario: Generation of heat

    Scenario Baseline option for LSIL

    Waste gas Heat

    energy1 W2 H4

    In step1 all the credible alternatives for waste gas and waste heat were considered. In the absence of

    project activity UGML would have vented through chimney the excess waste coke oven gas as UGML do

    not have further requirements in the process (W2) and LSIL would continue to use fossil fuel for

    providing heat in their furnaces (H4).

    Base line

    The baseline is the same scenario existing prior to the start of implementation of project activity.

    The base line is fossil fuel i.e. Furnace oil for RHF and LPG for Coiler/CGL furnaces are being been fired

    in pre project scenario and the same scenario of using fossil fuel for firing in furnaces would have been

    continued if waste coke oven gas is not available.

    The project activity reduces CO2emissions from replacement of fossil fuels used in the furnaces by waste

    coke oven gas which would have been otherwise burnt by UGML before letting into atmosphere in the

    absence of the project activity and in the project activity LSIL uses this waste coke oven gas in their

    furnaces to provide required heat which would have been otherwise provided by firing fossil fuels likefurnace oil in reheating furnace and LPG in coiler and CGL furnaces. CO2 emission due to burning of

    fossil fuel is avoided and thus achieves reduction in GHG emissions.

    B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below

    those that would have occurred in the absence of the registered CDM project activity (assessment

    and demonstration of additionality):It is required to describe how the anthropogenic emissions of GHG by sources are reduced below those

    that would have occurred in the absence of registered CDM activity. The proposed CDM project activity

    is designed to generate heat from the waste coke oven gases emitting out of an established industrial

    manufacturing process i.e. coke oven complex which would have been let into atmosphere after burning

    in the absence of project activity . The reduction in GHG emissions due to burning of fossil fuel is

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    22/68

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    23/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 23

    3 He further informed the board that to avail such CDM benefits it is desirable to apply to appropriate

    authorities for CDM registration and CDM benefits would make project viable.

    The extracts of the board meeting will be made available to DOE.

    The tool for the demonstration and assessment of additionality version 05.2 outlines four steps to

    demonstrate additionality.

    Time line of activities

    Time line of activities of Project Activity Time line of activities for CDM registration

    Board Resolution 25/10/2008 Board resolution 25/10/2008

    Agreement with

    UGML 15/01/2009

    Notification regarding

    CDM project activity

    to UNFCCC

    21/11/2009

    Starting of pipe line

    laying work

    01/11/2009 Appointment of DOE

    for validation

    12/01/2009

    Expected receipt ofReheating Furnace

    25/12/2009 Submission of PDD toDOE for pre

    validation check

    10/04/2009

    Expected date of

    completion of piping

    and storage tank work

    28/02/2010 DOE Comments

    receipt after pre

    validation check

    10/06/2009

    Installation of

    reheating furnace

    25/03/2010 DOE confirmation

    that PDD can be

    resubmitted

    10/01/2009

    Modification of Coiler

    and CGL furnaces

    25/03/2010 PDD resubmission

    To DOE for

    validation

    23/01/2009

    Expected date of

    commissioning

    14/04/2010 to

    15/6/2010.

    STEP 1 - Identification of the alternatives to the project activity considered with current laws

    and regulations

    Sub-Step 1.a Define alternatives to the project activity:

    Identify realistic and credible alternatives

    Proposed activity not undertaken as CDM

    project activity.

    All other plausible and credible alternative

    continuation of current situation

    In section B.4 all the possible alternatives have been

    discussed for the alternatives recognised were:

    1 The methodology lists six realistic and credible

    alternatives for waste gas and the alternative to vent

    to atmosphere the waste coke oven gases afterflaring was the only option in the absence of project

    activity for UGML.

    2 The methodology lists nine realistic and credible

    alternatives for heat generation. The only credible

    alternative in base line is using fossil fuel which is

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    24/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 24

    the continuation of current situation in the absence

    of project activity for LSIL.

    Step 1.b Consistency with mandatory laws and regulations:

    1 Alternative shall be in compliance with

    legal and regularly requirements.

    All the alternatives are in compliance with current

    legal and regulatory requirements.

    Additionality tool provides the option of selecting Step 2 or Step 3. LSIL select step 3 and hence proceed

    to Step 3.

    STEP 3 Barrier analysis to show additionality.

    Sub-Step 3.a Identification of barriers that would prevent the implementation of the type of the

    project activity.

