views of gridco on cerc discussion paper on terms & conditions of tariff

23
VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF Presented By: - GRIDCO,ORISSA Dt. 11-11-2003

Upload: donnel

Post on 11-Jan-2016

54 views

Category:

Documents


0 download

DESCRIPTION

VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF. Dt. 11-11-2003. Presented By: - GRIDCO,ORISSA. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

VIEWS OF GRIDCO ON

CERC DISCUSSION PAPERON TERMS & CONDITIONS OF TARIFF

Presented By: -

GRIDCO,ORISSA

Dt. 11-11-2003

Page 2: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

State Electricity Boards (SEB’s) were forced to be sick partly due to the following reasons: -

i) Introduction of accelerated rate of depreciation.

ii) Increase in Return on Equity from 12% to 16% on Debt Equity Ratio of 50:50 for ISGS.

iii) Allowing higher norm for Specific Fuel oil consumption,Heat Rate and Auxiliary Consumption.

iv) Higher incentive including deemed generation.

v) Fixation of normative PLF far below from the capacity.

vi) Income Tax burden including income tax on notional interest.

Page 3: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

State Electricity Utilities can survive

if the following aspects are addressed: -

i) Pre-92 rate of Depreciation may be allowed instead of Accelerated rate of Depreciation, i.e, the Depreciation may

be on linear basis.

ii) Return on Equity (ROE) may be allowed @ 11% Pre-Tax.

iii) For Specific Fuel oil consumption, Heat Rate and Auxiliary Consumption, the actual Consumption or Ceiling Norm,

which ever is lower may be passed on to Tariff.

iv) Incentive may be allowed beyond 85% PLF.

v) Swapping of Costlier Loan may be done with in a year.

Page 4: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

1.0 Debt Equity Ratio

CERC Discussion Paper

Broadly, a debt- equity ratio of 80:20 is generally preferable. However, in order to ensure a smooth change over, perhaps it would be advisable to adopt a normative debt equity of 70:30.

Views of GRIDCO

Gridco propose to consider Notional debt equity ratio of 80:20 for New Projects instead of 70:30 as proposed in the CERC

Discussion Paper. However, 70:30 normative debt equity ratio may be considered for Old Projects.

Page 5: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

2.0 ROE / ROCE

CERC Discussion Paper

It can be considered if this could be an appropriate time to switch over from ROE to ROCE in view of the fact that the interest rate are stabilising.

CERC assured to allow 16% ROE in its order dtd. 21.12.2000 in para 2.6. Now suggested for debate for consideration whether it would be advisable to disturb the existing ROE.

Suggested for debate whether to consider the present PLR for computation of ROCE (for debt portion only).

Rate base for computation of ROCE is suggested for debate.

Page 6: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

Views of GRIDCO

ROCE is preferred provided the followings are considered: -

(1) ROCE is on Net Fixed Assets (NFA) in each year instead of Gross . (2) ROCE may be determined on assumption of:

i. 11% Pre - Tax for equity portion (30%). (Based on Bank Rate)

ii. Concessional Loan Assistance Funded from ADB, World Bank etc.

iii. Swapping of debt other than concessional loan assistance.

Alternatively

(I) 12% Pre-Tax on ROE (30%) or (20%) for Old & New Plants

(ii) Interest on loan based on Net balance after Schedule /Normative repayment

(iii) Actual rate/Normative rate based on SBI PLR.

Page 7: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

3.0 Depreciation

CERC DISCUSSION PAPER

Whether Depreciation is to be linked with Loan Repayment

Whether Depreciation (Non Cash Exp) is necessary for a Cost based Tariff.

Whether liberal Depreciation would need to be deliberately provided.

Page 8: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

Views of GRIDCO

Pre-1992 rate of Depreciation may be allowed.

Advance Depreciation may be paid for loan repayment subject to the condition that:

(i) Depreciation + Advance Depreciation shall not in any year exceed 1/10 th of the actual / Normative loan amount.

(ii) Cumulative Depreciation + Advance Depreciation should not exceed cumulative actual / normative loan repayment

(iii) In case the Cumulative depreciation exceeds normative loan 70% or 80% for old & new plants respectively then the same may be reduced from the normative ROE.

(iv) Depreciation as per Companies Accounts may not be allowed in the Tariff as the tariff is based on normative.

Page 9: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

4.0 Interest on Loan

CERC Discussion Paper

- CERC concluded that the Cost of Capital Approach is preferable- Debt portion of Capital Employed is to be paid at Bank PLR.- Capital Base is to be debated.

