  • Initial Environmental Examination

    August 2013

    Viet Nam: Sustainable Rural Infrastructure Development Project in the Northern Mountain Provinces Subproject 03: Upgrading Ngo Khong I Pumping Station, Hiep Hoa District, Bac Giang Province

    Prepared by the Ministry of Agriculture and Rural Development for the Asian

    Development Bank

  • 2

    CURRENCY EQUIVALENTS

    (as of June 11 th , 2012)

    Currency Unit = Vietnamese Dong (VND) 1 VND = USD 0,048

    USD 1.00 = VND 20,828

    ABBREVIATIONS

    ADB - Asian Development Bank AH - Affected Households AP - Affected Persons CPC - Commune People‟s Committee CSB - Commune Supervision Board CSC - Construction Supervision Consultant CPMU - Central project management unit DARD - Department of Agriculture and Rural Development DIA - Direct Impact Area DONRE - Department of Natural Resources and Environment DPC - District People‟s Committee EM - Ethnic Minority ESC - Environmental Supervision Consultant EMP - Environmental Management Plan IEE - Initial Environmental Examination IIA - Indirect Impact Area MONRE - Ministry of Natural Resources and Environment PPC - Province People‟s Committee PPMU - Provincial Project Management Unit RP - Resettlement Plan SIA - Secondary Impact Area SRIDP - Sustainable Rural Infrastructure Development Project in the

    Northern Mountain Provinces UXO - Unexploded Bombs

    This environmental assessment and review framework is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

  • 3

    TABLE OF CONTENTS

    *** I. INTRODUCTION .................................................................................................... 1 II. DESCRIPTION OF PROJECT ................................................................................ 2 III. DESCRIPTION OF CURRENT ENVIRONMENT .................................................... 8 IV. ENVIRONMENTAL IMPACT SCREENING........................................................... 11 V. BRIEF PLAN OF ENVIRONMENT MANAGEMENT PLAN (EMP) ........................ 23 A. Environmental impact mitigation plan .......................................................................... 23 B. Environmental monitoring plan .................................................................................... 27 C. Environmental Compliance Monitoring ........................................................................ 29 D. EMP implementation plan ........................................................................................... 32 E. Monitoring and reporting system ................................................................................. 34 F. Expenditure for EMP implementation .......................................................................... 35 VI. PUBLIC CONSULTATION AND SUB-PROJECT INFORMATION DISCLOSURE 36 A. Description of activities to date .................................................................................. 36 B. Outcomes of public consultation up to the reporting time ........................................... 37 C. Community consultancy activities in the future ............................................................ 39 VII. ENVIRONMENTAL GRIEVANCE REDRESS MECHANISM ................................. 40 VIII. CONCLUSIONS AND RECOMMENDATIONS ...................................................... 42 APPENDICES ................................................................................................................. 43 Appendix 1: Cost for EMP implementation ...................................................................... 43 Appendix 2: Pictures on current status of the existing environment ................................. 45 Appendix 3: Minute on dump site identification ................................................................ 48 Appendix 4: Details of consultation activities ................................................................... 51 Appendix 5: Documentation of public consultation .......................................................... 64 Appendix 6: List of data sources used in IEE Preparation ............................................... 66 Appendix 7. Sample Complaint Form .............................................................................. 67

  • 4

    LIST FIGURES

    ***

    Figure 1: Map of sub-project area ...................................................................................... 6 Figure 2: Map of sub-project area and surrounding areas ................................................. 7

    LIST OF TABLES

    ***

    Table 1: Description of sub-project .................................................................................... 2 Table 2: Description of ground environment ...................................................................... 8 Table 3: Environmental impact screening ........................................................................ 11 Table 4: Environmental impact mitigation plan ................................................................ 23 Table 5: Environmental monitoring plan .......................................................................... 27 Table 6: Environmental compliance monitoring plan ........................................................ 29 Table 7: EMP Implementation ......................................................................................... 32 Table 8: Monitoring and reporting system ........................................................................ 34 Table 9: Expenditure for EMP implementation ................................................................. 35 Table 10: Public consultation and information disclosure ................................................ 36 Table 11: Outcomes of public consultation ...................................................................... 37 Table 12: Expected community consultation activities ..................................................... 39 Table 13: Estimated for disclosure information activities……………………………………………...42 Table 14: Cost estimation for implementation of capacity building…………………............42 Table 15: Attendance in consultation meetings……………………………………..……….....65 Table 16: Matrix of issues and concerns….……………………………….……..........................65

  • 1

    I. INTRODUCTION

    A. Subproject rationale

    1. Sustainable Rural Infrastructure Development Project in Northern Mountain provinces (SRIDP) is being implemented through a sector loan from Asian Development Bank (ADB). Ministry of Agriculture and Rural Development (MARD) is the executing agency for the sector loan. SRIDP coverage are 15 mountainous provinces in Northern Vietnam (Bac Giang, Bac Kan, Cao Bang, Dien Bien, Ha Giang, Hoa Binh, Lai Chau, Lang Sơn, Lao Cai, Phu Tho, Son La, Thai Nguyen, Tuyen Quang, Vinh Phuc, Yen Bai).

    2. While the poverty levels throughout the country had been significantly reduced as results of development efforts; the statistics in mountain provinces above had indicate rather slow improvement during the last decade (47% in 2002, 32.3% in 2006 and 27% in 2008)1. Part of the problem is due to the inadequate access facilities, social services, and commercial opportunities. It is for this reason that GOV and ADB had pursued the SRIDP to provide sustainable access facilities in these poverty stricken mountain provinces. These infrastructures include rural roads, public markets, irrigation and water supply facilities. As a part of the SRIDP, the sub-project Upgrading pumping station of Ngo Khong I will be conducted in the area of Chau Minh commune and Mai Dinh commune, Hiep Hoa District, Bac Giang province.

    B. Sub-project Objectives

    3. The objective of the sub-project is to upgrade the pumping station of Ngo Khong I

    to ensure the drainage of flood waters affecting 1,190 ha of mostly agricultural lands

    located at Chau Minh and Mai Dinh communes.

    C. Sub project Alternatives

    4. The efforts to minimize the negative social impacts include constructing in the dry

    season, especially the canal drain water in rainy season. Taking advantage of the local

    materials to reduce transport distance, limit negative impact on environment

    5. Initial Environmental Examination (IEE) has been prepared to meet the Social

    Policy Safeguards requirements of ADB2 and GOV3. The IEE contains the following

    contents:

    (i) Part II: Description of the project

    (ii) Part III: Description of current environment

    (iii) Part IV: Screening for environmental impacts

    (iv) Part V: Preliminary plan for environmental management

    (v) Part VI: The public consultation activities & sub-project information

    disclosure

    (vi) Part VII: Grievance redress mechanisms

    (vii) Part VIII: Conclusions and recommendations

    1 Report and Recommendation of the President to the Board of Directors, ADB, September 2010

Recommended