utm fab april 2010
TRANSCRIPT
-
8/17/2019 utm FAB April 2010
1/175
SO ALAN PEPERIKSAAN
SEMESTER DISEMBER
2009/2010
FAKULTI ALAM BINA UTM
-
8/17/2019 utm FAB April 2010
2/175
FAKULTIALAM BINA
SOALAN PEPERIKSAAN SEMESTER DISEMBER
2009/2010
BIL KOD MATA PELAJARAN NAMA MATA PELAJARAN MUKASURAT
1 SBQ 2122/SBC 1142 STRUCTURAL DESIGN
2 SBC 1422 ESTIMATING I
3 SBQ 3522 LEGAL STUDIES III4 SBC 3842 BUILDING MAINTENANCE
5 SBQ 4912 VALUES MANAGEMENT
6 SBQ 3314 CONSTRUCTION MEASUREMENT III
7 SBC 2242 CONSTRUCTION TECHNOLOGY II
8 SBQ 1223 CONSTRUCTION TECHNOLOGY I
9 SBC 1222 CONSTRUCTION TECHNOLOGY I
10 SBQ 4412 FINANCIAL MANAGEMENT
11 SBC 2443 FINANCIAL MANAGEMENT
12 SBC 1233 BUILDING SERVICES SYSTEM
13 SBQ 2233 BUILDING SERVICES II
14 SBQ 4314 UKUR BINAAN IV
15 SBC 2273 CONSTRUCTION TECHNOLOGY AND DESIGN
16 SBC 1512 PRINCIPLE OF LAW IN MALAYSIA
1
17 SBQ 3424 BUILDING ECONOMICS
18 SBC 2344 CONSTRUCTION PROJECT MANAGEMENT
19 SBC 3533 CONSTRUCTION AND DEVELOPMENT LAW
20 SBQ 3622 PRINCIPLES OF MANAGEMENT
21 SBC 1123 ENGINEERING SURVEY
22 SBQ 4324 INFORMATION MANAGEMENT
23 SBQ 1712 PROFESSIONAL PRACTICE I
24 SBQ 2314 UKUR BINAAN I
25 SBQ 1322 INTRODCUTION TO CONSTRUCTION...
26 SBC 2263 CONSTRUCTION PLANT AND TEMPORARY...
-
8/17/2019 utm FAB April 2010
3/175
30000010222992
UNIVERSITI TEKNOLOGI MALAYSIA
Fakulti Alam Bina
FINAL EXAMINATION
SEMESTER II SESSION 2009/2010
COURSE CODE
COURSE
PROGRAM
TIME
DATE
LECTURER
PERCENTAGE
SBQ 2122/SBC 1142
STRUCTURAL DESIGN
1 SBQ/1 SBC
2 HOURS
5 APRIL 2010
IR. MOHAMAD SALLEH YASIN
PROF. MADYA. BADRUL HISHAM
AHMAD
50 %
INSTRUCTION:
1. Answer ONE (1) questions from Section A and ONE (1) question from
Section B.
2. This is an open book examination.
THIS QUESTION PAPER CONSIST OF 5 PAGES INCLUDING THE
FRONT PAGE
-
8/17/2019 utm FAB April 2010
4/175
SBQ 2122
Section A
Al. a)
b)
Explain the roles of structural designer in building construction project.
(8 marks)
In the design process, engineers always use “partial safety factor” to
converts characteristic values into design values. Explain why they
need such factors and gives examples of the factors.
A 250 x 600 mm rectangular reinforced concrete beam of span 9.0 m is
shown in Figure Al. The beam is required to support an ultimate
uniformly distributed load of 20 kN/m and two ultimate point loads of
30’kN and 50 kN as shown in the figure. Use concrete grade C30 and
steel grade 500 and concrete cover 30 mm.
i. Sketch the shear force and bending moment diagrams of the
beam by showing all the important values.
ii. Design main reinforcement for bending.
iii. Design shear reinforcementiv. Sketch the detailing of reinforcements designed in (b) and (c).
(8 marks)
(34 marks)
30 kN 50 kN
1 20 kN/m A
650
3m ^ 3m ^ j,,
250
Cross-section
FIGURE Al
-
8/17/2019 utm FAB April 2010
5/175
SBQ 2122 3
A2. a) Reinforced concrete structure is a combination of several main elements.
State three of the elements and explain the behavior of each element when
subjected to loading. The explanation should be guided with sketch
showing the deformed shape of the element and the location of mainreinforcement.
(12 marks )
b) Figure A2 shows a reinforced concrete slab 4.0 m x 5.0 m, simply
supported on two reinforced concrete beams. This slab is required to
support a uniformly distributed live load of 3.0 kN/m2 and floor finishes
of 1.0 kN/m2. The design data are as follow:
Characteristic strength of concrete,^Characteristic strength of reinforcement, f y
Concrete cover, c
Bar size
= 30 N/mm2
500 N/mm2
= 25 mm
= 12 mm
A
4 m
-
8/17/2019 utm FAB April 2010
6/175
SBQ 2122 | 4
Section B
Bl. a) List down three differences between pre-tensioned and post-tensionedprestressed concrete beam.
(10 marks)
b) Explain in your own words the reasons why there is a reduction in
prestressing force after a long period of time.
(10 marks)
c) A pre-tensioned prestressed concrete beam is simply supported over a
span of 16 m and carries a total uniformly distributed service load of
19.5 kN/m, in addition to its own self weight. A standard TY beam
section as shown in Figure Bl is to be used. The following information
is given:
• Class 2 category; f ci = 40 N/mm2; f cu = 50 N/mm
2
• a = 0.9; (3 = 0.72
i) Calculate the stress limits at transfer and service
ii) Select the most economical section for the beam. (Choose between
TY9 and TY10)
(30 marks)
SECTJON PROPERTIES Design self weight per unit volume has been token ds 25 kN/m*
Section No Depth mm Area mrn! Yb mm Zt mm1 * 106 Zb mm1 x 106App self weight
kN./m
TY1 400 184155 140 6.5B 12.22 4.60
TY2 450 195538 155 8.40 15.98 4.83
TY3 500 207936 173 10.85 20.51 5.20
TY4 550 221351 194 13.97 25.68 5.54
W5 600 235780 216 47.70 31.47 5.90
TT6 650 251225 240 22.11 37.77 6.28
vn 700 267685 266 27.23 44.43 6,70TVS 750 285163 294 33,10 31.34 7.13
TY9 800 303655 322 39-61 58.80 7.59
TY10 850 323157 352 46.93 66*40 8.08
FIGURE Bl
4
-
8/17/2019 utm FAB April 2010
7/175
SBQ 2122 I 5
B2. a) Sketch the various stages of a structural steel beam undergoing
bending until it collapse
(10 marks)
b) Given two sections, one classified as plastic while the other as
compact. Which section will carry bigger load at collapse and explain
why?
(10 marks)
c) The slab shown in Figure B2 has an overall depth of 200 mm is
designed to carry an imposed load of 3 kN/m2 plus floor finishes and
ceiling loads of 1 kN/m2. It is supported by structural steel beams
457 x 191 x 82 UB (grade S275) and these beams are simply supported
at their ends. All the beams are fully laterally restrained and there is
nominal torsional restrain at supports.
i) Calculate the total service and ultimate loads on beam B/l-2 and
Beam 2/A-C
ii) Check whether the bending and shear capacities for beam B/l-2 are
adequate.
iii) Calculate the deflection for beam 2/A-C and check whether it is
within the allowable limit.
(30 marks )
|3.5 ro r . ! . , _________ .J-Sffl.
FIGURE B2
-
8/17/2019 utm FAB April 2010
8/175
UTMUNIVERSITI TEKNOLOGI MALAYSIA
Fakulti Alam Bina
FINAL EXAMINATION
SEMESTER II SESSION 2009/2010
COURSE CODE
COURSE
PROGRAM
TIME
DATE
LECTURER
PERCENTAGE
SBC 1422
ESTIMATING I
1 SBC
2 HOURS
5 APRIL 2010
NORAZAM B. OTHMAN
50 %
ARAHAN:
INSTRUCTION:
Jawab mana-mana 4 (empat) soalan.
Answer any 4 (four) questions.
Markah setiap soalan adalah seperti yang dinyatakan.
Marks for each question is as stated.
r0
THIS QUESTION PAPER CONSIST OF 7 PAGES INCLUDING THE FRONT PAGE
1
-
8/17/2019 utm FAB April 2010
9/175
SOALAN 1
Jelaskan penggunaan kaedah anggaran unit dan kaedah anggaran keluasan
lantai yang lazimnya digunakan dalam mendapatkan anggaran kos
pembinaan termasuk kebaikan dan keburukannya.
(25 markah)
QUESTION 1
Explain the usage of the unit and superficial area estimating methods
commonly used to derive the estimated cost of construction including its
advantages and disadvantages.
(25 marks)
SOALAN 2
Terangkan ciri-ciri tapak bina seperti lokasi, jenis dan saiz
bangunan/pembinaan, kemudahan sedia ada, keadaan tanah serta
topografi yang mungkin memberi kesan kepada penilaian keseluruhan kos
projek dan harga tender.
(25 markah)
QUESTION 2
Explain the characteristics of the site such as location, type and size of the
building/construction, available existing services, ground conditions and
topography which may affect the overall assessment of the cost of project and
the tender price.
(25 marks)
72
-
8/17/2019 utm FAB April 2010
10/175
SOALAN 3
Dengan menggunakan kaedah anggaran ‘superficial area’, tunjukkan
pengiraan anggaran kos seterusnya harga tender pembinaan untuk projek
dengan ciri-ciri berikut:
Tajuk projek
Lokasi
Ketinggian
Rekabentuk
Lain-lain
: Hotel 3 bintang untuk Budget™ Services Sdn Bhd
: Tainan Universiti Skudai (bersebelahan kompleks
membeli belah Jay a Jusco)
: 5 tingkat (atas tanah), 1 tingkat (tempat letak
kereta bawah tanah)
: Bilangan bilik tetamu : 50
Bentuk segiempat tepat
Setiap tingkat 70.0m panjang x 20.0m lebar
Tingkat 1 untuk lobi, restoren, dapur, pejabat
pengurusan, bilik seminar, perkhidmatan cucian
pakaian
: Pembinaan akan bermula Julai 2010
Jika setiap bilik direkabentuk untuk 2(dua) tetamu hotel, apakah kadar unit
kos semasa setiap tetamu hotel jika kos perkhidmatan mekanikal dan
elektrik (M&E) serta kos perkakasan dalaman adalah 40% dari kos
pembinaan?
Data projek lepas antara tahun 1998-2006 untuk lokasi Kuala Lumpur
(Lampiran A) boleh digunakan sebagai rujukan dan pemilaian
(25 markah)
b
3
-
8/17/2019 utm FAB April 2010
11/175
QUESTION 3
Using ‘superficial area’ method of estimating, show the calculations of the
estimated cost and the tender price offer for the construction of a project with
the following characteristics:
Project title
Location
Height
Design
Others
: 3 star hotel for Budget?™ Services Sdn Bhd
: Taman Universiti Skudai (next to Jaya Jusco
Shopping complex)
: 5 floors (above ground), 1 floor (basement car park)
: Number of rooms : 50
Rectangular shape
Each floor 70. Om long x 20. Om wide
I st floor for lobby, restaurant, kitchen, administrative
offices, seminar rooms, laundry services
: Construction will start in July 2010
If each room is designed to cater for 2(two) guests, what will be the present
unit cost rate for each guest if the cost of the mechanical and electrical
services (M&E) and the cost of interior decorations is 40% of the cost of
construction?
