v3 vs. v4 new protocols for leed tommy linstroth, principal

53
NEW PROTOCOLS FOR LEED Tommy Linstroth, Principal v3 vs. v4

Upload: antonia-powell

Post on 08-Jan-2018

234 views

Category:

Documents


0 download

DESCRIPTION

Tommy Linstroth, LEED AP, BD&C, ND Principal

TRANSCRIPT

Page 1: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

NEW PROTOCOLS FOR LEED

Tommy Linstroth, Principal

v3 vs. v4

Page 2: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

Tommy Linstroth, LEED AP, BD&C, ND

Principal

Page 3: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

1. About Us2. About LEED/USGBC3. LEED v34. LEED v45. Resources

Page 4: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

LEED AND SUSTAINABLE DESIGN SERVICES

ORGANIZATIONAL SUSTAINABILITY

MUNICIPAL SUSTAINABILITY SOLUTIONS

Page 5: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

- 60+ CERTIFIED PROJECTS

-15+ IN THE WORKS

~5,000,000 SF OF CERTIFIED BUILDINGS

~$400,000,000 MARKET VALUE…AND A FEW LESSONS LEARNED ALONG

THE WAY

Page 6: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

ABOUT LEED

Page 7: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 8: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 9: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 10: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 11: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 12: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 13: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 14: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 15: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 16: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

GREAT, SO WHAT?

Page 17: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 18: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 19: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 20: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 21: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 22: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 23: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 24: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 25: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

LEED V3TRIED AND TRUE

Page 26: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

LEED NC /LEED CI - 3 points (7.5%)• IEQ c3.1• IEQ c3.2• IEQ c5

LEED EBOM – 1 Prereq and 2 points (5%)• IEQ p1 – Minimum indoor air quality performance • IEQ c1.4 – Reduce particulates in air distribution• IEQ c1.5 – IAQ Plan for facility alterations

LEED Homes 1 Prereq and up to 2 points (4.5%)• IEQp7.1 – Good Filters• IEQc7.2/7.3 – Better/Best Filters

HOW DOES FILTRATION APPLY?

Page 27: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

LEED NEW CONSTRUCTION

Page 28: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

IEQ C3.1 – DURING CONSTRUCTIONIf permanently installed air handlers are used during construction, filtration media must be used at each return air grille that meets one of the following criteria below. • Filtration media with a minimum efficiency reporting

value (MERV) of 8 • Filtration media is Class F5 or higher, as defined by

CEN Standard EN 779-2002• Filtration media with a minimum dust spot efficiency

of 30% or higher and greater than 90% arrestance on a particle size of 3–10 µg

Replace all filtration media immediately prior to occupancy.

Page 29: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

IEQ C3.2 – INDOOR AIR QUALITY MANAGEMENT PLAN, BEFORE OCCUPANCY

After construction ends, prior to occupancy and with all interior finishes installed:• Install new filtration media and perform a

building flush-out by supplying a total air volume of 14,000 cubic feet of outdoor air per square foot (4,500 cubic meters of outdoor air per square meter) of floor area while maintaining an internal temperature of at least 60° F (15° C) and relative humidity no higher than 60%. Replace filtration media after flushout is complete.

Page 30: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

IEQ C5 – INDOOR CHEMICAL AND POLLUTANT SOURCE CONTROL

In mechanically ventilated buildings, each ventilation system that supplies outdoor air shall comply with the following:• Particle filters or air cleaning devices shall be provided to

clean the outdoor air at any location prior to its introduction to occupied spaces. – Filtration media is rated at a minimum efficiency reporting value

(MERV) of 13 or higher – Filtration media is Class F7 or higher, as defined by CEN

Standard EN 779: 2002– Filtration media has a minimum dust spot efficiency of 80% or

higher and greater than 98% arrestance on a particle size of 3–10 µg.

• Clean air filtration media shall be installed in all air systems after completion of construction and prior to occupancy.

Page 31: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

LEED FOR EXISTING BUILDINGS

Page 32: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

IEQ P1 – MINIMUM INDOOR AIR QUALITY PERFORMANCE

Implement and maintain an HVAC system maintenance program to ensure the proper operations and maintenance of HVAC components as they relate to outdoor air introduction and exhaust.

Page 33: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

IEQ C1.4 – REDUCE PARTICULATES IN AIR DISTRIBUTION

To reduce exposure of building occupants and maintenance personnel to potentially hazardous particulate contaminants, which adversely affect air quality, human health, building systems and the environment.

Page 34: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

IEQC1.4 CONTINUEDEach ventilation system that supplies outdoor air shall comply with the following during the performance period:• Particle filters or air cleaning devices shall clean the outdoor

air at any location prior to its introduction to occupied spaces.• These filters or devices shall meet one of the following criteria

for all outside air intakes and inside air recirculation returns:– Filtration Media is rated a minimum efficiency reporting

value (MERV) of 13 – Filtration media is Class F7 or higher, as defined by

CEN Standard EN 779: 2002– Filtration media has a minimum dust spot efficiency of

80% or higher and greater than 98% arrestance on a particle size of 3–10 µg

• Establish and follow a regular schedule for maintenance and replacement of these filtration media according to the manufacturer’s recommended interval.

Page 35: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

IEQ C1.5 – IAQ PLAN FOR FACILITY ALTERATIONS

If permanently installed air handlers are used during construction, filtration media must be used at each return air grille that meets one of the following criteria below. Replace all filtration media immediately prior to occupancy.• Filtration media with a minimum efficiency reporting

value (MERV) of 8 • Filtration media is Class F5 or higher, as defined by

CEN Standard EN 779-2002• Filtration media with a minimum dust spot efficiency

of 30% or higher and greater than 90% arrestance on a particle size of 3–10 µg

Page 36: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

IEQ C1.5 CONTINUED

After construction ends, prior to occupancy and with all interior finishes installed, install new filtration media and perform a building flush-out by supplying a total air volume of 14,000 cubic feet of outdoor air per square foot (4,500 cubic meters of outdoor air per square meter) of floor area while maintaining an internal temperature of at least 60° F (15° C) and relative humidity no higher than 60%.

Replace all filtration media after flushout is complete.

Page 37: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

LEED FOR HOMES

Page 38: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

IEQ 7 – AIR FILTERING

• Requirement – use MERV 8 Filtration

• IEQ7.2/7.3 – Better/Best Filters – use air filters that are MERV 10 or MERV 13

Page 39: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

LEED V4NEW HORIZONS…

Page 40: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

LEED V4 – New Concepts

Page 41: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

LEED v4 Certification Levels

Page 42: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

NEW CREDITS

Page 43: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

REFINED/COMBINED CREDITS

Page 44: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

NO CHANGE

Page 45: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

FOR FILTRATION…

Page 46: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 47: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal
Page 48: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

EBOM CHANGES

Page 49: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

LEED FOR HOMES

Page 50: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

FOR MORE INFO

Page 51: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

LEED V4 USERS GUIDE

Page 52: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

ALL LEED V4 RESOURCES AVAILABLE AT:

USGBC.ORG/LEEDV4

Page 53: V3 vs. v4 New Protocols for LEED Tommy Linstroth, Principal

QUESTIONS?

TOMMY LINSTROTHtommy@tridentsustainability.com912-695-4692www.tridentsustainability.com