visual nspection - aventri...gmp conference 12th november 2014 ... manual inspection - training •...
TRANSCRIPT
Visual nspection
Denise Coakley
GMP Conference
12th November 2014
Parallel Session 1A – Sterile Manufacture
212th November 2014
EU GMP Annex 1:
‘Filled containers of parenteral products
should be inspected individually for
extraneous contamination or other defects.’
312th November 2014
EU GMP Annex 1:
‘When inspection is done visually, it should be
done under suitable and controlled
conditions of illumination and background.’
412th November 2014
EU GMP Annex 1:
‘Operators doing the inspection should pass
regular eye-sight checks, with spectacles if
worn, and be allowed frequent breaks from
inspection.’
512th November 2014
EU GMP Annex 1:
‘Where other methods of inspection are used,
the process should be validated and the
performance of the equipment checked at
intervals. Results should be recorded.’
612th November 2014
Manual inspection – Ph. Eur. 2.9.20
712th November 2014
Manual inspection – Ph. Eur. 2.9.20
• A matt black panel of appropriate size held in a vertical
position,
• A non-glare white panel of appropriate size held in a vertical
position next to the black panel,
• An adjustable lampholder fitted with a suitable, shaded,
white-light source and with a suitable light diffuser (a
viewing illuminator containing two 13 W fluorescent tubes,
each 525 mm in length, is suitable). The intensity of
illumination at the viewing point is maintained between
2000 lux and 3750 lux, although higher values are preferable
for coloured glass and plastic containers.
812th November 2014
Manual inspection – Ph. Eur. 2.9.20
• Remove any adherent labels from the container and wash
and dry the outside. Gently swirl or invert the container,
ensuring that air bubbles are not introduced, and observe
for about 5 s in front of the white panel. Repeat the
procedure in front of the black panel. Record the presence of
any particles.
What else do we look for…….??
912th November 2014
Eye Test
GE T
Y O U
R E Y E S C
H E C K E D
1012th November 2014
Manual Inspection - Training
• Frequency/Duration
• Test kits
• Management of test kits
• Line speed
• Unit size
• Qualification/disqualification
1112th November 2014
Manual Inspection
Maintenance
• Procedure for back ground lighting
• Lux levels
Personnel
• Frequent breaks
1212th November 2014
Training
• Line speed during training
• Unit sizes
• Duration of training
• Challenge set – management
1312th November 2014
Manual Inspection - Defects
• Defect classification
-Particles
-Cracks
-Cosmetic
• Procedure for management of rejects
1412th November 2014
Semi- Automated Visual Inspection
• Removes the requirement for handling by the operator
• Units are fed/spun by conveyor for operator viewing
What do we look for…….??
• Exact same as for manual inspection
1512th November 2014
Automated Visual Inspection
- It is important to know the capabilities and limitations of equipment.
- Camera – Light reflection
- Static division -Light transmittance
- ‘Qualified’ – what does this mean?
1612th November 2014
Automated Visual Inspection
• URS
• Validation
• Detectability
• Repeatability
• How is the machine challenged
• Particles need to be moving to be detected by both SD and camera
• Equipment maintenance
• Management of rejects
1712th November 2014
Are there more specific requirements???....
• Defect classification
• Particle size – visible, sub visible
• Route of administration
• What is meant by ‘‘practically free”
• Risk based approach
1812th November 2014
Manual/Semi-Automated and Automated
• It is accepted that neither the machine or
the human can be 100% effective
• Whatever the system of inspection –
when a defect trend is detected the
production process and where necessary, the
inspection process must be investigated and
reassessed.
1912th November 2014
When things go wrong and they sometimes will....
• What is the procedure
• Deviation
• Re-inspection: Line speed, frequency
• At what stage is the batch considered rejected
• What is the source of the defect – container closure or production process
• Is the product compatible with the container closure – glass, rubber
• What is the impact to product on site
• What is the impact to product on the market
• Risk Management
2012th November 2014
Risk Assessment
2112th November 2014
Risk Assessment
• Critically assess what has happened and why.
• Do not play down the severity rating of the defect.
• Do not increase the level of detection rating if the defect has poor or no detectability.
• Do not decrease the probability of occurrence rating if there is a trend of the defect occurring.