Data of previous projects for the year 1998-2006for Kuala Lumpur (Appendix
A) is given as reference and assessment
(25 marks)
9
4
-
8/17/2019 utm FAB April 2010
12/175
SOALAN 4
Lakarkan hubungkait pihak-pihak yang terlibat dalam kaedah perolehan
tradisional dan jelaskan bagaimana kaedah perolehan tersebut memberi
implikasi kepada harga tender.
(25 markah)
QUESTION 4
Sketch out the relationship of all parties involved in a traditional procurement
method and explain how this procurement method affect the tender price.
(25 marks)
SOALAN 5
Terangkan setiap langkah yang terdapat dalam prosedur tender yang
bermula dari perlawaan membuat tawaran sehinggalah surat setujuterima
dikeluarkan kepada kontraktor.
(25 markah)
QUESTION 5
Explain each steps in the tendering procedure commencing from the invitation
to treat to the issuance of the letter of acceptance to the contractor.
(25 marks)
1 05
-
8/17/2019 utm FAB April 2010
13/175
SOALAN 6
Terdapat berbagai-bagai sumber data kos yang boleh dirujuk dalam
penyediaan anggaran kos seterusnya harga tender. Jelaskan bentuk sumber
maklumat yang diterbitkan atau boleh diperolehi dari Jabatan Kerja Raya
(JKR), Pertubuhan Juruukur Malaysia (ISM), firma perunding Juruukur
Bah an, kontraktor lain dan Jabatan Perangkaan Malaysia.
(25 markah)
QUESTION 6
There are many types and sources of cost data that can be referred to when
preparing cost estimate and tender price. Explain these sources of information
that are produced by or obtainable from Jabatan Kerja Raya (JKR),
Pertubuhan Juruukur Malaysia (ISM), Quantity Surveying consultant firms,
other contractors and Jabatan Perangkaan Malaysia.
(25 marks)
1 1
6
-
8/17/2019 utm FAB April 2010
14/175
LAMPIRAN A/APPENDIX A
Hotels
RMIm2
Resort Hotel indusive of F.F.&E.*■■■*3‘Star budge! hotels, ditto**"*5-star luxury hotels, ditto*
* Cost are at lower Tange cost
Alcost are at anaverage level unlessotherwise stated
12
7
-
8/17/2019 utm FAB April 2010
15/175
SBQ 3522
UTMUNIVERSITI TEKNOLOGI MALAYSIA
Fakulti Alam Bina
FINAL EXAMINATION SEMESTER II SESSION 2009/2010
COURSE CODE
COURSE
PROGRAM
TIME
DATE
LECTURER
PERCENTAGE
SBQ 3522
LEGAL STUDIES III
2 SBQ
2 ya HOURS (2.30 PM - 5.00 PM)
6 APRIL 2010
NOLIZA ISA
40 %
ARAHAN:INSTRUCTION:
1. Jawab empat (4) soalan sahaja. Semua soalan membawa markah yang
sama.
Answer four (4) questions only. All questions carry equal marks.
2. Kanun Tanah Negara 1965 di sediakan.
National Land Code 1965 is provided.
THIS QUESTION PAPER CONSIST OF 6 PAGES INCLUDING THE FRONT PAGE
1
1 3
-
8/17/2019 utm FAB April 2010
16/175
SBQ 3522
Soalan 1
Timbangtara sering dikatakan sebagai satu mekanisma penyelesaian
pertikaian sivil yang berkesan yang dibuat secara judisial. Penimbangtara
memperolehi kuasa menyelesaikan pertikaian dari persetujuan kedua-dua
pihak yang bertikaian di bawah peijanjian timbangtara. Award
penimbangtara adalah muktamat dan mengikat.
Bincangkan kelebihan dan kekurangan timbangtara sebagai satu kaedah
penyelesaian pertikaian.
(25 markah)
Question 1Arbitration is often said to be an efficient method of resolving civil disputes
conducted in judicial manner. The arbitrator derives his power to resolve
dispute from the consent of the disputing parties under the arbitration
agreement. The arbitrator’s award is final and binding on the parties.
Discuss the advantages and disadvantages of arbitration as a method of
resolving disputes.
(25 marks)
Soalan 2
Seseorang pemegang Lesen Pendudukan Sementara di bawah Bab Dua,
Bahagian Empat, Kanun Tanah Negara 1965 tidak “memiliki” tanah yang ia
didudukinya sepertimana yang dimiliki oleh orang yang diberimilik tanah
kerajaan atau pajakan negeri. Walaubagaimanapun, seksyen 44 Kanun
Tanah Negara 1965 menjamin hak pemegang Lesen Pendudukan Sementara
berhubung dengan kegunaan dan kenikmatan eksklusif, hak sokongantanah dan hak ekses.
Dengan merujuk kepada peruntukan dalam Kanun Tanah Negara
berhubung dengan Lesen Pendudukan Sementara dan kes-kes mahkamah
yang berkaitan huraikan sifat-sifat Lesen Pendudukan Sementara dan hak-
hak seseorang pemegang lesen tersebut.
(25 markah)
2
1 k
-
8/17/2019 utm FAB April 2010
17/175
SBQ 3522
Question 2
A holder of a Temporary Occupation License (“TOL”) under Part Four, Chapter
Two of the National Land Code 1965 does not “own” the land as in the case of
a person who has been alienated with a State land or a State lease.
Nevertheless, section 44 of the said Code guarantees the rights of such a TOL
holder with respect to exclusive use and enjoyment of the right of support and
the right of access.
With reference to the provisions in the National Land Code 1965 and the
relevan case law, elaborate the nature of the Temporary Occupation License
and the rights of the holders.
(25 marks)
Soalan 3
Mengikut pengamatan Lord Diplock dalam kes ENG MEE YONG & ORS. v.
LECHUMANAN (1979) 2 MLJ 212 sistem kaveat di Malaysia merupakan
gantian setempat kepada doktrin notis ekuiti di bawah undang-undang
Inggeris. Beliau juga menyamakan kaveat seperti injunksi interlokutori yangmenyekat penanggung kaveat daripada membuat sebarang urusniaga
berhubung dengan tanahnya sehingga mahkamah memutuskan tuntutan
pengkaveat terhadap tanah berkenaan. Matlamat kaveat adalah untuk
memelihara atau mengekalkan status quo pihak-pihak yang berkenaan
sementara menunggu pertikaian mereka di putuskan oleh mahkamah.
Dengan merujuk kepada kenyataan di atas, peruntukan yang berkaitan
dalam Kanun Tanah Negara 1965 dan kes-kes yang relevan, huraikan
fungsi kaveat.
(25 markah)
3
-
8/17/2019 utm FAB April 2010
18/175
SBQ 3522
Question 3
Lord Diplock observed in ENG MEE YONG & ORS. v. LECHUMANAN (1979) 2
MLJ 212 that the caveat system in Malaysia has served as a local substitute
for the equitable doctrine of notice under English land law. His lordship also
said that the caveat under the Torrens System has often been likened to a
statutory injunction of an interlocutory nature restraining the caveatee from
dealing with the land pending the determination by the court of the caveator’s
claim to title to the land. The caveat is principally aimed at maintaining the
status quo of the parties pending the resolution of their disputes by the court.
With reference to the above statement, the relevant sections in the National
Land Code and the case law, explain the functions of caveat.
(25 marks)
Soalan 4
Huraikan kes-kes berikut:-
(i) TEH BEE v. K. MARUTHAMUTHU [1977] 2MLJ 7
(10 markah)
(ii) MOHAMMAD BUYONG v. PEMUNGGUT HASIL TANAH GOMBAK &
ORS[1982] 2 MLJ 53
(15 markah)
Question 4
Elaborate on these cases:-
(i) TEH BEE v. K. MARUTHAMUTHU [1977] 2MU 7
(10 marks)
(ii) MOHAMMAD BUYONG v. PEMUNGUT HASIL TANAH GOMBAK & ORS
[1982] 2 MLJ 53
(15 marks)
4
1 G
-
8/17/2019 utm FAB April 2010
19/175
SBQ 3522
Soalan 5
En. Ali adalah tuan punya berdaftar sekeping tanah di bawah kategori
bangunan. Beliau adalah seorang usahawan dan mahu memperluaskan
perniagaannya. En. Ali telah menggadaikan tanah tersebut kepada
Maybank, Skudai sebagai sekuriti pinjaman. Di sebabkan kemelesetan
ekomoni, En. Ali sukar untuk membuat pembayaran bulanannya. Maybank,
Skudai telah melaksanakan suatu pengurusan kes untuk menolong En. Ali
dalam membuat pembayaran bulanannya, namun En. Ali masih enggan,
gagal dan cuai untuk membuat pembayaran balik pinjamannya.
Nasihatkan Maybank, Skudai akan hak-hak mereka.
(25 markah)
Question 5
En. Ali is a registered proprietor of a piece of land held under building
category. He is a business man and intends to expand his business. He then
charged the land to Maybank, Skudai as a security for a loan. Due to the
economy recession, he found it difficult to service his monthly loan
instalments. Maybank, Skudai extended assistance to En. Ali in undergoing a
case management to enable him to pay the said monthly instalments, but En.
Ali still failed, refused and neglected to make the monthly repayment of his loan.
Advise Maybank, Skudai on their rights.
(25 markah)
Soalan 6
En. Ahmad adalah tuan punya tanah yang bersebelahan dengan jalan raya.
Pihak Berkuasa Negeri, melalui Jabatan Keija Raya telah mewartakan
melalui Seksyen 4 Akta Pengambilan Balik Tanah 1960 satu pengisytiharan
pengambilan balik tanah untuk projek pelebaran jalan raya tersebut. Enam
bulan selepas warta tersebut diterbitkan, suatu peristiharan melalui
Seksyen 8 Akta tersebut di keluarkan. En. Ahmad tidak puas hati bahawa
sebahagian daripada tanahnya terlibat dalam pengambilan balik tanah
tersebut.
r _
5 ;
1 7
-
8/17/2019 utm FAB April 2010
20/175
SBQ 3522
Nasihatkan En. Ahmad tentang haknya untuk membantah pengambilan
balik tanahnya.
(25 markah)
Question 6
En. Ahmad is a registered proprietor of land, adjacent to the main road. The
State Authority through its agency, Public Work Department has gazetted vide
Section 4 of the Land Acquisition Act 1960 a declaration for acquisition of land
for the purpose of the main road upgrading project. Six months after the
publication of the said gazette, a declaration was made vide Section 8 of the
Act. En. Ahmad was not happy that part of his land was identified to be
acquired under the acquisition.
Advise En. Ahmad on his right to object against the acquisition of his land.
(25 marks)
6
-
8/17/2019 utm FAB April 2010
21/175
SBC 3842
UTMUNIVERSITI TEKNOLOGI MALAYSIA
Fakulti Alam Bina
FINAL EXAMINATION
SEMESTER 2 SESSION 2009/2010
COURSE CODE SBC 3842
COURSE BUILDING MAINTENANCE
PROGRAM 3 SBC
TIME 2 HOURS (2.30 pm - 4.30 pm)
DATE 6 APPRIL 2010
LECTURER DR. YAHYA MOHAMAD YATIM
PERCENTAGE 40 %
ARAHAN:
INSTRUCTION:
Jawab 4 SOALAN Sahaja.
Answer 4 Questions Only.
Di mana perlu, nyatakan andaian yang anda buat dengan jelas untuk
disesuaikan dengan jawapan yang anda beri.
Where necessary, please make your own assumptions on any aspects to suit
your answers.
KERTAS SOALAN INI TERDIRI DARIPADA _4_ MUKA SURAT TERMASUK
MUKA SURAT HADAPAN.
1 9
-
8/17/2019 utm FAB April 2010
22/175
SBC 3842
• Penyelenggaraan terdiri daripada beberapa aktiviti seperti memastikan
setiap peralatan and peralatan kemudahan sentiasa berada dalam
keadaan yang baik dan boleh beroperasi sekiranya diperlukan.
