Project Status Date 10/11/2011 Job no. Section Sheet no. Rev By GJ Checked Rev Date Details Tel Fax Part Introduction: Detailed design of 'walking' / 'raked' columns. Calculations include: 1. Assesment of 'strut and tie' forces based on column geometry and gravity loading. 2. Concrete compressive strut check and reinforcement as required. 3. Tie forces local to walking column within the slab above and below. Reinforcment requirements. 4. Vertical shear check. S concrete. 5. Horizontal shear check at slab interface. 6. Assessment of secondary moments to columns above and below walking column. 7. Reinforcement Summary. Diagram: Walk Width Walk Angle, 1 F cu_Walk mm Lvl (ref) Lvl (m) Lvl (ref) Lvl (m) (m) Deg. N/mm 2 E146 300 2 18.45 1 13.95 2.95 57 55 Geometry ZE - Walking Column E146 Head Level Base Level Column Reference New South Glasgow Hospital Design 24140333 5.1 1 44 (0)141 429 3555 44 (0)141 429 3666

Upload: raghunath-balu

Post on 25-Nov-2015

2.164 views

Category:

Documents


314 download

DESCRIPTION

Walking Column Design

TRANSCRIPT

  • Project Status

    Date 10/11/2011 Job no. Section Sheet no. RevBy GJChecked

    Rev Date Details Tel

    Fax

    Part

    Introduction:

    Detailed design of 'walking' / 'raked' columns. Calculations include:

    1. Assesment of 'strut and tie' forces based on column geometry and gravity loading.2. Concrete compressive strut check and reinforcement as required.3. Tie forces local to walking column within the slab above and below. Reinforcment requirements.4. Vertical shear check. S concrete. 5. Horizontal shear check at slab interface.6. Assessment of secondary moments to columns above and below walking column. 7. Reinforcement Summary.

    Diagram:

    Walk Width Walk Angle, 1 Fcu_Walkmm Lvl (ref) Lvl (m) Lvl (ref) Lvl (m) (m) Deg. N/mm2

    E146 300 2 18.45 1 13.95 2.95 57 55

    Geometry

    ZE - Walking Column E146

    Head Level Base LevelColumn Reference

    New South Glasgow HospitalDesign

    24140333 5.1 1

    44 (0)141 429 355544 (0)141 429 3666

  • Project Status

    Date 10/11/2011 Job no. Section Sheet no. RevBy GJChecked

    Rev Date Details Tel

    Fax

    Part ZE - Walking Column E146

    New South Glasgow HospitalDesign

    24140333 5.1 1

    44 (0)141 429 355544 (0)141 429 3666

    1 - Loading:

    Dead Imposed Dead Imposed SLS ULS Dead Imposed ULSkN kN kN kN kN kN DL/SIN 1, kN DL/SIN 1, kN kN

    3208 1335 3215 1138 4550 6637 3844 1596 7936

    Dead Imposed Total SLS Total ULSDL/TAN 1, kN LL/TAN 1, kN kN kN

    2108 875 2983 4351

    2 - Compression Strut Capacity:

    2 3 Strut Width bs As ProvAbove Below Calculated Selected deg. deg. (mm) (mm2)

    b1 b2 b2.tan1 user tan-1(dd/b2) 180-12 b2/cos2.sin3 0.4fcu wall.bs.Walk Width user

    600 400 610 850 65 58 801 5944 491010-H25

    3 - Tension 'Tie' Capacity

    Asreq As ProvAbove Below (mm2) (mm2) Width Depth Width Depth

    h1 h2 Ftie/0.87fy user600 900 10002 11260 600 850 900 850

    14-H32

    Beam Above Dims (mm) Beam Below Dims (mm)

    (Fstrut-Fc)/0.87fy

    Asreq(mm2)

    4579

    Downstand (mm) ddColumn Width (mm) Concrete Cap(kN) Fc

    Column depth (mm)

    Loading Hand LTD Loading RAMC LTD Vertical Loading Load in Raked Column - F Strut

    Lateral Load to Diaphragm (kN) - Tie Force - F tie

    Please refer to gravity load takedown information in section 1.2. A hand load takedown and a Ram C load takedown has been carried out with the most conservative results adopted.

    SLS Load Combination = 1.0 DL + 1.0 LLULS Load Combination = 1.4 DL + 1.6 LL

    The 'virtual' compression strut width will be calculated based on reasonable geometry over which stress can be assumed to distribute. Inorder to allow distribution of stress from wall to column below a downstand is to be included.

    Distribution of the lateral forces imparted to the slab diaphrgm are to be considered in the slab analysis. An additional mat of reinforcement local to the walking column is envisaged. The slab designer should be advised of the applied loads or a hand calculation/mark up provided showing additional rebar requirements.

