  State of Kuwait Ministry of Defence Military Engineering Projects  CONTRACTOR : _______________________________ VARIATION No. : ___________________ SUBJECT : _______________________________ DATE : ___________________ In accordance with clause 51 of Document II – General & Particular Conditions, you are hereby instructed to undertake work and/or amend the Contract as detailed below : DESCRIPTION OF WORK According to Clause 44 and 52, Extension of Time for Completion and Valuation of V.O. are a s follows: EXTENSION OF TIME :__________ DAYS VALUE OF THIS V.O. :__________ KWD (OMISSION /ADDITION) RELATED CORRESPONDENCE AND ATTACHEMENTS The following Correspondence and attachment constitute integral parts of the Contract Documents and this Variation Order We the undersigned Contractor hereby agree to carry out the works as ordered of this Variation Order and accept in full and final settlement of all related consequential costs and time. ________________________________ _________________________________ CONTRACTOR DATE CONSULTANT DATE OWNER DATE Original Contract Sum : KWD ________________ Previous Approved VO’s : KWD ________________ Approved Contract Sum : KWD ________________ Net Value of this V.O. : KWD Revised Contract Sum : KWD Contract Completion Date = _________________ Prev. Approved Extensions = Extension this V.O. = _________________ Revised Completion Date = cc: Contractor : Consultant: Owner : Quantity Surveyor : Variation Order

Upload: fred-anthony-a-uera

Post on 05-Nov-2015

214 views

Category:

Documents


0 download

DESCRIPTION

VO

TRANSCRIPT

  • State of Kuwait Ministry of Defence

    Military Engineering Projects

    CONTRACTOR : _______________________________ VARIATION No. : ___________________ SUBJECT : _______________________________ DATE : ___________________ In accordance with clause 51 of Document II General & Particular Conditions, you are hereby instructed to undertake work and/or amend the Contract as detailed below :

    DESCRIPTION OF WORK

    According to Clause 44 and 52, Extension of Time for Completion and Valuation of V.O. are as follows: EXTENSION OF TIME :__________ DAYS VALUE OF THIS V.O. :__________ KWD (OMISSION/ADDITION)

    RELATED CORRESPONDENCE AND ATTACHEMENTS The following Correspondence and attachment constitute integral parts of the Contract Documents and this Variation Order We the undersigned Contractor hereby agree to carry out the works as ordered of this Variation Order and accept in full and final settlement of all related consequential costs and time. ________________________________ _________________________________ CONTRACTOR DATE CONSULTANT DATE _______________________________________________ OWNER DATE Original Contract Sum : KWD ________________ Previous Approved VOs : KWD ________________ Approved Contract Sum : KWD ________________ Net Value of this V.O. : KWD _______________ Revised Contract Sum : KWD _______________

    Contract Completion Date = _________________ Prev. Approved Extensions = _________________ Extension this V.O. = _________________ Revised Completion Date = _________________

    cc: Contractor : Consultant: Owner : Quantity Surveyor :

    Variation Order