• Penyelenggaran juga dikenali sebagai satu cabang dalam sistem
pengurusan asset iaitu memastikan setiap asset tersebut sentiasa
berada dalam keadaan boleh beroperasi pada tahap yang optimum.
Berdasarkan kepada kedua-dua kenyataan diatas, patut atau tidak sebuah
organisasi yang mempunyai jumlah asset yang banyak, contohnya bangunan,
mengajikan staf untuk melakukan kerja-keija penyelenggaraan. Terangkan
peranan yang perlu dilakukan oleh saorang pengurus penyelenggaraan yangdilantik oleh organisasi.
(25 Markah)
QUESTION 1
• Maintenance encompasses all those activities that maintain facilities &
equipment in good working order so that systems can perform as
intended.
• Maintenance can also be termed as asset management system which
keeps them in optimum operating condition.
Based on the above statements, should or should not an organization with a
number of assets e.g. buildings, employ in-house maintenance staff. Describe
the role of in-house maintenance manager.
(25 Marks)
SOALAN 2
Berdasarkan kepada Kerangka Pengurusan Penyelenggaran, terangkan skop
kerja bagi penyelenggaraan bangunan. Rancangkan kerja-keija
penyelenggaran bagi membaikpulih sebuah rumah dua tingkat yang
mengalami kerosakan bumbung, cat yang lusuh dan jubin lantai yang
tertanggal.
(25 Markah)
SOALAN 1
2 02
-
8/17/2019 utm FAB April 2010
23/175
SBC 3842
QUESTION 2
Based on the Maintenance Management Framework (MMF), explain the scopes
of work for the building maintenance. Write a maintenance plan to repair a
double storey house with roof defect, painting peeled and floor tiles broken.
(25 Marks)
SOALAN 3
Kebanyakan kecacatan bangunan adalah disebabkan oleh lembapan,
penggunaan bah an binaan yang salah, rekabentuk bangunan yang lemah
dan faktor alam sekitar. Akibatnya, selepas beberapa bulan bangunan
diduduki oleh pembeli, keretakan dan kebocoran air akan mula kelihatan.
(i) Terangkan jenis-jenis keretakan dan di mana ia biasanya
berlaku di dalam bangunan.
(10 Markah)
(ii) Nasihatkan pembeli bagaimana masalah keretakan dan
kebocoran air di dalam bangunan mereka boleh dibaikpulih.
(15 Markah)
QUESTION 3
Most building defects are caused by dampness, defective materials used, poor
building design and environmental factors. The obvious result was building
cracks and water leakage appeared after a few month of building being
occupied by the purchaser.
(i) Explain the types of cracks and where it will normally be found in
a building.
(10 Marks)
(ii) Advice purchaser how to rectify cracks and water leakage
problems in their building.
(15 Marks)
SOALAN 4
Bincangkan faktor-faktor yang perlu dipertimbangkan apabila membuat bajet
bagi kerja-kerja penyelenggaraan.
2 13
-
8/17/2019 utm FAB April 2010
24/175
SBC 3842
(25 Markah)
QUESTION 4
Describe the factors to be considered when preparing budget for maintenance
works.
(25 Marks)
SOALAN 5
Bincangkan keperluan bagi menyediakan laporan penyiasatan dilapidation
bagi menyiasat tahap kondisi sesebuah bangunan dan terangkan perkara-
perkara yang perlu dimasukkan dalam laporan tersebut.
(25 Markah)
QUESTIONS
Describe the necessity of having a dilapidation survey report in building
condition survey and explain the items that should be included in the report.
(25 Marks)
SELAMAT MAJU JAYA
All the Best
2 24
-
8/17/2019 utm FAB April 2010
25/175
SBQ 4912
UTMUNIVERSITI TEKNOLOGI MALAYSIA
Fakulti Alam Bina
FINAL EXAMINATION
SEMESTER II SESSION 2009/2010
COURSE CODE
COURSE
PROGRAM
TIME
DATE
LECTURER
PERCENTAGE
SBQ 4912
VALUE MANAGEMENT
2SBC/3SBQ
2 HOURS (9.00 AM- 11.00 AM)
9 APRIL 2010
P.M. WAN YUSOFF WAN MAHMOOD
: 40 %
ARAHAN:
INSTRUCTION:
Jawab'empat (4) soalan sahaja.
Soalan satu (1) adalah wajib.
Semua soalan membawa markah yang sama.
Answer four (4) questions only.
Question one (1) is compulsory
All questions carry equal marks.
THIS QUESTION PAPER CONSIST OF 12 PAGES INCLUDING THE FRONT PAGE
-
8/17/2019 utm FAB April 2010
26/175
SBQ 4912
Anda telah dilantik sebagai Perunding Pengurusan Nilai untuk projek
cadangan pembinaan Rumah Kelab (Club House) bagi sebuah padang golf
eklusif yang terletak berhampiran Lapangan Terbang Antarabangsa Sultan
Ismail, Senai, Johor. Pihak klien telah meminta nasihat anda untuk
memilih beberapa jenis penutup bumbung yang sesuai digunakan untuk
rumah kelab berkenaan.
Berdasarkan beberapa kriteria yang anda cadangkan, buat analisa
pemilihan beberapa jenis penutup bumbung yang patut digunakan daripada
beberapa jenis yang ada dipasaran. Gunakan borang-borang diLampiran ‘A’
dan ‘B’ bagi membantu anda menilai cadangan yang terbaik.
(25 markah)
SOALAN 1
QUESTION 1
You are appointed as a Value Management Consultant for the proposed
construction of Club House for an exclusive golf course located adjencent to the
Sultan Ismail International Airport, Senai, Johor. The client seeks your advice
for the selection of a few type of suitable roof covering for the club house.
Based on your own criteria, analyse the selection of various type of roof
covering available in the market. Used forms in the Appendix A and B to
evaluate the best proposal.(25 marks)
2
2 4
-
8/17/2019 utm FAB April 2010
27/175
SBQ 4912
a) Fasa kreativiti merupakan peringkat yang penting didalam sesuatu
bengkel pengurusan nilai. Bincangkan pendekatan yang perlu
diambil oleh ahli kumpulan pengurusan nilai bagi memastikan ianya
dilaksanakan secara efektif.
(13 markah)
b) Huraikan dua (2) jenis teknik yang biasa digunakan untuk
meningkatkan pemikiran kreatif dikalangan ahli kumpulan
pengurusan nilai.
(12 markah)
SOALAN 2
QUESTION 2
a) Creativity phase is an important stage in value management workshop.
Discuss the approach to be taken by the value management team to
ensure it is effectively conducted.
(13 marks)
b) Explain two (2) types of techniques used for promoting creative thinking
to members of the value management team.
(12 marks)
3
-
8/17/2019 utm FAB April 2010
28/175
SBQ 4912
Borang kontrak FIDIC versi terkini telah memasukkan klausa berkaitan
Pengurusan/ Kejuruteraan Nilai yang menyediakan peruntukan bagi
‘Cadangan Pertukaran Pengurusan Nilai’ (VMCP).
a) Apakah yang dimaksudkan dengan ‘Cadangan Pertukaran
Pengurusan Nilai’ (VMCP) serta terangkan kaedah perlaksanaannya.
(10 Markah)
b) Bincangkan elemen-elemen yang mesti dimasukkan didalaxn sebuah
‘Cadangan Pertukaran Pengurusan Nilai’ (VMCP).
(15 Markah)
SOALAN 3
QUESTION 3
Latest FIDIC Form of Contract incorporates the Value Engineering/
Management clause that caters for Value Management Change Proposal
(VMCP) provisions.
a) What is meant by Value Management Change Proposal (VMCP) and
explain the method of their implementation.
(10 Marks)
b) Discuss the elements that must be included in the Value Management Change Proposal (VMCP).
(15 Marks)
-
8/17/2019 utm FAB April 2010
29/175
SBQ 4912
Universiti Teknologi Malaysia bercadang untuk membangunkan sebuah
kampus cawangan baru di Desaru, Kota Tinggi, Johor. Pekeliling Unit
Perancang Ekonomi, Jabatan Perdana Menteri Bilangan 3 Tahun 2009 telah
memutuskan supaya semua program dan projek kerajaan yang bernilai
RM50 juta dan ke atas perlu menggunakan pengurusan nilai. Oleh itu,
pihak pejabat pengarah kerja, Universiti Teknologi Malaysia mahukan
supaya cadangan konsep projek berkenaan dirujuk dan dinilai oleh
perunding pengurusan nilai. Sebagai perunding pengurusan nilai yang
dilantik untuk projek tersebut, anda dikehendaki menyediakan satu laporan
yang menerangkan tentang bagaimana anda akan melaksanakan kajian
berkenaan.
(25 markah)
SOALAN 4
QUESTION 4
Universiti Teknologi Malaysia intends to develop a new branch campus at
Desaru, Kota Tinggi, Johor. Circular of Economy Planning Unit, Prime Minister
Department Number 3 Year 2009 decided that all government programs or
projects value RM 50 millions and above have to apply Value Management.
Hence, Work Director Office, Universiti Teknologi Malaysia wants the concept
proposal for the project to be referred and evaluated by a value management
consultant. As an appointed consultant, you are required to prepare a report
explaining how you are going to implement the study.
(25 marks)
5
-
8/17/2019 utm FAB April 2010
30/175
SBQ 4912
a) Apakah yang dimaksudkan dengan Kos kitaran hayat (LCC) dan
terangkan mengapakah ia penting dalam kajian pengurusan nilai.
(10 markah)
b) Anda dikehendaki mencadangkan sistem penyaman udara kepada
klien anda. Terdapat dua pilihan yang ada untuk dinilai dan
maklumatnya adalah seperti berikut: (Kadar diskaun yang digunakan
adalah 10% - Rujuk lampiran C untuk jadual yang berkaitan).
SOALAN 5
Sistem A Sistem B
Kos Permulaan termasuk
Pemasangan.
RM50.000 RM75,000
Caj Tenaga Tahunan RM2.400 RM 1,500
Persenggaraan (Setiap 5 Tahun) RM2,500 RM 1,500
Jangka Hayat Sistem 20 Tahun 20 Tahun
Berdasarkan kesamaan tahunan (annual equivalent) pebelanjaan
yang terlibat sistem manakah yang akan anda cadangkan kapada
klien anda.
(15 markah)
QUESTION 5
a) What is meant by Life cycle costing (LCC) and explain why is it
important in Value Management study.
(10 marks)
-
8/17/2019 utm FAB April 2010
31/175
SBQ 4912
b) You are required to recommend an air-conditioning system to your
client Two choices are available for assessment and the information
available are as follows: ( a 10% discount rate is applied ) - Refer appendix C for related tables.)
System A System B
Initial cost including installation RM50,000 RM75,000
Annual Energy Charges RM2,400 RM1,500
Maintenance (every 5 years) RM2,500 RM 1,500
Life of system 20 years 20 years
Based on the annual equivalent of the expenses incurred, which system
would you recommend to your client?
(15 marks)
SOALAN 6
a) Terangkan bagaimana model kos disediakan dan bincangkan
kepentingan kos model dalam kajian pengurusan nilai.
(15 markah)
b) Apakah yang anda faham tentang Hukum ‘Pareto’ serta terangkan
bagaimanakah ia boleh membantu didalam kajian pengurusan nilai.
(10 markah)
QUESTION 6
a) Explain how to prepare a cost model and discuss the importance of cost
model in value management study.
(15 marks)
b) What is meant by Pareto Law and explain how they can help during
value management study.
(10 marks)
2 V
-
8/17/2019 utm FAB April 2010
32/175
Appendix A
JUDICIAL PHASE DETERMINING WEIGHTS FOR EVALUATION
STUDY TITLE
GOALS, DESIRED, CRITERIA, F FEATURES
UNCTIONS, RAWSCORE
ASSIGNEDWEIGHT
A.
B.
