documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/e... · web viewannex...

76
Annex 3 Soil Erosion Control Plan 1. Overall Arrangement for Soil Erosion Control The overall erosion control measures shall be determined for each protection zone according to the principles of the arrangement of erosion control. The overall layout of erosion control measures for the full line is shown in Table 1. Table 1 Overall Layout of Soil Erosion Control Measures along the New Rapid Railway from Zhangjiakou to Hohhot Control zones Control objects Conservation and prevention measures Hilly area Subgrade works Subgrade slope Retaining wall shall be located by using frame bolt and shaller to protect the deep cutting. Frame slope protection and vegetation measures shall be combined to protect subgrade slope, with vegetation measures mainly being slope shrubs, planting shrubs and grasses within the frame, etc.; and engineering measures are frame slope protection with water cut-off and drainage channels, mortar rubble slope protection and subgrade drainage works, etc. Both sides of subgrade Mainly plant-based measures, with shrubs inside and trees outside, and natural recovery of both sides of the subgrade shall be paid attention to. Subgrade stripped topsoil Temporary protective measures shall be taken on the temporary stockpiling field of the stripped topsoil in the subgrade. Station Station Engineering measures are mainly station slope protection and drainage works; plant measures are

Upload: lytruc

Post on 11-Mar-2018

221 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Annex 3 Soil Erosion Control Plan

1. Overall Arrangement for Soil Erosion Control

The overall erosion control measures shall be determined for each protection zone according to the principles of the arrangement of erosion control. The overall layout of erosion control measures for the full line is shown in Table 1.

Table 1 Overall Layout of Soil Erosion Control Measures along the New Rapid Railway from Zhangjiakou to Hohhot

Control zones Control objects Conservation and prevention measures

Hilly area

Subgrade works

Subgrade slope Retaining wall shall be located by using frame bolt and shaller to protect the deep cutting. Frame slope protection and vegetation measures shall be combined to protect subgrade slope, with vegetation measures mainly being slope shrubs, planting shrubs and grasses within the frame, etc.; and engineering measures are frame slope protection with water cut-off and drainage channels, mortar rubble slope protection and subgrade drainage works, etc.

Both sides of subgrade

Mainly plant-based measures, with shrubs inside and trees outside, and natural recovery of both sides of the subgrade shall be paid attention to.

Subgrade stripped topsoil

Temporary protective measures shall be taken on the temporary stockpiling field of the stripped topsoil in the subgrade.

Station Station Engineering measures are mainly station slope protection and drainage works; plant measures are landscaping design combining trees, shrubs, flowers and grass to beautify the environment and improve soil and water conservation.

Stripped topsoil in the station

Temporary protective measures shall be taken on the temporary stockpiling field of stripped topsoil in the station site.

Bridge and culvert works

Bridge and culvert Mortar rubble slope shall be used for the bridge cone slope and river bank; cofferdam shall be set up and removed, and temporary protective measures shall be strengthened.

Tunnel Tunnel Mortar rubble masonry shall be used for the side invert slope and gutter in the tunnel entrance, and water cut-off and drainage measures shall be taken.

Page 2: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Earth-fetching field

Earth-fetching field When the construction is completed, protection measures to spread grass seed and plant shrubs shall be taken, and temporary protective measures shall be strengthened for the stripped topsoil on the earth-fetching field.

Spoil (ballast) field

Spoil (ballast) field Engineering measures and plant measures shall be combined. Retaining walls and drains shall be installed, and topsoil cover measures shall be taken; grass seed shall be spread or shrubs be planted for natural recovery of spoil (ballast) body; and temporary protective measures shall be enhanced for spoil, and stripped topsoil in the disposable ballast.

Construction sidewalk

Construction sidewalk

It shall be remained for local use or maintenance of roads according to the actual situation. The sidewalk which is not used shall be cleaned up and leveled when the construction is finished, and grass seeds shall be spread for natural recovery.

Production and living

area in construction

Construction site, camp

After the construction, the garbage site and hardening space shall be cleaned, and the surface shall be leveled; plant recovery measures shall be taken according to the actual situation.

Plain area

Subgrade works

Subgrade slope Frame slope protection and plant measures shall be combined for the slope protection of the subgrade, with plant measures being shrubs planted at the slope, shrubs planted in the frame and seeding grass, etc. and engineering measures being frame slope protection with water cut-off and drainage channels, mortar rubble slope protection and subgrade drainage works.

Both sides of subgrade

Mainly plant-based measures, with shrubs inside and trees outside, and natural recovery of both sides of the subgrade shall be paid attention to.

Subgrade stripped topsoil

Temporary protective measures shall be taken on the temporary stockpiling field of the stripped topsoil in the subgrade.

Station Station Engineering measures are mainly station slope protection and drainage works; plant measures are landscaping design combining trees, shrubs, flowers and grass to beautify the environment and improve soil and water conservation.

Stripped topsoil in the station

Temporary protective measures shall be taken on the temporary stockpiling field of stripped topsoil in the station site.

Page 3: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Bridge and culvert works

Bridge and culvert Mortar rubble slope shall be used for the bridge cone slope and river bank; cofferdam shall be set up and removed, and temporary protective measures shall be strengthened.

Tunnel Tunnel Mortar rubble masonry shall be used for the side invert slope and gutter in the tunnel entrance, and water cut-off and drainage measures shall be taken.

Earth-fetching field

Earth-fetching field When the construction is completed, protection measures to spread grass seed and plant shrubs shall be taken, and temporary protective measures shall be strengthened for the stripped topsoil on the earth-fetching field.

Spoil (ballast) field

Spoil (ballast) field Engineering measures and plant measures shall be combined. Retaining walls and drains shall be installed, and topsoil cover measures shall be taken; grass seed shall be spread or shrubs be planted for natural recovery of spoil (ballast) body; and temporary protective measures shall be enhanced for spoil, and stripped topsoil in the disposable ballast.

Construction sidewalk

Construction sidewalk

It shall be remained for local use or maintenance of roads according to the actual situation. The sidewalk which is not used shall be cleaned up and leveled when the construction is finished, and grass seeds shall be spread for natural recovery.

Production and living

area in construction

Production and living area in construction

After the construction, the garbage site and hardening space shall be cleaned, and the surface shall be leveled; plant recovery measures shall be taken according to the actual situation.

Frame slope protection and plant measures shall be combined for the slope protection of the subgrade, with plant measures being shrubs planted at the slope, shrubs planted in the frame and seeding grass, etc. and engineering measures being frame slope protection with water cut-off and drainage channels, mortar rubble slope protection and subgrade drainage works.

2. Subgrade Protection Measures

2.1 Subgrade Protection

To reduce soil erosion resulted from subgrade filling and excavation and to ensure the safety of the subgrade project, the line of subgrade has been reinforced and appropriate

Page 4: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

measures such as retaining wall protection, slope protection by framework or mortar rubble revetment, arched or square slope, planted tank, and new soil grass have been take based on the characteristics of subgrade in different segments. In addition, appropriate drainage system has been designed.

(1) General subgrade slope protection

If the height of the subgrade slope <3.0m, hollow bricks with new soil grass and planted shrubs shall be used; if the height of the slope≥ 3.0m, a layer of two-way geogrid with a limit tensile strength of not less than 25.0kN/m shall be laid every a filling of 0.6m within the width of 3.0m at the outer section of the slope, C25 concrete hollow brick with new soil grass + planted shrubs in water disconnection framework shall be used for slope protection. The main frame shall be 0.6m thick, and C25 concrete masonry shall be used for the water disconnection tank. The interface between the subgrade surface drainage and slope drainage shall be paid attention to. Three-dimensional ecological bags may be considered for the protection of city road segments, scenic areas and ecologically sensitive areas. If the slope of the subgrade height is greater than 8.0m, a different slope rate shall be taken according to the filling height. It is 1:1.5 for the slope of 0 ~ 8.0m, 1:1.75 for the slope of 8.0 ~ 12.0m, and 1:2.0 for the slope below 12 m; and a 2.0m wide platform will be located at 12.0m for the slope. New soil grass and planted shrubs in the hollow bricks in C25 concrete arch water disconnection frame will be used for the slope of 0 ~ 12.0m under the shaller, and dry stone revetment or prefabricated solid block revetment will be used for the side slope below 12.0m.

(2) High subgrade slope protection

If the slope height exceeds 12m, the slope rate is 1:1.5 for 0 ~ 8.0m, 1:1.75 for 8.0 ~12.0m, 1:2.0 for the height below 12 m. A 2.0m-wide platform will be located at 12.0m for the slope. New soil grass and planted shrubs in the hollow bricks in C25 concrete arch water disconnection frame will be used for the slope of 0 ~ 12.0m under the shaller, and dry stone revetment or prefabricated solid block revetment will be used for the side slope below 12.0m. C25 concrete or rubble foot wall of concrete will be positioned at the slope. Gravity retaining wall may be located at some high-fill subgrades with less arable land to reduce the use of farmland.

(3) General graben slope protection

1) For the cutting slope of general clay and all-weathered layer, if the height of the slope is less than 3.0m, hollow bricks with new soil grass and planted shrubs shall be used for protection; if the height is equal to or greater than 3.0m, hollow bricks with new soil grass and planted shrubs in C25 concrete water disconnection frame shall be used for protection.

2) For gravel soil, sandy soil cutting slope, hollow bricks with new soil grass and planted shrubs in C25 concrete arched or square grass window shall be used for protection.

3) For strong-weak weathered soft rock cutting slope whose height is less than 8.0m, hollow bricks with new soil grass and planted shrubs in C25 concrete water disconnection frame shall be used for protection; if the height is greater than 8.0m, hollow bricks with new soil grass and planted shrubs in C25 concrete arch or square grass window shall be used for the lower side slope for protection, hollow bricks with new soil grass and planted shrubs in C25 concrete water disconnection frame shall be used for the most upper side slope for protection.

4) For strong-weak weathered hard rock cutting slope, if the slope height is less than 8.0m,

Page 5: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

hollow bricks with new soil grass and planted shrubs in C25 concrete arch or square grass window shall be used for protection; if the height is greater than 8.0m, hollow bricks with new soil grass and planted shrubs in the retaining wall of C25 concrete hollow window shall be used at the bottom, while hollow bricks with new soil grass + planted shrubs in C25 concrete arched or square grass window shall be used at the upper slope for protection.

Weakly- sligthly hard rock cutting: in general, the height of the slope is controlled within 30.0m, and M10 mortar rubbles will be embedded for the slope. Hollow bricks with new soil grass will be used for the protection in the concrete grass window or anchor rod and cable within the framework.

5) In the lots with absence of A, B group packing, if the cutting soil is sand gravel, hard rock, large platform shall be reserved for the foot and side slope of cutting slope, with one level every 8.0 ~ 10.0m, and the slope rate shall be reduced accordingly. C25 concrete grass window shall be used for the slope protection.

6) The types of water disconnection frame slope protection are arch, herringbone and box types. They shall be used based on the soil quality of the slope and the requirement for erosion prevention combined with landscape demand. The spacing between the main frame and the arch shall be 3.0m. For the general soil and soft rock cutting, the main frame is 0.65m thick, and the supporting frame is 0.4m thick; for very soft rock, red clay, swelling (rock) soil cutting, the main frame is 0.8m thick, and the supporting frame is 0.6m thick.

7) Planting tanks in which japanesecreepers and evergreen low shrubs are planted shall be located at the platform of the side trenches in the cutting where retaining wall, pile wall and protection wall are located and the platform from the flooding closed slope lot to the drainage.

(4) Deep cutting slope protection

If the height of soil and soft rock cutting slope exceeds 12.0m, and of hard rock slope exceeds 20.0m, the deep cutting shall be designed, and reinforced protection works shall be set.

