viaduct and bridge construction methods adopted at mtr sil(e
TRANSCRIPT
2013/8/29 Page 1MTR Corporation Limited Page 1Page 12013/8/29 Page 12013/8/29MTR Corporation Limited Page 1
MTR SIL(E) 903 Viaduct Construction Team28-8-2013
Viaduct and bridge construction methods adopted at MTR SIL(E) Contract 903
2013/8/29MTR Corporation Limited Page 2
Content
1. About SIL(E) Contract 903
2. Viaduct Construction
2.1 Value Engineering for Viaduct
2.2 Viaduct construction by Pre-cast segmental method
2.3 Stakeholder Management
3. Aberdeen Channel Bridge (ACB) Construction
3.1 Value Engineering for Aberdeen Channel Bridge
3.2 Bridge construction by in-situ balance cantilever
3.3 Stakeholder Management
4. Q&A
2013/8/29MTR Corporation Limited Page 3
1. About SIL(E) Contract 903
2013/8/29MTR Corporation Limited Page 4
1. About SIL(E) Contract 903
Works Contract 901
Works Contract 902
Works Contract 903OCP
LETSOH
WCH
ADM
Works Contract 907 / 908Works Contract 904
2013/8/29MTR Corporation Limited Page 5
Wong ChukHang Station
Ocean Park Station
Aberdeen ChannelBridge
Viaduct
Nullah Works
Viaduct
1. About SIL(E) Contract 903
2013/8/29MTR Corporation Limited Page 6
1. About SIL(E) Contract 903
Viaduct B
Viaduct C
Ocean Park Station
Ocean Park Station
Wong ChukHang
Station
2013/8/29MTR Corporation Limited Page 7
1. About SIL(E) Contract 903
Wong ChukHang
Station
Viaduct D
Aberdeen Channel Bridge
2013/8/29MTR Corporation Limited Page 8
1. About SIL(E) Contract 903
1. 2 Contractors can be selected at an early stage to help the Employer to identify value engineering solutions
2. The selected Contractor will have more time to mobilise sufficient resources and plan the works well before the actual commencement of the Contract.
3. The Employer and his construction team will be more proactive to help the Contractor to use the cheapest method to complete the project.
4. This contract arrangement is beneficial to foster a genuine partnering relationship between the Employer and the Contractor.
5. This form of contract facilities early identification of risks and allows these risks to be better managed during the construction stage, thus increasing the certainty of project delivery.
Beauty of Target Cost Contract
2013/8/29MTR Corporation Limited Page 9
1. About SIL(E) Contract 903
4 main benefits to use elevated railway for this section of SIL(E) are:
1. Less spoil will be generated from this Contract;
2. The passenger will be able to enjoy the beautiful scenery from Ocean Park to Ap Lei Chau;
3. The connection details between the Ocean Park Station and the main railway line will be much simpler and user friendly;
4. The elevated railway requires less land during construction compared to a tunnel option, which addresses the lack of available land in Southern District;
2013/8/29MTR Corporation Limited Page 10
2. Viaduct Construction
2013/8/29MTR Corporation Limited Page 11
Key information of SIL(E) Viaduct• Length of the viaduct is approx. 2 km;• Viaduct height is approx. 10 to 25m subject to topographical condition;• There are 47 nos. of viaduct piers with span length from 21m to 50m; and• 628 nos. of precast segments, 22-55 tonnes each.
