Visit to a Framed structure site

TRANSCRIPT

Page 1: Visit to a Framed Structure Site

Group Members

Haris Bilal 2010-civ-32

Shay haq 2010-civ-33

Hafiz Talat 2010-civ-31

Adeel Akbar 2010-civ-37

Abdul Sattar 2010-civ-20

Safeerullah 2010-civ-36

VISIT TO FRAMED STRUCTURE SITE

Page 2: Visit to a Framed Structure Site

Site IntroductionSite 2

• Project Name

NFC Flats• Client

NFC Residential• Contractor

King Crete Builders• Design & Supervision Consultant

Arcadia• Estimated Project Cost

Rs. 450 Millions• Total Site Area

8 Kanals (36000 sft)• Completion Time

22 Months• Address

Faisal Town, Lahore

Page 3: Visit to a Framed Structure Site

Report on NFC Flats

We have visited frame structure site NFC flats by NFC residential. Construction was under process. It had four different phases and only in one phase ground floor up to roof was completed. And for the other three phases foundation was being laid.

Isolated columns footings were used there to carry the load of the superstructure to the ground soil. Excavation was made 4 feet deep below the natural surface level.

Concrete used in foundation was high strength concrete having strength more than 6000 psi.

MATERIALSIn the construction, following materials were used related to concrete works in site.

Cement :

Mostly ordinary Portland cement (OPC) was being used

at the site. For some concrete sulphate resisting cement

(SRC) was also used.

Aggregate:

Aggregates used were Margalla and Sargodha.

Sand:

Sand used were Lawrencepur and Chenab.

Steel:

Bars used at different portions were of different numbers such as #3, #4, #8.

Different brands like Mughal and prime steel bars were used by the contractor.

Page 4: Visit to a Framed Structure Site

MIXINGConcrete mixing was being carried out by concrete

mixer machines placed at different positions near

the construction on the site.

BATCHINGBatching of the concrete was being done by the small hand trolleys.

TRANSPORTATIONThe concrete materials are transported from the market, plant by the help of tractor trolleys, while at the site small trolleys are used for this purpose at same floor but for transportation at different floors, the concrete lifter driven by electric motors is being used.

COMPACTION

Compaction was being done by

vibrators in the column just after

pouring concrete in the columns.

And on the floors compaction was

being carried out by hand compactors.

Page 5: Visit to a Framed Structure Site

FORMWORK AND SHATTERING

For the formwork of slabs and stairs

Steel plates were being used and for

Supporting the formwork, Bamboos

As shattering were utilized at the site.

Page 6: Visit to a Framed Structure Site

Site IntroductionSite 1

• Project Name

Tariq Hall, UET Lahore• Client

HEC strengthening of UET• Contractor

M/S Imperial Agencies• Estimated Project Cost

Rs. 544.876 Millions• Total Site Area

4 Kanals (18000 sft)• Completion Time

24 Months• Address

UET, Lahore

Page 7: Visit to a Framed Structure Site

Report on Tariq Hall, UET We have visited site at Tariq Hall,UET Lahore, under constructionby HEC. We met with contractorat the site regarding knowledgeof concreting in construction. Shattering and formwork werebeing laid. And also steel cutting,fixing and bending was underprocess.

MATERIALSIn the construction, following materials were used related to concrete works in site.

Cement :

Pioneer Cement , Lucky Cement, Pak and maple leaf cement were

present

Aggregate:

Margalla, Sakhi Sarwar

Sand:

Chenab Sand is used for plastering and Aerosine Sand (from Abbottabad) used for other concrete works like columns, slab and foundations etc.

Steel:

#3, #4, #8 steels are being used as reinforcement in RCC concrete. Brand of the steels used were mostly Mughal.

Page 8: Visit to a Framed Structure Site

MIXINGConcrete mixing is done by concrete mixers at the site. Ratio of the concrete was defined by the designer as per the requirement of the structure.

In column concrete ratio is 1:1.5:3 by using the volume batching of concrete and in slab it is 1:2:4.

Isolated foundations are used fortransferring load of the structure to the ground.

BATCHINGThe batching is mostly done byvolume. The small hand driventrolleys are used for this purpose.

TRANSPORTATIONThe concrete materials are

transported from the market, plant by the help of tractor trolleys, while at the site small trolleys are used for this purpose at same floor but for transportation at different floors, the concrete lifter driven by electric motors is being used.

Page 9: Visit to a Framed Structure Site

COMPACTIONThe compaction

was done by the compactors.

Robin Small Compactor was used for compaction of concrete in

column after pouring. Tamping Hammer

is used for compacting excavations of GSL

and floors of building, Similar work is done on large scale by the Heavy Hand Compactor.

FORMWORKThe formwork of steel platesis utilized for slab concreting.

Page 10: Visit to a Framed Structure Site

For columns, the formwork was just laid and also pouring for some of the columns was just completed and curing was being done by putting wet bags on the columns.

Steel fixing for the slabs and stairs.

Steel fixing in the formwork of the slabs was being carried out. Most of the slabs were one way.