C.
D.
E. ,
■F.
..
G. /
H.
J.
TOTAL
B' C D E F G H J
HOW IMPORTANT A IB
3. MAJOR PREFERENCE-
c
2. MEDIUM PREFERENCE •0
1. MiRMOR PREFERENCE E
% EQUAL PREFERENCE
G
H
-
8/17/2019 utm FAB April 2010
33/175
I Appendix B
EVALUATION MATRIX
List the best ideas
to see
which has best
trade-off or
optimm ization
potential
-
.
IDEAS WTASSIGNED VALUE
TOTAL
PRESENT WAY 5 E E E E E E E E . E RANK4 VG VG VG VG VG VG VG VG VG3 G G G G' G G G G G2 F F F F F F F F F1 P P P P P P P P P
SUBTOTAL
IDEA1
•
5 E E E E E E E E E RANK4 VG VG VG VG VG VG VG VG VG3 G G G G G G G G G2 F F F F F F F F F1 P P P P P P P P P
SUB
TOTAL
IDEA 2 5 E E E • E E E E E E RANK4 VG VG r VG VG VG VG VG VG VG3 G G G G G G G G G
2 F F F F F F F F F1 P P P P P P P P P
SUB
TOTAL
IDEA 3 5 E E E E E E E . E E RANK4 VG VG VG VG VG VG VG VG VG
3 G G G G G G G G G2 F F F F F F F F F1 P P P P P P P P P •
SUBTOTAL
IDEA 4 5 E E E E E E E E E RANK
4 VG VG VG VG VG VG VG VG VG
3 G G G G G G G G G2 F F F F F F F F F
1 P P P P P P P P P
SUB
TOTAL ....
IDEAS 5 E E E E E E E E E RANK
4 VG VG VG VG VG VG VG VG VG
3 G G G G G G G G G
2 F F F F F F F F F
1 P P P P P P P P P
SUB
TOTAL
SEEK THE BEST - NOT PERFECTION
9 3 1
-
8/17/2019 utm FAB April 2010
34/175
*OLE B Pi e i o n i Value of $1 Duo ot the End of n Potions
PVlf, „ = -------- !—-(I < M
Period
n 1 % 2 v. 3% 4 V. 5% 6 V. 7% 8 % 9 V. 1 0 % 1 1 V. 12 V.
I 99C 900J 9709 9615 9524 9434 9346 9259 9174 9091 9009 0929
2 90:3 9612 9426 92-iC 9070 0900 8734 0573 8-117 026-1 81 16 7972
3 9*:6. 9423 9! 51 8H90 6638 0396 0163 7930 7722 7513 "731 2 7 I 10
4 9C-!0 9238 B8D5 8 S« 8 0227 7921 7629 7350 7084 6030 6507 6355
5 95>5 9057 8626 0219 7035 7473 7130 6806 6499 6209 5935 5674
6 9-«?0 nnoo 0375 7003 7462 7050 6063 6302 :.nr>3 5(i-l5 5316 SHOO7 93:' 8700 ni3t 7099 7107 6G51 6227 51)35 54 70 -- 502 ■1017 4523
8 9 rjs P535 ?R'J4 7307 6 ’ 6 8 6274 5B20 5103 5019 •1065 4 339 ■1039
9 91 3 U360 7664 7026 G-1-1G 5910 5409 5002 •1604 .1 2 -1 1 3903 30U6
1 0 9K3 8203 74.11 6756 6139 55U4 5003 4632 4224 \1 U0 S- 3522 3220
1 1 eye: 8043 7224 6-196 SH4 7 52C0 4751 4209 3875 35C5 317."1 28/5
' 2 0 D'-. 7005 7014 6246 0560 4070 4440 3971 3555 3186 205B 2507
13 8767 7730 GfltU 610G 5303 460(1 4150 3677 3262 2897 2575 22921 0 8700 7579 6 6 1 1 5775 5051 4123 3878 3405 2992 2633 2320 2016
v’ 58 6 : 3 7430 6419 5553 4810 4173 3624 3152 2745 . 2394 2090 1027
ye r - 0520 7284 0232 £339 4501 393C 3387 2UI9 2519 2176 1883 IG31
17 ^ e-ua 71.126030
5i344363
37m3IG6 2703 2311 I97B 1696 141.6
IB 1 03g: 7002 5874 •1936 4155 3503 2959 2502 2120 1 799 1520 1309
l‘J 0?” 6961 5703 4 ,v.6 3957 3305 2765 231/ 19-15 1635 1377 1 16i
20 8‘35 6/30 5537 4564 3769 3110 2504 2145 I7B4 I486 1240 1037
?' 0 1 4 6598 5375 •131)0 3589 2942 2-115 191*7 16.17 I3M 1117 OU26
:? 0034 6468 5219 4 220 3410 2775 2257 1839 1502 l?28 1007 0026
2J ?9b-: 6342 5007 4057 3256 2610 2109 1/03 1378 IH7 090/ 0/30
7B'6 6217 4919 3901 3101 24 70 1971. 1577 1 ?r,.i 1015 0017 0059
25 7798 6095 4776 3751 2953 23J0 1842 1400 1 160 0923 0730 0580
26 7 720 5976 4637 3607 2012 21‘JO 1722 13!,2 106-1 0(139 01-63 0525
27 70*14 5859 4502 3468 2670 2074 ICO!) 1252 0376 0763 059/ 0469
20 7568 5744 •1371 3335 2551 1950 1504 ) 159 01195 0093 0530 04 19
.29 7.153 5631 4243 3207 2429 18-16 1406 1073 0022 0630 0405 0374
30 7 . 1 1 9 5521 4 130 OOB3 231-1 1 741 in 1 4 0!I!I4 07.VI nr ,n (1-1.3/ 111 14
.If): * V •- •
7 059 5000 3554 2534 10 in 1301 093 7 00 7 6 0-190 o;if.f. 0259 OlOU
40 6? ' ? •1529 3066 2083 1420 0972 0668 0160 0310 .0221 0 1 5-1 0107
45 CTT 4 10?2044 1712 . 1 1 13 0727 04 7G o:n n 020/ 0 1 .1 / OHO 1 (Kir. 1
50 c:c: 3715 27 81 1407 0872 05-13 0339 0213 0134 0005 005-1 0035
-
8/17/2019 utm FAB April 2010
35/175
3% 14% 15"/. 16% 17% IBV. 19% 20% 2SV. 30%
------- t R-
35% 4,0%
050
0.11
931
3J
428
87 72
7G95
n/!,0
;>P21
5 > y.i
eonr.
7501
or.75
0/10
4972
0021
7 132
GI07
5523
4 7Cy 1
054 7
7305
0244
5337
4‘ jGI
04 75
7102
fiOllli
5150
437 1
0103
7062
5!i:M
4' jo?
■1190
n333
6941
57Q7
•1023
4019
0000
6400
5120
40%
327 7
7692
5917
0
0000
A p p en d i
x
-
8/17/2019 utm FAB April 2010
36/175
B(_£ d Prevtnl Valu* ol on Annuity of 51 por P»flod lor n P»ilcxJ»
i
eriod
n 1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 11% 12% 13% 14% 15% 16% 17% 18% 19% 20% 25% 30% 35% 40%
1 0 9901 0 9804 0 9700 09GI5 0 9524 0 9434 0 9346 0 9259 09174 0 9091 0 9009 0 0029 0 0050 00772 0 0G96 011021 0 0547 0 0475 0 0403 0 8333 0 nooo 0 7602 0 7407 0 7143
2 1 9704 1 9416 1 9135 11)001 1 0594 ) B334 1 B0B0 1 7633 1 7591 1 7355 1 7)25 1 G90I 1 6681 1 6467 1 6257 1 6052 1 5B52 1 5G5G 1 5405 1 5278 1 4400 1 3609 1 2894 1 2245
3 2 94 10 2 8839 2 8286 2 7?5l 2 7232 2 6730 2 6243 2 5771 2 5313 2 4869 2 4437 2 4010 2 3612 2 3216 2 2632 2 2459 2 2006 2 1743 2 1399 2 1065 1 9520 10161 1 6959 1 5089
4 '3 9020 3 0077 3 7171 3 6299 3 5460 3 465) . P 3072 3 3121 3 2397 3 IG99 3 >024 3 0373 2 0745 2 9137 2 0550 2 7902 2 7432 ? 6901 2 0300 2 5007 2 3GIG 2 I6G2 1 9909 1 8492
5 4 8534 4 7135 4 5797 4 4518 •1 3295 •1 2124 4 1002 3 9927 3 0097 3 7908 3 G959 3 6048 3 5172 3 4331 3 3522 3 2743 3 >993 3 1272 3 0576 2 9906 2 6B93 2 4356 2 2200 2 0352
6 5 7955 56014 5 4172 5 24?) 5 0757 4.9173 4 7065 4 0229 4 4059 4 3553 4 2305 4 1114 3 9975 3 8007 3 7045 3 684 7 3 5002 3 4076 3 4090 3 3255 2 9514 2 6427 2 3052 2 IGOO
7 6 7202 6 4 720 6 2303 G 3021 5 7064 5 5024 5 31 )93 5 2064 5 0330 4 0G04 4 7122 4 5636 4 4226 4 2083 4 1604 4 038G 3 9224 3 Bl 15 3 7057 3 604G 3 1611 2 0021 2 5075 2 2628
8 7 6517 7 3255 70197 fi 7327 G 4632 6 2098 5 9713 5 74G6 5 5348 5 3349 5 1461 4 9076 4 7908 4 6309 4 4873 4 3436 4 2072 4 0770 3 95-14 3 83/2 3 3289 2 9247 2 5982 2 3306
9 6 5660 0 1622 7 7861 7 4353 7 1070 6 R017 G 5152 6 2469 5 9952 5 7590 5 5370 5 3282 5 1317 4 9464 4 7716 4 6065 4 4506 4 3030 4 1633 . 4 0310 3 >1631 3 0190 2 6653 2 3790
10 94713 8 9826 0.5302 8 1! 09 7 721 7 7 3601 7 0236 G 7101 64177 6 1446 5B092 5 G502 5 4262 5 2161 S01R8 4 0332 4 G50G 4 494 1 4 33U0 4 1025 3 5705 3 0915 2 7150 2 4138
11 10 368 9 78GB 9 2526 8 7G05 8 3004 7 BB69 7 -1987 7 1300 G nos? 0 4951 6 2005 5 9377 5 G0G9 5 4527 5 2337 5 0206 4 B304 4 0500 4 4005 .1 3271 3 0504 3 1473 2 7510 2 4.1113
12 11 255 10 575 9 9540 9 3051 0 0G.13 t i niun 7 9427 7 53G1 7 1007 G 6137 G 4024 G 1944 5 0170 5 0003 5 420G 5 1971 4 911114 4 703? 4 0105 4 4:i!)2 3 7251 3 1903 2 779? 2 4!,59
13^ ^
««5^
12 134 11 340 10G35 9 9nso 9 3030 8 8527 0 3577 7 90311 7 4000 7 1034 fi 7499 6 4235 0 1218 5 0424 5 :>o: j 1 5 3423 5 1 1113 4 9095 4 /147 4 5327 3 7001 3 2233 2 7994 2 4GII5
13 004 12 I0G II 29G 10 503 9 Wlllfi 9 ?u:.o 0 7455 n ?4.|;| 7 7Bli2 7 3007 G 9010 0 0202 G 3025 G 0021 5 7245 5 4675 5 2293 5 001)1 4 11023 ■I 0100 3 024 I 3 2487 2 8I4.| 2 47/5
IS''1-' I3 0GS 12 849 11 030 ii tie 10 3110 9 71^2 9 1079 8 5595 0 0007 7 0061 7 1900 6B109 6 4624 6 142? 5 04 74 5 5755 5 3242 5 OHIO 4 0750 4 0755 3 0593 3 2G02 2 0255 2 4039
16 . 14 718 13 570 12 561 11 652 io bub 10 >06 9 446G 0 8514 0 3126 7 8237 * 7 3792 6 9740 6G039 6 2G5I 5 9542 5 6GB5 5 4053 5 1024 4 9377 4 /2‘IC» 311074 3 2032 2 8337 2 4885
I? 15 562 14 292 13 166 12 166 11 274 10 477 9 7632 9 .104.17 44 12 0 0007 C 5335 G 1520 5 UO'IO 5 5010 5 ??:‘n 4 '100/ 3 9*J?3 3 3312 2 0505 2 40*10
29 25 066 21 844 19 mo 1G‘JB4 IS Ml 13 591 12 278 11 150 10 190 9 3696 B 6501 0 02)0 7 4 7QI 6 9830 6 5509 0 16565 8204 5 5000 5 2292 4 9747 3 99311 3 3317 2 B5G7 2 4999
30 25 808 22 396 19 600 17 292 15 372 13 705 12 409 II ?5B 10 274' 0 4269 R 093B 8 055? 7 40577 0027 0 5600 0 1 77? 5 0294 5 5100 5 2.14 7 4 97nn 3 0050 .13321 ? nr,Oil ? 4909
35 29 409 24 999 21 407 18 065 10 374 14 490 1? 94| l 11 055 10 5G7 9 0442 B 0552 8 1755 7 505G 7 0700 0 GIGC 0 2153 5 8502 5 5306 52512 4 99153 9904 3 3330 2 8571 2 5000
40 32 835 27 355 23 115 19 793 17 159 15 046 13 332 1) 925 10 757 9 7791 0 951) 0 24307 0344 7 1050 G 04 10 6 2335 5 07)3 5 5402 5 2502 4 99G0 3 9995 3 3332 2B57I 2 5000
-
8/17/2019 utm FAB April 2010
37/175
Appendix C
TABLE A.4 ANNUAL EQUIVALENT OF AN INITIAL PAYMENTo f £ i ( I N £ l * S )
No. Rate of interest