2. Key information of SIL(E) Viaduct
Wong Chuk Hang Station
Ocean Park StationSegmental construction
casting in-situ construction
Viaduct DViaduct C
Viaduct B
2013/8/29MTR Corporation Limited Page 12
Coloured Translucent Panels Where Required
Viaduct Pier
Opaque Panels at Absorptive Parapet
Barrier
Overhead Lines
Proposed Noise Barrier - Perspective Proposed Noise Barrier - Section
2m
Countershading
Track-Side Op’s
Noise Barrier - Integrated Approach
2013/8/29MTR Corporation Limited Page 13
Front Elevation Side Elevation Front Elevation at Portal
Rounded Piers
Profiled Capital
Planting at BottomOf Pier
Consistent Approachfor Portal Piers
13m
4000
4000
Typical Viaduct Section
2013/8/29MTR Corporation Limited Page 14
2. Viaduct Construction
2.1 Value Engineering for Viaduct
2013/8/29MTR Corporation Limited Page 15
Viaduct B
Viaduct B
2013/8/29MTR Corporation Limited Page 16
2.1.1 Value Engineering for Viaduct B
Viaduct construction in the vicinity of the road with heavy traffic
Page 17MTR Corporation Limited 2013/8/29
2.1.1 Value Engineering for Viaduct B
Change in piling design – Use a large diameter pile to replace a group of smaller diameter piles
Conforming design
Single 2.8m Dia. Bored Pile
Alternative design
3 nos of 1.5m dia piles
Wong ChukHang Road
Wong ChukHang Road
Wong ChukHang Road
Wong ChukHang Road
Page 18MTR Corporation Limited 2013/8/29
Legend
Piles
Pile cap
Traffic flow
Carriageway
2.1.1 Value Engineering for Viaduct B
B3
Conforming design
B3
Alternative design
‧Extent of works area required was greatly reduced
‧Less impact on road traffic
Change in Pilecap Design – Use a smaller rectangular pilecap to replace a larger irregular pilecap
Wong Chuk Hang Road
Wong Chuk Hang Road
Page 19MTR Corporation Limited 2013/8/29
2.1.1 Value Engineering for Viaduct B
Change in Pilecap Design – Use a smaller rectangular pilecap to replace a larger irregular pilecap
Revised Pile Cap
Existing 132 kV HEC cables
Existing 132 kV HEC cables
Original Pile Cap
Conforming design
Alternative design
‧Minimize the conflict with the existing utilities
Page 20MTR Corporation Limited 2013/8/29
1) Extent of works area required was greatly reduced2) Less impact on the road traffic3) Minimize the conflict with the existing utilities4) Cheaper and faster to construct the piling and pilecap works
Advantages of the alternative design over the conforming design
1) Volume of pile cap - Approx. 320 m3
2) Less construction and ELS required 1) Volume of pile cap - Approx. 480 m3
2) More construction and ELS required Pile caps
2.0 m to 2.8 m1.5 mSize of bored piles
18
Conforming design
9Number of bored piles
Alternative design
2.1.1 Value Engineering for Viaduct B
Comparison between conforming design and alternative design
Page 21MTR Corporation Limited 2013/8/29
Viaduct C
Viaduct C
Nullah
Page 22MTR Corporation Limited 2013/8/29
2.1.2 Value Engineering for Viaduct C
Viaduct construction over nullah
Page 23MTR Corporation Limited 2013/8/29
Conforming design
2.1.2 Value Engineering for Viaduct C
Alternative design
1. Reduce the number of portal from 11 to 8 2. Change in piling design – Use a large diameter pile to replace a group of smaller diameter piles
Page 24MTR Corporation Limited 2013/8/29
Approx. 50 mApprox. 35 mSpan length
1) Reduce construction time for bored piles and portals2) Minimize construction activities inside the nullah - critical to programme3) Less visual impact with wider spacing of portal structures4) Minimize the conflicts with the existing utilities
Advantages of the alternative design over the conforming design
811Number of portals
1.8 m (C1, C2 and C11 Piers)2.0 m (Portals)