  • Project Status

    Date 10/11/2011 Job no. Section Sheet no. RevBy GJChecked

    Rev Date Details Tel

    Fax

    Part ZE - Walking Column E146

    New South Glasgow HospitalDesign

    24140333 5.1 1

    44 (0)141 429 355544 (0)141 429 3666

    4 - Vertical Shear Check

  • Project Status

    Date 10/11/2011 Job no. Section Sheet no. RevBy GJChecked

    Rev Date Details Tel

    Fax

    Part ZE - Walking Column E146

    New South Glasgow HospitalDesign

    24140333 5.1 1

    44 (0)141 429 355544 (0)141 429 3666

  • Project Status

    Date 10/11/2011 Job no. Section Sheet no. RevBy GJChecked

    Rev Date Details Tel

    Fax

    Part ZE - Walking Column E146

    New South Glasgow HospitalDesign

    24140333 5.1 1

    44 (0)141 429 355544 (0)141 429 3666

  • Project Status

    Date 10/11/2011 Job no. Section Sheet no. RevBy GJChecked

    Rev Date Details Tel

    Fax

    Part ZE - Walking Column E146

    New South Glasgow HospitalDesign

    24140333 5.1 1

    44 (0)141 429 355544 (0)141 429 3666

    5 - Horizontal Shear Check

  • Project Status

    Date 10/11/2011 Job no. Section Sheet no. RevBy GJChecked

    Rev Date Details Tel

    Fax

    Part ZE - Walking Column E146

    New South Glasgow HospitalDesign

    24140333 5.1 1

    44 (0)141 429 355544 (0)141 429 3666

  • Project Status

    Date 10/11/2011 Job no. Section Sheet no. RevBy GJChecked

    Rev Date Details Tel

    Fax

    Part ZE - Walking Column E146

    New South Glasgow HospitalDesign

    24140333 5.1 1

    44 (0)141 429 355544 (0)141 429 3666

  • Project Status

    Date 10/11/2011 Job no. Section Sheet no. RevBy GJChecked

    Rev Date Details Tel

    Fax

    Part ZE - Walking Column E146

    New South Glasgow HospitalDesign

    24140333 5.1 1

    44 (0)141 429 355544 (0)141 429 3666

    6 - Secondary Moments to Columns

    S-Frame Member Properties

    b (mm) d (mm)900 400 4.80E+09 360000 200 -200

    0.00E+00 0 0 0600 600 1.08E+10 360000 300 -300400 900 2.43E+10 360000 450 -450600 600 1.08E+10 360000 300 -300

    0.00E+00 0 0 00.00E+00 0 0 00.00E+00 0 0 0

    300 801 1.28E+10 240161.565 400.2692757 -400.2693750 300 8.44E+09 1125000 150 -150

    Strut Dimensions

    Element DescriptionCol L01Col L02Col L03Col L04Col L05Col L06Col L07Col L08

    Slab Strut/TieVirtual Strut

    Member DimsI (mm4) A (mm2)

    Stress pt 1 (mm)Stress pt 2

    (mm)

    The columns at levels above and below are fixed by a continuous monolithic connection to the walking column. To assess secondary moments arising in the columns above and below the walk a 2d s-frame model has been adopted in accordance with TRM 261. The main factor influencing the rotation of the walking column, and therefore moments to columns is the elongation of the slab strut and tie. The walking column itself is a very stiff element and as such deformation of the panel itself contributes to a lesser extent.

    The virtual strut within the wall panel has been modelled as a beam element based on the dimensions determined in section 2. This is deemed to be conservative as an increased rotation is expected at the joints in comparison to if the full rigidity of the wall panel were modelled.

    The section dimensions of the slab struts and ties and the representative lengths back to the supports have been assesed on a column by column basis. Assuptions are conservative in this regard as it is difficult to approximate the true behaviour of the floor plate in a 2d model. Typically a half bay width of 3750mm has been considered of length equal to 'distance to closest point of support' i.e. core walls or Full Slab Diaphragm.

    These moments are to be considered in addition to Ram Concept Slab Moments

    Column E146 is located in close vicinity to core C. A minimum strut length of 5.2m has been adopted in the assessment.

  • Project Status

    Date 10/11/2011 Job no. Section Sheet no. RevBy GJChecked

    Rev Date Details Tel

    Fax

    Part ZE - Walking Column E146

    New South Glasgow HospitalDesign

    24140333 5.1 1

    44 (0)141 429 355544 (0)141 429 3666

    S-Frame Model Geometry S-Frame Member Properties

  • Project Status

    Date 10/11/2011 Job no. Section Sheet no. RevBy GJChecked

    Rev Date Details Tel

    Fax

    Part ZE - Walking Column E146

    New South Glasgow HospitalDesign

    24140333 5.1 1

    44 (0)141 429 355544 (0)141 429 3666

    S-Frame - Applied Loads/Axial Strut-Tie Loads

  • Project Status

    Date 10/11/2011 Job no. Section Sheet no. RevBy GJChecked

    Rev Date Details Tel

    Fax

    Part ZE - Walking Column E146

    New South Glasgow HospitalDesign

    24140333 5.1 1

    44 (0)141 429 355544 (0)141 429 3666

    S-Frame Column Moments

    Column MomentsHead Base (kNm) (kNm)

    L08L07L06L05L04L03 20 65L02 65 202L01 WC WCL00 140 90

    Column moments considered negligable L04 and above.

    These moments are to be considered in addition to Ram Concept Slab Moments

  • Project Status

    Date 10/11/2011 Job no. Section Sheet no. RevBy GJChecked

    Rev Date Details Tel

    Fax

    Part ZE - Walking Column E146

    New South Glasgow HospitalDesign

    24140333 5.1 1

    44 (0)141 429 355544 (0)141 429 3666

    7 - Reinforcement Summary

    10-H25

    14-H32

    NF1 + FF1

    NF2 + FF2

    600mm Wide by 850mm Deep from SSL

    900mm Wide by 850mm Deep from SSL

    Downstand Beam Above Dimensions =

    Downstand Beam Below Dimensions =

    H20 - 200 CRS

    H20 - 200 CRS

    Split Half FF + Half NF

    Total per Douwnstand BeamTension Tie Reinforcement =

    Horizontal Wall Reinforcement =

    Vertical Wall Reinforcement =

    Raked Compression Strut Reinforcement =