user guide for estimated rehabilitation cost calculator ... · the calculator, which replaces the...
TRANSCRIPT
User Guide for Estimated Rehabilitation
Cost Calculator for Mining
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) i
Prepared by: Operational Support, Department of Environment and Science
© State of Queensland, 2019.
The Queensland Government supports and encourages the dissemination and exchange of its information. The copyright in this publication is licensed under a Creative Commons Attribution 4.0 Australia (CC BY) licence.
Under this licence you are free, without having to seek our permission, to use this publication in accordance with the licence terms.
You must keep intact the copyright notice and attribute the State of Queensland as the source of the publication.
For more information on this licence, visit http://creativecommons.org/licenses/by/4.0/au/deed.en
Disclaimer
While this document has been prepared with care it contains general information and does not
profess to offer legal, professional or commercial advice. The Queensland Government accepts no
liability for any external decisions or actions taken on the basis of this document. Persons external to
the Department of Environment and Science should satisfy themselves independently and by
consulting their own professional advisors before embarking on any proposed course of action.
Approved: September 2020
Enquiries: Permits and Licencing
Department of Environment and Science
Ph. 1300 130 372 (option 4)
Fax. (07) 3330 5875
Email: [email protected]
Version history
Version Effective date Description of changes
1.00 1 April 2019 This user guide has been prepared to support the use
of the Mining Estimated Rehabilitation Cost Calculator.
2.00 1 October 2020 Amended to reflect minor changes made to the ERC
Calculator as part of the Minor Update 2020.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) ii
Table of Contents
1 Introduction ............................................................................................................... 2
1.1 Purpose of Document ................................................................................... 2
1.2 Purpose of Calculator ................................................................................... 2
1.3 Key Differences to the Financial Assurance Calculator .......................... 2
2 Process of Estimated Rehabilitation Cost Creation ....................................... 3
3 General Use Principles ........................................................................................... 7
3.1 Colour Coding ................................................................................................ 7
3.2 Quantity Entry ................................................................................................ 7
3.3 Comment Entries ........................................................................................... 9
3.4 Default Quantities .......................................................................................... 9
3.5 How to Enter an Alternate Rate ................................................................ 10
3.6 Navigation, Search and Information ......................................................... 10
3.7 Add Rows Buttons ....................................................................................... 11
3.8 Drop Down Menus ...................................................................................... 12
3.9 Review Elements ......................................................................................... 13
3.10 Other (User Entered) .................................................................................. 13
3.11 Freeze Panes............................................................................................... 14
4 Architecture of Calculator ................................................................................... 15
4.1 Security ......................................................................................................... 15
4.2 Sheets ........................................................................................................... 15
4.3 Contents Sheet ............................................................................................ 16
4.4 Registration Sheet ....................................................................................... 16
4.5 Summary Sheet (including Project Multipliers) ....................................... 17
4.5.1 Sheet Description ........................................................................... 17
4.5.2 Project Management Multiplier .................................................... 18
4.5.3 Environmental Maintenance and Monitoring Multiplier ............ 19
4.6 Quantity Summary ...................................................................................... 19
4.7 Table of Values ............................................................................................ 20
4.8 Assumptions Sheet ..................................................................................... 21
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) iii
4.9 User Input Sheets (including Map ID) ...................................................... 21
4.9.1 Default Rates and User-Defined Cost Build-up ......................... 22
4.9.2 Eligible Mining Activities User Input Sheet ................................. 23
4.9.3 Exploration User Input Sheet ....................................................... 24
4.9.4 Infrastructure User Input Sheet .................................................... 25
4.9.5 Overburden Dumps Piles User Input Sheet ............................... 26
4.9.6 Heap Leach Pads User Input Sheet ............................................ 26
4.9.7 Tailings Storage Facilities User Input Sheet .............................. 26
4.9.8 Pits User Input Sheet ..................................................................... 27
4.9.9 Water Storage and Management User Input Sheet ................. 27
4.9.9.1 Water Storage and Sludge Removal ................ 28
4.9.9.2 Water Management (Treatment) ....................... 28
4.9.10 Process Equipment User Input Sheet ......................................... 30
4.9.11 Underground Mines User Input Sheet ........................................ 30
4.9.12 Miscellaneous Activities User Input Sheet ................................. 31
4.9.12.1 Common Input Tables ......................................... 31
4.9.12.2 Preliminary and Intrusive Site Investigations ... 32
4.9.12.3 Remediation of Contaminated Areas ................ 34
4.9.12.4 Long Distance Haul ............................................. 34
4.9.12.5 Miscellaneous Scrap ........................................... 34
4.9.12.6 Fencing .................................................................. 35
4.9.13 Mobilisation/Demobilisation and Additional User Items User
Input Sheet………………………………………………………...35
5 Information on Rates............................................................................................. 37
5.1 Bottom-up, First Principles Calculation Method ..................................... 37
5.2 Labour Costs ................................................................................................ 37
5.3 Equipment Costs ......................................................................................... 37
5.4 Productivity ................................................................................................... 38
5.5 Scope and Unit Rates ................................................................................. 38
5.6 Alternate Rates ............................................................................................ 39
5.7 Contractor Rate Inclusions ........................................................................ 39
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) iv
6 Focus Items ............................................................................................................. 41
6.1 Capping of Waste Rock Dumps, Heap Leach Pads and Tailings
Storage Facilities ......................................................................................... 41
6.2 Pasture and Native Seed ........................................................................... 43
6.3 Haulage Distances ...................................................................................... 44
6.4 Fleet Sizes .................................................................................................... 44
7 Worked Examples .................................................................................................. 46
7.1 Seismic Easements .................................................................................... 46
7.2 User Defined Roads in Infrastructure User Input Sheet ........................ 47
7.3 Default Rates for Waste Rock Dumps ..................................................... 50
7.4 User-Defined Rates for Waste Rock Dumps, Heap Leach Pad and
Tailings Storage Facilities .......................................................................... 51
7.5 Pits – Safety Bund ....................................................................................... 57
7.6 Water Treatment ......................................................................................... 58
7.7 Underground Mines .................................................................................... 60
8 Glossary ................................................................................................................... 63
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) v
List of Tables
Table 3-1 Colour Coding or Cells
Table 3-2 Examples of Default Quantities
Table 4-1 Sheets
Table 4-2 Exploration User Input Sheet Information
Table 4-3 Indicative Pump Capabilities
Table 6-3 Fleet Sizes for Various Activities
Table 8-1 Definitions
Table A-1 Exploration User Input Sheet
Table A-2 Infrastructure User Input Sheet
Table A-3 Overburden Dumps Piles User Input Sheet
Table A-4 Heap Leach Pad User Input Sheet
Table A-5 Tailings Storage Facilities User Input Sheet
Table A-6 Pits User Input Sheet
Table A-7 Water Storage and Management
List of Figures
Figure 3-1 Colour Code Key
Figure 3-2 Example of Units in Adjacent Column
Figure 3-3 Example of Units in Row
Figure 3-4 Example of User Entered Quantities
Figure 3-5 Example of User Entered Volume
Figure 3-6 Alternate Rate Cells
Figure 3-7 Alternate Rate Cell turns Red upon Entry
Figure 3-8 Rationale for Alternate Rate
Figure 3-9 Example of Hyperlinks in the Infrastructure Input Sheet
Figure 3-10 Find Button in Table of Values
Figure 3-11 Example of Hover Text Overburden Dumps Piles User Input Sheet
Figure 3-12 Example of Add Row Button (Add Roads / Tracks in Infrastructure User Input
Sheet)
Figure 3-13 Example of Table prior to Adding Row
Figure 3-14 Example of Table after Adding Row
Figure 3-15 Example of Drop down Menu
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) vi
Figure 3-16 Show / Hide Rows button in Summary Sheet
Figure 3-17 Show / Hide Rows button in Quantity Summary Sheet
Figure 3-18 Example of User Entered Items area
Figure 4-1 Contents Sheet
Figure 4-2 Registration Sheet
Figure 4-3 Show / Hide Rows button in Summary Sheet
Figure 4-4 Project Management User Entry
Figure 4-5 Example of Data Collated in Quantity Summary Sheet
Figure 4-6 Show / Hide Rows button in Quantity Summary Sheet
Figure 4-7 Find Button and Search Box in Table of Values
Figure 4-8 Example of highlighted search results and prompt to find next result
Figure 4-9 Example of Use Box in Exploration User Input Sheet
Figure 4-10 Map ID
Figure 4-11 Example of “Rolled-up” Default Rates in Tailings Storage Facilities
Figure 4-12 Example of User Input Table in Tailings Storage Facilities
Figure 4-13 Eligible Mining Activities Entries
Figure 4-14 Hyperlinks in Infrastructure User Input Sheet
Figure 4-15 Alternate Rate Entry in the Basic Information Table of Pits
Figure 4-16 Example of Default Rates for Water Structures
Figure 4-17 Example of User Defined Tables for Water Structures (Key Input for calculation
circled)
Figure 4-18 Sludge Removal Table
Figure 4-19 Water Management Area Alternate Rate
Figure 4-20 Example of Rates in the Process Equipment User Input Sheet.
Figure 4-21 Alternate Rate Entry in for an Underground Mine
Figure 4-22 Quantity for Services for Mine
Figure 4-23 Example of Input Table in Miscellaneous Activities User Input Sheet
Figure 4-24 Preliminary Site Investigation Entry
Figure 4-25 Example of Use of One-off Cost
Figure 4-26 Example of a Fraction Entry of One-off Cost
Figure 4-27 Land Investigation Input Cells showing Options for Defining the Area
Figure 4-28 Long Distance Haul of Top Soil or Rock
Figure 4-29 Miscellaneous Scrap Disposal
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) vii
Figure 4-30 Fencing
Figure 4-31 Mobilisation and Demobilisation Default Rates
Figure 4-32 Mobilisation and Demobilisation - small projects
Figure 4-33 Disturbance Sheet
Figure 5-1 Inputs to Table of Values (Build-up of Unit Rates)
Figure 6-1 Total for Input Sheet
Figure 6-2 Seeding Example
List of Appendices
Appendix A User Input Sheets Options, Inputs, Defaults and Calculated Quantities
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) i
Acronyms, Initialisms and Abbreviations
AMD acid mine drainage
ARD acid rock drainage
DES Department of Environment and Science
EA Environmental Authority
ERC Estimated Rehabilitation Cost
GCL geosynthetic clay liner
h hour
ha hectare
HDPE high density polyethylene
km kilometre
LCM Loose cubic metres
mm millimetre
m metre
m2 square metre
m3 cubic metre
M million
ML megalitres
NMD neutral mine drainage
PAF potentially acid forming
TOV Table of Values
TSF Tailings Storage Facility
WRD Waste Rock Dump
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 2
1 Introduction
1.1 Purpose of Document
This document is a User Guide for the Estimated Rehabilitation Cost (ERC) Calculator (hereafter the “Calculator”) for mining activities in Queensland. The Calculator commenced on 1 April 2019, replacing the Financial Assurance Calculator.
The intended audience for this document is anyone who will prepare or review an ERC calculation.
This document includes:
Discussion on changes to key areas of the Calculator.
Explanation of how to use the Calculator.
Description of the architecture of the Calculator including the various Sheets.
Explanation of cost rates and how they are constructed.
Worked examples. Definitions of specific words and phrases used throughout this User Guide are listed in Section 8.
1.2 Purpose of Calculator
The purpose of the Calculator is to provide a tool to calculate the ERC as required by the Environmental Protection Act 1994 (EP Act). The Calculator provides consistent approach to estimating the full cost to the Queensland Government to decommission, rehabilitate and close a petroleum and gas operation.
The ERC calculator should be used to capture the maximum potential amount of liability to the State for the period the EA holder has applied for. Therefore EA holders should ensure the maximum potential liability is entered into the calculator, including where minor infrastructure modifications may need to be made during construction.
1.3 Key Differences to the Financial Assurance Calculator
The Calculator, which replaces the Financial Assurance Calculator, has been significantly revised:
1. The values in the Table of Values (TOV) are calculated using bottom-up, first principles methods (see Section 8 for definition of this term).
2. One User Input Sheet is used per Domain (e.g. Pits) with singular items (e.g. a Pit) added as rows.
3. One workbook in place of the former multiple workbooks (Exploration, Open Cut and Underground Mines).
4. Increased granularity (more ranges) of haulage distances. 5. Addition of fleet sizes and corresponding rates using those fleets. 6. Revised layout of the Summary Sheet. 7. A Quantity Summary Sheet is added for data collation (e.g. total volume of earth
pushed for re-shaping Waste Rock Dumps) and display.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 3
2 Process of Estimated Rehabilitation Cost Creation
The User is recommended to follow these steps to create an ERC for a mining activity:
1. Download the Calculator. The Calculator is available on the Queensland Government’s Business Queensland website at: www.business.qld.gov.au/business/running/environment/licences-permits/financial-
assurancerehabilitation/financial-assurance-security-deposit. 2. Click on the hyperlink to the Mining Calculator and a pop-up window like the one
below will appear (this will look different depending on the internet browser used) and click ‘Open’ (or similar depending on the internet browser).
3. Another window like the one below may pop-up. Click “Allow” and the Calculator will open in Excel™.
4. Enable Editing and Macros. When the spreadsheet opens in Microsoft Excel a yellow banner may appear at the top of the window asking the user to enable editing, click ‘Enable Editing’. Another yellow banner may appear stating that ‘Macros have been disabled’, click ‘Enable Content’.
5. Save the file as a new name preferably in the format Company Site ERC Date (e.g. Coal International Big Pit ERC 10Jan19). By downloading the Calculator, the User agrees to the Terms and Conditions. The Terms and Conditions can be found in the “Terms-con” Sheet which is the most right of the Sheets in the Calculator.
6. Either go direct or navigate via the CONTENTS Sheet (see below) to the Registration Sheet.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 4
7. Enter the required details to the Registration Sheet (see below).
8. Either go direct or navigate via the CONTENTS Sheet to the User Input Sheet you wish to populate.
Estimated Rehabilitation Cost (ERC) Calculator for Mining
REGISTRATION
Back to Contents
Environmental Authority Ref: EA Holder:
Tenure Numbers: Site Name:
Last ERC Decision Date: Current ERC Amount: -$
Site Contact: Position:
Site Address: Phone:
Email:
Alternate Project Overhead
Justification:
If the User enters a Project Management and / or Environmental Maintenance and Monitoring value, please provide justification above.
Signature of Assessor
(company):
Signature of Site Manager
(company):
Title: Title:
Print Name: Print Name:
Date: Date:
By signing above, the signees state this is an accurate assessment of the rehabilitation liability for the site.
Below this line for the Department's use only
Signature of Department
Reviewer:
Signature of Department
Manager:
Title: Title:
Print Name: Print Name:
Date: Date:
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 5
9. Read the Use information at the top of the User Input Sheet (example below).
10. In the User Input Sheets, enter quantities to Input cells and select options from the drop-down menus as required.
11. Continue populating the User Input Sheets applicable to the site. 12. Review the Summary Sheet for the Rolled-up totals.
13. If site-specific Project Management and/or Environmental Maintenance and Monitoring values are justified, enter these to the cells in the Summary Sheet and provide an explanation in the space provided in the Registration Sheet.
EXPLORATION
Back to Contents
Total Cost for this Input Sheet $0 $0 Total ERC (from Summary Sheet)
Use: Use this input sheet to show the quantities for exploration activities including seismic corridors, grid-lines minor tracks and drillholes.For seismic, the User may choose to enter the total length of 2D and 3D seismic in one line only if the individual line length are not known.Click in title cells for tips on specific use.Note: "not owned by company" means the infrastructure / facilities is owned by a third party and they would remove it. The only liability for the EA holder in these
SUMMARY
Back to Contents Total ERC: $0
Item Quantity Unit Rate Total Cost
Eligible Mining Activities Quantity Unit Rate Total Cost
Total 0 total $0 $0
$0
1. Exploration Quantity Unit Rate Total Cost
Seismic, Grid-Lines, Minor Tracks 0 km $0 $0
Drillholes 0 holes $0 $0
Tracks and Roads 0 km $0 $0
Show / Hide Rows
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 6
14. Review the quantities in the Qty Summary Sheet to ensure they are correct.
15. Re-visit the Registration Sheet and sign (or electronically add) in the space provided.
Please note that although preferred (to assist with future correspondence), signing is
not mandatory. However signing the ERC approved form is mandatory, and by
signing the approved form you certify that the calculation provided is true, correct,
complete and does not provide misleading information.