of -------------------------------------------------------- ------!------ ------------yean 4% 5% 6% 7%8% 9% • ZO%
I-06000 1*07000 1*08000 1*09000 1*10000
0*54544 0*55309 0*56079 0*56847 0*576200*37411 0*38105 0*38805 0*39507 0*402x2
X 1*04000 2*05000
2 0*53020 0-53781
3 0*36035 0*36721
4 0*27549 0*282015 0*22463 0*23098xo 0*12329 0'12951
25 0*08994 0*0963420 0-07358 0*08024
25 0*06401 0*07095
30 0*05783 0*06505
35 0*05358 0*0620740 0*05052 0*05828
45. 0*04826 0*05626
50 0*04655 0*0547855 0*04523 0*0536760 0*04420 0-05283
70 0*04275 0*05x70So 0*04x81 0*05x0390 0*04221 0*05063
100 l 0 0
O £ 0 0
0*10955 0*12746
0*09022 0*100130*09009 0*100040*09004 0*100020*09002' 0*20002
12
3 4
-
8/17/2019 utm FAB April 2010
38/175
SBC2242
UNIVERSITI TEKNOLOGI MALAYSIA
Fakulti Alam Bina
FINAL EXAMINATION
SEMESTER II SESSION 2009/2010
COURSE CODE
COURSE
PROGRAM
TIME
DATE
LECTURER
PERCENTAGE
SBC 2242
CONSTRUCTION TECHNOLOGY II
1 SBC
2 y2 HOURS (9.00 AM - 11.30 AM)
12 APRIL 2010
EN. SYAMSUL HENDRA B. MAHMUD
40 %
ARAHAN:
INSTRUCTION:
Jawab empat (4) soalan sahaja. Semua soalan membawa markah yang sama.
Answer four (4) questions only. All questions carry equal marks.
1. Di mana perlu, nyatakan andaian anda berkenaan dengan saiz elemen
dan kaedah kerja yang dijalankan.
Where necessary, please make your own assumptions on the size of the
items and relevant construction work/activities.
2. Semua lukisan perlu disertakan dengan huraian dan label lengkap.
All drawings must be completed with annotation and side notes.
THIS QUESTION PAPER CONSIST OF 7 PAGES INCLUDING THE FRONT PAGE
1
-
8/17/2019 utm FAB April 2010
39/175
SBC2242
Sebuah bangunan komersil setinggi 35 tingkat berkerangka keluli akan
dibina di pusat bandaraya Kuala Lumpur yang bakal menempatkan menara
pejabat dan pusat membeli-belah.
a) Terangkan berserta lakaran yang bersesuaian mengenai sambungan-
sambungan bagi struktur-struktur berikut menggunakan kaedah
kimpalan dan kaedah bolt:
i) Tiang ke tapak tiang
ii) Tiang ke tiang
iii) Rasuk ke tiang
(15 markah)
b) Terangkan berserta lakaran yang bersesuaian mengenai kaedah
perlindungan api untuk struktur kerangka keluli tersebut.
(10 markah)
QUESTION 1
A 35 storey steel structure commercial building will be built in Kuala Lumpur
city centre which consists of an office tower and shopping complex.
a) Explain with appropriate sketches the connections for these structures using
welding and bolting techniques:
i) Column to column base ii) Column to column
iii) Beam to column
(15 marks)
b) Explain with appropriate sketches the fire protection techniques for the steel
structures.
SOALAN 1
(10 marks)
2
5 2
-
8/17/2019 utm FAB April 2010
40/175
SBC2242
a) Huraikan berserta lakaran tentang konsep serta pembinaan bumbung
kerangka portal jenis keluli.
(15 markah)
b) Huraikan kebaikan dan keburukan penggunaan struktur bumbung
cengkerang dan bumbung berlipat.
(10 markah)
QUESTION 2
a) Explain with sketches the concept and construction of steel portal frame
roof
(15 marks)
b) Explain the advantages and disadvantages of shell roof and folded slab roof
structure.
(10 marks)
SOALAN 2
3
-
8/17/2019 utm FAB April 2010
41/175
SBC2242
a) Syarikat Crospax telah ditawarkan kontrak untuk kerja perobohan sebuah
bangunan rumah kedai 2 tingkat sedia ada di kawasan Taman Mutiara
Rini, Johor Bahru bagi membina bangunan pejabat 5 tingkat di atas
tanah tersebut. Lokasinya adalah berhampiran kawasan perumahan sedia
ada. Berikan penerangan ringkas kepada pihak klien mengenai:
i) Kriteria-kriteria yang perlu diambil kira sebelum sesuatu teknik
perobohan tersebut dipilih.
(15 markah)
ii) Langkah-langkah keselamatan yang bersesuaian dengan kerja
perobohan tersebut.
(10 markah)
QUESTION 3
a) Contractor Crospax has been offered a contract for demolition works of a
double storey shop house in Taman Mutiara Rini, Johor Bahru in order to build a new 5 storey office building in the proposed area. The location of the
site is nearby the existing residential area. Explain briefly to the client
about:
i) The criterias need to be considered before choosing any types of
demolition techniques.
(IS marks)
ii) The suitable safety precautions for the demolition project.
SOALAN 3
(10 marks)
4
5 4
-
8/17/2019 utm FAB April 2010
42/175
a) Huraikan faktor-faktor yang mempengaruhi pemilihan lantai atas.
(10 markah)
b) Huraikan berserta lakaran mengenai pembinaan papak rata dan lantai
waffle.
(15 markah)
QUESTION 4
a) Describe what are the factors influencing the selection of upper floors.
(10 marks)
b) Explain with sketches the construction of flat slab and Waffle floor.
(15 marks)
SBC2242
SOALAN 4
5
-
8/17/2019 utm FAB April 2010
43/175
SBC2242
a) Cadang dan lakarkan komponen perabot dalaman yang sesuai untuk
ruang tamu rumah kediaman untuk memuatkan buku, majalah, alat
sistem hiburan rumah dan barang hiasan.
(15 markah)
b] Terangkan fungsi perabot dalaman bagi sebuah kediaman mewah dua
tingkat.
(10 markah)
QUESTION 5
a) Suggest and sketch the suitable components for built in fitment suitable for
living area in residential houses for books, magazines, home theatre system
and decorations.
(1 Smarks)
a) Explain the function of built in fitment for a luxury two storey house
(10 marks)
SOALAN 5
6
5 6
-
8/17/2019 utm FAB April 2010
44/175
SBC2242
a) Cadangkan dua jenis kemasan lantai, satu jenis kemasan siling dan dua
jenis kemasan dinding yang sesuai bagi sebuah apartment mewah setinggi
10 tingkat. Berikan justifikasi terhadap pemilihan kemasan - kemasan
tersebut.
(25 markah)
QUESTION 6
a) Suggest two types of floor finishes, one type of ceiling finishes and two
types of wall finishes suitable for a 10 storey luxury apartment. Justify your
choices on the finishes.
(25 marks)
SOALAN 6
SELAMAT MENJAWAB DAN SELAMAT MAJU JAYA
-
8/17/2019 utm FAB April 2010
45/175
SBQ 1223
UNIVERSITI TEKNOLOGI MALAYSIA
Fakulti Alam Bina
FINAL EXAMINATION SEMESTER II SESSION 2009/2010
COURSE CODE SBQ 1223
COURSE CONSTRUCTION TECHNOLOGY I
PROGRAM 1 SBQ
TIME 2 HOURS (9.00 AM - 11.00 AM)
DATE 12 APRIL 2010
LECTURER EN. SYAMSUL HENDRA B. MAHMUD
PERCENTAGE 40 %
ARAHAN:
INSTRUCTION:
Jawab empat (4) soalan sahaja. Semua soalan membawa markah yang sama.
Answer four (4) questions only. All questions carry equal marks.
1. Di mana perlu, nyatakan andaian anda berkenaan dengan saiz elemen
dan kaedah kerja yang dijalankan.
Where necessary, please make your own assumptions on the size of the
items and relevant construction work/activities.
2. Semua lukisan perlu disertakan dengan huraian dan label lengkap.
All drawings must be completed with annotation and side notes.
THIS QUESTION PAPER CONSIST OF 6 PAGES INCLUDING THE FRONT PAGE
1
5 8
-
8/17/2019 utm FAB April 2010
46/175
SBQ 1223
a) Lakarkan lima (5) jenis susun atur binaan tangga yang biasa digunakan.
(10 markah)
b) Berbantukan lakaran berlabel, lakarkan proses pembinaan terperinci
sebuah tangga lurus konkrit tuang in-situ.
(15 markah)
QUESTION 1
a) Sketch five (5) types of staircase layout which are commonly used.
(10 marks)
b) Aided with annotated sketches, sketch the details components of an in-situ
straight concrete staircase.
(15 marks)
SOALAN 2
a) Berbantukan lakaran berlabel, terangkan mengenai perbezaan di antara
tingkap ram tetap dan tingkap ram boleh laras.
(15 markah)
b) Pintu panel biasa digunakan di rumah-rumah kediaman. Huraikan
berserta lakaran yang bersesuaian tentang komponen-komponen pintu
panel tersebut.
SOALAN 1
(10 markah) .
2
5 9
-
8/17/2019 utm FAB April 2010
47/175
SBQ 1223
a) Aided with annotated sketches, explain the difference between fixed
louvered window and adjustable louvered window.
(15 marks)
bj Paneled door are commonly used in residential buildings. Explain using
appropriate sketches the components of the paneled door.
(10 marks)
SOALAN 3
a) Bincangkan dengan ringkas kelebihan dan kelemahan tiga (3) jenis
kemasan lantai dan dua (2) jenis kemasan dinding yang biasa digunakan
bagi bangunan sekolah.
(15 markah)
b) Bincangkan dengan ringkas faktor pemilihan bagi kemasan lantai yang
biasa digunakan bagi rumah kediaman.