1.5 m (C1, C2 and C13 Piers)1.8 m or 2.2 m (Portals)
Size of bored piles
56
Conforming design
28Number of bored piles
Alternative design
2.1.2 Value Engineering for Viaduct C
Comparison between conforming design and alternative design
Page 25MTR Corporation Limited 2013/8/29
Viaduct D
Viaduct D
Page 26MTR Corporation Limited 2013/8/29
2.1.3 Value Engineering for Viaduct D (from D13 to D18)
Viaduct construction in hilly area
Page 27MTR Corporation Limited 2013/8/29
Conforming Design Alternatives Design
Spread Footing found on Rock
3 nos of 1.5m dia piles
Rock Dowels
Inferred Rockhead
Change in Foundation Design – Replace bored pile by spread footing
2.1.3 Value Engineering for Viaduct D (from D13 to D18)
Page 28MTR Corporation Limited 2013/8/29
- More timber formworks- Better quality control in casting yard- Environmental friendly - steel mould replace timber
formwork Advantage
Limitation- Construction is relatively simple and
faster with the use of a tower crane
In-situ Deck
- Difficult access at hilly area for erection of precast segment
Precast segmental deck
Change in viaduct design - Replace precast segmental deck by in-situ deck
Hilly area
Replace precast segmental deck by in-situ deck
Segmental construction
2.1.3 Value Engineering for Viaduct D (from D13 to D18)
Page 29MTR Corporation Limited 2013/8/29
Spread footing found on rock with rock dowels per column
3 nos of 1.5m dia piles per column
Type of pile per column
In-situ deckPrecast segmental deckViaduct type
1) No heavy piling plant is required in the hilly area
2) Less time to complete the foundation works as footing can be constructed simultaneously
3) The size of the haul road and the ELS works required can be reduced
4) The delivery of materials are relatively simple with the use of a tower crane or a mobile crane
Advantages of the alternative design over the conforming design
Conforming design Alternative design
2.1.3 Value Engineering for Viaduct D (from D13 to D18)
Comparison between conforming design and alternative design
Page 30MTR Corporation Limited 2013/8/29
2. Viaduct Construction
2.2 Viaduct Construction by Pre-cast Segmental Method
2013/8/29MTR Corporation Limited Page 31
2.2.1 Erection by Crane
2.2 Pre-cast segmental method
2.2.2 Erection by Beam-and-Winch
Two erection methods are being adopted:
2013/8/29MTR Corporation Limited Page 32
2.2.1 Erection by Crane
Step 1
B4B4
B5
Step 2
2013/8/29MTR Corporation Limited Page 33
2.2.1 Erection by Crane
B4 B4B5 B5Closure beams
Step 3 Step 4
2013/8/29MTR Corporation Limited Page 34
• Beam-and-Winch technology was introduced in the SIL(E) project to enhance the merits of precast segment erection method
2.2.2 Erection by Beam-and-Winch
B4B4
B5 B5
Step 1 Step 2
2013/8/29MTR Corporation Limited Page 35
2.2.2 Erection by Beam-and-Winch
B4 B4B5 B5Closure beams
Step 3 Step 4
2013/8/29MTR Corporation Limited Page 36
2.2.2 Erection by Beam-and-Winch
2013/8/29MTR Corporation Limited Page 37
Beam-and-Winch Launching gantry
Approx. one monthApprox. a weekTime required for machine assembly
Approx. 100m in length and 10m wideMore than 10 times larger than Beam-and-Winch equipment in size
Approx. 8m in length and 10mwide
ScaleLaunching GantryBeam-and-Winch
2.2.3 Beam-and-Winch and Launching Gantry
2013/8/29MTR Corporation Limited Page 38
Advantage of Beam-and-Winch over Launching Gantry • Less road space required, less disturbance to the traffic• Less construction time required • More flexibility and efficiency in works arrangement
Limitation of Beam-and-Winch • Allowance in Permanent Works Design• Mobile Crane required for mobilization from pier to pier.