Estimated Rehabilitation Cost (ERC) Calculator for Mining
QUANTITY SUMMARY
Back to Contents Show
Total ERC (from Summary Sheet) $0
Item Value Unit
1. Exploration
Total length of seismic easement - km
Total length of seismic easement to be rehabilitated - km
Number of Drillholes -
Total length of roads and tracks - km
Total number of water structures -
Show/Hide Rows
Signature of Assessor
(company):
Signature of Site Manager
(company):
Title: Title:
Print Name: Print Name:
Date: Date:
By signing above, the signees state this is an accurate assessment of the rehabilitation liability for the site.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 7
3 General Use Principles
3.1 Colour Coding
Table 3-1 describes the colour coding used throughout the Calculator. All cells except green
and yellow are locked to the User.
Table 3-1 Colour Coding or Cells
Word Definition
Green Cells to which the User can input values or text, select options from drop down menus and click on hyperlinks to access other Sheets or areas within a Sheet.
Yellow Reserved for User Entered Alternate Rates. If an Alternate Rate is entered, the yellow rate cell turns pink with red font to inform the Department. If an Alternate Rate is entered, the User must provide an explanation in the accompanying “Rationale for Alternate Rate” cells.
Purple cells Reserved for Default Rates sourced from the TOV.
Hatched cells Structural block-out cells indicating no active part in the Calculator
White cells Calculated quantities and fixed text that the User cannot change
A screen shot of the colour code key is shown as Figure 3-1.
Figure 3-1 Colour Code Key
3.2 Quantity Entry
The User enters quantities into the green cells. The units of each quantity are shown in either the adjacent column (Figure 3-2) or the top row of the table (Figure 3-3).
Figure 3-2 Example of Units in Adjacent Column
Colour Code Key
User Input Cells
User Input - Alternate Rates / justification
Locked cell - Default Rates
Locked cells - blanks
Locked cell - calculations or text (and blue and black)
OVERBURDEN DUMP DIMENSIONS
Total Footprint area of
Overburden Dump
(ha)
Tracks and Roads
Type Qty Unit
Track (earthen) - rip, grade and re-seed km
Road (gravel/crushed rock) - remove rock, grade and re-seed km
Road (gravel/crushed rock) - remove rock and replace km
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 8
Figure 3-3 Example of Units in Row
The order of Entry in the User Input Sheets is left to right and some cells must be entered to properly calculate a cost. In the example in Figure 3-4, the Total Footprint area of a Tailings Storage Facility (TSF), Embankment and Area must be entered to calculate a cost. Section 4 and the tables in Appendix A contain information on key entries.
Figure 3-4 Example of User Entered Quantities
The Calculator is set-up to allow as much flexibility as practical, allowing multiple ways to input quantities. An example of this is the volume of growth media (Figure 3-5). In this example, the User can directly enter the volume of growth media or enter a site-specific thickness of growth media. If a user has its own program to quantify volumes, the output from that can be entered into the user volume cells.
In the example below, if the User enters a User growth media value the Calculator uses this value in subsequent cost calculations. If the User enters a value to the User Growth Media Thickness, the Calculator uses this in preference to the default growth media thickness (in this example 0.15 m). If the User does not enter a growth media thickness or a growth media volume, the Calculator multiplies the default thickness by the area to obtain the Growth media volume.
Figure 3-5 Example of User Entered Volume
Width (m) Length (m) Diameter (m) User Area (ha)
Tailings Storage Facilities (User Defined)
TSF DETAILS EMBANKMENT ROCK COVER DIMENSIONS
TOV #
Default value 1.0
# Map ID Tailings Storage Facility Name
Risk Category (select
from drop-down)Total Footprint
area of TSF (ha)
Embankment
Area (ha)
User Input
Thickness of
Rock Cover for
Embankments
(m)
User Entered
volume for
embankment
rock armour (m3)
Volume for
embankment
rock armour
used in
calculation (m3)
X High Risk TSF -
1 Very Low Risk TSF -
- - - -
Add Tailing SF (UD)
0.15
User Growth
media Thickness
(m)
User growth
media volume
(m3)
Growth media
volume used in
calculations
(m3)
-
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 9
3.3 Comment Entries
The Calculator includes the following space for User comments:
Assumptions Sheet – the intent of this Sheet is to allow Users to enter general information about the ERC application (see Section 4.8 for further information).
User Input Sheets – a User Comments box is included at the top of each User Input Sheet and this is intended for information specific to the Domain (e.g. specific to Pits) and general for that Domain (e.g. applies to all the Pits).
Element Lines – in some instances, space is allowed at the end of each Element line (e.g. for a specific Pit) for information specific to that element.
Special Areas – in some cases, information is required to justify a selection or entry. An example is the selection of the Risk Category for a Tailings Storage Facility.
Rationale for Alternate Rate – wherever an Alternate Rate is allowed, there is an adjacent (or nearby) space for the User to provide the justification for this rate.
Disturbance Sheet – an additional sheet (sheet 12) is provided to allow the User to enter granular disturbance quantities and other information. The values on this sheet are not linked through the workbook.
The User is encouraged to provide succinct and specific information to assist the Department to understand the intent and assumptions underpinning the User’s entries.
3.4 Default Quantities
The Calculator has some cells which include default quantities which are used in the absence of a User entry. If a User enters a quantity where a default is present, the Calculator uses the User entry instead of the default. Examples of default quantities are shown in Table 3-2.
Table 3-2 Examples of Default Quantities
Sheet Default Quantity Type and Value
Screen Shot
Exploration Length of seismic easement requiring rehabilitation (5%)
Infrastructure Width of track / road (6 m)
Infrastructure Thickness of surface covering (150 mm)
Tailings Storage Facilities
Thickness of capillary break layer (0.6 m)
Seismic, Grid-Lines, Minor Tracks
5%
Land type
Total Length
(km)
Rehab length
(km)
In Pasture 0.0
In Native 0.0
ROAD DIMENSIONS AND COVER
TOV #
Default value 6.0
Road/Track Width (m)
Total Length
(km)
REPLACEMENT OF COVER (IF APPLICABLE)
150
Length of road
to replace rock
(km)
Thickness of
rock to replace
(mm)
0.0
0.0
Default
Thickness of
Capillary Break
Layer (m)
User Input
Thickness of
Capillary Break
Layer (m)
Thickness of
Capillary Break
Layer used in
Calculations
(m). Cannot be
below
mandatory
minimum
0.6 0.6
0.0 -
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 10
3.5 How to Enter an Alternate Rate
Alternate Rates are entered to the yellow cells in each User Input Sheet (Figure 3-6). Alternate Rates must have the same unit as the Default Rates, otherwise they should be listed as an additional item in the rows provided (see Section 3.10 for further information).
Figure 3-6 Alternate Rate Cells
If an Alternate Rate is entered, the calculator uses the Alternate Rate over the Default Rate and the Alternate Rate cell turns red (Figure 3-7) to alert the Department.
Figure 3-7 Alternate Rate Cell turns Red upon Entry
If the User enters an Alternate Rate, the User must provide justification in the ‘Rationale for Alternate Rate’ column (Figure 3-8). Alternate rates, including third party quotes, entered into the ERC Calculator must meet the requirements in the Estimated Rehabilitation Coast (ERC) Guideline (ESR/2018/4425).
Figure 3-8 Rationale for Alternate Rate
3.6 Navigation, Search and Information
Hyperlinks in the Contents Sheet are used to access Sheets within the Calculator, the “Back to Contents” hyperlink in the Sheets can be used to return to the Contents Sheet, and other hyperlinks link to areas within Sheets e.g. Mine Haul Roads within the Infrastructure User Input Sheet (Figure 3-9).
Figure 3-9 Example of Hyperlinks in the Infrastructure Input Sheet
Waste Rock Dumps (Defaults)
# Waste Rock Dump Name Area (ha) Risk Category TOV #
Default Rate
($/ha)
Alternate Rate
($/ha)
Total cost for
WRD ($)
1 High Risk WRD/OB #4.01 161,317$ -$
2 Medium Risk WRD/OB #4.02 78,635$ -$
Rationale for Alternate Rate
Quick Acess
Roads and Tracks
Mine Haul Roads
Laydown
Borrow Pits
Pipelines
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 11
As the Calculator is purpose-built and requires security to prevent inadvertent corruption, the standard Excel search function (i.e. ctrl+F) does not work. To account for this, a “Find” button is incorporated into the Table of Values Sheet and this allows Users to search for key words or phrases in this Sheet (Figure 3-10).
Figure 3-10 Find Button in Table of Values
Information items include the “Use” box at the top of each User Input Sheet and hover text in specific cells. Hover text is generally in the heading of a column (Figure 3-11). The hover text is viewed by the User clicking in the target cell. Not all cells have hover text.
Figure 3-11 Example of Hover Text Overburden Dumps Piles User Input Sheet
3.7 Add Rows Buttons
The Infrastructure, Overburden Dumps Piles, Heap Leach Pads, Tailings Storage Facilities, Pits and Water Storage Management User Input Sheets include tables with buttons that add a row (Figure 3-12). When the button is clicked (Figure 3-13), one additional Element (one per click) is added (Figure 3-14).
Figure 3-12 Example of Button to Add Row (Add Roads / Tracks in Infrastructure User Input Sheet)
Table of Values - Mining ERC Calculator
2018 Rates Prepared by EHS Support / Mike Slight and Associates
Find
Back to Top
ROAD DIMENSIONS AND COVER
Add Roads/Tracks
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 12
Figure 3-13 Example of Table prior to Adding Row
Figure 3-14 Example of Table after Adding Row
3.8 Drop Down Menus
Drop down menus allow selection of a range of items such as surface covering (Figure 3-15). Drop down menus are in green cells and allow selection of:
1. Risk category (e.g. for Waste Rock Dump or Tailings Storage Facility). 2. Haul distance (e.g. to cart rock for armour). 3. Fleet size (e.g. dozer size). 4. Slope angle (e.g. for re-profiled Waste Rock Dump surface). 5. Surface covering type (e.g. rock). 6. Thickness (e.g. of rock surface covering or concrete pad). 7. Camp type and capacity. 8. Building type and size. 9. Site or remote services disconnection. 10. Power generation type. 11. Power distribution pole material. 12. Seed type.
Figure 3-15 Example of Drop down Menu
Acces Roads / Tracks (User defined) Back to Top
ROAD DIMENSIONS AND COVER
TOV #
Default value 6.0
Map ID
# Road / Track Name Road/Track Width (m)
Total Length
(km)
1
Add Roads/Tracks
Acces Roads / Tracks (User defined) Back to Top
ROAD DIMENSIONS AND COVER
TOV #
Default value 6.0
Map ID
# Road / Track Name Road/Track Width (m)
Total Length
(km)
1
2
Add Roads/Tracks
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 13
Note: most drop downs which represent a range in values (e.g. slope angle and thickness) are presented with an (<=) option to ensure all values are clearly captured. However, in locations where this option is not available (e.g. concrete footings in Sheet 8 which only provides for < 0.3 m or > 0.3 m) and the site feature is equal to the range value, the User should use the (<) rate, treating is as (<=). Therefore where concrete pads are 0.3m thick, the (<0.3m) rate should be used.
3.9 Review Elements
Review elements are click buttons (see examples below) designed to allow easy viewing / finding of information and include:
Show / Hide Rows button in the Summary Sheet (Figure 3-16).
Figure 3-16 Show / Hide Rows button in Summary Sheet
Show / Hide Rows button in the Qty Summary Sheet (Figure 3-17).
Figure 3-17 Show / Hide Rows button in Quantity Summary Sheet
3.10 Other (User Entered)
Where appropriate, rows are included in Users Input Sheets to allow User Entered items. These are items that are not included in the Calculator and that the User must define specifically. In this case the User must enter a description of the rate, the unit of the quantity (e.g. km), the rate (e.g. cost per kilometre) and explanation for the rate. An example is shown in Figure 3-18.
Figure 3-18 Example of User Entered Items area
The User could enter a line item in this area and use a rate from the TOV. For example, if a fence was required around a Waste Rock Dump, the User could reference the TOV rate
SUMMARY
Back to Contents Total ERC:Show / Hide Rows
Estimated Rehabilitation Cost (ERC) Calculator for Mining
QUANTITY SUMMARY
Back to Contents Show
Total ERC (from Summary Sheet) $0
Show/Hide Rows
#8.33 Removal of conveyors and support services down Drift/Decline item $75,000 $0
#8.U1 User entered item $0
#8.U2 User entered item $0
#8.U3 User entered item $0
#8.U4 User entered item $0
#8.U5 User entered item $0
#8.U6 User entered item $0
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 14
here and enter the specific quantity (in this case the length of fence). In the case of fencing, the User could also use the table in the Miscellaneous Activities User Input Sheet (see Section 4.9.12.6).
3.11 Freeze Panes
The standard Freeze Panes function works in the Calculator so the User can freeze or unfreeze columns and rows to assist viewing and use.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 15
4 Architecture of Calculator
4.1 Security
To prevent inadvertent changing of formulas, text and processes, the Calculator is locked with only green and yellow cells available for User entry.
4.2 Sheets
Table 4-1 lists the Sheets in the Calculator with a description of the intended use. Further detail on each User Input Sheet is provided in the next sections.
Table 4-1 Sheets
Sheet Type of Sheet
Attributes, Purpose and Use
CONTENTS Navigation Lists the Sheets available to the User.
Registration User Input For entry of details defining the site, regulatory reference, previous ERC, key personnel and Department review details.
Summary Review Shows the Rolled-up total cost for each domain and the multipliers for maintenance and monitoring, project management and contingency.
Qty Summary Review Shows Rolled-up quantities such as volume of soil to be pushed, and rehabilitation footprints.
Table of values (TOV) Reference Lists all the Rolled-up unit rates used in the Calculator with description of the intended use and items included in the rate (scope).
Assumptions User Input This Sheet allows the User to enter general and/or specific information pertaining to the calculation overall and/or specifics of individual Input Sheets.
Eligible Mining Activities User Input This Sheet is to be used to calculate the ERC for an eligible mining activity on a mining lease only.
1. Exploration User Input This Sheet allows User Entered quantities for activities typically part of exploration.
2. Infrastructure User Input This Sheet allows User Entered quantities for Infrastructure.
3. Overburden Dumps Piles
User Input This Sheet allows User Entered quantities for Waste Rock Dumps, overburden piles and topsoil stockpiles.
4. Heap Leach Pads User Input This Sheet allows User Entered quantities for Heap Leach Pads.
5. Tailings Storage Facilities
User Input This Sheet allows User Entered quantities for Tailings Storage Facilities.
6. Pits User Input This Sheet allows User Entered quantities for Pits.
7. Water Storage and Management
User Input This Sheet allows User Entered quantities for water storage structures and pumping and treatment of water.
8. Process Equipment User Input This Sheet allows User Entered quantities for process equipment.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 16
Sheet Type of Sheet
Attributes, Purpose and Use
9. Underground Mines User Input This Sheet allows User Entered quantities for underground mines.
10. Miscellaneous Activities
User Input This Sheet allows User Entered quantities for rehabilitation, remediation and contaminated land investigation activities.
11. Mobilisation and User
User Input This Sheet allows User Entered quantities for mobilisation and user-specified activities.
12. Disturbance Sheet User Input This Sheet allows the User to enter disturbance quantities. The values entered in this sheet are not linked through the workbook.
Terms and Conditions (“Terms-con”)
Information The Terms and Conditions under which the Calculator can be used. The User must review the Terms and Conditions prior to use. By using the Calculator, the User accepts the Terms and Conditions.