1) Gravity retaining wall shall be used in the close of the slope for soil and completely weathered rock cutting, and the height of the retaining wall shall not exceed 4.0m. The measures of slope protection refer to slope subgrade. If the slope height is greater than 15.0m, stratified excavation shall be considered for hierarchical reinforcement or pre- strengthening of the lowest part of the slope.

2) In the lots where the slope height of soft rock cutting and hard weathered rock cutting is not more than 18.0m and there is no adverse impact on the structure surface, retaining wall, concrete window grass slope and framework anchored rod shall be used for protection. The height of the retaining wall shall not be greater than 6.0m. In the lots where the slope height is greater than 18.0m or there is adverse impact of the structure surface or broken lithology, stratified excavation shall be considered for hierarchy reinforcement or pre- reinforcement of the lowest part of the slope, such as prestressed cables, pre-reinforced piles and sheet pile walls. In general, the height of the slope shall be controlled within 25.0m. As the strata of the hard rock along this line is old, the joints are developed and the rocks are crushing, grass window wall shall be used for the slope or the slope shall be closed.

3) The slope rate for excavation of the cutting slope of weakly–slightly weathered hard rock shall be determined based on rock lithology, degree of weathering, level, geological

Page 6: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

structure, groundwater and required allocation of earth and stone. If the slope height is not greater than 24.0m and there are no lots with adverse impact on the structure surface, retaining wall, concrete grass window slope, wall and frame anchored rod shall be used for protection, with the height of the retaining wall not greater than 8.0m. If the height of the wall exceeds 6.0m, temporary shotcrete shall be taken for the excavated slope of the back of the wall. If the slope height is greater than 24.0m or there are lots with adverse side effects of structure and broken lithology, stratified excavation shall be considered for hierarchical reinforcement or pre-strengthening of the foot of the slope. The slope height of weak–slight weathered hard rock cutting shall, in general, be controlled within 30.0m. Finishing or pre-split blasting shall be used for the slope within the thickness of 3.0m, and M10 mortar rubbles shall be embedded. Hollow bricks with new soil grass shall be used inside the concrete grass windows or frame anchored rods and cables.

4) Planting tanks in which japanesecreepers and evergreen low shrubs are planted shall be located at the platform of the side trenches in the cutting where retaining wall, pile wall and protection wall are located and the platform from the foot of the flooding closed slope lot to the drainage.

5) In the lots with absence of A, B group packing, if the cutting soil is sand gravel or hard rock, depressed road's extension shall be designed and large platform shall be reserved for the foot and side slope of cutting slope, with one level every 8.0 ~ 10.0m, and the slope rate shall be reduced accordingly. C25 concrete grass window shall be used for the slope protection.

(5) Expansion rock (soil) cutting slope protection

1) The slope design of expansion rock (soil) excavation shall follow the principle of "reduced slope rate, wide platform, reinforced toe, enhanced drainage and appropriate slope protection". The excavation height shall be generally controlled within 15.0m. The rating of the slope height shall not be more than 6.0m. If the slope height of the cutting is less than 10.0m, the slope rate is generally 1:1.75 for weak swelling rock (soil), 1:2.0 for moderate swelling rock (soil), and 1:2.25 - 1:2.5 for strong expansion rock (soil). The width of the slope platform shall not be less than 2.0m for weak expansion rock (soil), and not less than 3.0m for medium and strong expansion rock (soil).

2) If the slope height of the cutting is less than 3.0m, the use of hollow bricks with new soil grass + planted shrubs shall be made for protection; if the slope height is greater than 3.0m but less than 10.0m, the use of hollow bricks with new soil grass and planted shrubs in C25 concrete water disconnection frame (expansion soil) or C25 concrete grass window (expansion rock) shall be made for protection; if the slope height is equal to or greater than 10.0m, a platform in a width of 3.0 ~ 6.0m shall be located at the slope of expansive soil cutting, hollow bricks with new soil grass and planted shrubs in C25 concrete water disconnection frame combined with supporting sewer shall be used for protection; if the slope is equal to or greater than 10.0m, hollow bricks with new soil grass and planted shrubs in framework anchoring rod (or anchoring cable) combined with supporting sewer shall be used for the protection of the slope of expansion rock. The thickness of the main frame of the C25 concrete water disconnection framework shall not be less than 0.8m, and that of the supporting frame shall be 0.6m. The main frame spacing and the spacing between arches is 3.0m.

Page 7: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

(6) Loess cutting slope protection

The excavation height of loess cutting slope is commonly controlled within 20.0m. Side-ditch platform in a width of 2.0 ~ 3.0m shall be located at the loess cuttings along the line. M10 cement mortar rubble or concrete solid block masonry shall be used for the platform.

If the cutting slope height H is ≤ 5.0m, concrete hollow bricks with new soil grass and planted shrubs inside shall be used for the slope protection. If the slope height is: 5.0m <H ≤ 16.0m, a small platform in a width of 2.0~3.0m shall be located every a height of 8.0m, and platform drainage ditches shall be located; the slope of the upper Pleistocene strata shall be protected using hollow bricks with new soil grass + planted shrubs in C25 concrete water disconnection framework; in mid Pleistocene strata, the slope shall be protected using C25 concrete space wall (mixed vegetation within). If the slope height exceeds 16.0m, the width of the slope platform shall be 4.0 ~ 6.0m, and drainage ditches shall be located at the platform; the slope shall be protected with hollow bricks with new soil grass and planted shrubs in frame anchoring rod in a length of 8.0m.

(7) Cutting of groundwater development

The slope rate shall be reduced by level 1~2 compared with the groundwater undeveloped section. C25 concrete grassed window or C25 concrete arched water disconnection frame + three-dimensional vegetation network solid soil grass + planted shrubs shall be used. The net frame spacing shall be 2.5m and the main frame shall be 0.8m thick. Water disconnection tank shall be reserved at the top, and supporting sewer in a width of 2.0m and a depth of 2.0~2.5m shall be located every 10.0~15.0m. At the junction of permeable and impermeable sections, a slope platform in a width of 3.0 ~ 5.0m shall be located with drainage ditches in it.

(8) Subgrade drainage works

1) Surface drainage design

① Side ditches, gutters, drains or drainage ditches shall be designed by the slope rate of 1/50, and the top shall be 0.2m higher than the designed water level. The longitudinal slope rate shall not be less than 2‰. The cross-section dimension of water surpassing for drainage facilities shall be calculated based on water flow. The connection with subgrade surface drainage, slope drainage and sub drainage systems shall be paid attention to.

② If the subgrade slope is protected with water disconnection framework, the slope water disconnection tanks on both sides will be the lateral gutters along the subgrade slope. Lateral gutters along the slope shall be located in the lots where C25 precast concrete hollow brick grassed pavement in a depth of 0.2m and a spacing of 10.0m is used.

③ In the lots where cross slope is significant on the subgrade ground, drainage ditches may be located in the top side. If the ground cross slope is not obvious, drainage ditches shall be located on both sides of the subgrade. Drainage plane shall be straight; if a turn is required, its radius shall not be less than 10.0~20.0m, and the length of the gutter shall be determined according to the actual needs. Drains are generally trapezoidal ditches in a bottom width of 0.4m and a depth of 0.6m with a slope rate of 1:1. Cast-in-site C30 reinforced concrete in a thickness of 0.2m shall be used for drainage ditches. The location of drains shall ensure that the water will be led outside the subgrade to prevent it from erosion.

④ C30 reinforced concrete rectangular cover trench shall be used for side ditches in a

Page 8: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

bottom width of 0.6m, a height of 0.8m, and a thickness of 0.25m. The drains between the lines in a standard spacing shall have a width of 0.4m, a depth of 0.8m, and a thickness of 0.20m in C30 reinforced concrete masonry. Precast C30 reinforced concrete shall be used for the cover of the side ditch. Trapezoidal side ditch shall be used for non easily weathered hard rock cutting, in a bottom width of 0.4m, a depth of not less than 0.6m and a slope rate of 1:1. M10 cement mortar in a thickness of 0.08m shall be used for the surface, and C25 concrete may be used for embedment at local sections.

⑤ In the lots where cross slope is significant on the subgrade ground, gutters may be located in the top side. If the ground cross slope is not obvious, gutters shall be located on both sides of the subgrade. 0.2m thick in-situ C30 reinforced concrete may be used for the gutters, and M10 mortar rubble shall be used to close the sections from expansive rock (soil), collapsible loess, the top of the bed cutting to the gutter. For the gutter which has the steep slope of the cutting top, rectangular gutter shall be used.

⑥ 0.40m × 0.40m rectangular groove shall be used for the water disconnection ditch at the slope platform for the cutting, and C25 concrete which is used in the slope shall be poured.

⑦ The anti-slope drainage of the tunnel entrance is based on the rigid transition section of the tunnel road, with the cross section of the ditch at the starting position being 0.4m deep. In the deep cutting and the lot with problems of anti-slope drainage(if the depth

of the side ditch is more than 1.50m, and the width more than 0.80m), and in the valley cutting lots, the addition of culverts and the use of 0.2m thick C30 reinforced concrete drains shall be made to lead the side ditch water out of the subgrade as soon as possible.

2) Base-bed waterproofing and drainage

Collecting well shall be located in the middle of the subgrade for the drainage between the tracks of slab track sections of straight lines and curves lines. The inside diameter of the drainage well is 0.6m, the depth 0.8m, and 0.3m thick cast-in-site C30 reinforced concrete is used. Precast C30 reinforced concrete is used for the cover spaced 50m or so, which are embedded into the drainage channels or side trenches for the slope of subgrade.

3) Groundwater waterproofing and drainage facilities

Drainage facilities such as open ditches, slope support sewers and porous drains shall be located where underground water brings hazards to the subgrade according to its nature and characteristics. Drainage shall be particularly designed for swelling rock (soil) cutting and underground water development cutting.

4) Connection between drainage system and natural system

The drainage system of subgrade main project uses its drains with devices such as wells and settling ponds by being connected to the existing ditches or channels around.

The subgrade slope protection, slope greening measures, drainage works, protective area, quantity and investments of protection, etc taken in the design shall meet water security requirements, and be included in this program investment. For the quantities of soil stripped and corresponding temporary protective measures excluded in the main project list, design will be added to them in the program. Special design of green channel is made for the both sides of the line in the main works, and costs are listed to meet water conservation requirements, but detailed design has not been made in the main engineering. Therefore it is not very targeted and operable, and may not be implemented specifically in the construction process. This soil and water conservation program has detailed design for

Page 9: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

the greening sections on both sides of the line, and quantities and investment costs of protection works based on sections have been included.