2.2.3 Beam-and-Winch and Launching GantryAdvantage and Limitation of Beam-and-Winch
2013/8/29MTR Corporation Limited Page 39
Independent checking system for segment erection
2.2.4 Safety Measures
Checklist of segment erection Checklist of B&W operation
2013/8/29MTR Corporation Limited Page 40
Key measures to minimize impacts on road traffic:1. Adopt Pre-cast segmental method2. Use Beam-and-Winch3. Night-time erection to minimize traffic impact on the public
3) Night time erection
2.2.5 Measures to minimize impacts on Road Traffic
2) Beam-and-Winch1) Pre-cast segmental method
Page 41MTR Corporation Limited 2013/8/29
2.3 Stakeholder Management
2. Viaduct Construction
Page 42MTR Corporation Limited 2013/8/29
2.3.1 Major Stakeholders around the Viaduct B & C
San Wai Village
TWGHs Wong ChukHang Complex
Ocean Park
Station
Viaduct
Viaduct
Police College Ocean Park
Bus Depot
Aberdeen Tunnel
Page 43MTR Corporation Limited 2013/8/29
Jockey ClubRehabilitatio
n CentreHoly SpiritSeminary
Tai Wong YeTemple
Little Sisters of the Poor
St. Mary’s Home for the
Aged
Viaduct
Wong Chuk Hang
Station
NLSR Cooked Food
Market
2.3.2 Major Stakeholders around the Viaduct D
Page 44MTR Corporation Limited 2013/8/29
Visit to the TWGHs Wong ChukHang Complex
Painting activity in Little Sisters of the Poor
Allowance for Tai Wong Ye Temple’s Yu Lam Festival event
JCRC visit and regular meeting
2.3.3 Stakeholder Engagement
Community Liaison Group Meeting
Football Match with Police College
Page 45MTR Corporation Limited 2013/8/29
Page 46MTR Corporation Limited 2013/8/29
3. Aberdeen Channel Bridge Construction
Page 47MTR Corporation Limited 2013/8/29
Aberdeen Channel
SIL(E) Aberdeen Channel Bridge
Existing Ap Lei Chau Bridge
N
58m
115m
73m
ASectionTotal Length = 250m
Max
7m
3. Aberdeen Channel Bridge
A
A
Page 48MTR Corporation Limited 2013/8/29
Photomontage of Aberdeen Channel Bridge
3. Aberdeen Channel Bridge
Aberdeen Channel Bridge (as of June 2013)
Page 49MTR Corporation Limited 2013/8/29
3.1 Value Engineering for Aberdeen Channel Bridge
3. Aberdeen Channel Bridge Construction
Page 50MTR Corporation Limited 2013/8/29
Conforming Arrangement
16 pairs segments (~3.5m long) 16 pairs segments (~3.5m long)
Alternative Arrangement
10 pairs segments (~4.3m long) 14 pairs segments (~4.3m long)
Falsework eliminated
Longer cantilever length for segment construction
One unbalanced cantilever segment
E2E3
E3 E2
3.1 Value Engineering for Aberdeen Channel Bridge
Temporary pier bracingTemporary pier bracing
Temporary pier bracing
E1E2E3E4
12m insitu end span on falsework
Hill
Hill
Page 51MTR Corporation Limited 2013/8/29
160 tons130 tonsMax. segment weight
65 m60 mMax. cantilever length
1) Segment weight in alternative design is heavier2) One set of form traveller instead of two sets of form traveller
is required to meet the programme3) Temporary bracing at E3 pier eliminated4) Scaffolding for end span near E1 eliminated5) Advantage to construction programme6) The alternative design can provide early access for P-way
construction
Remark:
1912 Number of strands per cantilever tendons
~ 40 weeks~ 50 weeksPeriod for segment construction
32 pairs
Conforming design
24 pairsNumber of segments
Alternative design
3.1 Value Engineering for Aberdeen Channel Bridge
Comparison between conforming design and alternative design
2013/8/29MTR Corporation Limited Page 52
3.2 Bridge construction by in-situ balance cantilever
3. Aberdeen Channel Bridge Construction
Page 53MTR Corporation Limited 2013/8/29
3.2 ACB – Comparison of different construction methods
Disadvantage1) Falsework cannot be
erected across the Aberdeen Channel
Disadvantage1)Barge for segment
erection is too large to gain access to the bridge
2) Segment (max 160T) too heavy for lifting
3) Disruption to Navigation Channel during segment erection
Advantage1) Only one set of form
traveller is required2) Without affecting the