• State the facts.
• It is better to identify the problem and fix it.
2212th November 2014
”Mistakes are the portals of
discovery.”
James Joyce
2312th November 2014
Risk Assessment
Deviations should be avoided but.....
...they can drive change and improvements.
2412th November 2014
Risk Assessment
Don’t just Risk Assess the ‘problem OUT’........
.....Risk Assess the ‘solution IN’
2512th November 2014
Risk Assessment
• Improve the manufacturing process by building in preventative
controls that scientifically support low probability of occurrence
ratings for particulates during risk assessments.
• Improve the inspection process and ensure that all high
detectability ratings assigned during risk assessments are
supported by scientifically sound detection-type controls.
• Identify the key risk-mitigating preventative and detection
controls that come out of such risk assessments, and ensure
that those controls are validated and proven effective.
2612th November 2014
Visual Inspection Deficiencies
• The controls in place with respect to the sites visualinspection programme were considered deficient in that:
• Investigations in relation to glass particulates were notconsidered to have been progressed in a timely manner
• The SOP was not followed in that the rig speed was notreduced to 50% upon identification of the tramp / loose glassdefect. There was no consideration given to re-inspection ofthe preceding vials that had been inspected up to that pointat such a reduced speed. A recurrence check for the previous3 months was undertaken. It was noted that a 3 monthrecurrence check was too confined a time limit to place onsuch assessments.
• IR X had been raised due to a loose glass defect. The rootcause of this defect was not identified.
2712th November 2014
Visual Inspection Deficiencies
• The inspection procedure did not require re-inspection of
preceding vials at reduced speed of 50% normal rate, when
critical defects, with low detectability, were identified.
• Where 2nd re-inspections identified additional defects, at no
point during the investigations was consideration given to
assessing the effectiveness of the visual inspection
programme nor was there any impact assessment performed
on those batches which were currently in date and on the
market.
2812th November 2014
Visual Inspection Deficiencies
• The investigations concluded that no corrective action was
required as the operators were validated to perform visual
inspection at a rate of xvpm for x minute intervals.
• This was despite the inherent issues identified with respect to
the sites visual inspection programme, as indicated by the
operators in the investigations.
• No due consideration was given to the statements from the
operators nor was there any consideration given to SOP X.
2912th November 2014
Visual Inspection Deficiencies
• The manner in which the trend analysis for defects was
conducted was considered deficient in that:
Data was not trended for all defect types e.g.
tramp/loose glass was trended as particles which
covered a number of other critical defect types
Additional rejects found during re-inspections were
not included in the trend analysis
The data captured for trending from visual inspection
was inputted by operators into the inspection log
database. There was no verification that this data was
inputted correctly.
3012th November 2014
Visual Inspection Deficiencies
• The ongoing issue in relation to glass particle defects and the potential impact to product on the market was not reported to the competent authority at the time of the inspection.
• There was no action taken in relation to the finished product visual inspection process or the post inspection AQL, following observations which confirmed that the visual inspection process was not effective in detecting the critical defect and that batches X, Y and Z, had passed the 100% inspection and post inspection AQL sampling but on subsequent 100% manual inspection, showed evidence of the particle defects.
• The timelines involved in the move to a tightened AQL for incoming inspection and the subsequent move to Unacceptable Quality Limit sampling was considered an unacceptable delay.
3112th November 2014
Visual Inspection Deficiencies
• In relation to Risk Assessment, X, it did not consider batches manufactured between MMM YY and MMM YY.
• The application of the same risk rating of ‘High’ to the detectability of ‘moving’ and ‘not moving’ particles, was not considered appropriate given that the system was not capable of detecting the latter and that batches had been noted to pass through the inspection process without such defects being detected.
• It was considered that the risk assessment placed an over reliance on the use of AQL sampling and statistical analysis of the same, to detect the critical defect
• There was no information in relation to the ongoing investigations in relation to this defect type in the APQR.
3212th November 2014
Conclusion
• Establish robust procedures
• Where equipment is used, know the capability and limitation
• Validation
• Appropriate defect classification
• Training
• Qualification/disqualification
• Equipment maintenance
• Risk Management – consider that the effectiveness of the current process may need to be critically assessed and improved.