    Investmentbarriers

    3.a.1

    Debt funding is

    not available for

    this type of

    proposed project

    activity.

    LSIL has incurred losses when the steel industry faced acute recession a

    few years back. The company has accumulated losses and is under BIFR

    (Board for Industrial and Financial Reconstruction, Government of India)

    with debt restructuring of liabilities. Hence the company faces the financial

    barrier due to the non availability of fresh funds to carry out expansion

    activities both from financial institutes and equity market. The companys

    finance demands go through close scrutiny of the concerned financial

    institutions and have not been able to secure institutional loans for project

    activity. The details of company financial are as follows

    Details of company are as follows

    Nature of company:

    LSIL is a public limited having two divisions. Steel division manufactures

    steel products in Wardha plant .Engineering division manufactures

    specialised equipment for chemical,petrochemical,steel,defence ,power

    plant etc

    Financials of company

    (Rs in Millions)

    2008-09 2007-08

    Sales 28415.644 24773.629

    Profit (loss) after tax for the year (164.8545) (46.8921)Profit(loss) brought from previous

    year (12631.012 ) ( 12162.091)

    payment made as per

    debt restructuring 461.4 826.7

    distribution of share holding

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    25/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 25

    promoters 18.51 20.43

    financial institutions/Banks 12.83 3.76

    MFs/UTI 0.46 0.51FII 0.20 0.22

    Others 68.00 75.08

    Paid up equity 2111.488 1911.462

    Promoters: Mr Mukesh Gupta, Mr Rajesh Gupta, Mr B.L.Agarwal by

    themselves and through their associate companies.

    When LSIL approached for finance of project activity, the financial

    lenders advised that the loans can not be sanctioned:

    1 As the project activity is an in house project not involving any costbenefits the loans can not be sanctioned.

    2 The company has accumulated losses and is under debt restructuring

    with BIFR.The financial lenders refusal / advice letter will be made available to DOE.

    As the debt funds were not available from banks for the project activity the

    project proponent has to raise the debt funds from private investors at higher

    interest than lending rates of banks.

    No access to

    international

    capital markets

    due to real or

    perceived risks.

    LSIL have not received any foreign assistance and they are not in a position

    to access the international capital markets.

    How CDM

    revenues help to

    alleviate the

    above barrier

    CDM revenues help to make the project activity more financially feasible

    and help convincing the private investors to lend funds for the project

    activity.

    Whether fossil

    fuel based heat

    generation face

    the barrier

    This is business as usual situation with no investment required. Hence the

    capital expenses are not involved and the economic barrier is not faced.

    3.a.b Technological

    barrier

    1 Skilled and or

    properly trained

    labour not

    available

    How CDM

    revenues help to

    alleviate the

    above barriers

    As Coke oven gas is highly poisonous gas the workers operating in the area

    are to highly skilled. Project participant is not having such skilled workers

    and they have to be recruited. The skilled persons are not available in the

    area as steel plants are not located near by where coke oven gas is generated

    and used. This can be supported by plant record of employment related

    matters.

    CDM revenues will enable the company to overcome the barrier partially by

    providing higher wages and other facilities to attract skilled people and also

    send existing staff for training and developing necessary skills. But as the

    company has accumulated losses making available higher wages to certain

    set of people can lead to internal worker problem on parity of wages and also

    company fails to attract the best talent due to its reputation of loss making

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    26/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 26

    2

    3

    4

    5

    Lack ofinfrastructure for

    implementation

    of the technology

    How CDM

    revenues help to

    alleviate the

    above barriers

    Lack of previous

    experience in

    using coke oven

    gas.

    How CDM

    revenues help to

    alleviate the

    above barriers

    Uncertainties of

    availability of

    coke oven gas.

    How CDMrevenues help to

    alleviate the

    above barriers

    Regulatory and

    organisation.

    Present lay out of the plant does not have the infrastructure does not havecorrect technology to handle coke oven gas as all jobs within a radius of 40

    m could be a source of fire/ignition . Un authorised persons can not be

    allowed to work in the area without shutting down the gas system. As per

    present lay out ,the material handling systems like EOT cranes work on

    overhead and run by electric supply connected with DSL ;there are

    continuous sparks . This is very dangerous the gas area has to be completely

    modified with new infra structure layout. This can be proved by plant

    records.

    CDM revenues help to overcome the barrier by changing the lay out and

    shifting and carry out infra structure changes.