Page 10: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Table 2 Subgrade slope protection measures

NoLandfo

rmMilestone Administration

Slope protection

3-d ecological slope

protection

TGSG25

Fence

Greening protection

Concrete bloc

k

Planting pool

Grass SoilsRiver locust tree

Creepers

C25Concrete

block

C25 concrete

Planting

soil

Fertiliezer

Water outlet 3-d

slope protectio

n

M type bag

PVC pip

e( 0.0φ5m)

m2 m2 m3 Nr / m3 m3 m3 m3 m m2 Nr

1 PlainCK000+000~CK0

02+570Zhangjiakou 640 170 17 1595 7

2Plain CK002+570~CK0

11+260Wangquan 26749 5208 521 48879 235

3Plain CK011+260~CK0

68+300Huai’an

488848

49703

497247157

21027

322005 935 3931 393 1868

4 HillsCK068+300~CK0

73+310Shangyi

5Hills CK073+310~CK0

74+560Xinghe

6Hills CK074+560~CK0

76+900Shangyi 36 4 342 2

Page 11: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

7Hills CK076+900~CK1

24+215Xinghe

139051

110007

14512

1075442

37444

4789 830 2382 237 16591944

31361

01

8Hills CK124+215~CK1

51+080Chanyouqianqi 24209

20306

418620045

51755 1017 106 309 31 213

9 PlainCK151+080~CK1

52+303Jining

10 PainCK152+303~CK1

60+796Chayouqianqi 20711 4466 447 41918 177

28292

198044

11 PainCK160+796~CK1

63+498Jining 7700 2648 265 24855 379 102 47 139 14 95

12Hills CK163+498~CK1

79+317Chayouqianqi 4673

12000

120112020

85000 459 109 347 34 218

13Hills CK179+317~CK2

55+248Zhuozi

111646

117330

13246

1114323

36806

4794 657 2007 202 13101613

91142

33

14Hills CK255+248~CK2

69+500Hohhot 55511

27715

377326227

78665 1199 166 476 47 336

15 PlainCK269+500~CK2

91+000

Hohhot 181362

35064

350432909

54742

31358 429 1810 182 861

16 HillsSections by

Second Jibaoline

Hohhot1053 2407 241 22599 1108

17 PlainSection by

Jingbao line(double line)

Hohhot57012

16711

167215685

14877

9

Total11191

654037

714856

138704

112402

046603

1327

91140

11140 6560

64054

448378

Page 12: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

(Continued)

NoLandfor

mMilestone

Administration

Slope protectionReinfo

rce

Interception structure slope protection Concrete(window type)wall

Geotextile,etc

s

Grooving

C25 Concr

ete

M10concrete struct

ure

Wall body

Filter

layer

Water outlet

Expansion joint

Soil Stone M10

C25

concrecte

block

Sand/gra

bble

PVC管(

0.1mφ)

Alphalt

linen(0.02m)

m3 m3 m3 m3 m3 m3 m3 m m2 m2

1 PlainCK000+000~CK002+5

70Zhangjiakou 48 49 394

Page 13: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

2Plain CK002+570~CK011+2

60Wangquan 282 283 15242

3Plain CK011+260~CK068+3

00Huai’an 15871 63 16005

266199

4 HillsCK068+300~CK073+3

10Shangyi

5Hills CK073+310~CK074+5

60Xinghe

6Hills CK074+560~CK076+9

00Shangyi 176

7Hills CK076+900~CK124+2

15Xinghe 26662 5481 32272

363902

8 HillsCK124+215~CK151+0

80Chanyouqian

qi 4831 668 5520 68226

9Plain CK151+080~CK152+3

03Jining

10Plain CK152+303~CK160+7

96Chayouqianq

i 1627 1634 7238

11Plain CK160+796~CK163+4

98Jining 627 630 16712

12Hills CK163+498~CK179+3

17Chayouqianq

i 923 2171 3108 41764

13Hills CK179+317~CK255+2

48Zhuozi 30473 2215 32835 8578 45 299 2589 897

381687

Page 14: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

14Hills CK255+248~CK269+5

00Hohhot 9331 35 9409 79156

15 PlainCK269+500~CK291+0

00Hohhot

22796 2392124417

3

16 Hills Sections by Second Jibaoline

Hohhot1228 2998

17 Plain Section by Jingbao line(double line)

Hohhot6043 10389

Total12011

511260

125666

13387 8578 45 299 2589 89714848

69

Page 15: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Table 3 Subgrade Drainage Protection Measures`

NoLandform

MilestoneAdministration

Ground drainage ditchWater

collection well

Side ditchSide ditch platform

drainage ditch Gutter JointWell bod

y

Cover

C30

Concret

e

M10 ceme

nt surfacing(0.05m)

M10

M10 ceme

nt surfacing

(0.05m)

M10

C30 Concret

e

Soils

M10C30 concrete

SoilsSoil

sM10

C30Concret

e

C30Concret

e

(m3

)(

m2)(m3

)(

m2)(m3

)(m3

)(m3

)(m3

)(m3

)(m3

)(m3

)(m3

)(m3

)(m3

)1 Plain

CK000+000-

CK002+570

Zhangjiakou 17 12 12 27

2

PlainCK002+570

-CK011+260

Wangquan 938

2095

9 1

3

PlainCK011+260

-CK068+300

Huai’an

4949

9313

3479

12327

18884

408279

1635

5809

3149

1158 19

4 Hills CK068+300-

Shangyi

Page 16: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

CK073+310

5

HillsCK073+310

-CK074+560

Xinghe

6

HillsCK074+560

-CK076+900

Shangyi 15 10 6 13

7

HillsCK076+900

-CK124+215

Xinghe

23246

16864

71461

3664

310643

23952

2847

30 209 22

8

HillsCK124+215

-CK151+080

Chanyouqia

nqi

4432

2457321

11489 355 541

2361

5228

232 39 5

9 PlainCK151+080

-CK152+303

Jining

10 PainCK152+303

-CK160+796

Chayouqian

qi445 696 298 4

11 PainCK160+796

-CK163+498

Jining121

8341 297 465 411

1972

199 10 1

12

HillsCK163+498

-CK179+317

Chayouqian

qi

2999

3090171

52504 113 333 399

1357

3055

170 48 23 2

13

HillsCK179+317

-CK255+248

Zhuozi

25114

13720

3477 201854

4945

3272

12214

234839

4051

100 220 18

Page 17: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

14

HillsCK255+248

-CK269+500

Hohhot

4220

2398

1100

737235

3214

2332

2100

8550 45 6

15 PlainCK269+500

-CK291+000

Hohhot 550

3408

410941

15480

723160

4663

3102 11

16 HillsSections by

Second Jibaoline

Hohhot 574 66 99 96 460 653 41

17 Plain

Section by Jingbao

line(double line)

Hohhot 116

8119

7717

610531

42 74451

5307

5

Total73455

554752931

747016335

39545

91699

72233108

281067

4038

1099

819 85

Page 18: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

2.2 Plant protection measures for both sides of the subgrade

In order to improve the environmental quality of the project area, reduce soil erosion caused by railway construction, while achieving the purposes of soil and water conservation, afforestation and beautification as well as the protection of railway operational safety, protection of plant measures shall be made for the both sides of the subgrade. Based on the site conditions in climate, soil, and water, the available lots on both sides of the subgrade within the land in the project may be greened under the principle of "trees and shrubs integrated", and green protective measures may not be taken for the lots without the space for green.

Green protective measures shall be taken for the available lots within the boundary of the land on both sides of the line with the total length of the green lots being 99.23km. A combination of planted bushes and trees will be taken for Hebei section, and shrubs will be planted in the Inner Mongolia section. Specific green measures for the Hebei section will be the following: one row of trees and two rows of shrubs will be planted at either side of the subgrade lot; three rows of shrubs planted on both sides of the cutting lot; the tree spacing will be 3.0×1.0m, shrub spacing 1.0m×1.0m; for the Inner Mongolia, the specific measures will be the following: three rows of shrubs will be planted on either sides of the subgrade lot in a spacing of 1.0m×1.0m. A total of 10,696 trees and 1,747,256 shrubs will be planted on both sides of the subgrade areas along the whole line.

Table 4 Greening along subgrade

No

Landform

MilestoneAdministr

ationSubgrade

length(km)

Greening quantity

Trees Bushes

1 PlainCK000+000~CK002+

570Zhangjiako

u 0.02 15 268

2Plain

CK002+570~CK011+260

Wangquan 0.87 577 10392

3Plain

CK011+260~CK068+300

Huai’an 15.16 10104 181867

4 HillsCK068+300~CK073+

310Shangyi 0.00 0 0

5Hills

CK073+310~CK074+560

Xinghe 0.00 0 0

6Hills

CK074+560~CK076+900

Shangyi 0.01 0 180

7Hills

CK076+900~CK124+215

Xinghe 22.27 0 400775

8 HillsCK124+215~CK151+

080Chanyouqi

anqi 3.88 0 69777

9Plain

CK151+080~CK152+303

Jining 0.00 0 0

1Plain

CK152+303~CK160+ Chayouqia 2.61 0 47003

Page 19: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

0 796 nqi

11

PlainCK160+796~CK163+

498Jining 0.95 0 17092

12

HillsCK163+498~CK179+

317Chayouqia

nqi 2.37 0 42713

13

HillsCK179+317~CK255+

248Zhuozi 23.39 0 420965

14

HillsCK255+248~CK269+

500Hohhot 4.50 0 80953

15

PlainCK269+500~CK291+

000

Hohhot16.77 0 301831

16

Hills Sections by Second Jibaoline

Hohhot0.65 0 11653

17

Plain Section by Jingbao line(double line)

Hohhot8.99 0 161787

Total 102.42 10696174725

6

(1) Temporary block and drainage measures for the subgrade stripped topsoil

During the filling works of the railway subgrade, as the surface soil fails to meet the requirements of subgrade filling in the engineering design, the topsoil must be stripped. The thickness of this surface soil is generally about 30cm. It has high content of humus, featuring good soil fertility, structure and texture. It is suitable for vegetation growth and may be used in the topsoil transformation for the subgrade slope green of grid, station and ballast along the railway.

According to the state of the environment in the project area, combined with the engineering characteristics, the land, woodland and grassland occupied by the subgrade are designed to have topsoil stripping in a strip thickness of 0~30cm, and a temporary stockpiling field is designed every 500~1000m in the land, where the stripped topsoil will be piled up and compacted. Retaining wall made of straw bags will be used as temporary protection at the foot of the outside slope surrounding the stockpiled soil, and other exposed surfaces will be covered with tarpaulin to prevent wind transport. Temporary drains will be dug at the border of the stockpile soil, temporary settling basin will be constructed at the outlet, and connected with the surrounding drainage system, so that the rainfall runoff may be discharged through the outlet and the simple settling basin to prevent soil erosion in the temporary stockpiling field.

The stockpiling height of the temporary stockpiling filed shall not be higher than 3.0m, and the stacked slope rate shall be controlled within 1:1.5. The straw bag retaining wall section shall be a rectangular trapezoidal cross-section in height × top width ×bottom width = 1.0m × 0.5m × 1.5m. When piling, the bags shall be engaged and lapped in a lap length not less than 1/3 of the length of the straw bag. The temporary drains shall be soil drains with a trapezoidal cross-section, whose design specifications are base width of 0.3m, top width of 0.9m, ditch depth of 0.3m and slope rate of 1:1. The ditch base and wall shall be compacted.

Page 20: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

The simple settling basin shall have a length of 2.0m, a width of 1.0m, and a depth of 1.5m, with its bottom compacted. A total of 89.57 × 104m3 topsoil used in the new soil grass of subgrade slope are stripped for the subgrade across the line.