4.3 Contents Sheet
The Contents Sheet is the primary navigation Sheet for the Calculator and allows quick access to the User Input Sheets and Summary Sheets. The mode of transport is hyperlinks which the user clicks on to access the target element.
Figure 4-1 Contents Sheet
4.4 Registration Sheet
The Registration Sheet is where the User enters:
EA and lease details.
Name and location of the site.
Personnel and contact details of the site contact.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 17
The date of the last ERC decision and the amount of ERC last decided by the Department. The amount of ERC last decided is used in the Summary Sheet to show the difference between that amount and the newly proposed ERC amount.
Explanation for any site-specific Project Management and/or Environmental Maintenance and Monitoring values entered to the Summary Sheet.
Details and signature of the people who prepared and approved the ERC, where relevant.
The space below (as per the heading) is for the Department’s use.
Figure 4-2 Registration Sheet
4.5 Summary Sheet (including Project Multipliers)
4.5.1 Sheet Description
The Summary Sheet reports the rolled-up total cost for each Domain and the multipliers for environmental maintenance and monitoring, project management, and contingency. The only User inputs available in this Sheet are site-specific Project Management and Environmental Maintenance and Monitoring percentage multipliers. If the User enters site-specific values for these items, justification must be added to the space provided in the Registration Sheet.
Estimated Rehabilitation Cost (ERC) Calculator for Mining
REGISTRATION
Back to Contents
Environmental Authority Ref: EA Holder:
Tenure Numbers: Site Name:
Last ERC Decision Date: Current ERC Amount: -$
Site Contact: Position:
Site Address: Phone:
Email:
Alternate Project Overhead
Justification:
If the User enters a Project Management and / or Environmental Maintenance and Monitoring value, please provide justification above.
Signature of Assessor
(company):
Signature of Site Manager
(company):
Title: Title:
Print Name: Print Name:
Date: Date:
By signing above, the signees state this is an accurate assessment of the rehabilitation liability for the site.
Below this line for the Department's use only
Signature of Department
Reviewer:
Signature of Department
Manager:
Title: Title:
Print Name: Print Name:
Date: Date:
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 18
To allow easier viewing, the User or Department can hide rows containing zeros (where no inputs were entered) by clicking the Show / Hide Rows button at the top of the Sheet (Figure 4-3).
Figure 4-3 Show / Hide Rows button in Summary Sheet
4.5.2 Project Management Multiplier
The Calculator includes a default multiplier for project management costs, which amounts to
10% of the total ERC from the Domains. The project management multiplier reflects the cost
to government to execute a rehabilitation program for a mine and includes:
Decommissioning and rehabilitation plan and feasibility studies.
Health and safety and overall work plans.
Identifying and obtaining permits.
Procurement of contractors and consultants and ongoing contract management.
Ongoing management of the project including scheduling, expenditure tracking and forecasting, internal communication, on-site supervision.
Stakeholder (including land-owner, community, municipal government and regulators, media) management.
Consulting and legal costs associated with the above items.
The User can enter a site-specific project management multiplier on the Summary Sheet. If the 10% default value is not used, quotes must be attached to the ERC application and the User must provide justification in the space provided in the Registration Sheet. If a User enters a site-specific project management multiplier, the Calculator applies this value instead of the default.
Figure 4-4 Project Management User Entry
SUMMARY
Back to Contents Total ERC:Show / Hide Rows
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 19
4.5.3 Environmental Maintenance and Monitoring Multiplier
The Calculator includes a default multiplier for environmental maintenance and monitoring costs, which amounts to 5% of the total ERC from the Domains.
The environmental maintenance and monitoring multiplier reflects the costs to government to undertake the following:
post-closure maintenance activities: o Minor repair of rehabilitated features eroded by surface water run-off and high
intensity rain-fall events. o Revegetation campaigns to rehabilitate areas where vegetation is damaged from
drought, fire, animals and/or infertile seed. o Weed management. o Repair of minor subsidence due to poor backfill operations. o Fence and signage repairs.
post-closure monitoring activities: o Environmental, revegetation and erosion monitoring and assessment. o Ground and surface water monitoring and drainage assessment. o Erosion and surface drainage assessments and inspections across all closure
areas. o Subsidence and ground movement assessments associated with underground
mining. o Engineering, geotechnical and compliance inspections and assessment,
surveys and reporting on the performance of the open pits, underground openings and tailings storage facilities.
o Weed mapping and assessment surveys. o Feral animal assessment and control. o Independent contamination auditing and assessment. o Satellite imagery for rehabilitation analysis and reporting purposes. o Preparation of annual environmental reporting and monitoring reporting.
requirements and data management and control. o Mobilisation and demobilisation of the monitoring and inspection teams.
The User can enter a site-specific environmental maintenance and monitoring multiplier on the Summary Sheet. If the 5% default value is not used, quotes must be attached to the ERC application and the User must provide justification in the space provided in the Registration Sheet. If a User enters a site-specific environmental maintenance and monitoring multiplier, the Calculator applies this value instead of the default.
4.6 Quantity Summary
The Qty Summary Sheet shows Rolled-up quantities such as volume of soil to be pushed and rehabilitation footprint. An example of such quantities is shown in Figure 4-5.
Figure 4-5 Example of Data Collated in Quantity Summary Sheet
3. Overburden Dumps and Soil Piles
Total footprint area of waste rock dumps / overburden (defaults) - ha
Waste Rock Dumps (user defined)
Total footprint area of waste rock dumps - ha
Total flat area of waste rock dumps - ha
Total volume to push on flat areas of waste rock dumps - m3
Total sloped areas on waste rock dumps - ha
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 20
To allow easier viewing, the User or the Department can hide rows containing zeros (where no inputs were entered) by clicking the Show / Hide Rows button at the top of the sheet (Figure 4-6).
Figure 4-6 Show / Hide Rows button in Quantity Summary Sheet
4.7 Table of Values
The TOV lists the Rolled-up unit rates used in the Calculator with description of the intended use and items included in the rate (scope).
To allow ready finding of a rate or key words, a “Find” button is included at the top of the Sheet (Figure 4-7). To find a word or phrase the User clicks on the Find button, types the word or phrase and clicks “OK”. To find the next occurrence of the target word or phrase the user clicks “YES” when prompted. “NO” must be clicked to end the search (Figure 4-8). In the example below the User searched for the word “seismic”.
Figure 4-7 Find Button and Search Box in Table of Values
Estimated Rehabilitation Cost (ERC) Calculator for Mining
QUANTITY SUMMARY
Back to Contents Show
Total ERC (from Summary Sheet) $0
Show/Hide Rows
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 21
Figure 4-8 Example of highlighted search results and prompt to find next result
4.8 Assumptions Sheet
The Assumptions Sheet allows the User to enter general and/or specific information pertaining to the calculation overall, and/or specifics of individual User Input Sheets. The User is encouraged to provide information that will assist the Department understand the processes and concepts behind the inputs.
Examples of information that could be entered are:
Details of infrastructure that has been excluded from the ERC calculation due to an agreement with landowner that the infrastructure can remain, for example, an access track. For full information please refer to the ERC Guideline (ESR/2018/4425).
Explanation of decisions previously agreed with the Department.
For comments specific to individual User Input Sheets, it is recommended the User enter these in the space provided at the top of each User Input Sheet.
4.9 User Input Sheets (including Map ID)
There are thirteen User Input Sheets (see Table 4-1) allowing User inputs. The User Input Sheets comprise Rolled-up rates in single lines and User-defined Input tables that build up the activity to calculate the total cost for the Element.
The User Input Sheets are to be filled out from left to right and only information relevant to the particular Element needs to be entered. Generally, dimension inputs need to be entered to allow calculation. Where defaults are listed, and no information is entered by the User, a default value will be used in the calculation.
The structure of each User Input Sheet is similar with header rows providing the Domain name, hyperlink Back to Contents, the total cost for the individual Sheet, the total ERC for the site, the colour code legend, notes on the intended use of the Sheet and a section for the user to enter any details specific to the Sheet that may assist the Department in understanding the inputs. An example is shown in Figure 4-9.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 22
The “Use” box at the top of each User Input Sheet informs the User of the intended use for each sheet.
Figure 4-9 Example of Use Box in Exploration User Input Sheet
Each User Input Sheet includes a column on the left-hand side of the table for each activity to allow the entry of a Map ID (Figure 4-10). The Map ID allows an entry which corresponds to a company-specific GIS (Geographic Information System) or other referencing system. A Map ID must be entered where spatial data is provided which aligns with the line item of the Calculator. The Estimated Rehabilitation Approved form (ESR/2018/4426) dictates where spatial information must or may be provided.
Figure 4-10 Map ID
Some User Input Sheets (e.g. Process Equipment) include spare rows to allow the User to enter items that are not included elsewhere (see Section 3.10 for more detail).
4.9.1 Default Rates and User-Defined Cost Build-up
All the Sheets except for Eligible Mining Activities, Exploration and Process Equipment allow the User flexibility to build site-specific costs via the Input Tables or use Rolled-up Default Rates. It is the User’s decision as to which option to use and will be determined by how much information is available for the specific element (e.g. specific capping design for a Waste Rock Dump). The method to calculate the cost of the element is the same for the Default and User Defined cases but in the User Defined option, the User has more flexibility to match the specific design / approach for the site.
Note that the rates in the calculator have been calculated using loose cubic metres (LCM). Users should enter all cubic meter quantities in LCM.
For an individual element (e.g. Waste Rock Dump), the User uses only one of the tables; if the User enters quantities for an element (e.g. for Waste Rock Dump A) in a Default Rate table they do not need to enter quantities for that element (Waste Rock Dump A in this example) to the User-Defined table.
The following have Default Rates and User-defined tables:
Infrastructure - roads and tracks, mine haul roads, laydown yards and pipelines.
Overburden Dumps Piles - waste rock dumps, overburden piles, topsoil stockpiles.
Heap Leach Pads.
Tailings Storage Facilities.
Estimated Rehabilitation Cost (ERC) Calculator for Mining
EXPLORATION
Back to Contents
Total Cost for this Input Sheet $0 $0 Total ERC (from Summary Sheet)
Colour Code Key User Comments (enter any information that will support assumptions and assist department review)
User Input Cells
User Input - Alternate Rates / justification
Locked cell - Default Rates
Locked cells - blanks
Locked cell - calculations or text
Use: Use this input sheet to show the quantities for exploration activities including seismic corridors, grid-lines minor tracks and drillholes.For seismic, the User may choose to enter the total length of 2D and 3D seismic in one line only if the individual line length are not known.Click in title cells for tips on specific use.Note: "not owned by company" means the infrastructure / facilities is owned by a third party and they would remove it. The only liability for the EA holder in these
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 23
Pits – safety bund, benches and highwall drill and blast, low wall shaping, backfill open pit and open pit ramp backfill.
Water Storage Management – process water storage, raw water storage, evaporation and other unlined water storage, other (e.g. weirs).
The User-defined Cost Build-up tables aim to break-down the rehabilitation activity into practical steps, for example:
Bulk earthmoving and re-profiling.
Working layer for cap.
Capillary break for cap.
Low permeability layer for cap.
Top layer.
Top soil and revegetation.
Engineering and testing.
The default Rolled-up rates (e.g. cost per unit area for a Tailings Storage Facility) are built using the bottom-up, first principles method described above.
An example of Rolled-up, Default Rates is shown in Figure 4-11 and an example of a User-defined table is shown in Figure 4-12.
Figure 4-11 Example of “Rolled-up” Default Rates in Tailings Storage Facilities
Figure 4-12 Example of User Input Table in Tailings Storage Facilities
4.9.2 Eligible Mining Activities User Input Sheet
As per the ERC Guideline (ESR/2018/4425), “Certain resource activities (mining claims, exploration permits, mineral development licence, mining leases) are authorised with standard conditions and eligibility criteria under the Environmental Protection Act 1994 (EP Act). The relevant Standards are prescribed under the Environmental Protection Regulation 2008.
Tailings Storage Facilities (Defaults)
# Map ID Tailings Storage Facility Name Area (ha) Risk Category TOV #
Default Rate
($/ha)
Alternate Rate
($/ha)
Total cost for
TSF ($)
1 High Risk TSF #6.01 193,096$ -$
2 Medium Risk TSF #6.02 109,915$ -$
0 -$
Add Tailing SF (TOV)
Tailings Storage Facilities (User Defined)
TSF DETAILS EMBANKMENT ROCK COVER DIMENSIONS
TOV #
Default value 1.0
# Map ID Tailings Storage Facility Name
Risk Category (select
from drop-down)Total Footprint
area of TSF (ha)
Embankment
Area (ha)
User Input
Thickness of
Rock Cover for
Embankments
(m)
User Entered
volume for
embankment
rock armour (m3)
1 High Risk TSF
Add Tailing SF (UD)
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 24
The Eligible Mining Activities Sheet can be used to calculate the ERC for an eligible mining activity on a mining lease only. If the User’s EA was applied for via a variation EA application, and the User chooses to use the calculator, this Sheet is to be used only to calculate the elements of the activity that comply with the standard conditions and eligibility criteria for the mining activity. Any elements which are the subject of the variation(s) are to be entered into the other relevant User Input Sheets.
This Sheet requires only a Map ID entry (if relevant); the input of quantities next to the appropriate line (Figure 4-13) and any information to assist the Department. If Alternate Rates are justifiable (see Section 5.6 for requirements) they can be entered to the yellow cells with an explanation in the Rationale for Alternate Rate section of each line.
The scope and key assumptions for each Default Rate are included in the Scope and Key Assumptions column.
Mobilisation and demobilisation is not included in the Default Rates for this Sheet so the User must either select a mobilisation and demobilisation from the summary screen by entering a ‘1’ into the line ‘Mobilisation & Demobilisation – small projects’ (only available for small project with a total ERC < $1,000,000), use the Default Rate(s) on the Mobilisation and User Sheet, or supply a third-party quote.
Figure 4-13 Eligible Mining Activities Entries
4.9.3 Exploration User Input Sheet
The Exploration User Input Sheet includes tables for activities typical to the Exploration phase of a mining project, including seismic surveys, drill-holes, roads and tracks, small water structures and disturbances from contractor-owned infrastructure and equipment such as camps and Water Treatment Plants.
The User should enter quantities to the line representing their disturbance. Most of the lines are self-explanatory and further information is provided in Table 4-2
Table 4-2 Exploration User Input Sheet Information
Disturbance Type Information
Seismic The User should enter the length of easement in each land type (native and pasture). The Calculator multiplies the User Entered length by a default 5% to calculate the length of easement to be rehabilitated. The User can over-ride this default by directly entering the easement length to be rehabilitated. The length to be rehabilitated is multiplied by the rate for pasture or native to obtain a total cost for that disturbance. A worked example is shown in Section 7.1.
Drillholes The User should enter the total number of exploration drillholes which are on site.
Roads and Tracks Options for the tracks and roads are shown in Table A-1. The “Road (gravel/crushed rock) - remove rock, grade and re-seed” option
Map ID ITEM SCOPE AND KEY ASSUMPTIONS QUANTITY DEFAULT RATE
ALTERNATE
RATE UNIT
TOTAL
COST ($)
Exploration
Exploration disturbance Includes costeans, bore holes,
exploration pits; drill pads
Backfill with removed material (<1 km haulage)
Cap and seal open bore holes
Rip and seed (pasture grass) 341.14$ pad -$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 25
Disturbance Type Information
would be used where the track or road is to be retained but where either the road surface is contaminated, or the quality of the surface is insufficient to support future use.
Water Structures The User can select from a range of sizes for lined and unlined water structures.
Camps and Water Treatment Plants
For Exploration activities, it is assumed the facilities are owned by third-party contractors and that they bear the cost of removing the facilities. The only liability for the EA holder in these cases is rehabilitation of the land (grade and seed). In cases where the EA holder owns the facilities, entries must be made to the appropriate User Input Sheet (e.g. Infrastructure for Camps) or a specific rate added to one of the “Other (user entered)” rows.
Table A-1 of Appendix A shows further details for the Exploration User Input Sheet.