    Company has no previous experience of using coke oven gas. Hence

    having no previous experience acts as technical barrier. This can be

    supported by plant records.

    CDM revenues enable company to appoint with previous experience by

    offering higher wages and other incentives. But as the company has

    accumulated losses making available higher wages to certain set of people

    can lead to internal worker problem on parity of wages and also company

    fails to attract the best talent due to its reputation of loss makingorganisation.

    The coke oven gas is sourced from UGML and the operations of UGML

    Blast furnace is not under control of LSIL. Any planned or unplanned

    shutdowns which are in control of UGML will immediately affect coke oven

    gas supply which will disrupt LSIL production. This is definite barrier which

    can not be overcome by LSIL and hence has to carry alternative furnace oil

    storage and burner system in addition to coke oven gas system. This can be

    supported by the agreement with UGML and plant visit.

    The CDM alleviate the barrier by allowing LSIL maintain the alternativeexisting system to eliminate disruption of production. But this is partial

    alleviation as the coke oven gas is sourced from UGML where LSIL do not

    have control.

    As the whole area will attract classification of highly hazardous area they

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    27/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 27

    6

    technological

    problem

    How CDM

    revenues help to

    alleviate the

    above barriers

    No control over

    coke oven gases

    and Related

    design problem.

    come under Chief Controller Of Explosives CCOE and permissions are to be

    sought and got.

    The following restrictions will be placed due to the poisonous and explosive

    nature of coke oven gas

    5.1 No personnel shall be allowed to work in or go to the area where fuel

    gases are present if the carbon monoxide content is more than 25 ppm. On

    line monitoring system with alarm for carbon monoxide concentrated will be

    provided near gas handling areas.

    5.2 The following precautions have to be ensured within 40 m of gas lines

    a) No manual hammering which may give spark.

    b) No use of sparking tool or instrument

    c) No naked fired) All welding or cutting jobs to be done with written clearance from

    competent authority. A minimum oxygen level of 20% is to be ensured.

    This acts as regulatory/ technological barrier for coke oven gas based heat

    generation. This can be supported by CCOE regulations.

    CDM revenues will help the company to plan provide for instrumentation to

    detect any leakages and increase the safety provisions so that regulatory

    conditions are adhered strictly.

    As coke oven gas is being sourced from UGML the project proponent does

    not have control on quality and quantity of gas availability.

    The coke oven gas produced by the pyrolysis process contains tar,

    ammonia,napthlene,light oil and sulphur before the gas is used as fuel. The

    cleaning process is responsibility of UGML as LSIL is getting the surplus

    coke oven gas after UGML have used coke oven gas in their processes.

    The furnace burner system is designed to use clean coke oven gas and due to

    any reason the coke oven gas is not free of these impurities then furnace

    working will be affected. The design of furnace burner is critical and hence

    unclean coke oven gas will present design problem.

    Water present in coke oven gas will also present design problems as the pipe

    line might get clogged if the atmospheric temperature falls below 4 deg c.

    The above can be supported by research article coke manufacturing in

    pollution prevention and abatement hand book of world bank group,

    research article investigation of the hazards of using manufactured gas in

    Baltimore by Shrader and other research articles.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    28/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 28

    7

    8

    How CDMrevenues help to

    alleviate the

    above barriers

    Production

    related problem

    How CDM

    revenues help to

    alleviate the

    above barriers

    Whether fossil

    fuel based heat

    generation face

    the barriers

    The CDM alleviate the barrier by allowing LSIL maintain the alternativeexisting system to eliminate disruption of production. But this is partial as

    the coke oven gas is sourced from UGML where LSIL do not have control.

    .

    The composition of coke oven gas is critical as it decides the heat

    availability. As the composition of coke oven gas can not be fully

    guaranteed the heat availability in the furnace can be subjected to variation

    and this will directly affect LSIL production.

    The problem of what to do with coke oven gases when LSIL furnaces are

    shut down is a concern which has to be addressed. The following twooptions are being considered.

    Option 1 A boiler needs to be installed which will burn the coke oven gases

    and produce steam. LSIL have presently no use for this steam and hence

    have to find a consumer for steam. LSIL is considering installation of such

    boiler so that waste heat is used and not wasted by burning while sending itto atmosphere through chimney. This option needs extra investments to the

    extent of approximately Rs 80 million.