Page 21: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Table 5 Temporary protection and drainage design for top soil from subgrade area

No

Landform

Milestone Administration

Topsoils(m3

)Soil cove

r(m3

)Length(m

)Soil bag

s(m3

)Pauli

n(m2

Temporary drainage(m

3)Temporary

settling tank

1 Plain CK000+000~CK002+570 Zhangjiakou 0 0 0 0 0 0 0

2Plain

CK002+570~CK011+260 Wangquan 10060 10060 409 409 4024 0 0

3Plain

CK011+260~CK068+300 Huai’an18242

018242

06960 6960 72968 0 0

4Hills CK068+300~CK073+310 Shangyi

14980 14980 610 610 5992 434 3HillsCK074+560~CK076+900 Xinghe

5

HillsCK073+310~CK074+560 Shangyi

Xinghe

282560

282560

10901

1090111302

47048 47Hills

CK076+900~CK124+215

6 Hills CK124+215~CK151+080 Chanyouqianqi

Jining55376 55376 2054 2054 22150 1366 9

7Plain

CK152+303~CK160+796

8Plain

CK151+080~CK152+303 Chayouqianqi

Jining0 0 0 0 0 0 0

9Plain

CK160+796~CK163+498

10

HillsCK163+498~CK179+317 Chayouqianqi 13844 13844 469 469 5538 334 2

11

HillsCK179+317~CK255+248 Zhuozi

228200

228200

8629 8629 91280 5661 38

Page 22: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

12

HillsCK255+248~CK269+500 Hohhot 43320 43320 1600 1600 17328 1068 7

13

Plain CK269+500~CK291+000Hohhot

64980 64980 8664 8664 25992 0 0

14

HillsSections by Second

Jibaoline

Hohhot0 0 0 0 0 0 0

15

PlainSection by Jingbao line(double line)

Hohhot0 0 0 0 0 0 0

Total89574

089574

04029

640296

358296

15911 107

Page 23: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

3. Protective measures for Station

3.1 Station subgrade protection

The water and soil conservation measures for the station in this project is mainly aimed at

the station subgrade, which are roughly the same as the soil and water conservation

measures for the subgrade. Slope protection of arched frame pavement, hollow bricks with

new soil grass and mortar rubble drainage ditch and porous drain are used for the subgrade.

If the subgrade slope height is less than 3.0m, six-diamond hollow bricks with planted grass

and Amorpha will be used for protection, and a precast concrete drainage tank will located

at both sides of the slope at intervals of 10.0m to connect the horizontal drainage channels

between the tracks; if the slope height is greater than 3.0m, 3×3m C25 concrete arch

framework with water disconnection tank will be used in the slope protection of the

subgrade, and in the framework, six-diamond hollow bricks will be paved with planted grass

and Amorpha. A layer of two-way stretch plastic geogrid (TGSG30-30) will be laid every

0.6m of the vertical height from the foot of the slope to the surface level of the base bed

within the lateral width of 3.0m on both sides of the slope; if the subgrade is filled with weak

weathered and slightly weathered broken rocks, the quantity of new soil shall be added into

the block.

The cutting slope rate shall be 1:1.25~1:1.5 for silty clay, 1:1.25 for gravel soil, and 1:1.25 for loess cutting. For the slope whose height is less than 3.0m, six-diamond hollow bricks with planted grass and Amorpha inside shall be used for protection; for the slope whose height is greater than 3.0m, C25 concrete arch frame paved with six-diamond hollow bricks with planted grass and Amorpha inside shall be used for protection. The stations are open-train layout, and the new sites are ground stations except that Huai An Station is an elevated one. The average earthwork height in plains is h≤ 3m (Huan An Station), 3m <h ≤ 5m (Ulanchabu Station), and in hilly area is 5m <h ≤ 7m (Xingheibei Station). Full sloping dry stone revetment is used for the slope protection of Xinghe Station and Ulanchabu Station, which is not included in the soil and water conservation engineering measures.

Page 24: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

3.2 Greening measures in the station area

There are three new stations across the line, with Trunk of treesozi Station and Trunk of treesozi East Station under the construction being integrated for locations. In order to maintain soil and water and beautify the station area environment, to improve ecological environment quality of the station area, and to meet the production and operating conditions, 20% of the new permanent site in the station are greened in line with the principle of multiple green. They are mainly located at the surrounding of the new buildings at each station and other open space available for concentrated green. Trees, shrubs, flowering shrubs and grass are integrated, in a green ratio of 30% by trees, shrubs 30%, flowering shrub 20%, and grass 20%, laid according to the principle of 3×3m for trees and 1 × 1m for shrubs. In the new stations, as Huai An Station is an elevated one, green design is considered for its areas available for green at the roads in the stops. The proportion of shrubs, flowering shrubs and lawns is 30%, 30% and 40% respectively. The shrubs are laid in 1× 1m. A total of 3,523 trees, 34,898 shrubs, 9,532 flowers and 4,958m2 paved turf are planted in the stations across the line.

Table 6 Greening measures in the station area

No

Landform

StationMilestone (center)

Greening are

a(m2

Greening

Trees BushGras

s(m2) Flowers(m2)

1 PlainHuai’an Station

CK043+075

10633 0 3190 4253 3190

2 HillsXinghe North

Station

CK099+400

30560 1019 9168 204 1834

3 PlainsUlanchabu

StationCK159+27

054933 1831 16480 366 3296

4 HillsZhuozi

East Station

CK207+200

20200 673 6060 135 1212

Total11632

73523 34898 4958 9532

3.3 Temporary block protection and temporary drainage measures for stripped topsoil in the station area22.25 × 104m3 stripped topsoil in the new stations across the line is used for the latter stage

green in the station. The stripped topsoil will be designed to be piled in the temporary

stockpiling site in the station area, and they will be compacted. Retaining wall made of straw

bags will be used as temporary protection at the foot of the outside slope surrounding the

Page 25: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

stockpiled soil, and other exposed surfaces will be covered with tarpaulin. Temporary drains

will be dug at the border of the stockpile soil, temporary settling basin will be constructed at

the outlet of the drains, and connected with the surrounding drainage system.

The stockpiling height of the temporary stockpiling filed shall not be higher than 3.0m, and

the stacked slope rate shall be controlled within 1:1.5. The straw bag retaining wall section

shall be a rectangular trapezoidal cross-section in height × top width ×bottom width = 1.0m

× 0.5m × 1.5m. When piling, the bags shall be engaged and lapped in a lap length not less

than 1/3 of the length of the straw bag. The temporary drains shall be soil drains with a

trapezoidal cross-section, whose design specifications are bottom width of 0.3m, top width

of 0.9m, ditch depth of 0.3m and slope rate of 1:1. The ditch base and wall shall be

compacted. The simple settling basin shall have a length of 2.0m, a width of 1.0m, and a

depth of 1.5m, with its bottom compacted. The stripped topsoil is used in the surface soil

transformation of green area in the station.

Table 7 Temporary protection and drainage design for stations

No

Landform

StationMileston

e

Toposoils(m3

Soil cover(m

3)Length(m

)Soil bag

s(m3)

Paulin(m

2)

Temp.

drainage(m3

Temp.

Settling

tank

1 PlainHuai’an Station

CK043+075

29500

29500

1118 11181180

00 0

2 HillsXinghe North

Station

CK099+400

45840

45840

1801 18011833

61012 4

3 PlainUlanchabu

StationCK159+2

703825

23825

21496 1496

15301

0 0

4 HillsZhuozi Station

CK207+200

27840

27840

1301 13011113

6652 2

5Plain

s

Hohhot Statio

n(yard)CK289+2

732700

02700

01064 1064

10800

0 0

6 Plains

Hohhot Statio

n(Utility

CK291+000

54100

54100

2044 2044 21640

0 0

Page 26: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Yard)Total

222532

222532

8824 88248901

31664 6

Page 27: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Table 8 Main Protection Measures for Stations

Station

Station subgrade reinforce

Geotextile

GrassingRiver locust tree

SoilsConcrete structure shoulder

M10 cement

surfacing

C25 Concrete

M7.5 Concrete

C30 Concrete

Units m2 m2 / m3 m3 m2 m3 m3 m3

Huai’an Station

Xinghe North Station 34269 1073 18

Ulanchabu Station 54308 1518 26

Zhuozi East Station 37972 1190 20

Hohhot Station(yard) 140463 11866 76284 1187 3044 9202 1268

Hohhot Station(Utility Yard) 10382 67085 1229 1000 3023 2493 2784

Station

Station drainage system

Side ditch of sugrade Drainage Drainage or gutter Joint

Earth work

quantity

Side ditch

length

C30 Concret

e

Side ditch

platform M10

concrete

Length

M7.5 Concret

e

Drainage length

C30 Concret

e

Foundation earth work

Earth work

quantity

M10 Concret

e

Units m3 m m3 m3 m m3 m m3 m3 m3 m3

Huai’an Station

Page 28: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Xinghe North Station 1925 4015 955 440 470 846 2915 1437 7288 825 220

Ulanchabu Station 1732 800 955 440 1165 1049 3600 1952 9900 743 220

Zhuozi East Station 1745 700 865 419 543 489 1875 1371 6953 748 179

Hohhot Station(yard) 11802 6744 5852 2833 2070 1863 5212 2570 13030 5058 1213

Hohhot Station(Utility

Yard) 3490 3141

Page 29: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

4. Control Measures in the Bridge and Culvert Works Area

4.1 Bridges and culverts set-up and design requirementsThe flood frequency of bridges and culverts is designed to be 1/100 for bridges, and 1/100

for culverts. In principle, one bridge (culvert) is set up for one river (ditch), and the river

channel shall not be compressed, so that the water may go through the bridge in a natural

state; where roads are crossing, interchange may be used; in the farming-intensive areas,

farmland channel shall be located; vertical drains shall be located within the bridge, and

connected with the drainage system in the subgrade so as to lead to the water in the side

ditches of the subgrade to the natural ditches under the bridge. M10 mortar rubble paving

protection shall be adopted.

Permeable soil shall be used to fill the cone packing of the bridge ancillary works and be

compacted, and 35cm thick M20 mortar rubble shall be used in the protection of slope with

a 10cm thick gravel layer located below.

For individual lots where river erosion may be increased due to the set-up of piers,

reinforced subgrade and mortar rubble revetment measures shall be taken to avoid the

river, flood erosion. The bridge foundation excavation shall be made full use of; if it is unable

to use, spoil field shall be selected for concentrated spoil to reduce soil erosion.

The foundation of the main pier crossing the river shall use island or cofferdam construction

and shall avoid flood. Complete cleanup shall be considered after the construction to ensure

the smooth water flow.

4.2 Bridge and culvert protective measures

(1) The flood frequency of 1/100 is used in the design of the bridge and culvert to

maintain the appropriate technical requirements; for the check calculation of extra large

bridge (or large bridge) which is technically complex, difficult to repair or very important,

the flood frequency is 1/300; for the bridge close to the upstream reservoir, check

calculation will be made according to the reservoir dam break flow.

(2) Natural river channel shall be avoided from compress and ditches from change when

Page 30: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

crossing the river channel for flood discharge so as to maintain the natural run-off state and

to ensure smooth flow of flood discharge. Streamlined piers shall preferably be used in the

river channel to reduce the water-blocking area of the pier, and avoid increased erosion, as

well as to reduce the impact on the upstream and downstream slopes of the bridge site and

to avoid soil erosion.

(3) Flood discharging capacity is fully considered in the design of the diameter of the

culvert to avoid the water restrain of the culvert caused by the small aperture, resulting in

soil erosion caused by increased downstream erosion.

(4) For the pier located in the ditch or in the water, cofferdam made of straw bags filled

with soil or steel sheet pile cofferdam is used based on the water depth in the construction

and geological conditions, and the protection of the sections where the water level is high

and the foundation layer is strongly permeable shall be paid attention to in the construction.

(5) During the construction, the spoil generated in the bridge foundation construction

shall be knocked into the pile foundation if permitted by conditions; abutment cone slope

shall be protected by M20 cement mortar rubble.

