vale dam audits – monthly meeting
TRANSCRIPT
Dams at Emergency Levels
2
No changes from September• Emergency Level 3
• B3/B4 • Emergency Level 2
• Doutor• Emergency Level 1
• Campo Grande • Dicão Leste• MAC B5 • MAC B6• MAC B7A• Maravilhas II • Mutuca B5 • Paracatu• Taquaras • Vargem Grande
Mar Azul - B3/B4 Dam
3
• Emergency Level 3 since March 2019
Reservoir
PDE XPDE Oeste
Dam B4
Dam B3
Reinforcement Berm - 2018
B3/B4 – Progress
4
• Backup Dam Gate completed Closing time tested and video received by SLR Spillway raise completed
• Dam Break Study Fugro report submitted & audit nearly completed Potamos declined peer review All tailings and runoff during tailings flow is contained SLR is requesting more detail on flow through spillway
• Slope maintenance PDE Ouest slope regraded before rainy season
Gates
B3/B4 – Progress & Priorities
5
• Decharacterization Additional radar monitoring installed to close SLR recommendation Lifeline testing and training completed, SLR auditing emergency plan Operating manual audit completed by SLR
• Priorities Commence PDE X excavation Finalize Dam Break Study reporting Second lifeline will be completed in November Install piezometers for pump tests monitoring
Mar Azul Taquaras Dam – Progress & Priorities
6
• Emergency Level 1 since April 30, 2020• Progress
Upstream slope earthworks completed Upstream slope revegetated
• Priorities Geotechnical investigations As-Is update
Doutor – Progress & Priorities
8
• Progress As-Is report with new investigations Doutor Dam mid-slope berm proceeding well Spillway construction:
– access road 84% / excavation 18%
• Priorities Revise As-Is Better documentation of geology in spillway excavation
Vargem Grande – Progress & Priorities
10
• Progress Channel excavation on tailings beach
(remotely operated equipment) Removing tailings from upstream cells Interpreted dam stability with new
piezometers
• Priorities Complete rain season preparation – Vale
& TPF (Engineer of Record) requested the use of manned equipment to increase productivity
Develop a decommissioning plan for water level indicators that do not function properly
Agreement on the Factor of Safety
Fernandinho Dam Decharacterization
12
• Progress Decharacterization 37.5% complete Deformation monitoring system improved, new reference station
Tamandua - Capão da Serra Dam
13
• Progress Former spillway remediation in progress
• Priorities Structural improvements to spillway in
the right abutment
Alegria - Campo Grande Dam
14
• Emergency Level 1 since July 2019
North/South Dyke
Main Dam
Saddle Dyke I
Campo Grande - Progress
15
• Progress Basic design of decharacterization completed
• Priorities Vibration test for Campo Grande and Xingu (Alegria Pit) SLR recommended vibrating-wire piezometers
Pico - Maravilhas II Dam
16
• Emergency Level 1 as of September 2019
Saddle Dyke II
Main Dam
Saddle Dyke I
Maravilhas II - Progress
17
• Progress Reservoir pumped lower than 2019/2020 rainy season Piezometer live-tests completed New seismographs installed (5) Downstream slope cracks healed with rains (supports shrinkage crack theory
• Priorities: Advance reinforcement design
Pico - Maravilhas III Dam
18
• Emergency Level 1 as of September 2019• Progress (dam under construction)
Foundation jet grouting test completed Right abutment cracks repaired
• Priorities Report on crack repairs scheduled for November
Mutuca - Dam 5
19
• Emergency Level 1 since July 29, 2020• Progress
Trenched at crest to confirm (for As-Is)
• Priorities As-Is and piezos delayed for drilling
Águas Claras - Dam 5 / Auxiliar Dyke
20
• Dam 5 / Auxiliar Dyke Emergency Level 1 since April 1, 2020
• Progress Dam 5 / Auxiliar Dyke Pump cable replaced and security
improved to prevent theft Dam break study completed for
SLR auditing
B6/B7A New stairways for inspection /
surveillance
Dicão Leste Dam
21
• Emergency Level 1 since May 8, 2020• Progress
Erosion protection (biomanta) on crest
Paracatu Dam
22
• Emergency Level 1 since May 8, 2020• Progress
Temporary spillway design completed and audited
• Priorities Install temporary spillway Commence spillway upgrade