Vinca Bridge ReplacementWelcomeDue to risks associated with in-person events and physical distancing protocols in place as a result of COVID-19, there will be no in-person public event for this project.
However, this presentation has been prepared for stakeholders and interested members of the public to learn more about the project.
alberta.ca©2020 Government of Alberta | Published October 2020
About the ProjectProject Location Map
HIGHWAY 38HIGHWAY 38
HIG
HW
AY 8
30
alberta.ca©2020 Government of Alberta | Published October 2020
Project Background
• The existing Vinca Bridge was built in 1967 and needs to be replaced due to its age and the condition of the structure.
• The Vinca Bridge has been identified as the preferred crossing over the North Saskatchewan River for Over-sized / Over-weight Loads heading to northern Alberta.
• Currently, the bridge serves 1500 vehicles per day, 24% of which are large trucks.
alberta.ca©2020 Government of Alberta | Published October 2020
Project Considerations
• The North Saskatchewan River channel is stable due to upstream dams, but the bridge crossing should still be perpendicular to water flow.
• Steep river banks and removing vegetation for construction could reduce slope stability. This needs to be considered during construction staging.
• The bridge over Beaverhill Creek is in good condition and and will not be impacted by this project.
alberta.ca©2020 Government of Alberta | Published October 2020
• 3 watercourses in the study area
• North Saskatchewan River
• Redwater River
• Beaverhill Creek
• 16 wetlands
• Numerous tree stands
• 6 Non-reclaimed Environmentally Sensitive Area sites
Project Constraints:Environmental
ESA SITE
WELL SITE
WATER WELL SITE
WETLANDS
TREE STANDS
HISTORICAL SITE
alberta.ca©2020 Government of Alberta | Published October 2020
• Rare vegetation
• Creeping ancylid
• Moss
• Wildlife habitats
• 43 birds
• 6 mammals
• 2 amphibians
• 1 reptile
• Fish Documented
• 5 sportfish
• Lake Sturgeon at risk
• 4 non-sportfish
Project Constraints:Environmental Cont’d
alberta.ca©2020 Government of Alberta | Published October 2020
• 24 pipelines
• 20 well sites
• 10 saltwater lines
• 3 overhead power lines
• Telecommunication lines
• 12 water wells
Project Constraints:Utilities
STURGEON COUNTYLAMONT COUNTY
STRATHCONA COUNTY
RIVER
HW
Y 83
0 IN
TER
SEC
TTIO
N
293.5
HWL
ACC
ESS
ACC
ESS
PRO
POSE
D A
CC
ESS
ESA SITE
WELL SITE
WATER WELL SITE
WETLANDS
TREE STANDS
HISTORICAL SITE
RIGHT OF WAY
CONSTRUCTION LIMITS
ROADWAY
BORROW PIT
COUNTY BOUNDARY
STROM POND
WELL SITE
WATER WELL SITE
PIPELINESSALTWATER LINESOVERHEAD POWERLINESTELECOMMUNICATIONS
WELL SITE
WATER WELL SITE
PIPELINES
SALTWATER LINES
OVERHEAD POWERLINES
TELECOMMUNICATIONS
alberta.ca©2020 Government of Alberta | Published October 2020
• No Aboriginal Traditional Use sites within the project limits
• 4 Historical Sites
• 3 Historical Structures
• Vinca Bridge
• Cook Family Farmstead
• Cook Family Cemetery
Project Constraints:Historical
ALIGNMENT-OPTION1
584586588590592594596598600602604606608610612614
0+000 0+100 0+200 0+300 0+400 0+500 0+600 0+700 0+800 0+900 1+000 1+100 1+200 1+300 1+400 1+500 1+600 1+700 1+800 1+900 2+000 2+100 2+200 2+300 2+400 2+500 2+600 2+700 2+800 2+900 3+000 3+100 3
620 620
RIVER
HW
Y 83
0 IN
TER
SEC
TTIO
N
11
6
9
17
HistoricalCook FamilyFarmstead
Quarter Section Contains an Unmarked Cemetery Location Unknown
Vinca Bridge
alberta.ca©2020 Government of Alberta | Published October 2020
Evaluation of Options
STURGEON COUNTYLAMONT COUNTY
STRATHCONA COUNTY
OPTION 1B - PLAN VIEW
PRELIMINARY FOR DISCUSSION PURPOSES ONLY
VINCA BRIDGE (BF 74233) REPLACEMENTON HWY 38 OVER THE NORTH SASKATCHEWAN RIVER
ESA SITE
WELL SITE
WATER WELL SITE
WETLANDS
TREE STANDS
HISTORICAL SITE
RIGHT OF WAY
CONSTRUCTION LIMITSCUT
ROADWAY
FORMER BORROW PIT
COUNTY BOUNDARY
PROVIDE ACCESS
ROAD CLOSURUEBARRIERS
HORZ1:5000
200m150100500
Wednesday, August 26, 2020
HORZ1:5000
200m150100500
38:10 1
CONSTRUCTION LIMITSFILL
STURGEON COUNTYLAMONT COUNTY
STRATHCONA COUNTY