Table 9 Bridge and viaduct protection measures

No

Landform

Milestone Administration

Cone protectionConstruction

protection

M20 Concrete(m3)

M10 Concrete(m3)

Soil wei

r(m3)

Steel wei

r(Number)

1 PlainCK000+000~CK

002+570Zhangjiakou 125 1413

2

Plai

nCK002+570~CK

011+260Wangquan 110 0 0

3

Plai

nCK011+260~CK

068+300Huai’an 1178

10375

200

Page 31: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

No

Landform

Milestone Administration

Cone protectionConstruction

protection

M20 Concrete(m3)

M10 Concrete(m3)

Soil wei

r(m3)

Steel wei

r(Number)

4 HillsCK068+300~CK

073+310Shangyi

5Hills CK073+310~CK

074+560Xinghe

6Hills CK074+560~CK

076+900Shangyi

7Hills CK076+900~CK

124+215Xinghe 2099 8181 14

8Hills CK124+215~CK

151+080Chanyouqianqi 545

35300

0

9 PlainCK151+080~CK

152+303Jining

10

PainCK152+303~CK

160+796Chayouqianqi 137 0 0

11

PainCK160+796~CK

163+498Jining 95 0 0

12

Hills CK163+498~CK179+317

Chayouqianqi 404 0 0

13

Hills CK179+317~CK255+248

Zhuozi 3803 5267 8

14

Hills CK255+248~CK269+500

Hohhot 862 0 9

15

PlainCK269+500~CK

291+000Hohhot

480 273 0 0

16

HillsSections by

Second Jibaoline

Hohhot

17

PlainSection by Jingbao line(double line)

Hohhot195

Total 10032 2736053

6231

Page 32: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

4.3 Temporary protection measures for bridge and viaduct

(1) Temporary measures to deal with bored pile foundation mud for the bridge

To minimize the pollution of the water quality of the rivers along the line by the bridge

drilling mud, bored pile foundation of the bridge crossing river is usually constructed during

the dry season, and mud pump is installed in steel casing barrel to raise the drilling mud to

the land TWA at both ends. The slurry generated during the bored pile foundation

construction shall be temporarily processed to reduce soil erosion during construction.

There are a total of two bridges which cross a river and possess piers in the water in this

project. They are the extra large Yanghe Bridge and extra large No. 4 Daheihe Bridge. Before

the drilling of the piers, one mud pool (seepage control shall be done to the mud pond, and

multiple drilling can be shared) and two settling tanks are built in the temporary

construction site. They are used in series to make the wall protection mud separate from the

ballast. The mud precipitated shall be recycled, and the surface dust and ballast of the

sedimentation tanks shall be dehydrated at the dumping ground. The effluent of the

sedimentation tank discharges into natural rivers through the nearby agricultural irrigation

ditches. During the drilling and the hole cleaning in the pier foundation construction process,

mud cars are used to transport the mud to the designated location. The excavation earth

from mud pools and the sedimentation pond is piled near the pier and compacted. It will be

used in the pier foundation and the backfill of the mud pools and the sedimentation tanks

after the construction.

The volume of each mud pool is designed to be 8m3, and the length, width and depth to be

2m. The volume of each sedimentation tank is designed to be 6m3, the length and width 2m,

and the depth 1.5m.

Table 10 Bridge slurry pond and sedimentation tank

No

Landform Milestone AdministrationSlurry tank

Settling tank

1 Plain CK000+000~CK002+570 Zhangjiakou 2 4

Page 33: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

2Plain

CK002+570~CK011+260 Wangquan 0 0

3Plain

CK011+260~CK068+300 Huai’an 4 8

4 Hills CK068+300~CK073+310 Shangyi 0 0

5Hills

CK073+310~CK074+560 Xinghe 0 0

6Hills

CK074+560~CK076+900 Shangyi 0 0

7Hills

CK076+900~CK124+215 Xinghe 2 4

8Hills

CK124+215~CK151+080 Chanyouqianqi 2 4

9 Plain CK151+080~CK152+303 Jining 0 0

10 Pain CK152+303~CK160+796 Chayouqianqi 0 0

11 Pain CK160+796~CK163+498 Jining 0 0

12Hills

CK163+498~CK179+317 Chayouqianqi 0 0

13Hills

CK179+317~CK255+248 Zhuozi 1 2

14Hills

CK255+248~CK269+500 Hohhot 1 2

15 Plain CK269+500~CK291+000Hohhot

0 0

16 Hills Sections by Second JibaolineHohhot

0 0

17 Plain Section by Jingbao line(double line)Hohhot

0 0

Total 12 24

Page 34: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

(2) Temporary block and protection measures for excavation stone earth of the

foundation for bridges and culverts

Soil erosion is likely to occur for the excavation earth of the bridge foundation in the rainy or

windy season. Temporary block and protection measures shall be taken to prevent soil

erosion in the construction process.

After the balance of the excavation earthwork in the bridge foundation along the line in the

project, abandoned earth of 79.00 × 104m3 are resulted. Temporary stockpiling field shall be

set up in the land of the bridge. The temporary stockpiling height shall not be higher than

3.0m, and the pile slope rate shall be controlled within 1:1.5. The straw retaining wall

section shall be set in the form of a rectangular trapezoidal cross-section with height ×top

width× bottom width = 1.0m × 0.5m × 1.5m, and during the piling, the straws shall engage

and lap each other, with the lap length not less than the length of 1/3 of the straw.

Temporary stockpiling soil shall be centralized and piled in straw block protection. After the

construction, timely backfill and clean up shall be made, and extra earth shall be abandoned

in time in the earth fetching field nearby so as to avoid new soil erosion caused by rainfall

runoff or wind erosion.

Table 11 Temporary measures for foundation building for bridge and viaduct

NoLandform

Milestone Administration

Disposal

soils(m3

Fencing & retaining work

Soil bag

s(m3

)Grass bags

Geotextile(m2

)1 Plain

CK000+000~CK002+570

Zhangjiakou 15347 630 8820 6139

2Plain CK002+570~CK

011+260Wangquan 108965 4109 57526 43586

3Plain CK011+260~CK

068+300Huai’an 81116 3338 46732 32446

4 HillsCK068+300~CK

073+310Shangyi 0 0 0 0

Page 35: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

5Hills CK073+310~CK

074+560Xinghe 0 0 0 0

6Hills CK074+560~CK

076+900Shangyi 0 0 0 0

7Hills CK076+900~CK

124+215Xinghe 140464 5371 75194 56186

8Hills CK124+215~CK

151+080Chanyouqianqi 32915 1291 18074 13166

9 PlainCK151+080~CK

152+303Jining 0 0 0 0

10 PainCK152+303~CK

160+796Chayouqianqi 72139 2726 38164 28856

11 PainCK160+796~CK

163+498Jining 51758 2010 28140 20703

12Hills CK163+498~CK

179+317Chayouqianqi 16691 656 9184 6676

13Hills CK179+317~CK

255+248Zhuozi 154210 5871 82194 61684

14Hills CK255+248~CK

269+500Hohhot 70955 2703 37842 28382

15 PlainCK269+500~CK

291+000Hohhot

43035 13906 194684 17214

16 HillsSections by

Second Jibaoline

Hohhot0 0 0 0

17 PlainSection by

Jingbao line(double line)

Hohhot2483 136 1904 993

Total 790078 42747 598458 316031

(3) Protection measures in the construction of water piers

According to the actual situation of the project, water piers shall be set up in the river for the

new bridge across the river. Cofferdam measures shall be taken accordingly for the

foundation in the water according to the river channel, water depth, flow rate and venues.

Straw cofferdam and steel sheet pile cofferdam shall be mainly used to build island in the

construction for the project, and the construction period shall be as far as possible in the dry

Page 36: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

season. After the cofferdam is used to build an island in the river, the construction shall be

made in the island, and all waste ballast and waste water generated in the foundation

excavation shall be transported to shore through the island. They will not be leaked into the

river, and will not have a big impact on the water quality. When the construction is complete,

timely removal of the cofferdam shall be made, and all cofferdam facilities shall be

transported to the nearest designated spoil site for storage. They shall neither be dumped in

the river, nor flowed into the river downstream.

Table 12 Protection measures for bridge and viaduct

No

Landform

MilestoneAdministratio

n

Cone protectionConstruction

protection

M20 Concrete(m3)

M10 Concrete(m3)

M20 Concrete(m3)

M10 Concrete(m3

)1 Plain

CK000+000~CK002+570

Zhangjiakou 125 1413

2

Plai

nCK002+570~CK011

+260Wangquan 110 0 0

3

Plai

nCK011+260~CK068

+300Huai’an 1178

10375

200

4 HillsCK068+300~CK073

+310Shangyi

5Hills CK073+310~CK074

+560Xinghe

6Hills CK074+560~CK076

+900Shangyi

Page 37: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

No

Landform

MilestoneAdministratio

n

Cone protectionConstruction

protection

M20 Concrete(m3)

M10 Concrete(m3)

M20 Concrete(m3)

M10 Concrete(m3

)7

Hills CK076+900~CK124+215

Xinghe 2099 8181 14

8Hills CK124+215~CK151

+080Chanyouqianqi 545

35300

0

9 PlainCK151+080~CK152

+303Jining

10

PainCK152+303~CK160

+796Chayouqianqi 137 0 0

11

PainCK160+796~CK163

+498Jining 95 0 0

12

Hills CK163+498~CK179+317

Chayouqianqi 404 0 0

13

Hills CK179+317~CK255+248

Zhuozi 3803 5267 8

14

Hills CK255+248~CK269+500

Hohhot 862 0 9

15

PlainCK269+500~CK291

+000Hohhot

480 273 0 0

16

HillsSections by Second

Jibaoline

Hohhot

17

PlainSection by Jingbao line(double line)

Hohhot195

Total 10032 2736053

6231

5. Control Measures in Tunnel Works Area

There are 25 new tunnels in a length of 59.66km built in this project. The new tunnels are

concentrated in the lots of mountainous and hilly areas. The longest tunnel is Dajianshan

Tunnel in a length of 15,390m. The excavation of these new tunnels seeks early hole, and to

Page 38: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

avoid deep cutting or high slope so as to minimize the destruction of the mountain and to

prevent soil erosion.

If the tunnel is longer than 500m, dual-port tunneling will be generally used; if the tunnel

length is less than 500m, single-port tunneling will be generally used. For Grade Ⅳ swelling

rock lots, if the expansion of the rock is medium to strong and the rock is shallow buried, the

method of "temporary invert of three steps " will be used; if the expansion is medium to

strong, the method of " temporary lateral bracket of three steps" will be used; weak

expansion lots shall as far as possible use the "three-step method" to strengthen the lock pin

bolt, and to strengthen the monitoring of measurement, so as to reduce the temporary

support works. For the lots of GradeⅤexpansion rock, the shallow buried section shall adopt

the method of "temporary invert of three steps"; and the deep buried segment may adopt the

method of " temporary lateral bracket of three steps" to reduce the temporary support

works. The ultra-shallow, or seriously pressured lots or sections which have to go through

buildings that require protection shall adopt the method of "CRD"; collapsible loess sections

shall try to use open-cut method, and the lots which require covered tunneling shall use the

method of "CRD".

5.1 Tunnel body protection

Tunnel entrance shall be chosen to minimize the excavation height of the side invert slope to

reduce the excavation, and the destruction of land and vegetation. Top-down stratified

excavation and layered protection shall be taken during the hole earthwork construction. In

case of poor geological conditions, measures to stabilize the side slope and the invert slope

shall be taken. The tunnel waterproofing and drainage shall follow the principle of "the

combination of prevention, disconnection, discharge and block for local conditions and in

comprehensive management", if necessary, the principle of "block-based, limited discharge"

shall be taken. Appropriate control measures shall be taken according to the tunnel length,

weather conditions, the nature and degree of development of groundwater to protect the

ecological environment. Fully enclosed lining of tunnel entrances of soil, swelling rock (soil),

Page 39: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

and schist formation is adopted for the protection of side invert slopes at the entrance; the

rest of the stone tunnels shall be protected at the entrances and within 2m of the foot of the

slope. 30cm thick M15 mortar rubble lining shall be used.