(10 markah)
QUESTION 3
a) Briefly discuss the advantages and disadvantages of three (3) types of floor
finishes and two (2) types of wall finishes commonly used for school
buildings.
(15 marks)
b) Briefly discuss the functional requirements for floor finishes which is
commonly used for residential housing.
/■"N
b(J
QUESTION 2
(10 marks)
3
-
8/17/2019 utm FAB April 2010
48/175
SBQ 1223
a) Huraikan berserta lakaran mana - mana lima (5) komponen bumbung
cerun yang berikut:
i. “Battem”
ii. “Valley Board”
iii. “Verge”
iv. “Wall Plate”
v. “Rain Water Down Pipe”
vi. “Common Rafter”
vii. “Gutter"
(15 markah)
b) Berbantukan lakaran berlabel, terangkan mengenai komponen-komponen
terperinci bagi ‘lean to roof dan ‘monopitch roof.
(10 markah)
QUESTION 4
a) Explain with sketches any five (5) of the following components of staircase:
i. “Battem”
ii. “Valley Board”
iii. “Verge”
iv. “Wall Plate”
v. “Rain Water Down Pipe”
vi. “Common Rafter”
vii. “Gutter”
(15 marks)
b) Aided with annotated sketches, explain the detail components for lean to roof
and monopitch roof
SOALAN 4
(10 marks)
4
6 1
-
8/17/2019 utm FAB April 2010
49/175
SBQ 1223
a) Huraikan perbezaan di antara dinding galas beban dan dinding tidak
galas beban.
(10 markah)
b) Berbantukan lakaran bernota, huraikan proses pembinaan dinding bata
dengan menggunakan ikatan Flemish.
(15 markah)
QUESTION 5
a) Describe the differences between load bearing wall and non-load bearing
wall.
(10 marks)
b) Aided with annotated sketches, explain the construction process for
brickworks using Flemish bonding.
(15 marks)
SOALAN 6
a) Bincangkan dengan ringkas keperluan fungsi bagi siling yang biasa
digunakan bagi rumah teres dua tingkat.
(10 markah)
b) Berbantukan lakaran bernota, terangkan mengenai komponen siling
gantung.
SOALAN 5
(15 markah)
-
8/17/2019 utm FAB April 2010
50/175
SBQ 1223
a) Briefly discuss the functional requirements for ceiling which is commonly
used for two storey terrace housing.
(10 marks)
b) Aided with annotated sketches, explain the component for suspended
ceiling.
(15 marks)
QUESTION 6
SELAMAT MENJAWAB DAN SELAMAT MAJU JAYA
-
8/17/2019 utm FAB April 2010
51/175
SBC1222
UNIVERSITI TEKNOLOGI MALAYSIA
Fakulti Alam Bina
FINAL EXAMINATION SEMESTER II SESSION 2009/2010
COURSE CODE SBC 1222
COURSE CONSTRUCTION TECHNOLOGY I
PROGRAM 1 SBC
TIME 2 HOURS (9.00 AM - 11.00 AM)
DATE 12 APRIL 2010
LECTURER EN. SYAMSUL HENDRA B. MAHMUD
PERCENTAGE 40 %
ARAHAN:
INSTRUCTION:
Jawab empat (4) soalan sahaja. Semua soalan membawa markah yang sama.
Answer four (4) questions only. All questions carry equal marks.
1. Di mana perlu, nyatakan andaian anda berkenaan dengan saiz elemen
dan kaedah kerja yang dijalankan.
Where necessary, please make your own assumptions on the size of the
items and relevant construction work/activities.
2. Semua lukisan perlu disertakan dengan huraian dan label lengkap.
All drawings must be completed with annotation and side notes.
THIS QUESTION PAPER CONSIST OF 6 PAGES INCLUDING THE FRONT PAGE
1
6 k
-
8/17/2019 utm FAB April 2010
52/175
SB Cl 222
a) Lakarkan lima (5) jenis susun atur binaan tangga yang biasa digunakan.
(10 markah)
b) Dengan bantuan lakaran berlabel, lakarkan proses pembinaan terperinci
sebuah tangga lurus konkrit tuang in-situ.
(15 markah)
QUESTION 1
a) Sketch five (5) types of staircase layout which are commonly used.
(10 marks)
b) Aided with annotated sketches, sketch and label the construction process of
an in-situ straight concrete staircase.
(15 marks)
SOALAN 2
a) Bincangkan dengan ringkas keperluan fungsi bagi tingkap yang biasa
digunakan bagi rumah kediaman.
(5 markah)
b) Dengan bantuan lakaran berlabel, terangkan mengenai perbezaan di
antara pintu panel dan pintu rata.(20 markah)
SOALAN 1
2
-
8/17/2019 utm FAB April 2010
53/175
SBC1222
a) Briefly discuss the functional requirements for windows which are commonly
used for residential housing.
(5 marks)
b) Aided with annotated sketches, explain the difference between panelled door
and flat flush door.
(20 marks)
SOALAN 3
a) Dengan bantuan lakaran berlabel, terangkan mengenai proses
pemasangan kemasan dinding jenis jubin seramik bersaiz 200mm x
200mm bagi bilik air sebuah rumah teres dua tingkat.
(15 markah)
b) Bincangkan dengan ringkas faktor pemilihan bagi kemasan lantai yang
biasa digunakan bagi rumah kediaman satu tingkat.
(10 markah)
QUESTION 3
a) Aided with annotated sketches, explain the installation process for 200mm x
200mm ceramic tiles finishes for a double storey terrace houses bathroom.
(15 marks)
b) Briefly discuss the selection factors for floor finishes which is commonly
used in single storey residential housing.
QUESTION 2
(10 marks)
3
6 6
-
8/17/2019 utm FAB April 2010
54/175
SBC1222
a) Huraikan berserta lakaran mana - mana lima (5) komponen-komponen
bumbung cerun yang berikut:
i. “Hip Rafter”
ii. “Jack Rafter”
Hi. “Valley Rafter”
iv. “Wall Plate”
v. “Rain Water Down Pipe”
vi. “Ridge Board”
vii. “Verge”
(25 markah)
QUESTION 4
a) Explain with sketches any five (5) of the following components of staircase:
i. “Hip Rafter”
ii. “Jack Rafter”
iii. “Valley Rafter”
iv. “Wall Plate”
v. “Rain Water Down Pipe”
vi. “Ridge Board”
vii. “Verge”
(25 marks)
SOALAN 4
4
6 7
-
8/17/2019 utm FAB April 2010
55/175
SBC1222
a) Dengan bantuan lakaran bernota, terangkan mengenai sistem kerangka
yang bersesuaian bagi sebuah rumah banglo dua tingkat.
(15 markah)
b) Dengan bantuan lakaran bernota, huraikan proses pembinaan dinding
bata dengan menggunakan ikatan Flemish.
(10 markah)
QUESTION 5
a) Aided with annotated sketches, explain the frame system suitable for a
double storey bungalow.
(15 marks)
b) Aided with annotated sketches, explain the construction process for
brickworks using Flemish bonding.
(10 marks)
SOALAN 5
6b
5
-
8/17/2019 utm FAB April 2010
56/175
a) Dengan bantuan lakaran bernota, terangkan mengenai komponen siling
gantung.
(25 markah)
QUESTION 6
a) Aided with annotated sketches, explain the component of suspended
ceiling.
(25 marks)
SBC1222
SOALAN 6
SELAMAT MENJAWAB DAN SELAMAT MAJU JAYA
-
8/17/2019 utm FAB April 2010
57/175
SBC 1233
UTMUNJVERSITl TEKNOLOGI MALAYSIA
Fakulti Alam Bina
FINAL EXAMINATION
SEMESTER 2 SESSION 2009/2010
COURSE CODE
COURSE
PROGRAM
TIME
DATE
LECTURER
PERCENTAGE
SBC 1233
BUILDING SERVICES SYSTEM
1 SBC
2 HOURS (9.00 pg - 11.00 pg)
13 APRIL 2010
DR. YAHYA MOHAMAD YATIM
40 %
ARAHAN:
INSTRUCTION:
Jawab 4 SOALAN Sahaja.
Answer 4 Questions Only.
Di mana perlu, nyatakan andaian yang anda buat dengan jelas untuk
disesuaikan dengan jawapan yang anda beri.
Where necessary, please make your own assumptions on any aspects to suit your answers.
KERTAS SOALAN INI TERDIRI DARIPADA _4_ MUKA SURAT TERMASUK MUKA
SURAT HADAPAN.
7 0
i
-
8/17/2019 utm FAB April 2010
58/175
SBC 1233
Terangkan fungsi komponen-komponen berikut yang berkaitan dengan sistem
kumbahan di dalam bangunan.
(i) Paip air kumbahan dan paip air buangan
(ii) Perangkap Air
(iii) Paip pengudaraan
(iv) Peralatan Kumbahan
(v) Peralatan Air buangan
(25 Markah)
QUESTION 1
Explain the function of sewerage components in building as follows:
(i) Soil and waste stack pipe
(ii) Water trap
(iii) Vent pipe
(iv) Soil Appliances
(v) Waste Appliances
(25 Marks)
SOALAN 2
(i) Terangkan perbezaan diantara sistem pengudaraan semulajadi dengan
pengudaraan makanikal.
(10 Markah)
(ii) Terangkan bagaimana pengudaran semulajadi bagi bangunan satu
tingkat boleh diperolehi dangan berkesan.
(15 Markah)
QUESTION 2
(i) Explain the distinctions of mechanical and natural ventilation system.
(10 Marks)
(ii) Explain how natural ventilation can effectively be achieved in a single
storey house.
(15 Marks)
SOALAN 3:
(i) Lakar dan terangkan bagaimana kitaran refrigeren di dalam penyaman
udara jenis tingkap.
(10 Markah)
(ii) Dengan berbantu lakaran, terangkan bagaimana sistem penyaman udara
unit terpisah dipasang pada bangunan
(15 Markah)
SOALAN 1
7 12
-
8/17/2019 utm FAB April 2010
59/175
SBC 1233
QUESTION 3
(i) Sketch and explain the refrigerant cycle in window type air-conditioning
system.
(10 Marks)
(ii) With the aid of sketches, explain how split air-conditioning system be
installed in buildings.
(15 Marks)
SOALAN 4
Lakar (tidak mengikut sekala) rajah pendawaian bagi rumah kediaman bermula
dari fius pemotong bekalan sehingga ke litar akhir serta namakan dan
terangkan fungsi bagi setiap komponen tersebut.
(25 Markah)
QUESTION 4
Sketch (not to scale), name and explain the function of the main component of the
domestic electrical diagram from cutout fuse to the final circuit.
(25Marks)
SOALAN 5
(i) Terangkan keperluan pemasangan lift bagi bangunan tinggi seperti yang
dikehendaki oleh Undang-Undang Bangunan Seragam 1984
(10 Markah)
(ii) Namakan dan terangkan fungsi utama komponen lif electrik.
(15 Markah)
QUESTION 5
(i) Explain the requirement of lift in high-rise buildings as ruled out in Uniform
Building By-Laws 1984.
(10 Marks)
(ii) Name and explain the main component of electric lifts.
(15 Marks)
SOALAN 6
(i) Apakah definisi eskalator.
(5 Markah)
(ii) Terangkan kelebihan dan kekurangan sudut kecondongan eskalator.
(10 Markah)
(iii) Terangkan tiga jenis susunatur eskalator yang biasa dipasang pada
kompleks membeli belah.
(10 Markah).
7 23
-
8/17/2019 utm FAB April 2010
60/175
QUESTION 6
(i) What is the definition of escalator?
(5 Marks)
(ii) Explain the advantages and disadvantages of the escalator slope.
(10 Marks)
(Hi) Explain three types of escalator layout commonly installed in a shopping
complex.