4.9.4 Infrastructure User Input Sheet
The Infrastructure User Input Sheet includes disturbances relating to access and transport (e.g. roads and rail loading facilities), storage and staging (e.g. laydown), buildings and structures (e.g. camps and communications towers), power generation and distribution (including rates for steel, concrete and wood poles), landfills and sewage treatment plants. A table is also included for miscellaneous concrete pads not associated with infrastructure or equipment (e.g. the rate for demolition and removal of a coal handling preparation plant includes removal of the underlying pad, and therefore the User does not need to add a line to the miscellaneous concrete pads table).
Due to the length of this User Input Sheet, the header section of this Sheet includes a quick access table with hyperlinks to the relevant sections (Figure 4-14).
Figure 4-14 Hyperlinks in Infrastructure User Input Sheet
Table A-2 of Appendix A shows the details for the Infrastructure User Input Sheet. A worked example for a User Defined Road is shown in Section 7.2.
Quick Acess
Roads and Tracks
Mine Haul Roads
Laydown
Borrow Pits
Pipelines
Camps
Buildings
Communication Towers
Power Distribution
Power Generation
Concrete Pads
Rail Infrastructure
Landfills
Sewage Treatment Plants
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 26
4.9.5 Overburden Dumps Piles User Input Sheet
For Waste Rock Dumps, the User can elect to use the Rolled-up Default Rates or use the input table to enter the rehabilitation specific to their site. The choice is dependent on the information the User has for the specific Element.
The Default Rates for rehabilitation of Waste Rock Dumps (#4.01, #4.02, #4.03 and #4.04 in the TOV) are based on the chemical properties (e.g. presence, or likely presence, of reactive materials) and physical properties (e.g. shear strength limiting the plant selection for material placement) of the waste. The User must select the category representing the particular dump.
Supporting information must be attached to the ERC application to satisfactorily demonstrate to the Department why a particular capping rate has been applied. Information requirements in relation to capping are outlined in the ERC Guideline (ESR/2018/4425).
Further discussion on capping is included in Section 6.1 and a worked example is included in Section 7.3. Table A-3 of Appendix A shows the available selections, defaults and calculated quantities for the Waste Rock Dumps, Overburden Piles and Top soil stockpiles User Input Sheet.
4.9.6 Heap Leach Pads User Input Sheet
For Heap Leach Pads, the User can elect to use the Rolled-up Default Rates or use the input table to enter the rehabilitation specific to their site. The choice is dependent on the information the User has for the specific Element.
The Default Rates for rehabilitation of Heap Leach Pads (#4.01, #4.02, #4.03 and #4.04 in the TOV) are based on the chemical properties (e.g. presence, or likely presence, of reactive materials) and physical properties (e.g. shear strength limiting the plant selection for material placement) of the waste. The User must select the category that represents the particular pad.
Supporting information must be attached to the ERC application to satisfactorily demonstrate to the Department why a particular capping rate has been applied. Information requirements in relation to capping are outlined in the ERC Guideline (ESR/2018/4425).
Further discussion on capping is included in Section 6.1 and a worked example is included in Section 7.3 (note this is for a Waste Rock Dump but the concepts are similar). Table A-4 of Appendix A shows the available selections, defaults and calculated quantities for the Heap Leach Pads User Input Sheet.
4.9.7 Tailings Storage Facilities User Input Sheet
For Tailings Storage Facilities, the User can elect to use the Rolled-up Default Rates or use the input table to enter the rehabilitation specific to their site. The choice is dependent on the information the User has for the specific Element.
The Default Rates for rehabilitation of Tailings Storage Facilities (#6.01, #6.02, #6.03 and #6.04 in the TOV) are based on the chemical properties (e.g. presence, or likely presence, of reactive materials) and physical properties (e.g. shear strength limiting the plant selection for material placement) of the waste. The User must select the category that represents the particular TSF.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 27
Supporting information must be attached to the ERC application to satisfactorily demonstrate to the Department why a particular capping rate has been applied. Information requirements in relation to capping are outlined in the ERC Guideline (ESR/2018/4425).
Further discussion on capping is included in Section 6.1 and a worked example is included in Section 7.3 (note this is for a Waste Rock Dump but the concepts are similar). Table A-5 of Appendix A shows the available selections, defaults and calculated quantities for the Tailings Storage Facilities User Input Sheet.
4.9.8 Pits User Input Sheet
The Pits User Input Sheet is slightly different to the others in that basic pit information and details entered to the top table automatically populates through to the treatment tables below. Section 7.5 shows a worked example and Table A-6 of Appendix A shows the details.
The following treatments are available for Pits:
Safety bund (with fencing and signs).
Benches and Highwall Drill and Blast and Doze to Make Safe.
Backfill Open Pit with Waste Rock.
Low Walk Shaping / Load and Haul to Make Safe.
Open Pit Ramp Backfill.
The User enters the quantities in the Basic Pit Information table for the treatment(s) required for each pit. The tables below the Basic Pit Information table contain the detail for each treatment and the User can change quantities in these tables as required.
In the Basic Pit Information table, the User is requested to provide a brief explanation as to how the area of the pit was derived (e.g. GIS, length of X m by width of Y m, circle of diameter D). For example, if the Pit is a rectangle, it is likely the area was derived by multiplying the length by the width. If the Pit is irregular in shape, an area estimation package may have been used.
An Alternate Rate can be entered for a specific Pit and this is added at the end of the Basic Information Table (Figure 4-15).
Figure 4-15 Alternate Rate Entry in the Basic Information Table of Pits
4.9.9 Water Storage and Management User Input Sheet
The Water Storage and Management User Input Sheet is used to calculate costs to decommission water structures, and to pump and treat water in both those water structures and from other areas of the site (including Pits).
User Comments
TOTAL FOR PIT Alternate Rate TOTAL FOR PIT User Comments
-$ -$
-$ -$ -$
-$ -$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 28
4.9.9.1 Water Storage and Sludge Removal
The Sheet includes Default Rates for water structures to which Alternate Rates can be added (Figure 4-16) and User Defined tables where specific inputs can be entered.
Figure 4-16 Example of Default Rates for Water Structures
User Defined tables are included for the following storage structures:
Process water storage.
Raw water storage.
Evaporation and other unlined water storage.
Other (e.g. weirs). The inputs for each water structure are similar and include basic dimensions as shown in Figure 4-17. The Size or Capacity (megalitres, ML) does not feature in the calculation, rather it provides context. The key inputs for the calculation are circled and if the User does not have these quantities, they should use either the Default Rates or supply Alternate Rates.
Figure 4-17 Example of User Defined Tables for Water Structures (Key Input for calculation circled)
The Sludge Removal table is similar to the water structure tables but with drop-down menus for the distance to haul sludge (Figure 4-18). This table is for sludge not within water structures as those rates include sediment and sludge.
Figure 4-18 Sludge Removal Table
4.9.9.2 Water Management (Treatment)
The Water and Salt Management table captures pumping and treatment of water in water structures, Pits and any other areas of the site where water is to be managed. There is no other place in the Calculator where water to be managed is captured.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 29
For water management, the User can stipulate one or multiple treatments including:
Evaporate water using the sun (per structure).
Enhanced evaporation of water using fine mist spray (per structure).
Operation of reverse osmosis plant (per ML).
Treat organics only (e.g. activated carbon) (per ML).
Adjust pH only (neutralisers) (per ML).
Management of salt (load, transport, dispose at suitable facility). The User must provide explanation for the treatment selected. For example, if solar evaporation is selected, the User must demonstrate the water volume can be managed in a reasonable (for rehabilitation) time-frame and costs for management of the remaining material have been included (e.g. by adding quantities to the sludge table) or are not required (e.g. evaporation water storage).
The Water and Salt Management table includes entries for:
Site Establishment and engineering for site inspections, sampling programs, engineering and design of water management systems.
Construction of infrastructure required to implement water management including water structures, drains, pumping, treatment plants, power generation and water infrastructure.
Operations management including site supervision, operational staff and consultants.
Installation and consumption of power and water required for water management.
The calculation uses User inputs of total volume of water to be pumped (ML), the pump set size (e.g. 2 inch) and the number of pump sets to calculate a pumping rate and duration to pump the entered water volume. Table 4-3 gives the User an indication of the capability of various size pumps.
Table 4-3 Indicative Pump Capabilities
Pump Flowrates (all at 100 metres head)
Flow (ML/h) Flow (ML/day)
2" pump with hoses 0.05 1.2 3" pump with hoses 0.07 1.7 4" pump with hoses 0.15 3.6 6" pump with hoses 0.25 6.0
The User can enter an Alternate Rate for the water management area at the end of each row (Figure 4-19).
Figure 4-19 Water Management Area Alternate Rate
Water management scenarios will vary from site to site depending on the mine type and degree of processing undertaken. The User should provide sufficient information to support the:
Determination of the volume of water to be pumped.
Selection of the size of pumps and number of pump sets which will relate to the volume of water to be pumped and potentially to the head required (e.g. if the water is very deep, multiple stages may be required).
Pump and
hoses Rate
($/pump per
day)
Total cost for
pumps ($) User entry
Alternate Rate
(total $)
Total cost per
area Rationale for Alternate Rate
$ 289.48 $ - -$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 30
Selection of water treatment options which will be informed by water quality results and an understanding of the mine processes.
Table A-7 of Appendix A shows the details for Water Storage. A worked example for water and salt management is included in Section 7.6.
4.9.10 Process Equipment User Input Sheet
The Process Equipment User Input Sheet requires only the input of quantities next to the appropriate line. If Alternate Rates are justifiable they can be entered to the yellow cells with an explanation in the Justification for Alternate Rate section of each line.
Figure 4-20 Example of Rates in the Process Equipment User Input Sheet.
4.9.11 Underground Mines User Input Sheet
In the Underground Mines User Input Sheet, the User enters details in the first table and the costs are calculated in the second table. The Sheet includes:
Ventilation shafts. Treatments are backfill, plug or cover. The number of ventilation shafts must be entered and the total depth (m) if backfill is the selected treatment.
Hoisting shafts. Treatments are backfill, plug or cover. The number of hoisting shafts must be entered and the total depth (m) if backfill is the selected treatment.
Adits (<2m in diameter) with options for covering and sealing. The User enters the number to be treated by each method.
Declines/ Drifts. The User enters the number of these.
Drifts/Declines with conveyors. The User enters the number of these.
Small (historical) shafts proposed for closure. The User enters the number of these. A worked example is included in Section 7.7. An Alternate Rate can be entered for a specific underground mine at the end of the Cost table (Figure 4-21). Justification must be provided in the space below the Cost table.
Figure 4-21 Alternate Rate Entry in for an Underground Mine
The Calculator defaults the “Terminate and disconnect all services to the U/G workings?” to 1 (and applies the Default Rate of $35,000) when the User enters a Name of the mine. If the services are already disconnected, the User sets this value to 0, to prevent the application of
Map ID # Activity Quantity Unit Default Unit Rate Alternative Unit Rate Total Cost
#8.01 Demolish and remove processing equipment m2/floor $265 $0
#8.02 Remove stacker or reclaimer Item $1,000,000 $0
#8.03Demolish and remove bucket wheel stacker/reclaimer or wing
stackerItem $2,500,000 $0
Total Cost for
underground
mines using
defaults
($)
Alternate Rate
($/mine)
Total Cost for
underground mines
($)
3,116,560$ 3,116,560$
3,492,742$ $2,000,000 2,000,000$
3,619,335$ 3,619,335$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 31
the Default Rate. In Figure 4-22, the Calculator has applied a quantity of 1 as the User has entered the name of a mine. For Mine 2, the User has changed the default to 0.
Figure 4-22 Quantity for Services for Mine
4.9.12 Miscellaneous Activities User Input Sheet
The Miscellaneous Activities User Input Sheet requires only User entries such as area and number. The following are included:
Land Rehabilitation and Repair of Subsidence and Land Management.
Natural Drainage and Diversions.
Land investigations.
Remediation of contaminated areas.
Miscellaneous rehabilitation and maintenance – this is for areas not covered elsewhere.
Bores and gas drainage.
Long distance carting of top soil and rock.
Long distance carting of clay.
Long distance carting of lime.
Miscellaneous scrap (not associated with facilities, buildings, pipelines etc.).
Fencing (not included elsewhere).
Rehabilitation of land areas (not included elsewhere).
4.9.12.1 Common Input Tables
Most of the tables in the Miscellaneous Activities are like that shown in Figure 4-23. They require only the names of the area and simple inputs such as area. These are summed and multiplied by the Default Rate (circled). Alternate Rates can be added below the Default Rates if justification is provided.
Figure 4-23 Example of Input Table in Miscellaneous Activities User Input Sheet
Name
Terminate and
disconnect all
services to the
U/G workings ?
Mine 1 1
Mine 2 0
Land Rehabilitation and Repair of Subsidence and Land Management
Map ID Name of Area
Maintenance of
rehabilitated areas
(ha)
Minor earthworks
and ripping or
maintenance of
mine subsidence
areas (ha)
Existing
rehabilitation
repair - minor (ha)
1
2
3
4
5
6
7
8
9
10
Quantity Totals 0.00 0.0 0.0
TOV#: #10.01 #10.02 #10.03
Rate / Default: 2,133$ 1,746$ 1,194$
Alternate Rate:
Total cost -$ -$ -$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 32
4.9.12.2 Preliminary and Intrusive Site Investigations
The Calculator has Default Rates for contaminated land investigations, both preliminary and intrusive site investigations. These Default Rates must be considered for any project that:
Produces one or more hazardous contaminants in a concentration with the potential to cause serious or material environmental harm and a person, animal or other part of the environment may become exposed to the hazardous contaminant(s).
Includes notifiable activities; and/or has contaminated land on the environmental management register (EMR) or contaminated land register (CLR).
Preliminary Site Investigation
The Preliminary Site Investigation unit rate is a one-off cost. A Preliminary Site Investigation in the context of mine closure is typically a part of planning activities and aims to identify areas of known, suspected or reasonably probable contamination resulting from the mine operations. The Preliminary Site Investigation comprises a review of the site setting, site history, operational history (including any accidents and incidents), hazardous liquids and solids storage schedules and sources of potential impacts and receptors.
To apply a cost for a Preliminary Site Investigation, the User selects Y in the “Preliminary Site Investigation needed?” column Figure 4-24.
Figure 4-24 Preliminary Site Investigation Entry
Intrusive Site Investigations
An intrusive investigation would be targeted and may not be required for all contaminated or preliminary investigation areas. The intrusive investigation rate should be applied considering risk, site history, past incidents and the planned rehabilitation program. An intrusive investigation should be considered if a site has contaminated land on the EMR or CLR, and if scalping and disposal of contaminated material is not accounted for in key areas with potential for contamination (e.g. process areas, maintenance yards, go lines).
There are two Default Rates for intrusive site investigations - a one-off cost (termed “Separate Area” in the Calculator) and per area cost. The User must add entries for both these rates to cost an intrusive site investigation.
One-Off Cost for Site Investigations
The approach to estimating costs for site investigations recognizes that most investigations of this nature comprise a single campaign (one mobilisation) taking in multiple areas. The one-off cost allows for planning and preparation, ongoing project management, health and safety plans, work plans and reporting. A combination of the factors outlined above (risk, rehabilitation program, site history and grouping and relative proximity of infrastructure) must be considered in determining the number of one-off costs to apply. Examples of areas that may individually comprise one campaign are:
Service facility area – fuel or chemical stores, workshop, vehicle washdown, sewage treatment.
Land Investigations
TOV#: #10.14
Rate / Default: 15,000$
Alternate Rate:
Map ID Area
Separate area?
(Or portion) Width (m) Length (m) Diameter (m) User Area (ha)
Preliminary site
investigation
needed?
Calculated Area
(ha)
Area for
calculations
(ha)
Preliminary Site
Investigation ($)
1 Washdown area 0.5 100.0 20.0 Y 0.20 0.20 15,000$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 33
Processing plant – ore and product storage, mine waste storage and disposal rail load out.
Remote pit facilities - vehicle re-fuel, sewage treatment, secondary workshop, chemical storage.