Drainage ditches shall be located at the tunnel roof, with the distance of the drainage ditches

from the stone at the top of the slop excavation line not less than 5m. The soil shall not be

less than 10m so as to intercept surface water so that it may be imported into the subgrade

drainage system, thus avoiding the formation of new erosion.

5.2 Tunnel spoil protection

The spoil of the new tunnels totals 958.12×104m3. The spoil field shall be selected to heap

the abandoned spoil based on the factors like topographical conditions near the tunnel along

the line and transport distance.

Retaining wall shall be located at the foot of the slope for the spoil field, and protected by

mortar rubble for the foundation. After the disposable ballast is carried out, reclamation and

afforestation shall be conducted, and waterproofing and drainage facilities shall be equipped

to prevent soil erosion, and reduce the impact from drop ballast on the surrounding

environment.

Page 40: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Table 13 Tunnel portal protection and drainage measures

No

Landform

MilestoneAdministratio

n

Tunnel

length(m

Tunnel numbe

r

Tunnel portal, gutter and greening

Interception gutter Dike Greening

C25 Concrete(m3)

M10 Concrete(m3)

Soil stone refil

l(m3

Planting

soil(m3)

Bushes

1 Plain CK000+000~CK002+570 Zhangjiakou

2Plain

CK002+570~CK011+260 Wangquan

3Plain

CK011+260~CK068+300 Huai’an

15390 1 1482 1421 969 4335 4335

4 Hills CK068+300~CK073+310 Shangyi

5Hills

CK073+310~CK074+560 Xinghe

6Hills

CK074+560~CK076+900 Shangyi

7Hills

CK076+900~CK124+215 Xinghe 5529 3 532 510 348 1558 1558

8Hills

CK124+215~CK151+080 Chanyouqianqi 3470 2 334 320 219 978 978

Page 41: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

9 Plain CK151+080~CK152+303 Jining

10 Pain CK152+303~CK160+796 Chayouqianqi

11 Pain CK160+796~CK163+498 Jining

12Hills

CK163+498~CK179+317 Chayouqianqi 6602 4 636 609 416 1860 1860

13Hills

CK179+317~CK255+248 Zhuozi 27328 14 2631 2523 1721 7698 7698

14Hills

CK255+248~CK269+500 Hohhot 1337 1 129 123 84 377 377

15 Plain CK269+500~CK291+000Hohhot

16 Hills Sections by Second JibaolineHohhot

17 Plain Section by Jingbao line(double line)Hohhot

Total 59655 25 5743 5507 3757 16805 16805

Page 42: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

6. Control Measures in Earth-fetching Area

6.1 Earth-fetching field set-up and optimizations

The earth-fetching fields set up along the line are mainly for the earth fetching of subgrade

and station, and the main type of land is unused land. In the earth excavation works, in the

spirit of the principle of concentrated earth fetching, the construction shall be made in

accordance with the position of earth-fetching field designed. The expansion of the

excavation area is not allowed, and flayer earth is strictly prohibited. The 0~30cm surface of

the earth-fetching field is prohibited to be used as fill. The surface layer shall be cleared and

stacked before earth fetching, and when the earthwork is completed, then they shall be

backfilled to the earth pit. Excavator with a dump truck is used to fetch the earth layer by

layer. It is proposed that if the excavation of soil complies with the requirements of packing,

the slope rate shall be slowed down, and the earth excavation depth may be enhanced to

reduce the project disturbance area. After the completion of the earth fetching, the slope of

the earth field shall be cut in a gradient of 1:1.5, and the slope shall be slowed down to

facilitate construction operations in an economic and safe way in preventing collapse and

soil erosion. Clean, flatting, green and other necessary measures shall be taken. In the next

stage of design, each earth field is required to sign an agreement on fetching and abandoning

of soil with the local Land and Resources Bureau.

6.2 Earth fetching and protection principles

1) The centralized and close earth fetching shall be carried out, and the priority in the

use of the existing earth field shall be made.

2) The selection of the earth field location shall obtain the coordination of the local

government and the soil and water conservation authority. The locacation shall be

determined through the consultation in the unified planning of the soil and water

conservation department based on the local water resources, agricultural

development planning, and environmental construction plan.

Page 43: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

3) For the sloping earth field, after earth fetching, the slope of the excavation area shall

be adjusted, the bottom shall be cleaned and leveled, and green measures of shrub

planting shall be taken.

4) For the earth field ready to restore planting, before earth fetching, the surface

mellow soil shall be pushed aside, and leveled back after earth fetching. Reasonable

temporary protective measures shall be taken according to the terrain of the

temporary dump.

6.3 Earth field slope cutting and drainage design

In the excavation and earth fetching, the expansion of the disturbance area shall be avoided,

and the lane in a width of 10m and a longitudinal slope rate of 1:5 shall be reserved for the

access of the earth fetching pit. The lane shall stay in the side facing the construction area,

and the slope rate shall take 1: 1.5. The slope shall be cut by half-dug and half-fill to the limit

of 1/ 2 of the excavation depth. The upper earth of cut slope shall be used to fill the lower

slope, and the fill slope shall be backfilled and compacted layer by layer. To intercept the

slope runoff, and protect the overhead slope formed during earth fetching from directly

impact of wind and water erosion, a retaining ridge in a height of 80cm and a top width of

50cm shall be built beyond the upper sloping shoulder of the earth field, and intercepting

drains shall be located at the outside close to the retaining ridge so that the runoff above the

top of the slope will be channeled to both sides, then discharged to the close ditches. The

intercepting ditch has a bottom width of 0.5m, a top width of 1.5m, and a depth of 0.6m. The

soil ditches of semi-filled and semi- dug section shall be adopted and interior wall shall be

compacted. Base gutters in a bottom width of 50cm, a depth of 50cm, and a top width of 1m

shall be located at 1m outside the foot of the slope. Soil ditches shall be used, and interior

wall shall be compacted. If the slope has two platforms, the platform shall be an invert slop

directing toward interior side, namely, the side of the second slope, so as to create

conditions for the casing and the drainage in the future. Meanwhile, drains shall be located in

the middle platform and the foot of the secondary slope to discharge the slope runoff. The

Page 44: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

water in the drains in the middle platform will flow down to lead the rainfall runoff into

natural ditches or the existing drainage ditch system. The drains in the foot of the secondary

slope shall adopt the same design standard with drains at the bottom of the slope.

6.4 Plant protection measures in the earth field

After the fetching in the earth field is completed, and when the engineering measures such as

slope adjustment of excavation area, leveling and cleaning of the underside, casing (casing

source is the topsoil stripped before earth fetching, and the casing thickness is about 30cm),

appropriate plant protection measures shall be taken on the bottom of the fetching pit, side

slope and platform. Through the green initiatives of sowing grass seed, planting shrubs, and

conservation and management measures of watering, fertilizing, and soil moisture to ensure

seedling survival rate, the purposes of soil and water conservation and the erosion control

may be achieved. The shrub spacing is 1 × 1m.

A total of 121.00hm2 rehabilitation area will be adopted for the earth fields across the line,

270,000 shrubs will be planted, and 88.60hm2 grass seed will be spread.

6.5 Temporary protection measures of stripped topsoil in the earth field

Before the fetching in the earth field, the 0~30cm surface layer of mellow soil shall be

scooped and stacked within the earth field. No new temporary area shall be used. The

bottom of the stockpiled soil shall be protected with temporary straw. The surface of the

temporary stockpiling shall be smooth and compacted and covered with a tarp to prevent

the erosion of rain runoff. Temporary soil drains shall be set up around the foot of the

stockpiling slope, so that the water collected may be discharged into the existing drainage

system around to prevent the new soil erosion. After completion of the earth fetching, the

topsoil shall be backfilled and leveled to facilitate the reclamation and revegetation.

A total of 32.40×104m3 topsoil is stripped in the earth fields across the line, with the

temporary block retaining length of 12, 585m, the stripping topsoil covering tarpaulin of

129,600m2, temporary drains of 4401m3, and temporary settling basins of 33.

Page 45: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Table 14 Protection Measures for Borrow pits

No Administration Location

Area(hm2

)Soils

amount(m3)

Re-vegetation and planting protection

Temporary measures for stripping tops soils

Leveling

(hm2)Bushes

Grassing(m2)

Top soil

s(m3)Temp

retaining lengt

h(m)

Soils in bag

s(m3

)Grass

bag(Nr)

Paulin(m2)

Temp drainage(m3)

Temp settling

tank(Nr)

1 Wanquan, Taishizhuang CK5+000 left 5000m 2.00 64212 2.00 0 20000 0 0 0 0 0 0 0

2 Huai’an Chunfa Company CK25+000 right 2000m 4.00 185330 4.00 0 40000 0 0 0 0 0 0 0

3 Huai’an Nanxingtun CK35+500 left 2500m 6.67 293970 6.67 16667 46667 20000 727 727 10178 8000 0 0

4 Huai’an Lijiayao CK37+300 left 3000m 4.67 164408 4.67 11667 32667 14000 584 584 8176 5600 0 0

5 Huai’an Dukoupu, Caijiantan CK51+000 left 60m 4.00 180000 4.00 10000 28000 12000 454 454 6356 4800 0 0

6 Huai’an Dukoupu, Manzhoupo CK57+000 right 1000m 2.00 81177 2.00 5000 14000 6000 227 227 3178 2400 0 0

7 Xinghe, Chengguan, Gaomiaozi CK80+600left1500m 2.67 95967 2.67 6667 18667 8000 357 357 4998 3200 184 1

8 Xinghe, Chengguan, Qijia CK91+000 right 300m 1.00 83527 1.00 2500 7000 3000 156 156 2184 1200 73 1

9 Xinghe, Chengguan, Mqiaocun CK93+400 right 200m 1.00 12481 1.00 2500 7000 3000 156 156 2184 1200 73 1

10 Xinghe, Chengguan, Haoqiancun CK99+200 right 800m 4.00 110410 4.00 10000 28000 12000 454 454 6356 4800 262 2

11 Xinghe, Chengguan, Dongshihao CK103+000 left 2000m 4.00 86408 4.00 10000 28000 12000 454 454 6356 4800 262 2

12Xinghe, Minzutuanjiexiang,

SihihaocunCK110+400 left 1000m 2.00 45025 2.00 0 20000 0 0 0 0 0 0 0

13 Xinghe, e’erdong, Dianzicun CK112+000 left 200m 1.00 21570 1.00 2500 7000 3000 156 156 2184 1200 73 1

14Xinghe, e’erdong,

DianzicunCK114+000 right 200m 1.67 29456 1.67 4167 11667 5000 192 192 2688 2000 110 1

15Xinghe, e’erdong,

DianzicunCK117+000~+300 left hill 3.33 46570 3.33 8333 23333 10000 409 409 5726 4000 224 2

16Chayouqianqi, Pingdiquanzhen,

LaijiadicunCK166+100~+500 right hill 13.33 105476 13.33 33333 93333 40000 1544 1544 21616 16000 878 7

17Zhuozi, Shibataizhen,

YushugoucunCK188+000~+600 right hill 3.33 96669 3.33 8333 23333 10000 409 409 5726 4000 224 2

18Zhuozi,

Shibataizhen,hafengjingcunCK190+000~CK195+000left hill 6.67 53345 6.67 16667 46667 20000 727 727 10178 8000 431 3

19 Zhuozi, Zhuozishan, Dongtan CK205+100~CK206+600 right hill 6.67 54583 6.67 16667 46667 20000 727 727 10178 8000 431 3

20 Zhuozi, Lihuazhen, Sidaogou CK247+050left2000m 4.00 173341 4.00 10000 28000 12000 454 454 6356 4800 262 2

21Hohhot, Saihan, Yulin,

ShimengouCK261+350left3500m 14.00 155089 14.00 35000 98000 42000 1589 1589 22246 16800 916 7

22 Hohhot, Saihan, Yulin, CK267+100 right 3200m 5.00 86160 5.00 0 50000 0 0 0 0 0 0 0

Page 46: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Sanyingyao

23Hohhot, Saihan,

Yulin,QiannaimobancunCK274+200left2200m 12.67 182043 12.67 31667 88667 38000 1492 1492 20888 15200 0 0

24Hohhot, Saihan, Bayan,

TengjiayingCK280+000left2100m 11.33 97144 11.33 28333 79333 34000 1317 1317 18438 13600 0 0

Total 121.00 2504360 121.00 270000 886000 324000 12585 12585 176190 129600 4401 33

Page 47: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

7. Disposal Sites

7.1 Earth disposal site

There are 18 earth disposal sites, total earth disposed will be 4320700m3, occupying

54.8hm2.

