WelcomeVeranda Street Bridge Replacement
Public Meeting
East End Community Center195 North Street, Portland, ME
Thursday, August 8, 20196:00 PM
Veranda Street Bridge ReplacementPublic Meeting
• Welcome• Project Schedule• April Workshop Recap• Alignment Design Selection & Enhancements• Discussion/Question and Answer• Close
Agenda:
Project Schedule
April 2019 Public Workshop Findings
• Alignment 2b received the most public support• Decreasing motorist speed is a priority • Increasing bicycle and pedestrian safety is
important• Addition of green space is positive for the
neighborhood• The multiuse path should connect (now or in the
future) to neighboring areas • Opinions varied about parking options on the
street • Opinions varied about center turning lanes
Alignment Selection
NORTH
Alignment Alternative 2b
Veranda Street Beneath Bridge (Looking toward Falmouth)
11’-0” Lane
11’-0” Lane
5’-0” Bike w/2’-0” Buffer
5’-0” Bike w/2’-0” Buffer
10’-0” Multi-Use Path5’-0”Sdwk.
3’-0” 3’-0”
57’-0”
Veranda Street Away From Bridge (Looking toward Falmouth)
11’-0”Lane
11’-0”Lane
Varies 6’-0” to 10’-0”6’-0”Sdwk.
5’-0” Bike2’-0” Buffer
5’-0” Bike2’-0” Buffer
Alignment Selection
• Broadly supported by public workshop attendees
• Provides sufficient capacity in the current year and future
• Reduces vehicle speeds and maximizes green space
• Signalized intersections at both interstate ramps
• Increases safety for all transportation modes
• Provides community green space as well as a buffer to existing homes
• Supports accelerated construction of the new bridge
• Facilitates multi-use pathway connections
Benefits of Selected Alignment
Alignment Enhancements
NORTH
Alignment Alternative 2b
Install radar speed sign south of Martin’s Point Bridge
Alignment Enhancements
NORTH
Alignment Alternative 2b
Rectangular Rapid Flashing Beacons, signage and high-visibility crosswalks
mid-block crossings
Alignment Enhancements
NORTH
Alignment Alternative 2b
Painted bike lane buffers
Alignment Enhancements
Limited on-street parking, two separate parking areas
Alignment Enhancements
Shifting roadway alignment south further improves visibility and sight lines
Alignment Enhancements
Bicycle & Pedestrian Accommodations
Bridge Improvements• Unchanged from concepts previously presented• Includes accelerated construction of a new single span steel girder bridge• Remainder of existing bridge converted to embankment
Bridge Improvements• Unchanged from concepts previously presented• Includes accelerated construction of a new single span steel girder bridge• Remainder of existing bridge converted to embankment
Construction Phasing
Existing Conditions
Construction Phasing
Phase 1 (Approx. May 2020 – August 2020)
• Maintain Veranda Street traffic pattern and pedestrian movement
• Construct foundations, abutments, and falsework
Construction Phasing
Phase 2 (Approx. August 2020 – Nov. 2020)
• Combine Veranda Street NB and SB traffic
• Construct lightweight fill embankment
• Construct upper portion of bridge
Construction Phasing
Phase 3Accelerated Bridge ConstructionClosure Period, Step 1 (April 2021)(Total closure period approx. 56 hours)(Step 1 closure period approx. 22 hours)
• I-295 and Veranda Street closed• Demolish existing bridge
Construction Phasing
Phase 3Accelerated Bridge ConstructionClosure Period, Step 2 (April 2021)(Total closure period approx. 56 hours)(Step 2 closure period approx. 17 hours)
• I-295 and Veranda Street closed• Complete lateral slide and construct
earth embankment
Construction Phasing
Phase 3Accelerated Bridge ConstructionClosure Period, Step 3 (April 2021)(Total closure period approx. 56 hours)(Step 3 closure period approx. 13 hours)
• I-295 and Veranda Street closed• Construct bridge approaches
Construction Phasing
Phase 3Accelerated Bridge ConstructionClosure Period, Step 4 (April 2021)(Total closure period approx. 56 hours)(Step 4 closure period approx. 11 hours)
• I-295 and Veranda Street closed• Place I-295 pavement, install median
barrier and guardrail
Phase 4(Approx. April 2021 – July 2021)
• I-295 and Veranda Street reopened to traffic
• Construct north portion of Veranda Street
Construction Phasing
Construction Phasing
Phase 5(Approx. July 2021 – November 2021)
• I-295 and Veranda Street open• Construct south portion of Veranda
Street and I-295 ramps
Construction Phasing
Completed Project(November 2021)
• Potential green space improvements not shown and will be completed under the direction of the City of Portland
Detours
Interstate Through Traffic Northbound Interstate Traffic Southbound Interstate Traffic
Detours
Southbound Route 1 Traffic Northbound Route 1 Traffic Southbound Route 88 Traffic
Next Steps
Discussion and Questions
Thank You!