The User should enter a 1 for the one-off entry demonstrating that the areas described in the line will be investigated in one campaign1. The Calculator defaults to 1 when an area is added (Figure 4-25).
Figure 4-25 Example of Use of One-off Cost
The User can enter a fraction of 1 if they want to list individual areas that will be investigation in one campaign (Figure 4-26).
Figure 4-26 Example of a Fraction Entry of One-off Cost
By Area Cost for Site Investigation
The by area rate accounts for activities undertaken on-site. The rate includes costs for field staff to collect soil samples, sampling equipment and consumables and laboratory analytical costs.
The User can describe the area for a land investigation by entering width and length or diameter or the area (Figure 4-27). This recognizes that Users will have different quantity types. Some Users may use GIS that outputs area and others may be measure length and width off a plan. In this example, the hierarchy is User Entered Area then Width and Length and then Diameter. If both length and width and diameter are added, the Calculator uses length and width and ignores diameter. The Calculated Area column shows the calculation of area based on the User Entered dimensions and if a value is entered directly to the User Area column, the Area for calculations column will default to that entry (see Figure 4-27 for examples).
1 These areas were termed “cluster” in the Financial Assurance calculator.
Area
Separate area?
(Or portion)
Service area 1 1.0
Processing area 1.0
0.0
Area
Separate area?
(Or portion)
Washdown area 0.5
Vehicle serrvice area 0.5
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 34
The per area rate is applied only to the area to be investigated. For example, a tank farm within a processing facility – in this case only the tank farm area is entered.
Figure 4-27 Land Investigation Input Cells showing Options for Defining the Area
4.9.12.3 Remediation of Contaminated Areas
This table accounts for any known contamination on the site. Remediation of contaminated areas is not included in any of the other User Input Sheets, so any area must be entered this to the table.
The table includes inputs and rates for material beneath process facilities; disposal of contaminated material to landfill, on-site landfarming of soil impacted by organics (e.g. oily soil or sludge) and asbestos.
4.9.12.4 Long Distance Haul
Long distance haul tables are available for top soil and rock (Figure 4-28), gypsum (for amendment of top soil), clay (e.g. for low permeability caps) and lime (for neutralization). The User must use these tables if required material is not within 6 km of the intended use area. The distance is selected from the drop-down menu (circled) which has increments extending up to 200 km. The User enters the mass of material required and this is multiplied by the distance and Default Rate to obtain the total cost for that area. The purchase price is separate to the transport cost and this is shown in the adjacent column. The Default Rate can be changed by the User if they provide justification. An Alternate Rate can be added in the standard way for the Calculator.
Figure 4-28 Long Distance Haul of Top Soil or Rock
4.9.12.5 Miscellaneous Scrap
The miscellaneous scrap table accounts for any scrap not associated with Elements in other User Input Sheets (e.g. debris from a facility demolished in the past that has yet to be cleared). Scrap resulting from demolition of infrastructure and process equipment covered in other User Input Sheets does not need to be added here as it is incorporated into those rates.
Two rates are available – bury on-site and dispose off-site. An Alternate Rate can be added in the standard way for the Calculator.
Area
Separate area?
(Or portion) Width (m) Length (m) Diameter (m) User Area (ha)
Preliminary site
investigation
needed?
Calculated Area
(ha)
Area for
calculations
(ha)
Washdown area 0.5 100.0 20.0 N 0.20 0.20
Vehicle serrvice area 0.5 0.05 N 0.00 0.05
Processing area 1.0 30.0 N 0.07 0.07
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 35
Figure 4-29 Miscellaneous Scrap Disposal
4.9.12.6 Fencing
The fencing table (Figure 4-30) is to account for miscellaneous fencing not associated with Elements in other User Input Sheets. The Default Rates in the TOV for the different fencing types are listed and Alternate Rates can be added in the standard way for the Calculator.
Figure 4-30 Fencing
4.9.13 Mobilisation/Demobilisation and Additional User Items User Input Sheet
The Mobilisation and User Input Sheet allows entries for mobilisation / demobilisation and any additional site-specific items that do not have a space elsewhere in the Calculator.
Mobilisation and demobilisation is the process of transporting earthmoving machinery to the site for the rehabilitation work and transporting the machinery back to the supply centre. Typically, the supply centre for earthmoving equipment is a major centre such as Brisbane or Rockhampton. The mobilisation / demobilisation costs reflect the effort required for safe transport of earthmoving equipment which typically includes floats and convoys.
The Calculator includes mobilisation / demobilisation rates for small, medium and large fleets and in distance ranges of <=150 km, >150 km and <=500 km, > 500 km and <=1000 km and > 1000 km (Figure 4-31). The Default Rates allow for transport both ways and therefore the User should use the one-way distance (from supply centre to source) when determining the appropriate line to select. The Default Rates includes costs for utility and service vehicles to support the earthmoving equipment.
Mobilisation and Demobilisation
Map ID TOV# Description Qty Default Rate Alternate Rate Total
#11.01 Mobilisation & Demobilisation - Small Fleet (<= 150 km) 123,000$ $0
#11.02 Mobilisation & Demobilisation - Small Fleet (> 150 km and <= 500 km) 1 226,000$ $226,000
#11.03 Mobilisation & Demobilisation - Small Fleet (> 500 km and <= 1000 km) 427,500$ $0
#11.04 Mobilisation & Demobilisation - Small Fleet (> 1000 km) 526,000$ $0
#11.05 Mobilisation & Demobilisation - Medium Fleet (<=150 km) 184,000$ $0
#11.06 Mobilisation & Demobilisation - Medium Fleet (> 150 km and <= 500 km) 337,500$ $0
#11.07 Mobilisation & Demobilisation - Medium Fleet (> 150 km and <= 500 km) 638,000$ $0
#11.08 Mobilisation & Demobilisation - Medium Fleet (> 1000 km) 785,000$ $0
#11.09 Mobilisation & Demobilisation - Large Fleet (<= 150 km) 201,000$ $0
#11.10 Mobilisation & Demobilisation - Large Fleet (> 150 km and <= 500 km) 368,500$ $0
#11.11 Mobilisation & Demobilisation - Large Fleet (> 500 km and <= 1000 km) 697,000$ $0
#11.12 Mobilisation & Demobilisation - Large Fleet (> 1000 km) 858,000$ $0
226,000$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 36
Figure 4-31 Mobilisation and Demobilisation Default Rates
The number of mobilisation / demobilisation units entered is dependent on the activities selected throughout the Calculator. Typically, the expectation is for only one entry with the fleet size reflecting the predominant size used through the calculation. For large projects, two entries may be required, for example a small fleet is sourced from a local centre and a large fleet is sourced from a major centre. The User should justify the distance and fleet size selected in the User Comments section of the Mobilisation and demobilisation User Sheet or the Assumptions Sheet. Irrespective, at least one of these rates must be applied once for every submitted ERC. Figure 4-31 shows a typical example (with only one unit entered). This Sheet requires only the input of quantities next to the appropriate line. If Alternate Rates are justifiable they can be entered to the yellow cells with an explanation in the Rationale for Alternate Rate section of each line.
For small projects (total ERC < $1,000,000 before mobilisation costs), the User may choose to apply mobilisation and demobilisation costs by using the 10% flat rate option contained on the Summary Screen. The User can choose this option by entering a ‘1’ into the line ‘Mobilisation & Demobilisation – small projects’. Using this functionality will apply mobilisation and demobilisation costs of 10% of the total ERC amount. If using this approach the User should not enter quantities into the Mobilisation Sheet.
Figure 4-32 Mobilisation & Demobilisation – small projects
4.9.14 Disturbance Sheet
The disturbance sheet allows for Users to enter free text data, which may include granular disturbance quantities and other miscellaneous supporting information.
It is important to note that the values entered into this sheet are not linked through the workbook, and the User must ensure that all disturbance values are separately entered into the relevant Sheets.
Figure 4-33 Disturbance Sheet
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 37
5 Information on Rates
5.1 Bottom-up, First Principles Calculation Method
The Unit Rates for an activity are constructed using “bottom-up, first-principles” whereby costs for relatively complex activities are built starting from basic singular values such as cost ($) per hour for machinery hour and productivity of that machinery. The build of Unit Rates is illustrated in Figure 5-1.
The bottom-up, first principles method is generally:
A scope for an activity is defined.
Productivity values are used to estimate the time an activity may take.
The time is multiplied by an hourly rate (encompassing Labour and Equipment rates) to obtain a cost for that activity.
Labour Costs, Equipment Costs and Productivity Rates are the most fundamental values (base rates) underpinning the Unit Rates and these are discussed further below.
5.2 Labour Costs
The Labour costs (e.g. cost per hour for equipment operator) are calculated by adding the following allowance to a base rate:
Annual leave
Long service leave
Paid notice
Severance / retrenchment
Payroll tax
Workers compensation
Superannuation
Profit
Operating hour proportion
5.3 Equipment Costs
The Equipment costs (e.g. cost per hour for an excavator) are built assuming:
The capital (ownership) cost of new equipment is depreciated over a much longer life within the Calculator than what it is likely for used equipment.
The new equipment would be depreciated (and used) over several contracts by a typical earthmoving contactor unless they are long term contracts.
Operating time of 3,723 hours per year for closure works.
The new equipment ownership (depreciation) rates per hour are anticipated to be similar to used equipment ownership (depreciation) rates per hour a contractor would apply to a typical earthmoving contract based on the typical age of used equipment proposed for the contract.
The following depreciation periods for new equipment are used in the Calculator rates:
Dozers 35,000 hours
Graders 55,000 hours
Excavators 54,000 hours
Front End Loaders 35,000 hours
Haul Trucks 75,000 hours
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 38
The Equipment costs are calculated by adding the following allowance to a base rate:
Rolled-up labour cost as described above.
Fuel is a set price per litre. The fuel cost per hour is calculated using fuel consumption rates from the Caterpillar™ manual.
Preventative maintenance and wear.
Contractor profit and administration of 16%.
5.4 Productivity
Productivity (e.g. cubic metres of soil a dozer can push over a specific length range) defines the performance capability of a machine or equipment and is used to estimate the time an activity may take so that an hourly rate can be applied to obtain a cost for that activity. Productivity rates are generally sourced from the Caterpillar™ earthmoving manual.
5.5 Scope and Unit Rates
The scope for a Unit Rate is the sequence of events or activities (which could be thought of as sub-activities) required to be undertaken to complete an Activity. For example, sourcing rock to fill a void comprises loading the rock, transporting the rock and placing the rock. Each activity has a Unit Rate and these are summed to obtain the Unit Rate for the Activity.
Depending on the complexity of the Activity, Unit Rates either are a rate in the TOV (or Default Rate) directly or are combined with other unit rates to form a rate in the TOV. Instructions on appropriate application of each rate in the TOV are included in the Use and Scope and Key Assumptions columns in the TOV Sheet.
The scope for each activity was developed by a team of engineers with mine closure and engineering cost estimation experience ranging from 20 to over 35 years. The base costs (e.g. cost per hour for an excavator) are based on contemporary third-party rates.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 39
Figure 5-1 Inputs to Table of Values (Build-up of Unit Rates)
5.6 Alternate Rates
Users must review all Default Rates and ensure they are applicable to their site conditions. If not, they can specify an Alternate Rate and insert this rate into the Calculator. Alternate rates and additional items include third-party quotes or contracted rates.
Third-party quotes or contracted rates used in the Calculator must meet the requirements in the ERC Guideline (ESR/2018/4425).
Users must provide justification for any Alternate Rates or additional items provided in the Calculator.
5.7 Contractor Rate Inclusions
The contractor rates (e.g. $/h for an excavator) that form the basis of the Unit Rates include built-in allowances for:
Health and safety plans and personnel protective equipment.
Passenger vehicles / utilities for crew, support staff (e.g. fitters) and supervisors.
Service vehicles for fueling, oiling and greasing primary machinery.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 40
Ancillary equipment such as power generators, air compressors and hoses, lighting units.
Signage and fencing.
Consumables including fuel, oils and greases, other consumables.
Maintenance personnel and tools.
Temporary accommodation camps, workshops, offices and stores and equipment and consumables therein.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 41
6 Focus Items
6.1 Capping of Waste Rock Dumps, Heap Leach Pads and Tailings Storage Facilities
The Calculator has separate User Input Sheets for Overburden Dump/Waste Rock Dumps, Heap Leach Pads and Tailings Storage Facilities.
For all three of these domains, the Calculator provides two options:
1. Default, “Rolled-up” rates that use unit rates and sub-activities to generate a single rate value (typically as $/ha); or
2. User Defined table. These tables allow the user to enter site-specific details of the structure and use the unit rates to generate a single rehabilitation value.
The User can enter quantities into both tables for different structures. The User does not enter details into both tables for the same structure. In each Sheet, the sum of the Default and User-Defined entries is shown at the top (Figure 6-1). The title ERC is also shown for reference.
Figure 6-1 Total for Input Sheet
The method to calculate the cost of the structure is the same for the Default and User Defined cases but in the User Defined option, the User has more flexibility to match the specific design / approach for the site.
Both the default and User Defined options consider the following capping features:
A working rock layer over the tailings to provide a stable surface for the cap. Note that a working layer is not required for Waste Rock Dumps or Heap Leach Pads.
Capillary break layer to mitigate salt uptake into the vegetation surface.
Low permeability layer (typically clay) to prevent infiltration of surface water into the waste.
Growth media (typically top soil) and vegetation.
The key entry for review by the Department is the Risk Category selected by the User, which should reflect the risk the element poses to the environment. The User should provide notes to inform the Department of the rationale behind the selection and Table 4-1 provides a guide for the characteristics of Waste Rock, Heap Leach and Tailings for each category.
Estimated Rehabilitation Cost (ERC) Calculator for Mining
WASTE ROCK DUMPS, OVERBURDEN DUMPS, SPOIL PILES AND STOCKPILES
Back to Contents
Total Cost for this Input Sheet -$ $0 Total ERC (from Summary Sheet)
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 42
Table 6-1 Risk Category Characteristics
Risk Category
Waste Rock Dumps Heap Leach Pads Tailings Storage Facilities
High
Select this category if the waste structure has one or more of the following characteristics:
Potentially acid forming material (PAF)
Other highly reactive materials including (ARD/AMD/NMD)
Observed contaminated seepage capable of causing environmental harm
Potentially acid forming material (PAF)
Other highly reactive materials including (ARD/AMD/NMD)
Observed contaminated seepage capable of causing environmental harm.
Potentially acid forming (PAF) material
Other highly reactive materials including (ARD/AMD/NMD)
Poor consolidation and low shear strength tails materials
Requiring composite liners (e.g. HDPE)
Embankments > 30 metres high
Observed contaminated seepage capable of causing environmental harm.
Medium Moderately reactive materials (ARD/AMD/NMD)
Hypersaline tailings that could impact on the proposed end land use
Moderately reactive materials (ARD/AMD/NMD)
Hypersaline tailings that could impact on the proposed end land use
Moderately reactive materials (ARD/AMD/NMD)
Hypersaline tailings that could impact on the proposed end
Low strength consolidated tailings land use objectives for the facility
Embankments 15 to 30 m high
Low Low reactive materials (ARD/AMD/NMD)
Low reactive materials (ARD/AMD/NMD
Low reactive materials (ARD/AMD/NMD)
Moderate to low salinity
Moderate strength consolidated tailings
Embankments less than 15 m high
Very Low Benign materials Benign materials Zero reactive materials (ARD/AMD/NMD)
Low salinity
Moderate strength consolidated tailings
Embankments less than 15 m high
An allowance for engineering and design of Waste Rock Dumps, Heap Leach Pads and Tailings Storage Facilities is included in the Default and User-Defined rates.
The engineering costs and default minimum thicknesses of each cap item are shown in Table 6-2.