7.2 Tunnel spoils disposal site

There will be 52 spoil disposal sites, total spoils disposed will be 10726400m3, occupying

121.21hm2.

7.3 Design of retaining wall

On the principle of “Firstly retaining and then discarding and retaining by grading”, adopt

mortar flag stone gravity type retaining wall protection for spoil ground.

To decrease active earth pressure, inclined type is adopted for gravity type retaining wall

this time. When designed, height of retaining wall is 4 to 8m. When change occurs on height

of wall, rectigradation transition is adopted for size of wall body; slope ratio of wall back is

1:0.25; wall surface is paralleled with wall back. Retaining wall is adopted for retaining base

of ballast slope. Embedded depth of foundation is not lower than 2.0m. The part below

ground of wall body is made into step-form, to increase stability of wall body; basement is

made into reverse slope, to increase resisting overturning ability of wall body.

100 PVC pipe is embedded for retaining wall body and is used as escape hole, distance is φ

2m×2m. Intercepting ditch and drainage ditch is set at ballast top. Bottom part of ditch must

be backfilled densely. Set one settlement joint each 10m longitudinally for the ditch; width of

joint is 2~3cm. For earthy spoil, filtration bed of crushed stone with width of about 500mm

needs to be set behind wall to facilitate drainage and avoid elapse of fine soil in earth filling.

Set blind drain in the middle of wall body with bigger height.

7.4 Drainage design

Drainage shall be provided at the top and foot of the disposal sites in order to timely discharge

runoff to avoid soil erosion and threats to the retaining wall.

Page 48: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

7.5 Design of spoil grounds leveling and earth backing

After spoil is completed, top part of spoil ballast should be leveled. To facilitate recovery of

vegetation, mature soil of certain thickness should be covered onto soil body and buffer top

after leveled; earth backing comes from stripped surface soil of spoil grounds.

7.6 Reclamation and greening design for spoil grounds

After site leveling and earth backing work is completed for spoil, through combining local

actual situation, adopt reclamation measure for spoil grounds occupying fallow land for the

project and adopt protection measure of grass planting and shrub planting for spoil grounds

occupying timberland and not using land.

7.7 Design of temporary retaining measure for stripped surface soil for

spoil grounds

For spoil grounds where vegetation recovery is to be made, before spoil, shovel mature soil

by about 0~30cm of surface and stack them within the scope of spoil grounds without newly

increasing occupied area. Temporary straw bag is adopted for retaining bottom part of

stacked soil. Level and compact surface of temporary stacked soil, use fabric for covering and

build drainage ditch for temporary soil and make rainfall runoff influx before make it be

successfully discharged into surrounding trench and other existing drainage system, to avoid

causing new soil and water erosion. After spoil project is completed, level soil body and

buffer, cover stripped surface soil, to facilitate land reclamation and greening.

Page 49: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Table 15 Site specific management of soil disposal sites

No

Administration Location

Area(hm

2)

Disposal

quantity(m3

Disposal

depth(m)

Clearance and

leveling (hm2)

Retaining and fencing

Greening Temporary measures for stripping tops soils

C25 Retainin

g wal

l(m3)

C25 Concret

e drainage(m3

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

Temp. drainage(m3

Temp settlin

g tan

k(Nr

)1 Huai’an, Dukoubao, Caijiantan CK52+100left60m 2.00 150223 7.51 2.00 257 172 5000 14000 6000 227 227 3178 2400 0 0

2 Xinghe, Chengguan, Qinjiaaocun CK77+750left400m 5.33 306181 5.74 5.33 606 404 13333 37333 16000 650 650 9100 6400 357 3

3 Xinghe, Chengguan, Qinjiaaocun CK82+200left1500m 2.00 153091 7.65 2.00 262 175 5000 14000 6000 227 227 3178 2400 131 1

4 Xinghe, Chengguan, Qinjiaaocun CK83+100left100m 2.00 102060 5.10 2.00 198 132 5000 14000 6000 227 227 3178 2400 131 1

5 Xinghe, Chengguan, yangpocun CK85+300 right 300m 2.00 153091 7.65 2.00 262 175 5000 14000 6000 227 227 3178 2400 131 1

6 Xinghe, Chengguan, yangpocun CK88+600 right 300m 6.67 408241 6.12 6.67 1140 760 16667 46667 20000 811 8111135

48000 446 3

7 Xinghe, Chengguan, Qijiacun CK91+000 right 300m 4.67 255151 5.47 4.67 495 330 11667 32667 14000 584 584 8176 5600 315 2

8 Xinghe, Chengguan, Maqiaocun CK93+400 right 200m 2.00 159700 7.99 2.00 237 158 5000 14000 6000 227 227 3178 2400 131 1

9 Xinghe, Chengguan, Haoqiancun CK99+200 right 800m 5.33 425601 7.98 5.33 724 483 13333 37333 16000 636 636 8904 6400 354 3

10

Xinghe, Chengguan, Dongshihaocun

CK103+400 right 200m 6.67 532600 7.99 6.67 257 172 16667 46667 20000 811 8111135

48000 446 3

11

Xinghe, Chengguan, Dongshihaocun

CK107+500left1500m 2.00 159700 7.99 2.00 267 178 5000 14000 6000 227 227 3178 2400 131 1

12

Zhuozi, Shibatai, HuangqitancunCK183+000~CK184+000 right

240m4.00 316693 7.92 4.00 627 418 10000 28000 12000 454 454 6356 4800 262 2

13

Zhuozi, bayinxile, Dahaicun CK197+000~CK198+000left山沟 4.00 334780 8.37 4.00 663 442 10000 28000 12000 454 454 6356 4800 262 2

14

Zhuozi, Lihuazhen, Tuchengzi CK233+500left50m 1.13 53345 4.71 1.13 103 69 2833 7933 3400 176 176 2464 1360 83 1

15

Zhuozi, Qixiaying, Lvmeiping CK252+750 2.00 247022 12.35 2.00 479 320 5000 14000 6000 227 227 3178 2400 131 1

16

Zhuozi, Qixiaying, Lvmeiping CK254+330 0.67 197618 29.64 0.67 0 0 1667 4667 2000 130 130 1820 800 53 0

17

Sihanqu, Yulinzhen, Shihaoyao CK256+400 1.67 247022 14.82 1.67 479 320 4167 11667 5000 220 220 3080 2000 115 1

18

Sihanqu, Yulinzhen,Sanhaoyao CK257+120 0.67 118571 17.79 0.67 0 0 1667 4667 2000 130 130 1820 800 53 0

Page 50: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Total 54.80432068

854.8 7060 4707

137000

383600

164400

6645 66459303

06576

03531 26

Page 51: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Table 16 Mitigation measures for spoils disposal sites 

No

Spoils disposal site and location

Area(hm2)

Disposal quantity(m3

)Disposal

depth(m)

Clearance and

leveling (hm2)

Greening measures Retaining and fencing Temporary measures for stripping tops soils

Re-vegetation(hm2)

BushesGrassing(m2)

M10 retaining wall(m3)

M10 interception and drainage

(m3)

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

)Temp.

drainage(m3)

Temp settling

tank(Nr

)1 Dajianshan Portal entrance 393931 4.18 9.43 4.18 3.84 833 2333 3652 4173 12532 459 459 6426 5013 0 0

2 Dajianshan #1shaft 366082 4.00 9.16 4.00 3.86 333 933 3393 3878 11986 454 454 6356 4795 0 0

3 Dajianshan #2 shaft 488109 5.40 9.04 5.40 5.26 333 933 4525 5171 16190 668 668 9352 6476 217 3

4 Dajianshan #3 shaft 488109 5.32 9.17 5.32 5.19 333 933 4525 5171 15970 651 651 9114 6388 213 3

5 Dajianshan4 shaft 390487 4.60 8.50 4.60 4.46 333 933 3620 4137 13789 461 461 6454 5516 166 2

6 Dajianshan exit 341676 4.14 8.25 4.14 3.81 833 2333 3167 3620 12421 458 458 6412 4968 157 2

7 Xishihao entrance 102493 1.23 8.31 1.23 0.90 833 2333 950 1086 3701 154 154 2156 1481 50 1

8 Xishihao exist 108662 1.30 8.39 1.30 0.96 833 2333 1007 1151 3886 155 155 2170 1555 51 1

9 Dalianggou entrance 95274 1.29 7.41 1.29 0.95 833 2333 883 1009 3857 155 155 2170 1543 51 1

10 Dalianggou exit 95274 1.29 7.41 1.29 0.95 833 2333 883 1009 3857 155 155 2170 1543 51 1

11 Jiabazi entrance 270393 3.04 8.91 3.04 2.70 833 2333 2506 2864 9108 373 373 5222 3643 122 2

12 Jiabazi exit 270393 3.04 8.91 3.04 2.70 833 2333 2506 2864 9108 373 373 5222 3643 122 2

13 Xiying Entrance 125758 1.43 8.81 1.43 1.09 833 2333 1166 1332 4282 170 170 2380 1713 56 1

14 Xiying exit 125758 1.43 8.81 1.43 1.09 833 2333 1166 1332 4282 170 170 2380 1713 56 1

15 Liujiagou entrance 205184 2.21 9.27 2.21 1.88 833 2333 1902 2174 6642 232 232 3248 2657 82 1

16 Liujiagou exit 205184 2.21 9.27 2.21 1.88 833 2333 1902 2174 6642 232 232 3248 2657 82 1

17 Dongtukan entrance 291957 3.40 8.59 3.40 3.06 833 2333 2706 3093 10194 411 411 5754 4078 135 2

18 Dongtukan 1 shaft 208541 2.47 8.43 2.47 2.14 833 2333 1933 2209 7420 252 252 3528 2968 90 1

19 Dongtukan exit 250249 2.98 8.40 2.98 2.65 833 2333 2320 2651 8939 407 407 5698 3576 127 1

20 Yiyuanxing entrance 83416 1.24 6.75 1.24 0.90 833 2333 773 884 3709 155 155 2170 1484 50 1

21 Xituken entrance 47974 0.81 5.90 0.81 0.48 833 2333 445 508 2439 152 152 2128 975 63 1

22 Xituken exit 47974 0.81 5.90 0.81 0.48 833 2333 445 508 2439 152 152 2128 975 63 1

23 Lujiabuzi entrance 55967 0.89 6.27 0.89 0.56 833 2333 519 593 2678 154 154 2156 1071 64 1

Page 52: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

No

Spoils disposal site and location

Area(hm2)

Disposal quantity(m3

)Disposal

depth(m)

Clearance and

leveling (hm2)

Greening measures Retaining and fencing Temporary measures for stripping tops soils

Re-vegetation(hm2)

BushesGrassing(m2)

M10 retaining wall(m3)

M10 interception and drainage

(m3)

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

)Temp.

drainage(m3)