VINCA BRIDGE (BF 74233) REPLACEMENTON HWY 38 OVER THE NORTH SASKATCHEWAN RIVER
OPTION 2N - PLAN VIEW
VINCA BRIDGE (BF 74233) REPLACEMENTON HWY 38 OVER THE NORTH SASKATCHEWAN RIVER
PRELIMINARY FOR DISCUSSION PURPOSES ONLY
ESA SITE
WELL SITE
WATER WELL SITE
WETLANDS
TREE STANDS
HISTORICAL SITE
RIGHT OF WAY
CONSTRUCTION LIMITSCUT
ROADWAY
FORMER BORROW PIT
COUNTY BOUNDARY
PROVIDE ACCESS
ROAD CLOSURUEBARRIERS
HORZ1:5000
200m150100500
Wednesday, August 26, 2020
HORZ1:5000
200m150100500
38:10 1
CONSTRUCTION LIMITSFILL
STURGEON COUNTYLAMONT COUNTY
STRATHCONA COUNTY
VINCA BRIDGE (BF 74233) REPLACEMENTON HWY 38 OVER THE NORTH SASKATCHEWAN RIVER
OPTION 3C - PLAN VIEW
PRELIMINARY FOR DISCUSSION PURPOSES ONLY
ESA SITE
WELL SITE
WATER WELL SITE
WETLANDS
TREE STANDS
HISTORICAL SITE
RIGHT OF WAY
CONSTRUCTION LIMITSCUT
ROADWAY
FORMER BORROW PIT
COUNTY BOUNDARY
PROVIDE ACCESS
ROAD CLOSURUEBARRIERS
HORZ1:5000
200m150100500
Wednesday, August 26, 2020
HORZ1:5000
200m150100500
38:10 1
CONSTRUCTION LIMITSFILL
STURGEON COUNTYLAMONT COUNTY
STRATHCONA COUNTY
VINCA BRIDGE (BF 74233) REPLACEMENTON HWY 38 OVER THE NORTH SASKATCHEWAN RIVER
OPTION 4B - PLAN VIEW
PRELIMINARY FOR DISCUSSION PURPOSES ONLY
ESA SITE
WELL SITE
WATER WELL SITE
WETLANDS
TREE STANDS
HISTORICAL SITE
RIGHT OF WAY
CONSTRUCTION LIMITSCUT
ROADWAY
FORMER BORROW PIT
COUNTY BOUNDARY
PROVIDE ACCESS
ROAD CLOSURUEBARRIERS
HORZ1:5000
200m150100500
Wednesday, August 26, 2020
HORZ1:5000
200m150100500
38:10 1
CONSTRUCTION LIMITSFILL
Option 1: Not recommended because it bisects agricultural farmland, requires a skewed bridge and impacts the Red Water River and 3 historical sites.
Option 2N: Not recommended because it impacts the Red Water River, an Environmentally Sensitive Area and 3 historical sites.
Option 3: Not recommended because it bisects agricultural farmland and would require raising the Highway 38/830 intersection, which increases construction detouring.
Option 4: Not recommended because the posted speed limit would be lower than what the project was trying to achieve.
STURGEON COUNTY
ESA SITE
WELL SITE
WATER WELL SITE
WETLANDS
TREE STANDS
HISTORICAL SITE
RIGHT OF WAY
CONSTRUCTION LIMITSCUT
ROADWAY
FORMER BORROW PIT
COUNTY BOUNDARY
PROVIDE ACCESS
ROAD CLOSURUEBARRIERS
CONSTRUCTION LIMITSFILL
OPTION 1 ALIGNMENT
OPTION 4 ALIGNMENT
OPTION 2N ALIGNMENT
OPTION 3 ALIGNMENT
alberta.ca©2020 Government of Alberta | Published October 2020
Recommended Option
STURGEON COUNTYLAMONT COUNTY
STRATHCONA COUNTY
R 600A 200
R 600A 200
R 60
0A
200
R 600A 200
HWY 38
HW
Y 83
0
EXISTING BF 74233-1,SCHEDULED TO BE DEMOLISHED
PROPOSED BF 74233-2
EXISTING BF 1766
SITE 11
SITE 9
SITE 6
SITE 17
RG
E R
D 2
05
ESA SITE
WELL SITE
WATER WELL SITE
WETLANDS
TREE STANDS
HISTORICAL SITE
RIGHT OF WAY
CONSTRUCTION LIMITSCUT
ROADWAY
FORMER BORROW PIT
COUNTY BOUNDARY
PROVIDE ACCESS
ROAD CLOSURUEBARRIERS
VINCA BRIDGE (BF 74233) REPLACEMENTON HWY 38 OVER THE NORTH SASKATCHEWAN RIVER
EXHIBIT 7.1: RECOMMENDED PLANHORZ1:5000
200m150100500
Wednesday, August 26, 2020
HORZ1:5000
200m150100500
38:10 1
CONSTRUCTION LIMITSFILL
Option 2S: recommended because it has the smallest impact on adjacent landowners, minimized construction requirements and avoids the most constraints.
STURGEON COUNTY
ST
ESA SITE
WELL SITE
WATER WELL SITE
WETLANDS
TREE STANDS
HISTORICAL SITE
RIGHT OF WAY
CONSTRUCTION LIMITSCUT
ROADWAY
FORMER BORROW PIT
COUNTY BOUNDARY
PROVIDE ACCESS
ROAD CLOSURUEBARRIERS
CONSTRUCTION LIMITSFILL
OPTION 2S ALIGNMENT
alberta.ca©2020 Government of Alberta | Published October 2020
Project Schedule and Next Steps
• Finalize Functional Planning – early Fall 2020
• Consult with affected landowners – Summer to Fall 2020
• Field Investigations – Summer to Fall 2020
• Preliminary Engineering – Fall 2020 to Spring 2021
• Construction timeline unknown at this time. Dependant on funding.
alberta.ca©2020 Government of Alberta | Published October 2020
Thank you for your interest in the project For more information and updates, please visit the project website: https://www.alberta.ca/major-transportation-projects.aspx