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 43
Table 6-2 Capping Engineering Cost and Default Minimum Thicknesses
Risk Category
Waste Rock Dumps Heap Leach Pads Tailings Storage Facilities
High Engineering $2,000/ha
Working layer 0 m
Capillary break 0.6 m
Low permeability layer 0.5 m
Top Rock Layer 1.5 m
Engineering $2,000/ha
Working layer 0 m
Capillary break 0.6 m
Low permeability layer 0.5 m
Top Rock Layer 1.5 m
Engineering $2,000/ha
Working layer 0.5 m
Capillary break 0.6 m
Low permeability layer 0.5 m
Top Rock Layer 1.5 m
Medium Engineering $2,000/ha
Working layer 0 m
Capillary break 0.3 m
Low permeability layer 0 m
Top Rock Layer 1.0 m
Engineering $2,000/ha
Working layer 0 m
Capillary break 0.3 m
Low permeability layer 0 m
Top Rock Layer 1.0 m
Engineering $2,000/ha
Working layer 0.5 m
Capillary break 0.3 m
Low permeability layer 0 m
Top Rock Layer 1.0 m
Low Engineering $1,500/ha
Working layer 0 m
Capillary break 0 m
Low permeability layer 0 m
Top Rock Layer 0.5 m
Engineering $1,500/ha
Working layer 0 m
Capillary break 0 m
Low permeability layer 0 m
Top Rock Layer 0.5 m
Engineering $1,500/ha
Working layer 0 m
Capillary break 0 m
Low permeability layer 0 m
Top Rock Layer 1 m
Very Low Engineering $500/ha
Working layer 0 m
Capillary break 0 m
Low permeability layer 0 m
Top Rock Layer 0 m
Engineering $500/ha
Working layer 0 m
Capillary break 0 m
Low permeability layer 0 m
Top Rock Layer 0 m
Engineering $500/ha
Working layer 0 m
Capillary break 0 m
Low permeability layer 0 m
Top Rock Layer 0 m
The default thickness for growth media is 0.15 m for all cases.
A worked example illustrating how to calculate the cost of capping of a Waste Rock Dump using the Default and User Defined options is shown in Section 7.
For High Risk Waste Rock Dumps, Heap Leach Pads and Tailings Storage Facilities, the default minimum top rock, capillary break and low-permeability layer thicknesses are locked. This means if the User enters a value below the minimum, it will not be accepted, and the Calculation will default to the minimum. If the User enters a thickness greater than the default minimum, the Calculator uses the User-entered value. The default thickness is not fixed for elements of Medium, Low and Very Low Risk Category. See the worked example in Section 7.4.
6.2 Pasture and Native Seed
Most activities require re-vegetation of the land surface and the Calculator allows for native or pasture type seed. The Calculator typically includes a drop-down menu to allow the selection of native or pasture seed. The Calculator applies the appropriate rate to area required to be seeded. If an area covers both native and pasture land, the User must input separate lines (
Figure 6-2).
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 44
Figure 6-2 Seeding Example
6.3 Haulage Distances
The haulage distance is the round-trip distance to/from a source of material (e.g. gypsum) or to an end-use / disposal location (e.g. void for rock placement). (Note this is different to the mobilization / demobilization costs).
6.4 Fleet Sizes
A range of fleet sizes is included in the Calculator to reflect the varying size of earthmoving projects. For large projects, economies of scale can be realized by using larger fleets. It is important the right size fleet is used for each activity to improve the accuracy of the calculation. Table 6-3 provides examples of the fleet size for various activities.
Table 6-3 Fleet Sizes for Various Activities
Fleet Size Typical Composition Activities
Small 740C (ADT) Truck
980M Loader
14M Grader
19kL water truck
D9R Dozer
Load, haul and spread top soil and other growth media materials
Load, haul and dump bitumen, stabilised materials, demolition rubble and concrete
Load, Haul, Dump Spread Fill (small scale) - Waste Rock Landforms, Spoil Piles, Roadways, contaminated soil footprints, ponds, dams, shallow voids, in-pit and other tailings storage facilities and other fill areas – volumes of materials up to 1.0M m3.
Excavate, load, haul, dump and spread water storage sediment and silt
Medium 777G Truck
PC 1250 Excavator
16M Grader
777G Truck
D10T Dozer
Load, Haul, Dump Spread Fill (medium scale) - Waste Rock Landforms, Spoil Piles, Roadways, contaminated soil footprints, ponds, dams, shallow voids, in-pit and other tailings storage facilities and other fill areas – volumes of materials up to 5.0M m3.
Large 793F Truck
EX2500 Excavator
16M Grader
785D Water Truck
D11T Dozer
Load, Haul, Dump Spread Bulk Material including Fill - Waste Rock Landforms, Spoil Piles, Roadways, contaminated soil footprints, ponds, dams, shallow voids, in-pit and other tailings storage facilities and other fill areas – volumes of materials up to 10M m3.
Truck/ Shovel 797F Truck Source, Load, Haul, Dump Spread overburden for pit backfill and recontouring –
HEAP LEACH PILE REVEGETATION
#10.58 #10.59
1,415$ 3,635$
Area of seeding
required (ha) Type of seed
Area requiring
rehab in Pasture
(ha)
Area requiring
rehab in Native
(ha)
Cost for Seeding
($)
100.0 Pasture 100.0 0.0 141,500$
1.0 Native 0.0 1.0 3,635$
101.0 100.0 1.0 145,135$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 45
Fleet Size Typical Composition Activities
CAT 6090 Hydraulic Shovel
16M Grader
785D Water Truck
D11T Dozer
Waste Rock Landforms, Spoil Piles, Stockpiles, Run of Mine pads, Heap Leach piles, Tailings Storage Facilities - Source local material, cart and spread to cap and/or cover
Small Dozers D6R or D7R Push / rip lengths <= 100 m
Clear vegetation
Low height Waste dumps and spoil dump, TSF embankment slope re-profiling and shaping
Medium Dozers D8R Push / rip lengths <= 250 m
Clear vegetation
Waste dump, spoil dump, TSF embankment slope re-profiling and shaping
Shape and doze to establish drainage, spread cover/topsoil/rock mulch layer slopes and flats
Capping of Waste Rock Dumps, Heap Leach Pads and Tailings Storage Facilities
Large Dozer D9R, D10T or D11T Bulk Push / rip lengths <= 500 m
Waste dump, spoil dump, TSF embankment slope re-profiling and shaping
Shape and doze to establish drainage, spread cover/topsoil/rock mulch layer slopes and flats
Capping of Waste Rock Dumps, Heap Leach Pads and Tailings Storage Facilities
Small Grader 12M Rip / grade to match fleet activities
Medium Grader 14M Rip / grade to match fleet activities
Large Grader 16M Rip / grade to match fleet activities
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 46
7 Worked Examples
7.1 Seismic Easements
To calculate the cost for rehabilitation of seismic easements, the User should follow the steps below.
1. Enter the length of easement in each land type (native and pasture).
2. The Calculator multiplies the User Entered length by a default 5% calculate the length of easement to be rehabilitated. If 5% is not correct for the site, the User enters the easement length to be rehabilitated. The screen shot below shows the calculated 1.0 km length over-ridden by the User Entered 0.5 km.
3. The length is multiplied by the rate for pasture or native to obtain a total cost for that disturbance.
4. The total easement length (20 km in this example) and the total length to be rehabilitated (0.5 km in this example) are reported as below.
5. The total cost for the individual disturbance ($18,029 and $167,844 in the example below) and total for all the seismic disturbances are reported as shown below
Seismic, Grid-Lines, Minor Tracks
5%
Map ID Land type
Total Length
(km)
Rehab length
(km)
In Pasture 20.0 1.0
In Native 0.0
Seismic, Grid-Lines, Minor Tracks
5%
Map ID Land type
Total Length
(km)
Rehab length
(km)
In Pasture 20.0 0.5
In Native 0.0
5%Total Length
(km)
Rehab length
(km) TOV# Default Rate Alternate Rate Total Rationale for Alternate Rate
20.0 0.5 #1.01 901$ $ 18,029
0.0 #1.02 1,678$ $ -
0.0 $ -
0.0 $ -
20 0.5 18,029$ 36,058$
5%Total Length
(km)
Rehab length
(km) TOV# Default Rate Alternate Rate Total Rationale for Alternate Rate
20.0 0.5 #1.01 901$ $ 18,029
0.0 #1.02 1,678$ $ -
0.0 $ -
0.0 $ -
20 0.5 18,029$ 36,058$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 47
($185,873 in the example below). The average cost per unit distance is also reported ($33,795 in the example below).
6. If required the User can enter and Alternate Rate and justify it in the Rational for Alternate Rate column.
7. As with the other User Input Sheets, the User can enter site-specific entries at the bottom of the table. The example below shows the entry of a specific area and using the Default Rate and a second specific area with an Alternate Rate.
7.2 User Defined Roads in Infrastructure User Input Sheet
To calculate the cost for rehabilitation of a road, the User should follow the steps below.
1. Enter the name of the road (or group of roads) and the length of the road (or total length of the group of roads). Enter the width of the road or leave this cell blank. If the User leaves the cell blank, the default quantity (6.0 m in this example) is used in the calculation.
2. Select the surface covering of the Road from the drop-down menu. The total length defaults to the next column (Length of Road surface covering to be removed or rip) though the User can enter a site-specific length with justification.
5%Total Length
(km)
Rehab length
(km) TOV# Default Rate Alternate Rate Total Rationale for Alternate Rate
20.0 0.5 #1.01 901$ $ 18,029
100.0 5.0 #1.02 1,678$ $ 167,844
0.0 $ -
0.0 $ -
120 5.5 185,873$ 33,795$ per km (average)
5%Total Length
(km)
Rehab length
(km) TOV# Default Rate Alternate Rate Total Rationale for Alternate Rate
20.0 0.5 #1.01 901$ $1,000 $ 20,000 Supplied by third-party
0.0 #1.02 1,678$ $ -
0.0 $ -
0.0 $ -
20 0.5 20,000$ 40,000$ per km (average)
Seismic, Grid-Lines, Minor Tracks
5%
Land type
Total Length
(km)
Rehab length
(km) TOV# Default Rate Alternate Rate Total Rationale for Alternate Rate
In Pasture 20.0 0.5 #1.01 901$ $ 18,029
In Native 100.0 5.0 #1.02 1,678$ $ 167,844
Seismic in area X 10.0 0.5 $1,000 $ 10,000 Thiird-party quote (details attached)
Other (used entered) 0.0 $901 $ - Seismic in pasture using TOV rate #1.01
130 6 195,873$ 32,645$ per km (average)
Acces Roads / Tracks (User defined) Back to Top
ROAD DIMENSIONS AND COVER
TOV #
Default value 6.0
Map ID
# Road / Track Name Road/Track Width (m)
Total Length
(km)
1
Add Roads/Tracks
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 48
3. The User can enter a thickness for the surface covering or accept the defaults (by leaving the cells blank). The defaults reference the surface covering selected in the previous step. The Calculator calculates the volume of material to remove (90,000 m3 for the waste rock road in the example below).
4. From the drop-down menu, the User selects the distance to haul the surface cover material for disposal. The Calculator multiplies the appropriate Default Rate for haulage by the volume to haul to calculate the total cost for removal.
5. The next section, for replacement of surface covering, is an optional and the User should only enter information if required. Examples of where this may occur are a) the road was to be retained but contaminated material had to be removed and b) the road was earthen but the agreement with the land-owner is to install a hardstand road. The default length of surface covering to replace is 0 km (first line in the
ROAD DIMENSIONS AND COVER REMOVAL OF COVER
6.0
Road/Track Width (m)
Total Length
(km) Type of Surface Covering
Length of Road
surface covering
to be removed
or rip (if earthen
(km)
Earthen 0.0
0 0
Add Roads/Tracks
REMOVAL OF COVER
Type of Surface Covering
Length of Road
surface covering
to be removed
or rip (if earthen
(km)
Thickness of
surface covering
(mm)
Surface covering
thickness used
in calculations
(mm)
Volume of
surface covering
to remove (m3)
Earthen 100.0 0 0
Waste Rock 100.0 150 90000
Haul distance to surface material (km) TOV#
Default Rate
($/km)
Cost to remove
surface covering
($)
<=200 m #2.13 2.99$ -$
<=200 m #2.13 2.99$ 269,270$
269,270$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 49
example below) and the User must enter a value if material is to be replaced (second line in the example below).
From the drop-down menu, the User selects the distance to the source of surface cover material. The Calculator multiplies the appropriate Default Rate for haulage by the volume to haul to calculate the total cost for replacing surface cover.
6. Grade and seed is calculated in a similar manner to other Domains. The Default area to seed is the total length by the width of the road, but the User can enter a site-specific area with justification. The User selects the type of seed from the drop down menu and the Calculator places the area in the appropriate column. The Calculator multiplies the Unit Rate for the seed-type by the area for seeding to calculate the total cost for seeding.
7. The Calculator sums all the totals described above to calculate the total cost for the Element (a road in this case), sums all the Elements to get the total cost for the Disturbance type and divides the total cost by the total length to obtain the cost per kilometer.
REPLACEMENT OF COVER (IF APPLICABLE)
150
Length of road
to replace rock
(km)
Thickness of
rock to replace
(mm)
Volume of rock
to replace (m3) Distance to return rock (km) TOV# Default Rate
Cost to replace
rock ($)
0.0 0 <=200 m Return #2.24 3.81$ -$
10.0 9000 <=200 m Return #2.24 3.81$ 34,245$
10 0 9000 34,245$
GRADE AND SEED
TOV# TOV# >> #10.58 #10.59
385$ 1,415$ 3,635$
Length of track /
bare road to rip,
grade, seed
(km)
Area of track /
bare road to rip,
grade, seed (ha)
Cost to rip road /
track and grade
Area of seeding
required (ha) Type of seed
Area requiring rehab
in Pasture (ha)
Area requiring rehab
in Native (ha) Cost to re-seed ($)
100.0 60.00 23,100$ 60.00 Pasture 60.0 0.0 84,900$
90.0 54.00 20,790$ 54.00 Pasture 54.0 0.0 76,410$
190 114 43,890$ 114 0 114 0 161,310$
Cost to re-seed ($) Total Cost ($)
84,900$ 108,000$
76,410$ 400,715$
161,310$ 508,715$
Cost per km 2,544$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 50
7.3 Default Rates for Waste Rock Dumps
To calculate the cost for capping a Waste Rock Dump using the default rate option, follow the steps below. The process for Waste Rock Dumps is similar for Heap Leach Pads and Tailings Storage Facilities.
1. Enter the name or identifying reference for the element (e.g. Waste Rock Dump East) into the ‘Waste Rock Dump Name’ column.
2. Enter the total footprint area (ha) of the element into the ‘Area (ha)’ column. 3. Select the Risk Category from the drop-down menu.
The selected Risk Category references a Default Rate ($/ha) from the Table of Values. This is multiplied by the total footprint area to calculate the total cost for the element.
4. Enter an explanation for the Risk Category selection in the ‘Justification for Risk Category Selection’ column (see below).
5. If required, the User can enter an Alternate Rate in the yellow ‘Alternate Rate’ column. In this event, the calculation uses the Alternate Rate over the Default Rate and the Alternate Rate cell turns red (see below) to alert the Department.
If the User enters an Alternate Rate, the User must provide justification in the ‘Rationale for Alternate Rate’ column (see below).
6. The User must determine whether top soil or amendment materials (i.e. lime and clay) are required to be transported from > 6 km from the Element and if so, click on the appropriate hyperlinks (see below) to access the long-distance haul sections of the Miscellaneous Activities User Input Sheet (Section 4.10.11).