    Option 2 LSIL will send coke oven gases to chimney and flare them before

    letting out into atmosphere. The energy is wasted and LSIL have to provide

    flare system at an additional cost of approximately Rs 30 million.

    CDM revenues will enable the company to overcome the problem by

    providing one of the above options or any other measure.

    1 Barrier 1 : fossil fuel based system is very well established technology and

    do not face skilled personnel problem as pool of trained people is large while

    waste heat recovery systems are developing technology which is why skilled

    personnel problem is faced by project activity. As LSIL is operating the

    fossil fuel based system from inception it is business as usual and hence this

    barrier will not be faced.

    2 Barrier 2 : fossil fuel based systems do not face this problem as it is

    existing system. As LSIL is operating the fossil fuel based system from

    inception it is business as usual and hence this barrier will not be faced.

    3 Barrier 3 : Company has fossil fuel handling experience hence furnace oil

    based systems will not face this barrier in . As LSIL is operating the fossil

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    29/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 29

    fuel based system from inception it is business as usual and hence this

    barrier will not be faced.

    4 Barrier 5: fossil fuel based heat generation is steady and proper regulations

    are in place. As LSIL is operating the fossil fuel based system from inception

    it is business as usual and hence this barrier will not be faced.

    5 Barrier 4,6,7 : These are specific coke oven gas related barriers not

    applicable to fossil fuel based systems. As LSIL is operating the fossil fuel

    based system from inception it is business as usual and hence this barrier

    will not be faced.

    Barriers due to

    prevailing

    practice.

    1

    Discuss the

    project activity in

    host country.

    How CDM

    revenues help toalleviate the

    above barrier

    Whether fossil

    fuel based heat

    generation face

    the barrier

    LSIL is a steel manufacturing company equipped with DR-EAF-

    Continuous slab caster based steel plant of capacity about 600000

    tonnes/year of steel. There are 36 units in India who have similar process

    and capacity as per Ministry of Steel Government of India site

    www.steel.nic.in

    None of these units are having furnaces using coke oven gas for heating in

    furnaces. Coke oven gas is available only with blast furnace based

    manufacturers as they use coke

    CDM revenues help to make the project activity feasible and enable the

    company to put the project activity and cross the barrier of prevailingpractice of not using the waste heat in sponge iron industry.

    Fossil fuel based heat generation does not face this barrier as it is common

    practice to establish such units.

    Sub-Step 3.b. Show that the identified barriers would not prevent the implementation of at least

    one of the alternatives (except the proposed project activity).

    In section B.4 all the realistic and credible alternatives have been discussed in step 1 in line with

    methodology and in the above section the barriers have been discussed and the concludes as follows:

    The conclusion arrived was the continuation of use of fossil fuel as fuel in the furnaces was the only

    viable and credible alternative( H4) as it is existing scenario and is business as usual scenario also.

    As this is business as usual since the year1994 and faces no barrier.

    STEP-4 Common practice analysis

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    30/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 30

    Sub step -4a Analyse other activities similar to project activity

    Analysis of

    activities similar

    to the project

    activity.

    LSIL is a steel manufacturing company equipped with DR-EAF-

    Continuous slab caster based steel plant of capacity about 600000

    tonnes/year of steel. There are 36 units in India who have similar process

    and capacity as per Ministry of Steel Government of India site

    www.steel.nic.in

    None of these units are having furnaces using coke oven gas for heating

    in furnaces.

    The project activity is to generate heat from excess waste coke oven

    gas generated in coke ovens after the use of gases in coke ovens. The

    coke ovens produce coke and coke is used in steel industry where the

    blast furnace is used for melting. Hence the steel unit which does nothave blast furnace do not have requirement of coke and hence coke oven

    gas is not available as they do not have coke ovens.

    Hence LSIL project activity is first of its kind in steel plants

    using EAF route and using coke oven gas as heat source in furnaces.

    This is possible as UGML who are in the same complex forming joint

    facility with LSIL under which utilities are shared and all the product of

    pig iron is sourced by LSIL as their input.

    The industry followed the practice of letting the excess coke oven gases

    out into atmosphere without utilising waste heat.