Temp settling

tank(Nr

)24 Lujiabuzi exit 55967 0.89 6.27 0.89 0.56 833 2333 519 593 2678 154 154 2156 1071 64 1

25 Dabaiying entrance 77703 1.11 7.00 1.11 0.78 833 2333 720 823 3330 190 190 2660 1332 54 1

26 Dabaiying exit 77703 1.11 7.00 1.11 0.78 833 2333 720 823 3330 190 190 2660 1332 54 1

27 Gonghudong entrance 134163 1.47 9.10 1.47 1.14 833 2333 1244 1421 4422 200 200 2800 1769 63 1

28 Gonghudong exit 137385 1.54 8.91 1.54 1.21 833 2333 1274 1455 4628 202 202 2828 1851 64 1

29 Gujiapu entrance 286170 3.19 8.96 3.19 2.86 833 2333 2653 3032 9581 421 421 5894 3832 133 2

30 Gujiapu exit 279705 3.13 8.94 3.13 2.80 833 2333 2593 2963 9387 247 247 3458 3755 101 2

31 Zhangjiabu entrance 151262 1.85 8.20 1.85 1.51 833 2333 1402 1602 5536 210 210 2940 2214 71 1

32 Zhangjiabu exit 146358 1.80 8.15 1.80 1.46 833 2333 1357 1550 5389 210 210 2940 2155 70 1

33 Chengbuzi entrance 59830 0.79 7.59 0.79 0.45 833 2333 555 634 2365 150 150 2100 946 63 1

34 Chengbuzi exit 59769 0.79 7.59 0.79 0.45 833 2333 554 633 2363 150 150 2100 945 63 1

35 Baliang exit 71736 1.05 6.83 1.05 0.72 833 2333 665 760 3151 158 158 2212 1260 47 1

36 Mogaitu entrance 75452 1.09 6.94 1.09 0.75 833 2333 699 799 3262 160 160 2240 1305 48 1

37 Mogaitu exit 74991 1.08 6.93 1.08 0.75 833 2333 695 794 3249 160 160 2240 1299 48 1

38 Daxigou entrance 72639 1.06 6.86 1.06 0.73 833 2333 673 770 3178 160 160 2240 1271 48 1

39 Liangshanentrance 261510 2.95 8.87 2.95 2.61 833 2333 2424 2770 8841 381 381 5334 3537 122 1

40 Liangshan #1 shaft 345935 3.76 9.20 3.76 3.51 833 2333 3207 3665 11284 421 421 5894 4514 143 2

41 Liangshan #2 shaft 334138 3.72 8.97 3.72 3.32 833 2333 3097 3540 11174 421 421 5894 4470 143 2

42 Liangshan exit 320321 3.22 9.96 3.22 2.88 833 2333 2969 3393 9645 405 405 5670 3858 131 2

43 Naobaowan exit 176441 1.77 9.97 1.77 1.44 833 2333 1636 1869 5308 194 194 2716 2123 67 1

44 Xiaopingdingshan entrance 483905 4.85 9.97 4.85 4.52 833 2333 4486 5126 14556 606 606 8484 5822 196 2

45 Xiaopingdingshan exit 631537 6.32 9.99 6.32 5.99 833 2333 5854 6690 18970 704 704 9856 7588 241 3

46 Shanghaocun exit 76994 0.94 8.17 0.94 0.61 833 2333 714 816 2829 156 156 2184 1132 64 1

47 Duguigou entrance 181011 1.92 9.42 1.92 1.59 833 2333 1678 1918 5763 227 227 3178 2305 75 1

48 Duguigou exit 181011 1.92 9.42 1.92 1.59 833 2333 1678 1918 5763 227 227 3178 2305 75 1

Page 53: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

No

Spoils disposal site and location

Area(hm2)

Disposal quantity(m3

)Disposal

depth(m)

Clearance and

leveling (hm2)

Greening measures Retaining and fencing Temporary measures for stripping tops soils

Re-vegetation(hm2)

BushesGrassing(m2)

M10 retaining wall(m3)

M10 interception and drainage

(m3)

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

Top soil

s(m3

)Temp.

drainage(m3)

Temp settling

tank(Nr

)49 Xiaobaiyangou entrance 286937 2.89 9.92 2.89 2.56 833 2333 2660 3040 8681 379 379 5306 3472 120 1

50 Xiaobaiyangou exit 288168 2.89 9.96 2.89 2.56 833 2333 2671 3053 8681 379 379 5306 3472 120 1

51 Quyangyaogou entrance 168070 1.71 9.83 1.71 1.38 833 2333 1558 1780 5129 206 206 2884 2052 68 1

52 Quyangyaogou exit 170705 1.71 9.98 1.71 1.38 833 2333 1582 1808 5129 206 206 2884 2052 68 1

Total 10726363 121.22 438.17 121.22 104.70 41333 115733 99429 113632 363673 14877 14877 208278 145469 4694 61

Page 54: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

8. Access Roads

Because of construction vehicles rolling, surface of construction detour is disturbed,

vegetation is being destroyed and soil and water erosion will be easily produced. Therefore,

we put forward following prevention and treatment measure and suggestions for

construction detour soil and water erosion:

(1) Fully use existing rural road and road as transportation road, decrease quantity and

length of newly built road. For newly built construction detour, reasonably plan strike

direction, length and width of construction detour, decrease disturbance scope on surface,

control soil and water erosion.

(2) When constructing construction detour, through combining relief and existing traffic

condition, we should set it through combining construction of incoming road and rural road

as possible. Adopt road building scheme with small influence of disturbing surface. Decrease

excavation and fill on large scale. Spoil ballast produced from construction detour should be

removed and used for being filled and be allocated and used. Spoil which cannot be allocated

should be discarded into centralized earth-fetching area of main project design.

(3) During building process of road, strengthen retaining measure for excavated

earthwork and slope and avoid entrance of soil and ballast into farmland, to avoid causing

soil and water erosion .

(4) Construction detour should be set within land expropriation scope of railway as

possible. Try to avoid crossing forestry grass land with high coverage rate of vegetation.

(5) Waste earthwork produced from developing construction detour must be timely

cleaned and unitively handled. Do not freely discard because it will provide loose soil source

to soil and water erosion. Strictly regulate drive route of vehicles during construction

process.

(6) After use of construction detour is completed, we should negotiate with local relative

departments according to actual situation. Try to make construction detour used locally and

Page 55: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

make it further used as maintenance road of railway. For road which cannot be used, adopt

site control measures of cleaning and leveling according to concrete situation and adopt

plant protection measure of planting shrubs and spreading grass seed for restoration.

After construction is ended, the area needing to be cleaned and leveled is 46.27hm2 for

prevention and treatment of construction detour; the area spreading grass seed reaches

46.27hm2.

Page 56: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Table 17 Management of access roads

No Landform 起讫里程 Administration Area(hm2)Length(km) Clearance

and levelin

g(hm2)Grassin

g(hm2)Single track

Double track

1 Plain CK000+000~CK002+570 Zhangjiakou 0.00 0.00 0.00 0.00 0.00

2Plain

CK002+570~CK011+260 Wangquan 0.52 0.60 0.30 0.52 0.52

3Plain

CK011+260~CK068+300 Huai’an 5.90 7.00 3.00 5.90 5.90

4 Hills CK068+300~CK073+310Shangyi

Xinghe0.57 0.60 0.40 0.57 0.57

5Hills

CK074+560~CK076+900

6Hills

CK073+310~CK074+560Shangyi

Xinghe5.90 7.00 3.00 5.90 5.90

7Hills

CK076+900~CK124+215

8Hills

CK124+215~CK151+080 Chanyouqianqi

Jining8.26 9.80 4.20 8.26 8.26

9 Plain CK163+498~CK179+317

10 Pain CK151+080~CK152+303 Chayouqianqi

Jining1.18 1.40 0.60 1.18 1.18

11 Pain CK160+796~CK163+498

Page 57: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

12Hills

CK152+303~CK160+796 Chayouqianqi 2.36 2.80 1.20 2.36 2.36

13Hills

CK179+317~CK255+248 Zhuozi 14.38 16.80 7.70 14.38 14.38

14Hills

CK255+248~CK269+500 Hohhot 4.85 5.80 2.40 4.85 4.85

15 Plain CK269+500~CK291+000Hohhot

2.36 2.80 1.20 2.36 2.36

16 Hills Sections by Second JibaolineHohhot

0.00 0.00 0.00 0.00 0.00

17 Plain Section by Jingbao line(double line) Zhangjiakou 0.00 0.00 0.00 0.00 0.00

Total 46.27 54.60 24.00 46.27 46.27

Page 58: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

9. Prevention and Treatment Measure for Manufacturing and Living Area for

Construction

Because of influence of artificial activities at construction site and camp site, surface

vegetation and soil structure within land use scope of site and camp site will be easily

destroyed, and it will cause losing original soil and water conservation function. Therefore,

following protection measures should be adopted:

(1) When select address for construction site, under the premise meeting principle

of proximity, try to use surrounding idle site or uncropped soil. Build of manufacturing and

living houses at construction site, tools and stone material stacking and material processing

site and arrangement of all other temporary manufacturing and living facilities should be

guaranteed reasonable, tidy and orderly. Try to more use local existing place, avoid

occupying more land caused by casualness of temporary project building and avoid

damaging soil and water conservation function.

(2) Definitely set position and scope of construction site and camp site. Do not freely

expand scope during construction process and not freely change address. Avoid occupying

more land caused by fluidity of engineering construction and clarify environmental

protection responsibility of construction site.

(3) After construction is ended, temporary facilities built during construction

process should be handed to local government through combining opinion from local

government. Clean waste from construction site and camp site surface and carry out

necessary leveling. Adopt vegetation measure of spreading grass for ground which can be

greened and recover its soil and water conservation function.

After construction is ended, adopt cleaning and leveling measure for temporarily occupied

construction site and camp site for the project and involved area reaches 147.99hm2, the

area spreading grass seed is147.99hm2.

Page 59: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall

Table 18 Management of Construction field`

NoLandfor

mMilestone Admnistration

Are

a(hm2

Clearance and levelin

g(hm2

Grassin

g(hm2

1Plain

CK000+000~CK002+570Zhangjiakou

0 0 0

2 Plain CK002+570~CK011+260Wangquan

1.19 1.19 1.19

3 Plain CK011+260~CK068+300Huai’an

38.15 38.15 38.15

4Hills

CK068+300~CK073+310

Shangyi

Xinghe

2.37 2.37 2.375 Hills CK074+560~CK076+900

6 Hills CK073+310~CK074+560

Shangyi

Xinghe

17.56 17.56 17.56

7 Hills CK076+900~CK124+215

8 Hills CK124+215~CK151+080Chanyouqianqi

Jining

36.68 36.68 36.68

9Plain

CK163+498~CK179+317

10Pain

CK151+080~CK152+303Chayouqianqi

Jining

1.19 1.19 1.1911

PainCK160+796~CK163+498

12 Hills CK152+303~CK160+796Chayouqianqi

1.47 1.47 1.47

13 Hills CK179+317~CK255+248Zhuozi

30.36 30.36 30.36

14 Hills CK255+248~CK269+500Hohhot

16.37 16.37 16.37

15Plain

CK269+500~CK291+000 Hohhot 2.65 2.65 2.65

16Hills Sections by Second Jibaoline

Hohhot 0 0 0

17Plain

Section by Jingbao line(double line)

Hohhot 0 0 0

Total 147.99 147.99 147.99

Page 60: documents.worldbank.orgdocuments.worldbank.org/curated/en/153381468012624097/E... · Web viewAnnex 3 Soil Erosion Control Plan. Overall Arrangement for Soil Erosion Control. The overall