Waste Rock Dumps (Defaults)
# Waste Rock Dump Name Area (ha) Risk Category TOV #
Default Rate
($/ha)
Alternate Rate
($/ha)
Total cost for
WRD ($)
1 High Risk WRD/OB #4.01 161,317$ -$
2 Medium Risk WRD/OB #4.02 78,635$ -$
Justification for Risk Category Selection
Waste Rock Dumps (Defaults)
# Waste Rock Dump Name Area (ha) Risk Category TOV #
Default Rate
($/ha)
Alternate Rate
($/ha)
Total cost for
WRD ($)
1 High Risk WRD/OB #4.01 161,317$ $100,000 -$
2 Medium Risk WRD/OB #4.02 78,635$ -$
Rationale for Alternate Rate
Total cost for
WRD ($)
Long Distance
Haul of Clay
Long Distance
Haul of
Limestone
Long Distance
Haul of Top-
soil Justification for Risk Category Selection
-$ Clay off-site Lime off-site Soil off-site
-$ Clay off-site Lime off-site Soil off-site
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 51
7.4 User-Defined Rates for Waste Rock Dumps, Heap Leach Pad and Tailings Storage Facilities
To calculate the cost for capping a Waste Rock Dump using the User-Defined rates option, follow the below steps:
Dimensions
1. Enter the name or identifying reference for the element (e.g. Waste Rock Dump East).
2. Enter the total footprint area (ha) of the element. 3. Select the Risk Category from the drop-down menu. 4. For the User-Defined option, the selected Risk Category references default
thicknesses for capping elements (see Table 6-2). These defaults are shown in other areas of the table as discussed below.
5. Enter the flat area (ha) of the element and average doze thickness for soil to push during re-shaping.
6. Enter the sloped area (ha) of the element and average doze thickness for soil to push during re-shaping.
7. Enter the ramps area (ha) of the element.
Re-shaping
8. Select the target slope angle for the re-profiled surface. This selection determines which push rate to apply.
9. The User can enter the volume of material to push (for the flat and the slopes) if they have this information, otherwise that cell is left blank and the calculation accepted.
10. The User selects the length of dozer push and dozer size from the drop-down menus based on the size of the element and specifics of earthmoving at the site.
11. The Calculator then multiplies the Unit Rates by the quantities to calculate the total cost for re-shaping of the flat and sloped (including ramps) areas.
Rock Armouring
12. The User can enter the thickness of rock armour for the slopes or accept the default (1.0 m in the example below).
Waste Rock Dumps (User Defined)
WRD DIMENSIONS
TOV#
Default value
# Name
Total Footprint area of
WRD (ha)
Risk Category (select
from dropdown)
Rehabilitation of flat
areas (tops,
benches, berms etc)
area (ha)
Average doze
thickness flat
areas (m)
Rehabilitation of
slope/batter
areas(ha)
Average doze
thickness slope
areas (m)
Rehabilitation of
WRD access
ramps (ha)
1 Medium Risk WRD/OB
0.0 0.0 0.0 0.0
Add Waste Rock Dump
WRD RESHAPE AND DOZE
Reprofiled slope angle
User entered
volume to push
on flat surfaces
(m3)
Volume to push
on flat surfaces
used in
calculations
(m3)
User volume to
push slopes
(m3)
Volume to push
slopes used in
calculations
(m3) Length of Dozer Push Dozer TOV #
Flat Areas Unit
Rate ($/m3)
Cost for Dozer
Push All Areas
($) TOV #
Slope Areas Unit
Rate ($/Ha)
Cost to Doze
and Shape
slopes and
ramps ($)
>10<=15 degrees - - > 150m push D9R Dozer #4.50 1.47$ -$ #4.68 2,148$ -$
- - - - -$ -$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 52
13. From the drop-down menus, the User selects the haulage distance to the source of rock and the fleet size based on the specific of the site. Guidance on fleet size selection is included in the User Guide.
14. The Calculator then multiplies the Unit Rates by the quantities to calculate the total cost for rock armouring of the slopes.
Capillary Break Layers
15. The User can enter the area of the surface to be capped but generally the default is the total footprint or flat area depending on the element.
16. The User can enter the thickness of capillary break layer or accept the default (see Table 6-2). For High Risk: Waste Rock Dumps, Heap Leach Pads and Tailings Storage Facilities, the default minimum capillary break thickness is locked. This means if the User enters a value below the minimum, it will not be accepted, and the Calculation will default to the minimum. If the User enters a thickness greater than the default minimum, the Calculator uses the User-entered value. The default thickness is not fixed for elements of Medium, Low and Very Low Risk Category.
17. The User can enter the volume of material to be used for the capillary break layers (if they have this information, otherwise that cell is left blank and the calculation accepted.
18. From the drop-down menus, the User selects the haulage distance to the source of rock and the fleet size based on the specific of the site. Guidance on fleet size selection is included in the User Guide.
19. The Calculator multiplies the Unit Rates by the quantities to calculate the total cost for preparing (screening to produce the required size) the capillary break materials.
20. From the drop-down menus and based on the specific of the site, the User selects the push distance and the dozer size for pushing out the capillary break materials.
21. The Calculator then multiplies the Unit Rates by the quantities to calculate the total cost for pushing out the capillary break materials.
22. The Calculator then sums the totals for preparing; transporting; and placing the capillary break materials to calculate the total for this activity (installing the capillary break layer of the cap).
Low Permeability Layers
23. The User can enter the area of the surface to be capped but generally the default is the total footprint or flat area depending on the element.
WRD ROCK ARMOUR FOR STABILITY
1.00
User Slope Rock
Armour Cover
Thickness (m)
User Slope Rock
Armour Cover
Volume (m3)
Rock armour
volume used in
calculations
(m3)
Haulage
Distance for
Slope Rock
Armour (m) Fleet Size TOV # Unit Rate ($/m3)
Cost for Rock
Armour ($)
- >2500 m to <=3000 m Rock Small Fleet #4.95 6.05$ -$
- - -$
WASTE ROCK DUMP CAPILLARY BREAK LAYERS
#6.08
4.40$
WRD Surface
area (ha)
Default
Thickness of
Capillary Break
Layer (m)
User Input
Thickness of
Capillary Break
Layer (m)
Thickness of
Capillary Break
Layer used in
Calculations
(m). Cannot be
below
mandatory
minimum for
High Risk
User Input
Volume of
Capillary Break
Layer (m3)
Volume Used in
Calculations for
Capillary Break
Layer (m3)
Source and
prepare
Capillary Break
Layer Material
($)
Haulage
Distance for
Capillary Break
layer (m) Fleet Size TOV # Unit Rate ($/m3)
Cost for source,
load haul and
dump capillary
break layer ($)
Length of Dozer
Push Capillary
Break Layers Dozer TOV # Unit Rate ($/m3)
Cost for Dozer
Push Capillary
Break Layers ($)
Total Cost for
Capillary Break
layers ($)
- 0.3 0.3 - -$ >2000 m to <=2500 m Rock Large Fleet #4.116 1.94$ -$ > 75m to <= 100m push D9R Dozer #4.32 0.80$ -$ -$
- - - -$ -$ -$ -$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 53
24. The User can enter the thickness of low permeability layer or accept the default (see Table 6-2). For High Risk Waste Rock Dumps, Heap Leach Pads and Tailings Storage Facilities, the default minimum low permeability thickness is locked. This means if the User enters a value below the minimum, it will not be accepted, and the Calculation will default to the minimum. If the User enters a thickness greater than the default minimum, the Calculator uses the User-entered value. The default thickness is not fixed for elements of Medium, Low and Very Low Risk Category.
25. The User can enter the volume of material to be used for the low permeability layer (if they have this information, otherwise that cell is left blank and the calculation accepted.
26. The Calculator then multiplies the Unit Rates by the quantities to calculate the total cost for sourcing, placing and compacting the low permeability materials.
Top Rock Layer
27. The User can enter the area of the surface to be capped but generally the default is the total footprint or flat area depending on the element.
28. The User can enter the thickness of top rock layer or accept the default (see Table 6-2). For High Risk Waste Rock Dumps, Heap Leach Pads and Tailings Storage Facilities, the default minimum top rock thickness is locked. This means if the User enters a value below the minimum, it will not be accepted, and the Calculation will default to the minimum. If the User enters a thickness greater than the default minimum, the Calculator uses the User-entered value. The default thickness is not fixed for elements of Medium, Low and Very Low Risk Category.
29. The User can enter the volume of material to be used for the top rock layer (if they have this information, otherwise that cell is left blank and the calculation accepted.
30. From the drop-down menus, the User selects the haulage distance to the source of rock and the fleet size based on the specific of the site. Guidance on fleet size selection is included in the User Guide.
31. The Calculator multiplies the Unit Rates by the quantities to calculate the total cost for preparing (screening to produce the required size) the top rock materials.
32. From the drop-down menus and based on the specific of the site, the User selects the push distance and the dozer size for pushing out the top rock materials.
33. The Calculator then multiplies the Unit Rates by the quantities to calculate the total cost for pushing out the top rock materials.
34. The Calculator then sums the totals for preparing; transporting; and placing the top rock materials to calculate the total for this activity (installing the top rock layer of the cap).
WASTE ROCK DUMP LOW PERMEABILITY CLAY LAYERS
#6.09
7.80$
WRD Surface
area (ha)
Default
Thickness of
Low
Permeability
(Clay) Layers
(m)
User Input
Thickness of
Low
Permeability
(Clay) Layers
(m)
Thickness of
Low Perm Layer
used in
Calculations
(m). Cannot be
below
mandatory
minimum for
High Risk
User Input
Volume of Low
Permeability
Layer (m3)
Volume Used in
Calculations for
Capillary Break
Layer (m3)
Source, prepare,
place and
compact Low
Permeability
Layer Material
($)
- 0.0 - - -$
0.0 - - -$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 54
Additional Capping and Drainage
35. Typically, the build-up described above is sufficient for a cap cost estimate. If additional or replacement materials are required, they are entered in the cells shown below. A company may elect to replace the low-permeability clay layer with a geosynthetic clay liner that would likely also need geofabric (typically 2) and a geomembrane. The Calculator sums these additional capping layers as shown below.
36. Drainage is typically required on the finished cap to ensure surface water drains off the cap. The User enters the area to drain in the cell shown below. The Calculator multiplies the area required to drain by the unit rate to calculate the total for drainage.
Top Soil / Growth Media
37. The User can enter the thickness of top soil / growth media or accept the default. 38. The User can enter the volume of material to be used for top soil / growth media (if
they have this information), otherwise the cell is left blank and the calculation accepted.
39. From the drop-down menus, the User selects the haulage distance to the source of top soil / growth media and the fleet size based on the specific of the site.
40. The Calculator multiplies the Unit Rates by the quantities to calculate the total cost for sourcing, hauling and placing top soil / growth media.
Amendment
Amendments may be required to adjust the chemistry of growth media / top soil or the waste rock materials.
WASTE ROCK DUMP TOP ROCK COVER LAYER
WRD Surface
area (ha)
Default
Thickness of
Rock Cover
Layer (m)
User Input
Thickness of
Rock Cover
Layer (m)
Thickness of
Rock Layer used
in Calculations
(m). Cannot be
below
mandatory
minimum for
High Risk
User Input
Volume of Rock
Cover Layer
(m3)
Volume Used in
Calculations for
Rock Cover
Layer (m3)
Haulage
Distance for
Rock Cover
layer (m) Fleet Size TOV # Unit Rate ($/m3)
Cost for source,
load haul and
dump rock cover
layer ($)
Length of Dozer
Push Rock
Cover Layers Dozer TOV # Unit Rate ($/m3)
Cost for Dozer
Push Rock
Cover Layers ($)
Total Cost for
Rock Cover
layers ($)
- 1.0 1.0 - >2500 m to <=3000 m Rock Medium Fleet #4.106 4.67$ -$ > 50m to <= 75m push D9R Dozer #4.26 0.55$ -$ -$
0 - - -$ -$
WASTE ROCK DUMP ADDITIONAL CAPPING WRD DRAINAGE
#6.05 #6.06 #6.07 #4.159 #4.160
2.00$ 12.00$ 13.00$ 3,000$ 23,419$
Geofabric area
(m2)
Geosynthetic
clay liner (m2)
Geo-membrane
(m2)
Total for Geo
layers ($)
Cost For Water
Management
Earthworks On
Dump ($)
Major Drains
and Drop
Structure
footprint on
dump (Ha)
Costs for major
drains and drop
structures on
dump ($)
-$ -$ -$
- - - -$ -$ 0 -$
WRD GROWTH MEDIA/TOPSOIL / AMMENDMENT APPLICATION
0.15
User Growth
Medium
Thickness (m)
User growth
media volume
(m3)
Growth media
volume used in
calculations
(m3)
Haulage
Distance for
Growth Media
(m) Fleet Size TOV # Unit Rate ($/m3)
Cost for Growth
Media ($)
- <=200 m GM Small Fleet #4.126 3.81$ -$
- - -$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 55
41. The User can enter the area to be amended with lime for pH adjustment or accept the default equal to the flat area. (Note: the user must set this cell to zero if no pH adjustment is required).
42. The Calculator multiplies the Unit Rate by the quantities to calculate the total cost for pH adjustment.
43. From the drop-down menus, the User can select type of top soil amendment (e.g. gypsum).
44. The User can enter the area of top soil to be amended or accept the default equal to the flat area. (Note: the user must set this cell to zero if no amendment is required).
45. The Calculator multiplies the Unit Rate by the quantities to calculate the total cost for soil amendment.
46. The Calculator sums the totals for pH adjustment and soil amendment to calculate the total for these activities.
47. The User must determine whether amendment materials are required to be transported from > 6 km from the site and if so, click on the appropriate hyperlinks (see below) to access the long-distance haul sections of the Miscellaneous Activities User Input Sheet (described in another section).
Re-vegetation
48. The area to be seeded defaults to the sum of the flat and sloped areas of the element.
49. From the drop-down menus, the User selects the type of seed (e.g. native). 50. The Calculator multiplies the Unit Rate for the seed-type by the area for seeding to
calculate the total cost for seeding.
#10.45
860$
pH Control add
lime (top of WR)
(ha)
pH Control add
lime (top of WR)
($) Amend soil?
Area to amend
(ha) TOV # Rate ($/ha) Amend Cost ($)
Cost for Growth
Media /
Amendment ($)
Long Haul
Sourcing (click
to go to other
activities if
required)
0.0 -$ Recycled gypsum 0.0 #10.47 125$ -$ -$ Long Haul >
0.0 -$ 0.0 -$ -$
WRD REVEGETATION
#10.58 #10.59
1,415$ 3,635$
Area of seeding
required (ha) Type of seed
Area requiring
rehab in Pasture
(ha)
Area requiring
rehab in Native
(ha)
Cost for Seeding
($)
0 Native 0.0 0.0 -$
- 0 0 -$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 56
Other Activities
51. Permeability testing. The User can enter the total number of points (for the whole flat area) for permeability testing or accept the default (1 point per hectare shown below).
52. The calculation assumes 10 points can be completed per day. The shown Unit Rate is a day rate for a Geotech rig. The Calculation divides the day rate by the number of points per day to calculate the cost per point and then multiplies by the number of points to get the total cost for testing.
53. The Engineering / Design cost is set to the defaults shown in Table 6-2. 54. The User can enter a lump sum cost to account for activities not covered elsewhere
in the calculation and should provide explanation in the User Notes section at the top of the Sheet.
Total Cost for Element
55. The Calculator sums all the totals described above to calculate the total cost for the element (a Waste Rock Dump in this case) and divides by the total footprint display the cost per hectare.
Additional Elements and Total Cost for User-Defined Rates
56. The User can repeat the process for additional elements by clicking on the Add (in this case Add Waste Rock Dump) button.
Total Cost for
WRD ($)
Cost per Unit
Area ($/ha)
-$ -$
-$ -$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 57
7.5 Pits – Safety Bund
To calculate the cost for installing a Safety Bund around a Pit, follow the steps below.
1. The User enters the Name of the pit and the Safety Bund Length. For this treatment, the open pit void area is used only to calculate the cost per unit area. If this is the only treatment being applied to the Pit, it is not necessary to explain how the pit area was derived.
2. The User can enter dimensions for the safety bund (second line in the example below) or accept the defaults (by leaving the cells blank) (first line in the example below). The Calculator calculates the specific volume (per unit length) and multiplies by the total length of the bund to obtain the total volume of soil or rock required. A default of 15% is allowed for rock swell. The Calculator multiplies the bund dimensions by a Default Rate to obtain the cost for surface preparation.
3. From the drop-down menu, the User can select the construction method for the safety bund. If Excavate and Place is selected, the length of the bund is multiplied by the Default Rate to obtain this cost. If Haul and Place is selected, the User either accepts the 4 km default by selecting N in the User Input Haulage Distance (as in the second line below) or specifies the distance (see next step).