    As per the ministry web site www.steel.nic.in the small steel mills splitup is as follows

    1 EAF based units : 36

    2 Induction furnace based units : 970

    3 MBF,ETF based units:2

    2 The following steel plants in private sector have blast furnaces.

    1 Tata Steel Limited 5 million tonnes

    2 Jindal steel limited 1.37 million tonnes

    3 JSW Steel Limited 6.8 million tonnes

    4 Ispat industries 3 million tonnes

    5 kalyani steel 1 million tonne

    Excess Coke oven gas in all the above industries is being used for

    captive power generation and are under CDM project activities . If the

    part of coke oven gases could have been used in furnace heating then

    also 5 out of 36 units make less than 15% diffusion.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    31/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 31

    Sub-Step 4.b Discuss any similar options that are occurring

    Activities

    in similar

    scale.

    LSIL is a steel manufacturing company equipped with DR-EAF-Continuous

    slab caster based steel plant of capacity about 600000 tonnes/year of steel.

    There are 36 units in India who have similar process and capacity as per

    Ministry of Steel Government of India site www.steel.nic.in

    None of these units are having furnaces using coke oven gas as heat source.

    The industry followed the practice of letting the excess coke oven gases out

    into atmosphere without utilising waste heat.

    As per the ministry web site www.steel.nic.in the small steel mills split up is as

    follows

    1 EAF based units : 36

    2 Induction furnace based units : 970

    3 MBF,ETF based units:2

    2 The following steel plants in private sector have blast furnaces.

    1 Tata Steel Limited 5 million tonnes

    2 Jindal steel limited 1.37 million tonnes

    3 JSW Steel Limited 6.8 million tonnes

    4 Ispat industries 3 million tonnes

    5 Kalyani steel 1 million tonne

    Excess Coke oven gas in all the above industries is being used for captive

    power generation and are under CDM project activities .

    3 The difference in the above project activities is

    1 LSIL do not have blast furnace and coke oven batteries which generate coke

    oven gas.

    2 Excess coke oven gas is sourced from UGML after their consumption of

    coke oven gas in coke ovens3 Coke oven gas is used as heat source only and no power generation is done.

    .

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    32/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 32

    N

    Optional

    Y

    Y

    STEP 1. Identification of

    alternatives to the project

    activity consistent with

    mandatory laws and

    regulations.

    STEP 2. Investment analysis

    Does sensitivity analysis conclude

    that the proposed CDM projectactivity is unlikely to be the most

    financially attractive or is

    unlikely to be financially Attractive?

    STEP 3. Barrier analysis

    (1) Is there at least one barrier

    preventing the implementation of theproject activity without the CDM

    And

    (2)Is at least one alternative

    Scenario, other than proposed CDM

    CDM project activity, not prevented

    by any of the identified barriers?

    STEP 4. Common practice Analysis

    (1)No similar activities can be Observed,

    or (2) if similar Activities are observed,

    are the essential distinctions between the

    proposed CDM project Activity and

    similar activities can reasonably be

    explained?

    Project is

    Additional

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    33/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 33

    B.6. Emission reductions:

    B.6.1. Explanation of methodological choices:

    >> Selected methodology is ACM 0012 Version 3.2 Sectoral Scope 1&4 EB 51

    a) The methodology gives 4 steps to determine the baseline. All these 4 steps have been discussed in B.4

    and arrived at baseline scenario of W2/H4 as the WECM would have been flared before letting into

    atmosphere and the existing business as usual scenario where fossil fuel is used to provide heat in

    furnaces of LSIL.

    The baseline is the same scenario existing prior to the start of implementation of project activity.

    The base line is fossil fuel i.e. Furnace oil for RHF and LPG for Coiler/CGL are being been fired in preproject scenario and the same scenario of using fossil fuel for firing in furnaces would have been

    continued in the absence of project activity as it is business as usual scenario.

    The methodology lists realistic and credible alternatives to project activity and arrives at conclusion ofcontinuation of current situation as the only plausible alternative in the absence of project activity.

    b) The emission reductions are achieved by displacing fossil fuel used in furnaces with waste coke oven

    gas which uses only waste heat and does not use any fuel.

    c) The additionality has been proved using additionality tool the tool for the demonstration and

    assessment of additionality (version 05.2) EB 39.

    d) The baseline emissions have been calculated for scenario 1 using equations 1, 1a, 1a.2, 1h. The

    methodology states that if the project activity is generation of heat only then one of the two sub sections

    under scenario 1 shall be used for estimating the base line.