(10 Marks)
SBC 1233
SELAMAT MAJU JAYA All the Best
4
7 3
-
8/17/2019 utm FAB April 2010
61/175
SBQ 2233
UTMUNIVERSITI TEKNOLOGI MALAYSIA
Fakulti Alam Bina
FINAL EXAMINATION SEMESTER II SESSION 2009/2010
COURSE CODE
COURSE
PROGRAM
TIME
DATE
LECTURER
PERCENTAGE
SBQ 2233
BUILDING SERVICES II
1 SBQ
2 HOURS (2.30 PM - 4.30 PM)
13 APRIL 2010
ISMAIL BIN HARON
40 %
ARAHAN:INSTRUCTION:
Jawab empat (4) soalan sahaja. Semua soalan membawa markah yangsama.
Answer four (4) questions only. All questions carry equal marks.
THIS QUESTION PAPER CONSIST OF 6 PAGES INCLUDING THE FRONT PAGE
1
-
8/17/2019 utm FAB April 2010
62/175
SBQ 2233
a) Terangkan dengan ringkas klasifikasi risiko yang digunapakai
pada sistem semburan.
( 7 markah )
b) Dengan berbantukan lakaran, terangkan komponen-komponen
asas serta teknik pemasangan sebuah sistem semburan.
( 18 markah)
SOALAN 1
QUESTION 1
a) Briefly describe the risk classification used in a sprinkler system.
( 7 marks )
b) With the aid of sketches, describe the basic components and
installation techniques of a sprinkler system.
(18 marks )
SOALAN 2
a) Terangkan perbezaan antara sistem penyaman udara kemas-siap
penyejukkan udara dengan sistem kemas siap penyejukkan air.
( 5 markah )
b) Dengan berbantukan lakaran, terangkan prinsip operasi sistem
penyaman udara menggunakan sistem logi pusat air sejuk.
( 20 markah )
-
8/17/2019 utm FAB April 2010
63/175
SBQ 2233
a) Describe the difference between an air cooled packaged and water
cooled packaged air conditioning system.
(5 marks )
b) With athe aid of sketches, describe the operation principles of a
central water chiller air conditioning system.
( 20 marks )
QUESTION 2
SOALAN 3
a) Terangkan apa yang dimaksudkan dengan Population Equivalents
(PE) dalam perawatan kumbahan.
( 5 markah )
b) Dengan berbantukan lakaran, terangkan prinsip operasi sistem
Turas Pencucur Kadar Tinggi.
( 20 markah )
QUESTION 3
a) Explain what is meant by Population Equivalents (PE) in the sewage
treatment.
( 5 marks )
b) With the aid of sketches, describe the operation principles of the
High Rate Trickling Filter (HRTF) system.
(20 marks )
3
7 6
-
8/17/2019 utm FAB April 2010
64/175
SBQ 2233
a) Terangkan ciri-ciri yang menentukan kecekapan sesebuah sistem
lif.
( 10 markah )
b) Terangkan komponen-komponen asas sebuah sistem lif elektrik.
( 15 markah )
QUESTION 4
a) Describe the characteristics that determines the efficiency of a lift
system.
(10 marks )
b) Describe the basic components of an electric lift.
(15 marks )
SOALAN 5
a. Terangkan kelebihan penggunaan tangga gerak berbanding lif di
dalam bangunan.
( 5 markah )
b. Terangkan dengan ringkas fungsi komponen tangga gerak berikut:
i) Kerangka penyokong utama
ii) Motor tarikan
iii) Anak tangga dan rantai anak tangga
iv) Susur tangga
SOALAN 4
( 20 markah )
7 7
-
8/17/2019 utm FAB April 2010
65/175
SBQ 2233
a) Describe the advantages of the use of escalators compared to lift in
building.
( 5 marks )
b) Briefly describe the function of the following components of an
escalator:
i) Main support truss
ii) Traction motor
iii) Steps and step chain
iv) Balustrade
(20 marks )
QUESTION 5
SOALAN 6
Terangkan dengan ringkas perkara-perkara berikut:
a) Sistem automasi bangunan
b) Sistem penyaman udara jenis unit pisah
c) Sistem melawan kebakaran jenis pemasangan tetap CO2
d) Sistem perlupusan kumbahan jenis parit pengoksidaan
e) Perbezaan antara eskalator, travelator dan walkalator
( 25 markah )
5
7 6
-
8/17/2019 utm FAB April 2010
66/175
SBQ 2233
Briefly describe the followings:
a) Building automation system
b) Split unit air conditioning system
c) Fixed C02 fire supression system
d) Oxidation ditch sewage disposal system
e) Difference between escalator, travelator and walkalator
( 25 marks )
QUESTION 6
6
-
8/17/2019 utm FAB April 2010
67/175
SBQ 4314
UTMUNIVERSITI TEKNOLOGI MALAYSIA
Fakulti Alam Bina
UNIVERSITI TEKNOLOGI MALAYSIA FAKULTI ALAM BINA
PEPERIKSAAN AKHIR SEMESTER II
SESI 2009/2010
KOD MATA PELAJARAN
MATA PELAJARAN
KURSUS
MASA
TARIKH
PENSYARAH
MARKAH
SBQ 4314
UKUR BINAAN IV
3 SBQ
3 JAM (9.00 AM-12.00 PM)
14 APRIL 2010
DR. MOHD SAIDIN BIN MISNAN
40%
ARAHAN KEPADA CALON :
1. Sila j awab SEMUA soalan.
2. Sila baca dan fahami soalan serta lukisan dengan teliti sebelum
menjawab.
3. Pelajar diminta membuat andaian/ as sumption yang munasabah jika
terdapat percangahan maklumat atau maklumat yang disediakan
tidak mencukupi. Andaian-andaian hendaklah dinyatakan di dalam
Senarai Kemusykilan dan dihantar bersama-sama kertas jawapan.
4. Markah akan diberikan berdasarkan kepada pemahaman terhadap
prinsip pengukuran, ketepatan ukuran, kejelasan huraian dan
keteraturan kerja.5. Semua keija pengukuran hendaklah merujuk kepada MCESMM.
6. Semua lukisan hendaklah dikembalikan bersama kertas jawapan
KERTAS SOALAN INI TERDIRI DARI PAD A _7_ MUKA SURAT TERMASUKMUKA SURAT HADAPAN.
I
8 0
-
8/17/2019 utm FAB April 2010
68/175
«
Berdasarkan kepada Lukisan No. KPKR/J/R/149336/AM7, AM8 dan AM9,
KPKR/J/R/ 149336/ST1, ST2, ST3 dan ST4, ukur kuantiti bagi semua kerja yang
berkaitan dengan Pembinaan Lintasan Keretapi Bertingkat di Kampung Selamat,
Pantai Dalam, Kuala Lumpr (KTM-Pakej 7). Skop kerja termasuk kerja-kerja
cerucuk, jambatan {prestressed beam), dan pembinaan jalan.
(60 markah)
QUESTION 1
Based on the drawing No. KPKR/J/R/149336/AM7’, AM8 and AM9,
KPKR/J/R/ 149336/ST1, ST2, ST3 and ST4, take-off the quantities of all related
works to Pembinaan Lintasan Keretapi Bertingkat di Kampung Selamat, Pantai
Dalam, Kuala Lumpr (KTM-Pakej 7). Scope of works involved are piling works,
bridge works (prestressed beam), and roadworks.
(60 marks)
SOALAN 2
Berdasarkan kepada Lukisan No. KPKR/J/R/149336/ ST8, ukur kuantiti bagi
semua keija yang berkaitan dengan Precast Vechicular Box Culvert and Sewer
Protection, Projek Pembinaan Lintasan Keretapi Bertingkat di Kampung Selamat,
Pantai Dalam, Kuala Lumpr (KTM-Pakej 7).
(40 markah)
QUESTION 2
Based on the drawing No. KPKR/J/R/149336/ ST8, take-off the quantities of all
related works to Precast Vechicular Box Culvert and Sewer Protection, Pembinaan
Lintasan Keretapi Bertingkat di Kampung Selamat, Pantai Dalam, Kuala Lumpr
(KTM-Pakej 7).
SBQ 4314
SOALAN 1
(40. marks)
2
8 1
-
8/17/2019 utm FAB April 2010
69/175
SBC 2273
UNIVERSITI TEKNOLOGI MALAYSIA
Fakulti Alam Bina
FINAL EXAMINATION
SEMESTER II SESSION 2009/2010
COURSE CODE SBC 2273
COURSE CONSTRUCTION TECHNOLOGY AND
DESIGN
PROGRAM 2 SBC
TIME 2 HOURS 30 MINUTES
(9.00AM - 11.30AM)
DATE 14 APRIL 2010
LECTURER NURSHIKIN BINTI MOHAMAD
SHUKERY
PERCENTAGE 40 %
ARAHAN:
INSTRUCTION:
Jawab empat (4) soalan sahaja. Semua soalan membawa markah yang sama.
Answer four (4) questions only. All questions carry equal marks.
1. Di mana perlu, nyatakan andaian anda berkenaan dengan saiz elemen
dan kaedah kerja yang dijalankan.
Where necessary, please make your own assumptions on the size of the
items and relevant construction work/activities.
2. Semua lukisan perlu disertakan dengan huraian dan label lengkap.
All drawings must be completed with annotation and side notes.
THIS QUESTION PAPER CONSIST OF 10 PAGES INCLUDING THE FRONT PAGE
1
8 I
-
8/17/2019 utm FAB April 2010
70/175
SBC 2273
a) Terdapat dua (2) implikasi terhadap defmisi kebolehbinaan. Huraikan
implikasi-implikasi tersebut dengan jelas.
(6 markah)
b) Mengapa perlunya rekabentuk kebolehbinaan dalam projek pembinaan?
(6 Markah)
c) Huraikankan 16 prinsip-prinsip kebolehbinaan dengan terperinci.
(13 Markah)
SOALAN 1
QUESTION 1
a) There are two (2) implications of buildability definition. Elaborate those
implications clearly.
(6 marks)
b) Why design for buildabilty in construction project?
(6 Marks)
c) Elaborate 16 principles of buildability in detail.
(13 marks)
SOALAN 2
Terangkan dengan terperinci aktiviti-aktiviti yang terlibat dalam proses
rekabentuk arkitek dan rekabentuk struktur.
(25 markah)
2
8 b
-
8/17/2019 utm FAB April 2010
71/175
SBC 2273
Explain in detail the activities involved in architectural design and structural
design process.
(25 marks)
QUESTION 2
SOALAN 3
a) Terangkan dan lakarkan dengan terperinci sistem lantai berikut:
i) Papak berusuk
ii) Sistem lantai rasuk jalur
iii) Sistem lantai pratuang
iv) Plat rata
v) Papak rata
(15 Markah)
b) Huraikan hanya tiga (3) faktor-faktor yang mempengaruhi pemilihan
sistem lantai yang sesuai.
(10 Markah)
QUESTION 3
a) Explain and sketch in detail each of following flooring system:
i) Ribbed slab
ii) Band beam floor system
iii) Precast floor system
iv) Flat plate
v) Flat slab
(15 Marks)
b) Elaborate only three (3) factors that influenced in selecting an
appropriate flooring system.
(10 Marks)
< 3 v
-
8/17/2019 utm FAB April 2010
72/175
SBC 2273
Sebuah rasuk konkrit bertetulang mempunyai 300mm lebar dan kedalaman
efektif 552mm diperlukan untuk merentang sepanjang 6m. Rasuk tersebut
membawa momen rekabentuk maksimum (M) sebanyak 321.5 kNm dan daya
ricih muktamad (V) sebanyak 214.4kN. Anggapkan diameter penyambung
ialah 10mm, f cu = 30 N/mm2, f y = 460 N/mm
2, fvy = 250 N/mm2 dan keadaan
dedahan (cuaca) adalah ringan, rekabentukkan rasuk ini. Rumus dan jadual
rekabentuk yang berkaitan terdapat di dalam LAMPIRAN.