marine traffic underneath the bridge
3) No heavy lifting involved 4) Cheapest and fastest
way to build this bridge
Advantage and disadvantage
Cast bridge span by span with the support by falsework
Segment pre-cast and erection
Cast in-situ segments by balanced cantilever method with form traveller
Description
Cast in-situ span by spanPre-cast segmental methodCast in-situ segments by balanced cantilever
(Selected option)
Page 54MTR Corporation Limited 2013/8/29
3.2.1 ACB – Construction Sequence
Stage 1 – Pier Table construction at E2
Stage 2 – Pier Table construction at E3 - Erect form traveller at E2
Page 55MTR Corporation Limited 2013/8/29
Stage 3 – Complete cantilever span at E2 by insitu balanced cantilever method
Stage 4 – Launch back form traveller & remove tower crane from E2
3.2.1 ACB – Construction Sequence
Page 56MTR Corporation Limited 2013/8/29
Stage 5 – Tower Crane & form traveller removed from E2
Stage 6 – Erect tower crane & form traveller at E3
3.2.1 ACB – Construction Sequence
Page 57MTR Corporation Limited 2013/8/29
Stage 7 – Complete E3 cantilever span by insitu balanced cantilever method
Stage 8 – Cast Mid-span stitch
3.2.1 ACB – Construction Sequence
Page 58MTR Corporation Limited 2013/8/29
Stage 9 – Cast unbalanced segment at E4
Stage 10 – Cast End-span stitch at E4
3.2.1 ACB – Construction Sequence
2013/8/29MTR Corporation Limited Page 59
3.2.2 Modular Form Traveller (MFT)
Major component:Modular Form Traveller• Main Frame x 2• Front Transverse Truss x 1• Rear Transverse Truss x 1• Rear Anchorage x 2• Rail Beam x 2
Formwork system• Inner Form• Outer Form• Bottom Form
2013/8/29MTR Corporation Limited Page 60
General characteristics of Modular Form Traveller:
Bridge alignment• Gradient of +/-5%• Cross-fall of +/-5%• Minimum curve in plan of 500m
radius
Segment geometry• Maximum length of 5m• Maximum weight of 180 tons (with 2
main frames)• Single or multiple cells• Vertical or inclined webs
System capacity: 180 tons
Load test could be carried out prior to assembly
3.2.2 Modular Form Traveller (MFT)
Page 61MTR Corporation Limited 2013/8/29
Rear truss
Bottom Form
Front truss Wall Form
3.2.2 Modular Form Traveller (MFT)Main frames
2013/8/29MTR Corporation Limited Page 62
3.2.2 Modular Form Traveller (MFT)
2013/8/29MTR Corporation Limited Page 63
3.3 Stakeholder Management
3. Aberdeen Channel Bridge Construction
2013/8/29MTR Corporation Limited Page 64
3.3.1 Stakeholders around Aberdeen Channel Bridge
Aberdeen Channel Bridge
Dragon Boat Association
Aberdeen Boat Club
Marine Police Port
Tai Shue Wan
Aberdeen Channel
Sham WanJumbo
Restaurant
Kaito
2013/8/29MTR Corporation Limited Page 65
Key measures to minimize marine traffic impact:1. Use cast-insitu balanced cantilever method
2. Maintain navigation channel
3. Advance notice to all marine users about the construction works
4. Use of guard boat
3.3.2 Minimize impact on Marine Traffic
40m min. wide
14 m min. high
2. Navigation Channel
1. Cast-insitu balanced cantilever method
2013/8/29MTR Corporation Limited Page 66
4. Use of guard boat 3. Early notice to all marine users about the construction works
3.3.2 Minimize impact on Marine Traffic
2013/8/29MTR Corporation Limited Page 67
Use of silt curtain
3.3.3 Minimize impact on Marine Environment
Key measures to minimize marine environment impact:
1. Use of silt curtain2. Use of temporary steel formwork for pile cap construction
Use of temporary steel formwork for pile cap construction
2013/8/29MTR Corporation Limited Page 68
3.3.4 Entertain the need of Dragon Boat Association
Relocate the existing dragon boats to the new permanent storage area for the Dragon Boat Association before the commencement of the construction on site
Aberdeen Channel Bridge
Existing storage area for dragon boat before bridge constructionNew permanent storage area for
dragon boat
2013/8/29MTR Corporation Limited Page 73
多謝Q & A