Views of GRIDCO

- Cost of Capital approach is preferred on Net Fixed Assets.- SBI PLR may be considered for Debt Portion and 11% pre-Tax may be considered for Equity Portion.

Alternatively

(I) Interest on loan based on average Net balance after Schedule /Normative repayment

(iii) Actual rate/Normative rate based on SBI PLR.

Page 10: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

5.0 Operation and Maintenance Expenses

CERC Discussion Paper

Whether it would be advisable to move away from “Actual“ to “Normative” system.

Views of GRIDCO Prudence of actual expenditure is difficult to be tested.

There is wide variation in expenditure towards O&M from plant toplant.

GRIDCO propose that the O&M charges should be restricted to 2.5%, 1.5% & 1.5% of the Actual Capital Cost approved by the authority

instead of past 5 years average at actual for Thermal Stations, Hydro Stations and Transmission systems respectively.

The derived figure may be escalated as per the formula for WPI andCPI arrived at by the Commission.

Page 11: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

6.0 Interest on Working Capital

CERC Discussion Paper

Whether the ROCE needs to be increased suitably to take care of the additional cash flows which may be necessary for the actual operation of the project.

Views of GRIDCO

Gridco propose to allow interest on net working capital instead of gross working capital i.e the credit given by the suppliers should be deducted from the working capital value.

The rate of interest may be linked with working capital finance available with PFC to NTPC instead of linking to PLR.

Margin money deduction from working capital should be discouraged to avoid return on equity on the margin money.

Page 12: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

The base interest rate for working capital may be fixed for the Tariff period, in case there is a increase or decrease in interest rate, the same may be passed on to the beneficiary like FPA.

Salary/ Wages may be excluded from Operation and Maintenance Expenses for the purpose of computation of working capital as the Salary and Wages due for payment is being paid after the completion of the month.

Thirty days stock of Secondary Fuel Oil may be allowed instead of sixty days under the present improved Transportation and

communication link .

Page 13: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

7.0 Incentive

CERC Discussion Paper

An alternative approach is to be debated which could be delinkincentive totally from the fixed cost and providing incentive forgeneration above target PLF at a flat rate (Paise/kWh), which isattractive to the generators and fare to beneficiaries.

Views of GRIDCOThermal

Flat Rate at a reasonable rate beyond the normative PLF of 85% to all thermal station may be fixed.

Gridco propose to consider 3.0 paise per every rise of 1% Availabilityover & above the normative availability of 85% instead of linking the same to ROE. If the incentive is linked to ROE then the New plant shall get more incentive than the old plant.

Page 14: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

HYDRO STATION

It has been proposed to determine the incentive payment calculated on the following formula.

Actual Peak time Generation x (Incentive Rate in Rs./kWh) x (CIA -CIN)/100

It may be difficult to recommend a uniform incentive rate for all hydro stations (Old & New), having different operating conditions.

As ROE is paid to achieve normative Capacity Index (CI), GRIDCO proposes the following formula

Incentive = ROE X(CIA -CIN)/ CIN

However the Capacity Index should be 90% and 88% for ROR or Storage Plants respectively for computation of Incentive.

Page 15: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

INTER STATE TRANSMISSION

Incentive for Transmission system may be linked with ROE based on the following formulae.

Incentive = ROE X(Actual Availability - Normative Availability )/ Normative Availability.

However the incentive over 99.75% Availability may not be allowed.

The Commission should fix a Normative loss in transmission system. In case of loss exceeding the normative loss, the incentive should be reduced in the same proportion.

Income Tax on Incentive may be borne by the Generators / CTU.

Page 16: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

Views of GRIDCO on other aspects

8.0 Variable CostThe Generator may provide the required information as per the CERC format no. 13, 13A,14 & 14A in the respective month to the beneficiary along with the reasons for change in cost. The ratio of F.O. and L.D.O. should be specified for fuel consumption. Normative percentage of loss of coal & oil may be fixed instead of allowing the actual loss. Any insurance benefit covering against abnormal loss to be passed on to Tariff in FPA.