    1 Base line emissions

    As the project activity is for generation of heat only ,Base line emissions are calculated for Scenario 1 as

    the heat is obtained from fossil fuel in baseline. The applicable equations is 1a.2

    2 Calculation of energy generated (heat) in units supplied by waste heat

    The heat generated is calculated by using gas analysis and calculate heating value and the flow of

    WECM. As 100% heat is generated by WECM the metered values of flow will be used and heating value

    is calculated using gas analyser data.

    3 Capping of baseline emissions

    The methodology requires capping for element of conservativeness. We have selected Method 2 usingmanufacturers data and applicable equation 1g to calculate baseline cap f cap.

    The baseline emissionsfor the year shall be determined as follows

    BE y = BE En, y + BE fist y = BE En, y (equation 1)

    Where,

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    34/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 34

    BE y = Total baseline Emissions during a given year y.

    BE En y =Baseline emissions from energy generated by the project activity during a given year y.

    BE fist, y = Baseline emission from generation of steam, if any, using fossil fuel that would

    have been used for flaring in the absence of the project activity =0 as no steam from fossil fuel is used for

    flaring in baseline

    BEy = BEElec,y + BEThermy = BETherm, y (equation 1.a)

    Where,

    BEy = Total baseline Emissions during a given year y.

    BEElec y =Baseline emissions from electricity by the project activity during a given year y =0.

    BETherm, y = Baseline emission from generation of thermal energy

    As the project activity is for generation of heat only, Base line emissions are calculated for Scenario 1 as

    clarified by note under this scenario. The applicable equations is 1a.2

    Baseline emissions from thermal energy (BE Therm y)

    BETher.y = fcap*f wcm**( (HG j y *EFheat, y )+(MG/ mech,tur))*EFheat, y (equation 1a-2)

    MG/ mech,tur = 0 as no mechanical energy is generated in the project activity the equation becomes

    BETher.y = fcap*f wcm**HG j y *EFheat, y (equation 1a-2)

    BETher.y = Base line emissions from thermal energy during the year in tons of CO2

    HG j y =Net quantity of heat supplied by the project activity in the year TJEFheat, y = CO2 emission factor t CO2/TJ

    wcm = fraction of total heat generated by project activity using waste energy =1 as the heat generation

    Is purely from waste energy

    fcap= fraction of total energy produced using equation 1hEFCO2,I,j

    EFheat, y = wsi,j ------------- ( 1a-22)

    EP,I,y

    EFCO2,I,j = CO2 Emission factor for base line fuel t CO2/TJ

    EP,I,y =Maximum efficiency 100%wsi,j = fraction of total heat that is used by the recipient =1 as total heat is used is purely waste energy.

    Capping of baseline emissions

    As UGML is a new plant and no historical data is available Method 3 Case 1 is selected and following

    equations will be used to estimate fcap.,

    Q OE,BL

    fcap = ------------ (1h)

    Q OE, y

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    35/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 35

    Q OE,BL = Output energy that can be theoretically produced to be determined on the basis of maximum

    recoverable energy from WECM which would have been released in the absence of project activity.

    Q OE, y = quantity of actual out put energy during yeary

    The project emissions (PE y) are zero as no cleaning of gases is done in the project activity and no

    electricity is used for any other purpose during handling of delivered coke oven gas. No auxiliary fuel is

    used while using waste energy.

    Leakage is zero as per methodology.

    Emission Reductions

    ERy =BETherm, y - PE y =BETherm, y

    ERy = Total emission reductions during the year y in tons of CO2

    PE y = 0

    BETherm, y = Base line emissions for the project activity during the year y in tons of CO2

    B.6.2. Data and parameters that are available at validation:

    (Copy this table for each data and parameter)

    Data / Parameter: EP,I,yData unit:

    Description: Baseline efficiency. Source of data used: Project participant has assumed 100% efficiency.

    Value applied: 100%

    Justification of the

    choice of data ordescription of

    measurement methods

    and procedures actually

    applied :

    For conservativeness maximum efficiency is assumed.

    Any comment: nil

    Data / Parameter: Hwcm,BL

    Data unit: KJ/m3

    Description: Calorific value

    Source of data used: UGML the waste coke oven gas supplier

    Value applied: 4000x4.18 KJ/M3

    Justification of thechoice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    UGML the waste coke oven gas supplier has provided this data based on thecoke oven gas composition of Composition

    CO 7.5 -9 % CO2 2.0-3.0% H2 55-57 % N2 2-6% CH4 24-26% CnHn 5%

    Any comment: nil

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    36/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 36

    Data / Parameter: twcm,BL

    Data unit: Deg CDescription: Average temperature of WECM

    Source of data used: UGML the waste coke oven gas supplier

    Value applied: 100 deg C

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    UGML the waste coke oven gas supplier has provided this data based on the

    coke oven gas availability.

