Waikane Valley Impact Area Remedial Design Phase
![Page 2: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/2.jpg)
Topics
• Introduction & Background • Status of Decision Document • Remedial Design Phase• Remedial Action Phases
![Page 3: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/3.jpg)
Introduction
• Background– Final SI Report- (Nov 13, 2009)– RAB Established - (April 2009)– Final RI Report - (Aug 3, 2011)– Final FS Report - (Jan 2, 2012)– Final Proposed Plan - (Jan 2, 2012)– Final Decision Document - (Feb 26, 2013)– Remedial Design (current)
![Page 4: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/4.jpg)
Status of Decision Document
• Final DD – Defines the Selected Remedy to meet
Remedial Action Objectives (RAOs)• Public Comments Received/ Incorporated• Signed by HDOH / MCB Hawaii
![Page 5: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/5.jpg)
Remedial Design Phase
• Detailed Design that outlines the requirements to implement the Selected Remedy from the DD.
• RD is incorporated into the Remedial Action Contractor's Scope of Work
• Included Public Input on Corridor Designs
![Page 6: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/6.jpg)
Selected Remedy
![Page 7: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/7.jpg)
RAB Site Visit/ Input to the RD
RD Team and RAB members conducted site visit on 1 September 2012 for the purposes gathering public input for the RD
![Page 8: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/8.jpg)
RAB Site Visit/ Input to the RDCont.
• Suggested screening methods:– Locating fencing behind terrain features (ridgelines
and gullies)– Offsetting fencing behind areas of dense vegetation– Use of “cattle fencing” in select areas (steep terrain)
![Page 9: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/9.jpg)
RAB Site Visit/ Input to the RDCont.
• RD team marked suggested fencing routes using Global Positioning Systems (GPS) based on RAB input.
• GPS points for fencing locations, terrain, and other significant features were translated to design maps for the RD.
![Page 10: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/10.jpg)
Kamaka Shrine Corridor
![Page 11: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/11.jpg)
Waikane Spring Corridor
![Page 12: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/12.jpg)
RA Map: Surface Clearance Plan
![Page 13: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/13.jpg)
RA Map: Subsurface Clearance Plan
![Page 14: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/14.jpg)
RA Map: Fencing and Signage Plan
![Page 15: Waikane Valley Impact Area Remedial Design Phase · 2014. 2. 12. · Introduction • Background – Final SI Report- (Nov 13, 2009) – RAB Established - (April 2009) – Final RI](https://reader033.vdocuments.site/reader033/viewer/2022060101/60b2d87061968b01967ab85a/html5/thumbnails/15.jpg)
Remedial Design Schedule
• Final RD (March/April 2013)• RA Contract Award (29 March 13)• RA Field Work (2013-2014)• Long-term Maintenance