(25 Markah)
QUESTION 4
A reinforced concrete beam which is 300mm wide and effective depth is 552mm
is required to span 6m. The beam carries a maximum design moment (M) of
321.5 kNm and ultimate shear force (V) of 214.4kN. Assuming the diameter of
links is 10mm, fcu = 30 N/mm 2 , f y = 460 N/mm 2 , f vy = 250 N/mm
2 and the
exposure conditions (weather) are mild, design the beam. Relevant design
formulas and tables are in the APPENDIX.
(25 Marks)
SOALAN 5
Rajah 1 menunjukkan, 400mm tiang segiempat sama membawa beban mati
sebanyak lOOOkN dan beban hidup sebanyak 250kN. Keupayaan galas
selamat tanah ialah 168kN/m2. Rekabentukkan tapak pad segiempat sama
bagi menanggung beban tersebut. Anggapkan kekuatan bahan-bahan
berikut.
Ketumpatan konkrit = 24kN/m3
fcu = 35 N/mm2
f y = 460 N/mm2
20mm diameter bar bagi tetulang lenturan di kedua-dua arah. Rumus dan
jadual rekabentuk yang berkaitan terdapat di dalam LAMPIRAN.
SOALAN 4
(25 Markah)
4
9 0
-
8/17/2019 utm FAB April 2010
73/175
SBC 2273
Axial load: Dead = 1000kN
Imposed = 250kN
Rajah 1/Figure 1
QUESTION 5
Figure 1 shows, a 400mm square column carries a dead load of lOOOkN and
imposed load of250kN. The safe bearing capacity of soil is 168kN/m 2 . Design a
square pad footing to resist the loads. Assuming the following materials
strength.
Concrete density = 24kN/m 3
feu = 35 N/mm 2
f y = 460 N/mm 2
20mm diameter bars for bending reinforcement for both directions. Relevant
design formulas and tables are in the APPENDIX.
(25 Marks)
SOALAN 6
Rajah 2 menunjukkan, 6m rentang sebuah rasuk segiempat tepat disokong
mudah membawa beban mati (gk ) sebanyak lOkN/m. Rekabentukkan
tetulang ricih bagi rasuk tersebut menggunakan penyambung keluli lembut
(fvy = 250 N/mm2) bagi kes-kes beban hidup (qk) berikut;
i) 0 kN/m
ii) 10 kN/m
iii) 29 kN/m
iv) 45 kN/m
5
9 1
-
8/17/2019 utm FAB April 2010
74/175
Dimensi ukur lebar rasuk (b) ialah 300mm dan kedalaman efektif (d) ialah
547mm. Anggapkan f cu =25N/mm2 dan saiz bar 4T25 (As= 1960mm
2). Rumus
dan jadual rekabentuk yang berkaitan terdapat di dalam LAMPIRAN.
(25 Markah)
b=300mm
H r~qk=Varies
gk=10kN/m
Rajah 2/Figure 2
QUESTION 6
Figure 2 shows, a simply supported rectangular beam of 6m span carries a
characteristic dead load (gk ) of lOkN/m. Design the shear reinforcement for the beam using mild steel (f vy = 250 N/mm
2 ) link for the following imposed load (qk)
cases;
v) 0 kN/m
vi) 10 kN/ m
vii) 29 kN/ m
viii) 45 kN/ m
The beam dimensions are breadth b, 300mm and effective depth d, 547mm.
Assuming fu =25N/mm 2 and bar size is 4T25 (A s = 1960mm 2 ). Relevant design
formulas and tables are in the APPENDIX.
(25 Marks)
SELAMAT MENJAWAB DAN SELAMAT MAJU JAYA
-
8/17/2019 utm FAB April 2010
75/175
SBC 2273
LAMPIRAN / APPENDIX
Mu €.156 bd2f cu
MAs 0.87f y z
z :rf[o.5 + 7(0.25-&/0.9)J< 0.95
M
k fcubd2
V
v M
Ultimate load, W = (1.4gk + 1.6qk) x span
i) Deflection criteria
Support ConditionsSpan/Effective depth(rectangular section)
For Initial design
Cantilever 7 < 7 could be a problemSimply Supported 20 20 but be cautiousContinuous 26 26 or maybe more for a cont. slab
ii) The code (BS8110) requires the final design to pay attention to:
Min and Max reinforcement as a percentage of the gross CSA. (Cl. 3.12.5.3. &3.12.6.1) - This will on the one hand, help the control of cracking, increasedurability, while on the other assist placing and compaction.
0.24%bh
-
8/17/2019 utm FAB April 2010
76/175
SBC 2273
iv) Form and area of links in beams.
ix. Where v < 0.5vcNo links required but provide nominal links for the whole length:
0 87
/„ x. Where 0.5vc < v < (vc + 0.4)Provide: nominal links for the whole length0-87
xi. Where (vc + 0.4) < v < 0.8\/f cu or 5 N/mm2
Provide: nominal links and design links
AJSt = KL̂ L 0.87
A further limitation placed on the spacing of links by the BS is that the
maximum spacing should be less than 0.75d, which is obviously necessary toavoid a failure plane forming which misses the links altogether.
v) Table for design concrete shear stress vc
100A,
bvd
Effective depth (mm)
150 175 200 225 250
\
1 300!
ii >400i
-
8/17/2019 utm FAB April 2010
77/175
vi) Table of modification factor for tensile reinforcement:
SBC 2273
Service _____________________ M/bd2 ____________________ stress ________ 0.50 0.75 1.00 1.50 2.00 3.00 4.00 5.00 6.00
1.00 2.00 2.00 2.00 1.86 1.63 1.36 1.19 1.08 1.011.50 2.00 2.00 1.98 1.69 1.49 1.25 1.11 1.01 0.94
(f y =250) 1.56 2.00 2.00 1.96 1.66 1.47 1.24 1.10 1.00 0.942.00 2.00 1.95 1.76 1.51 1.35 1.14 1.02 0.94 0.882.50 1.90 1.70 1.55 1.34 1.20 1.04 0.94 0.87 0.82
(f y =460) 2.88 1.68 1.50 1.38 1.21 1.09 0.95 0.87 0.82 0.783.00 1.60 1.44 1.33 1.16 1.06 0.93 0.85 0.80 0.76
vii) Table of nominal depths of cover to be used for a variety of exposure conditions.
Conditions of exposure Nominal cover (mm)
Mild - protected from weather 25 20 20 20 20
Moderate - sheltered from weather 35 30 25 20
Severe - exposed to severe rain 40 30 25
Veiy Severe - salts, fumes etc. 50 40 30
Extreme - abrasives e.g. sea water 60 50
Max. Free water/cement ratio 0.65 0.60 0.55 0.50 0.45
Min. Cement Content kg/m3 275 300 325 350 400
Lowest grade C30 C35 C40 C45 C50
viii) Cross-sectional areas of group of bars, As (mm2)
Dia. Areas in mm2 for groups of bars(mm) 1 2 3 4 5 6 7 i 8 9 10....[
283 ;
11 ^ 126 28 57 85 113 142 170 ! 198 i 226 255 1 311 340
8 50 rioi 151 201 252 302 1 352 402 453 | 503 i 553 60410 79 157 236 314 392 471 ! 550 i 628 707 785 ! 864 94212 113 226 339 452 566 679 ; 792 | 905 1020 ; 1130 j 1240 136016 201 402 603 804 1010 1210 j 1410 j 1610 1810 ; 2010 12210 241020 314 628 943 1260 1570 1890 |2200 ; 2510 2830 T 3140 ! 3460 377025 h491 982 1470 I960 2450 2950 ; 3440 1 3930 4420 : 4910 ! 5400 589032 804 1610 2410 3220 4020
6280
4830 j 5630 ! 6430 7240 : 8040 8850 965040 1260 2510 3770 5030 7540 ! 8800 i 10100 11300, 12600;13800 1510050 196013930 j5890 i 78501 982011800!13700! 15700 17700; 19600!21600 23600
9
9 b
-
8/17/2019 utm FAB April 2010
78/175
SBC 2273
ix) Cross-sectional area per meter width for various bar spacing (mm2)
- Foundation design
Bar size
(mm)
Spacin g of bars
50 75 100 ■ 125 150 175 200 250 300
6 566 377 283 226 189 162 142 113 94.3
8 1 010 671 503 402 335 287 252 201 168
10 1 570 1 050 785 628 523 449 393 314 262
12 2 260 1 510 1 130 905 754 646 566 452 377
16 4 020 2 680 2010 1 610 1 340 1 150 1 010 804 670
20 6 280 4 190 3 140 2 510 2 090 1 800 1 570 1 260 1 050
25 9 820 6 550 4910 3 930 3 270 2 810 2 450 1 960 1 640
32 16 100 10 700 8 040 6 430 5 360 4 600 4 020 3 220 2 680
40 25 100 16 800 12 600 •10 100 8 380 7 180 6 280 5 030 4 190
10
-
8/17/2019 utm FAB April 2010
79/175
SBC 1512
UTMUNIVERSITI TEKNOLOGI MALAYSIA
Fakulti Alam Bina
FINAL EXAMINATION
SEMESTER II SESSION 2009/2010
SUBJECT CODE
COURSE
PROGRAM
TIME
DATE
LECTURER
PERCENTAGE
SBC 1512
PRINCIPLE OF LAW IN MALAYSIA
1 SBC
3 HOURS (9.00 AM - 12.00 PM)
14 APRIL 2010
TN. HAJI ROSLI BIN KAMARUDDIN
50%
ARAHAN:
INSTRUCTION:
1. ANSWER QUESTION NO 1 AND 3 OTHERS
(Jawab soalan No 1 dan 3 soalan yang lain).
2. CANDIDATES WILL BE PROVIDED WITH CONTRACT ACT 1950
(Calon-calon akan dibekalkan dengan Akta Kontrak 1950).
3. ANSWER MUST BE SUPPORTED WITH LAW AUTHORITIES(LAW PROVISIONS AND CASES)
(Jawapan-jawapan hendaklah disokong dengan Otoriti dan Kes
Undang-Undang).
THIS QUESTION PAPER CONSIST OF 5 PAGES INCLUDING THE
FRONT PAGE
1
9 7
-
8/17/2019 utm FAB April 2010
80/175
Prinsip jiran merujuk kepada penghakiman klasik dalam Kes Donoghue v
Stevenson [1932] AC 562. Hakim Lord Atkin dalam penghakimannya telah
menyatakan seperti berikut
“The rule that you are to love your neighbour becomes in law you
must not injure your neighbour; and the lawyer’s question ‘Who is my
neighbour’ receives a restricted reply. You must take reasonable care to
avoid acts or omissions which you can reasonably foresee would be likely
to injure your neighbour. Who, then, in law is my neighbour? The answer
seems to be persons who are so closely and directly affected by my act
that I ought reasonably to have them in my contemplation as being so
affected when I am directing my mind to the acts or omissions which are
called in question...”
Berdasarkan prinsip di atas, bincangkan perkara-perkara berikut
a) Tugas atau kewajipan beijaga-jaga. (10 markah)
b) Pemecahan kewajipan berjaga-jaga. (8 markah)
c) Satu (1) kes tempatan yang menerimapakai
prinsip dalam Donoghue v Stevenson. (7 markah)
QUESTION 1
Neighbour principle refer to the classical judgment in Donoghue v Stevenson
[1932] AC 562 Lord Atkin in delivering the judgment has quoted the following:
“The rule that you are to love your neighbour becomes in law you
must not injure your neighbour; and the lawyer’s question ‘Who is my
neighbour > receives a restricted reply. You must take reasonable care to
avoid acts or omissions which you can reasonably foresee would