    Any comment: nil

    Data / Parameter: Pwcm,BL

    Data unit: Kg/cm2Description: Pressure of WECM

    Source of data used: UGML the waste coke oven gas supplier

    Value applied:

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    UGML the waste coke oven gas supplier has provided this data based on the

    coke oven gas delivery.

    Any comment: Nil

    Data / Parameter: Q OE,BLData unit: MJ

    Description: Output energy that can be theoretically produced to be determined on the basis

    of maximum recoverable energy from the WECM which would have been

    flared in the absence of project activity.

    Source of data used: UGML the waste coke oven gas generator

    Value applied: 17.942 X 10 8 MJ/Year

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    UGML have provided this data as excess coke oven gas that can be made

    available to LSIL after considering their internal consumption.

    Any comment: Nil

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    37/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 37

    B.6.3. Ex-ante calculation of emission reductions:

    >>

    In step1 of B.4 all the credible alternatives for waste gas and waste heat were considered . in the absenceof project activity UGML would have vented through chimney the excess waste coke oven gas as UGML

    do not have further requirements in the process(W2) and LSIL would continue to use fossil fuel for

    providing heat in their furnaces(H4) .

    Base line

    The base line is Furnace oil/LPG which could have been fired if waste coke oven gas is not available. The

    furnace oil is used in RHF and LPG is used in CGL and Coiler furnaces in current situation.

    The project activity reduces GHG emissions as Waste coke oven gas would have been burnt by UGML

    before letting into atmosphere in the absence of the project activity and LSIL uses this waste coke ovengas in their reheating furnace to provide required heat which would have been otherwise provided by

    firing Furnace oil/LPG. GHG emission due to burning of fossil fuel is avoided and thus achieves reductionin GHG emissions.

    Baseline emissions from thermal energy (BE Therm y)

    BETher.y = fcap*f wcm**( (HG j y *EFheat, y )+(MG/ mech,tur))*EFheat, y (equation 1a-2)

    MG/ mech,tur = 0 as no mechanical energy is generated in the project activity the equation becomes

    BETher.y = fcap*f wcm**HG j y *EFheat, y (equation 1a-2)

    BETher.y = Base line emissions from thermal energy during the year in tons of CO2

    HG j y =Net quantity of heat supplied by the project activity in the year TJ

    EFheat, y = CO2 emission factor t CO2/TJ

    fwcm =fraction of total heat generated by project activity using waste energy =1 as the heat generation

    is purely from waste energy

    fcap= fraction of total energy produced using equation 1gEFCO2,I,j

    EFheat, y = wsi,j ------------- ( 1a-22)

    EP,I,yEFCO2,I,j = CO2 Emission factor for base line fuel t CO2/TJ

    EP,I,y =Maximum efficiency 100%wsi,j = fraction of total heat that is used by the recipient =1 as total heat is used is purely waste energy.

    The step wise calculations are as follows

    1 Calculation offcap

    As UGML is a new plant and no historical data is available Method 3 Case 1 is selected and following

    equations will be used to estimate fcap.,

    Q OE,BL

    fcap = ------------ (1h)

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    38/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 38

    Q OE, y

    Q OE,BL = Output energy that can be theoretically produced to be determined on the basis of maximum

    recoverable energy from WECM which would have been released in the absence of project activity.

    Q OE, y = quantity of actual out put energy during yeary

    S No Description Reheating

    Furnace

    CGL

    furnaces

    Coiler

    Furnace

    Reference

    document

    1 Production

    capacity

    tonnes/year

    1000000 250000 400000 Manufacturer

    specifications

    2 Base line

    fuel

    Furnace

    oil

    LPG LPG

    3 Specific

    heat

    requirement

    MJ/tonne

    1350 1210 254 Manufacturer

    specification

    for RHF

    3 years average

    4 Heat

    provided by

    coke oven

    gas MJ

    Q OE,y

    =Productioncapacity

    *specific

    heatrequired

    13.5 X 108

    3.025X

    108

    1.016X

    108

    5 Q OE,y MJ 17.541 X 108 MJ/Year

    6 Quantity of

    WECM

    12250 NM3/hr

    7 Calorific

    value

    KJ/NM3

    16720 KJ/NM3

    =16.72 MJ/NM3

    8 Q OE,BL MJ 12250 X 16.72 X 24 X365

    = 17.942 X 108

    MJ/Year

    9 fcap = Q OE,BL/ Q OE,BL

    = 17.942 X 10 8 / 17.541 X 10 8

    = 1.023 But as per methodology consider f cap = 1

    Calculation off wcm

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    39/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 39