9.0 Target Availability and target PLF may be same at 85%.

10.0 Colony Consumption may be excluded from Auxiliary Consumption.

11.0 Station wise tariff may be computed instead of region wise.

12.0 LPS @ 1.00% (simple) may be allowed rather than 1.5% under the existing norm notification dtd. 26.03.01.

13.0 Income Tax element may be eliminated as ROE before tax may be allowed.

14.0 Peak, Off-peak tariff may be ignored for Generation.

Page 17: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

15.0 Development Surcharge may be eliminated.

16.0 Long term tariff (for 3 years) may be considered.

17.0 Terms and Conditions of Tariff under the new policy may also be applicable to the existing PPA’s.

18.0 Present Bank Rate may be considered for fixation of ROE / ROCE.

19.0 Transformation loss for Thermal Generating Station may be determined.

20.0 Normative Transmission Loss in % may be specified for CTU.

21.0 O&M expenses for transmission system may be computed separately for linesand substations based on the norms instead of actual expenses for last 5 years.

22.0 ERL / FERV may be on account of Generators / CTU if ROCE is allowed.

Page 18: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

23.0 FERV may be allowed as Bullet payment instead of capitalizing the same as the FERV is directly linked with Debt only.

Alternatively the same may be linked with Hedging tools.

24.0 Commitment Charges for non Drawal of Scheduled loan may not be allowed in Tariff.

25.0 Reduced Guarantee Fees may be passed on to tariff after deducting the actual repayment.

Page 19: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

(THERMAL) CERC GRIDCO PROPOSAL Views1.0 Debt Equity Ratio 80:20 / 70:30 80 :20 New Plant

70:30 Old Plant2.0 ROCE 13% on (NFA) 11% on (NFA)

(Pre- Tax) (Pre –Tax)

3.0 Interest on Loan:- Included To be includedin ROCE in ROCE.

4.0 Depreciation At actual cash At actual/Normout flow for cash out flow forrepayment of debt. Repayment of debt.

5.0 O & M Exp. Normative Normative.

TARIFF STRUCTURE

Page 20: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

CERC GRIDCO

6.0 Int. on W.Cap may be Included may be included in ROCE in ROCE.

7.0 INCENTIVE(a) Thermal Flat rate Flat rate(b) Hydro Linked to Peak-time ROE based on higher

generation availability8.0 INCOME TAX Generator A/c. Generator A/c.

9.0 FERV Generator A/c. Generator A/c.

10.0 TARGET PLF 80% 85%

11.0 Operational Norm SEB’s to provide CERC is to determine from the data collected from NTPC as per assurance given under Cl. 5.5.3 of CERC order dated 21-12-2000 on Tariff Norms.

Page 21: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

Operating Norm for different capacity may be fixed.

upto 60 61 MW to 111 MW to 251 MW to MW 110MW 250 MW 500 MW

(i) Aux. Cons. 10.0% 9.0% 8.0% 7.0% to Generation.(ii) Heat Rate 2700 2600 2400 2300 (Kcal/kWh)(iii) Specific Oil 2.5 2.0 1.5 1.0 Consumption (Ml./ kWh)

Information to the actual variable cost to be furnished to beneficiaryin each month in the prescribed format of CERC(13,13A,14,14A)

VIEWS OF GRIDCO FOR OPERATING NORM

Page 22: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

VARIABLE CHARGES

• Landed Cost of Coal and Oil may be fixed based on the Existing price Circular of Coal & Oil Authorities instead of depending on the audited report of the Generator as it is very much relevant in the present improved Communication Link. However the Monthly FPA Formulae may be prescribed.

• Information to the actual variable cost to be furnished to the beneficiaries in each month in the prescribed format of CERC (13,13A,14,14A) The reasons of increase / decrease in landed Cost of Coal & Oil may be outlined with the certified Copy of the Price Circular.

Page 23: VIEWS OF GRIDCO ON CERC DISCUSSION PAPER ON TERMS & CONDITIONS OF TARIFF

Presently IB Thermal is operating at 88% PLF. GCV of oil is 10,000 Kcal/KL

YEARGENERATION (MU) PLF (%)

SPECIFIC COAL

CONSUMPTION (Kg/kWh)

COAL GCV (Kcal/kg.)

SPECIFIC OIL

CONSUMPTION

(Ml./kWh)

Station Heat Rate

(Kcal/kWh)

1998-1999 2804 76.21% 0.88 2749.08 1.74 2436.59

1999-2000 3166 85.82% 0.86 2816.79 1.21 2434.539

2000-2001 3001 81.58% 0.85 2730.43 1.43 2335.166

2001-2002 2599 70.64% 0.84 2709.23 1.52 2290.953

PERFORMANCE OF IB THERMAL POWER STATION (2x210) MW