    As only waste heat is used for heat generation f wcm =1

    Calculation ofHGj y

    S No Description Reheating

    Furnace

    CGL

    furnaces

    Coiler

    Furnace

    Reference

    document

    1 Production

    capacity

    tonnes/year

    1000000 250000 400000 Manufacturer

    specifications

    2 Base line

    fuel

    Furnace

    oil

    LPG LPG

    3 Specific

    heat

    requirement

    MJ/tonne

    1350 1210 254 Manufacturer

    specification

    for RHF and

    for CGL/Coilerfurnaces

    3 years average

    4 Heat

    provided by

    coke oven

    gas MJ

    13.5 X 108

    3.025X

    108

    1.016X

    108

    5 HG j y 17.541 X 108 MJ/Year

    Calculation ofEFheat, y

    EFCO2,I,j

    EFheat, y = wsi,j ------------- ( 1a-22)EP,I,y

    EFCO2,I,j = CO2 Emission factor for base line fuel t CO2/TJ

    EP,I,y =Maximum efficiency 100%wsi,j = fraction of total heat that is used by the recipient =1 as total heat is used is purely waste energy.

    S No Description Reheating

    Furnace

    CGL

    furnaces

    Coiler

    Furnace

    Reference

    document

    1 Baseline

    Fuel used

    Furnace

    oil

    LPG LPG

    2 EP,I,y 100% 100% 100% Considered

    maximum for

    conservativeness3 wsi,j =

    fraction of

    total heat

    that is used

    by the

    recipient

    1 1 1

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    40/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 40

    4 EFCO2,I,j 0.0719 0.0494 0.0494 As per CO2

    Baseline data

    Version 5November 2009

    Available on

    www.cea.nic.in

    5 EFheat, y

    kg of

    CO2/MJ of

    base line

    fuel using

    1a -22

    0.0719 0.0494 0.0494

    Calculation of baseline emissions BETher.y

    BETher.y = fcap*f wcm**HG j y *EFheat, y (equation 1a-2)

    S No Description Reheating

    Furnace

    CGL

    furnaces

    Coiler

    Furnace

    Reference

    document

    1 Production

    capacity

    tonnes/year

    1000000 250000 400000 Manufacturer

    specifications

    2 Base line

    fuel

    Furnace

    oil

    LPG LPG

    3 Specific

    heatrequirement

    MJ/tonne

    1350 1210 254 Manufacturer

    specificationfor RHF

    3 years average

    4 Heat

    provided by

    coke oven

    gas MJ

    HG j y

    13.5 X 108

    3.025X

    108

    1.016X

    108

    5 EFheat, y

    kg of

    CO2/MJ of

    base line

    fuel

    0.0719 0.0494 0.0494 As per CO2

    Baseline data

    Version 4

    Available on

    www.cea.nic.in

    6 fcap 1 1 1 Assumed.

    Actual value to

    be taken during

    every year

    calculations.

  • 8/8/2019 Waste Heat Project at LSIL PDD Date 05 Feb

    41/68

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Board

    page 41

    7 f wcm 1 1 1 All heat will be

    supplied by

    waste gas8 wsig 1 1 1 Total heat will

    be used by the

    utility point.

    9 Base line

    reductions

    tonnes of

    CO2/year

    97065 14943.5 5019.04

    10 Total base

    line

    reductions

    Tonnes of

    CO2/year

    BETher.y

    117027.54 rounded to 117028

    Project emissions

    As no other fuel is used in the normal operation.

    PE y = 0

    Leakage

    No leakage is applicable under methodology

    Calculation of emission reductions

    ERy =BETherm, y - PE y = 117028-0 = 117028 tons of CO2 per year

    ERy = Total emission reductions during the year y in tons of CO2

    PE y = 0BETherm, y = Base line emissions for the project activity during the year y in tons of CO2

    = 117028 tons of CO2.

    T