Waste Rock Dumps (User Defined)
WRD DIMENSIONS
TOV#
Default value
# Name
Total Footprint area of
WRD (ha)
1
2
0.0
Add Waste Rock Dump
Long Distance Carting of Lime
Name of Area
Volume to import
(t)
Distance to source
(km). Select Rate ($/t-km)
Alternate Rate ($/t-
km) Total cost ($) Rationale for Alternate Rates
1 Waste Rock Dump East 200 0.19$ -$
Basic Pit Information
# Map ID Name
Open Pit Void
Surface Area
(ha) Explain how the pit area is derived
Safety Bund
Length
(m)
1 West Pit (defaults) 20.0 3,000
2 West Pit (user) 20.0 3,000
40.0 6,000
Add Basic Pit Information
Safety Bund, Fencing and Signs
SAFETY BUND DETAILS SAFETY BUND CONSTRUCTION
TOV # #4.159
Default value 2.5 5.0 2.0 15% 3,000$
# Map ID Name
Open Pit Void
Surface Area
(ha)
Safety Bund (or
highwall) length
(m) Bund Height (m)
Bund Base Width
(m)
Bund Top Width
(m)
Bund Volume
(m3/m length)
Volume of bund
(m3)
Bund Surface
Preparation
(dozing, clearing
and access)
($)
1 West Pit (defaults) 20 3,000 9.13 27,375 4,950$
2 West Pit (user) 20 3,000 2.0 4.0 1.0 5.15 15,450 3,960$
40 6,000 42,825 8,910$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 58
4. If the User selects Haul and Place and selects Y to User Input Distance, they must select the distance to the source of the rock for bund construction and the size of the fleet to load, transport and place the rock. The Calculator multiplies the appropriate Default Rate by the bund volume to obtain the cost to construct the safety bund by Haul and Place with User Entered distance to the source of the rock.
5. The Calculator sums the individual items to obtain the total cost for safety bund construction.
7.6 Water Treatment
To calculate the cost for rehabilitating a Process Water Storage structure, follow the steps below.
1. The User must list all the areas requiring pumping and water treatment. For each area the User enters quantities reflecting the treatment required. In the example below:
a. Line 1: Pit 1 has 1,000 ML of water requiring treatment by reverse osmosis. The water is saline and will produce 10,000 tonnes of salt. The default for transport of salt is 250 km (circled). If reverse osmosis is selected and the plant will be mobilized to the site, an entry must be made to the Mobilise Portable Reverse Osmosis Plant (return) column as shown below.
b. Line 2: There are four structures where the water will be evaporated by solar energy.
c. Line 3: Oily water ponds contain 10 ML of oily water requiring petroleum hydrocarbon removal only.
2. The total volumes and salt mass are multiplied by the corresponding Default Rates to obtain the treatment costs.
SAFETY BUND CONSTRUCTION
#4.159 #3.02 #3.03
3,000$ 23.23$ 46.10$
Bund Surface
Preparation
(dozing, clearing
and access)
($)
Safety Bund
Construction Method
Default
Excavate and
Place
($)
User input Haulage
Distance
Default Haul and
Place (4km haul)
($)
4,950$ Excavate and Place 69,687$ Y -$
3,960$ Haul and Place -$ N 138,291$
8,910$ 69,687$ 138,291$
Haulage Distance for Safety Bund Rock (m) Fleet Size Unit Rate # Unit Rate ($/m3)
Cost for Safety Bund
Rock with User
Haulage Distance
($)
Total Cost for Safety
Bund Construction
($)
>2000 m to <=2500 m Rock Small Fleet #4.94 5.57$ -$ 74,637$
>2000 m to <=2500 m Rock Small Fleet #4.94 5.57$ 86,070$ 90,030$
86,070$ 164,666$
Water and Salt Management TREATMENT
250
Map ID Name / Area
Evaporate Water in
Water Structure or
Pit with Natural
Solar (per structure
or pit)
Evaporate Water in
Water Structure or
Pit with Fine Mist
Spray (per structure
or pit)
Mobilise Portable
Reverse Osmosis
Plant (return)
Operate Reverse
Osmosis Plant (ML)
Load Salt
(tonne)
Transport Salt
(t-km)
Dispose salt
(tonne)
Treat Organics
only (ML)
1 1 1000 10000 2500000 10000
2 4 0 0
3 0 0 10
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 59
3. The User must enter quantities for the additional activities shown below (see Section 4.9.9.2). The unit in each case is ML and the User enters the total volume of water to be treated for each area and this multiplies by an allowance in $/ML.
4. The User must enter the volume of water to be pumped and the pumping details. In the example below the volume to pump for Pit 1 is made equal to that treated by reverse osmosis. As the water to be evaporated treatment rate is based on per pond, the User must enter the volume of water to be pumped (circled below). A volume must be specifically entered for the oily water pond(s). The User selects the pump size from the drop-down menu and the number of pump sets. These are selected based on the User’s knowledge of the required pumping conditions (e.g. depth to water in the pit, length of piping to the treatment system).
5. The Calculator calculates the pumping duration and multiples this by the number of pump sets to get the total hire days. The total hire days is multiplied by the hire rate for the pumps to get a pumping cost.
Evaporate Water in
Water Structure or
Pit with Natural
Solar (per structure
or pit)
Evaporate Water in
Water Structure or
Pit with Fine Mist
Spray (per structure
or pit)
Mobilise Portable
Reverse Osmosis
Plant (return)
Operate Reverse
Osmosis Plant (ML)
Load Salt
(tonne)
Transport Salt
(t-km)
Dispose salt
(tonne)
Treat Organics
only (ML)
Adjust pH
using
Neutraliser (ML)
1 1000 10000 2500000 10000
4 0 0
0 0 10
0 0
0 0
0 0
0 0
0 0
0 0
0 0
4 0 1 1000 10000 2500000 10000 10 0
#7.02 #7.03 #7.04 #7.05 #7.06 #7.07 #7.08 #7.09 #7.10
4,899$ 51,750$ 45,455$ 2,680$ 8.93$ 0.07$ 95$ 1,995$ 1,995$
19,597$ -$ 45,455$ 2,680,219$ 89,333$ 179,202$ 950,000$ 19,954$ -$
Site
Establishment
and
Engineering
(ML)
Infrastructure
Construction
(ML)
Operations
Management
(ML)
Power/Water
(ML)
0 0 0 0
#7.11 #7.12 #7.13 #7.14
1,000$ 1,500$ 150$ 50$
-$ -$ -$ -$
Total Volume
of Water to
Pump (ML) Pumps and hoses (select)
Number of
Pump Sets
Total Pumping
Rate (ML/day)
Pumping
Duration
(days)
Pump Days for
rental cost
calculation (days)
Pump and hoses
Rate ($/pump per
day)
Total cost for
pumps ($)
1,000 4" pump with hoses 8 28.8 35 280 $ 392.70 $ 109,956
500 3" pump with hoses 2 3.4 147 294 $ 392.70 $ 115,454
10 2" pump with hoses 1 1.2 8 8 $ 289.48 $ 2,316
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 60
6. The pumping costs are added to the treatment costs to obtain the total cost for each water management area and these are summed to obtain a total for all water management. If required the User can enter an Alternate Rate and Rationale in this area of the table.
7.7 Underground Mines
To options for calculating the cost of rehabilitating an Underground Mine are illustrated below.
1. When the User enter a name for the mine, an electrical disconnection fee is automatically applied ($35,000 per mine) and the Calculator populates the ‘Terminate and disconnect all services to the U/G workings?’ column with a 1 (as shown for the first two lines in the example below). If services have been terminated and disconnected already, the User can enter a ‘0’ in this column (line three of the example below) and the electrical disconnection fee is not applied.
Pump Days for
rental cost
calculation
(days)
Pump and
hoses Rate
($/pump per
day)
Total cost for
pumps ($)
0 $ 289.48 $ -
0 $ 392.70 $ -
0 $ 392.70 $ -
0 $ 504.90 $ -
0 $ 289.48 $ -
0 $ 289.48 $ -
0 $ 289.48 $ -
0 $ 289.48 $ -
0 $ 289.48 $ -
0 $ 289.48 $ -
User entry
Alternate Rate
(total $)
Total cost per
area Rationale for Alternate Rate
3,944,209$
19,597$
19,954$
-$
-$
-$
-$
-$
-$
-$
0
-$ 3,983,760$ ok ok
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 61
2. The User enters quantities to the top table as required. For ventilation and hoisting shafts, the User has an option to backfill, cover or plug. These three options are shown below. The User must enter the number of shafts and the total depth (sum of all the shaft type) to calculate a cost.
3. The User enters the number of adits and historical shafts to manage.
4. Costs are calculated based on the inputs in the top table. The cost results are shown below for the above example.
UNDERGROUND MINE INFORMATION
# Map ID Name
Number of
Ventilation
Shafts
Total Depth of
Ventilation
Shafts
(m)
Backfill, plug or
cover ventilation
shafts
Number of
Hoisting Shafts
(persons and/or
materials)
Total Depth of
Hoisting Shafts
(m)
Backfill hoisting
shafts or cover
with steel plate
UG1 Bounty example Backfill and adits 4 100 Backfill 2 200 Backfill
UG2 Bounty example Cover 4 100 Cover 2 200 Cover
UG3 Bounty example plug 4 100 Plug 2 200 Plug
Number of
small Adits
(<2m in
diameter)
proposed to
cover
Number of
small Adits
(<2m in
diameter) to
seal
Number of
Declines/ Drifts
Number of
Drifts/Declines
with conveyors
Number of
small (historic)
shafts
proposed for
closure
10
2
2
UNDERGROUND SURFACE INFRASTRUCTURE REMOVAL
TOV X #2.01 #9.01 #9.02 #9.03
Default value 35,000$ 25,000$ 1,200,000$ 75,000$
Name
Terminate and
disconnect all
services to the
U/G workings
($)
Remove
Ventilation fans
including
electrics
($)
Remove
hoisting shaft
headframe and
support
infrastructure
($)
Removal of U/G
Drift/Decline
Conveyor and
services down
decline
($)
Bounty example Backfill and adits 35,000$ 100,000$ 2,400,000$ -$
Bounty example Cover 35,000$ 100,000$ 2,400,000$ -$
Bounty example plug 35,000$ 100,000$ 2,400,000$ 150,000$
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 62
5. The Calculator sums all the individual costs to obtain the total for the mine and sums those to get a total cost for all the Underground Mines. If required an alternate rate can be entered and justification must be provided in the space below the cost table.
SEALING OF UNDERGROUND OPENINGS
#9.04 #9.05 #9.06 #9.07 #9.08 #9.09 #9.10 #9.11 #9.12
7,000$ 26,574$ 276,148$ 123,181$ 220,806$ 53,181$ 96,362$ 256$ 1,023$
Cover small
adits (< 2 m in
diameter)
Seal small
adits (< 2m in
diameter)
($)
Seal portals,
declines, adits,
drifts, (width >2
m)
($)
Plug to seal
(concrete plug)
and rehabilitate
ventilation
shafts (up to
4m diameter)
($)
Plug to seal
(concrete plug)
and rehabilitate
hoisting and
man haulage
shafts (up to
8m diameter)
($)
Cover to seal
(steel plate)
and rehabilitate
ventilation
shafts (up to
4m diameter)
($)
Cover to seal
(steel plate)
and rehabilitate
hoisting and
man haulage
shafts (up to
8m diameter)
($)
Backfill
Ventilation and
small shafts
using suitably
sized
(screened)
material (up to
4m diameter)
($)
Backfill hoisting
and man
haulage shafts
using suitably
sized
(screened)
material (up to
8m diameter)
($)
70,000$ -$ -$ -$ -$ -$ -$ 102,312$ 409,248$
-$ -$ 552,295$ -$ -$ 212,723$ 192,723$ -$ -$
-$ -$ -$ 492,723$ 441,612$ -$ -$ -$ -$
Total Cost for
underground
mines using
defaults
($)
Alternate Rate
($/mine)
Total Cost for
underground mines
($)
3,116,560$ 3,116,560$
3,492,742$ $2,000,000 2,000,000$
3,619,335$ 3,619,335$
-$ -$
-$ -$
-$ -$
-$ -$
-$ -$
-$ -$
-$ -$
$10,228,638 $2,000,000 $8,735,896
ERC calculator user guide - mining
Queensland Department of Environment and Science (ESR/2019/4626) 63
8 Glossary
Table 8-1 shows the terms referenced throughout this document and their specific definition.
Table 8-1 Definitions
Word Definition
Activity A general term applied to simple and singular items such as excavating soil, and more involved, multi-faceted items such as capping a Tailings Storage Facility.
Alternate Rate A site-specific rate entered by the User which over-rides the Default Rate (see Section 5.6 for requirements).
Benign Benign waste material is material that is geochemically stable (non-acid Forming) and is suitable for rehabilitation purposes with low risk of generating any environmental harm.
Bottom-up, first principles cost method
The process of building Rolled-up costs for relatively complex, multi-faceted activities using basic singular values for plant, equipment and labour and productivity (e.g. cubic metres of soil excavated per hour) to estimate the time to complete an activity.
Calculator The Excel™ workbook that calculates the ERC for the site
Department Refers to the Queensland Department of Environment and Science
Default Rate A standard (default) cost rate for an activity in the Calculator
Domain Discrete operational areas within a site, usually with unique function and purpose and therefore similar geophysical characteristics. Domains could include:
Infrastructure
Underground workings (e.g. adits and shafts)
Tailings Storage Facilities
Overburden and waste rock dumps
Water management
Pits
Eligible Mining Activities
Mining activities that are authorized with standard conditions and eligibility criteria under the EP Act (i.e. EAs approved through a standard or variation application).
Process equipment
Equipment used in the mine operations to transport and stack (e.g. conveyor, stacker), store (e.g. silo) and prepare (e.g. coal handling preparation plant) raw and processed materials.
Productivity The performance capability of a machine or equipment. For example, the volume of soil an excavator can move per unit time.
Rolled-up With respect to unit cost rates Rolled-up means a single value generated from smaller activities and cost rates. Bottom-up, first principles are used to generate Rolled-up rates.
Sheet The individual worksheet within the Calculator.
User The applicant or holder of an environmental authority and the individual who prepares the ERC.
ERC calculator user guide - mining
Queensland Department of Environment and Science
APPENDIX A USER INPUT SHEETS OPTIONS, INPUTS, DEFAULTS AND CALCULATED QUANTITIES
ERC calculator user guide - mining
Queensland Department of Environment and Science
Table A-1 Exploration User Input Sheet
Activity Options Inputs Defaults Calculated Quantities
Seismic surveys, grid-lines and minor tracks
Easement in native or pasture vegetation Total easement length (km) and the length of easement requiring rehabilitation is required.
If no rehabilitation length is entered, the calculation assumes a default of 5% of the total length. This approach recognizes that the disturbance to land caused by such activities is minor.
None
Drill-holes Exploration drill-holes (coal / mineral sands / large impact drilling).
Exploration drill-holes (metalliferous / low impact drilling).
Number of drill-holes None None
Tracks and roads Track (earthen) - rip, grade and re-seed.
Road (gravel / crushed rock) - remove rock, grade and re-seed.
Road (gravel / crushed rock) - remove rock and replace1.
Total length (km). None None
Small water structures
Lined Ponds ranging from <=1 ML to >10 and <= 20 ML.
Unlined Ponds ranging from <=1 ML to >10 and <= 20 ML.
Number of ponds in each category
None None
Camps and Water Treatment Plants2
Demountable camps (not owned by company) - pasture land.
Camps (not owned by company) - native land.
Water treatment plants (not owned by company) - pasture land.
Water treatment plants (not owned by company) - native land.
Disturbance area (ha) None None
Notes: 1. This option would be used where the track or road is to be retained but where in either the road surface is contaminated, or the quality of the surface is insufficient to
support future use. In both cases, this option assumes the surface material will be removed and replaced.
2. For Exploration activities, it is assumed the facilities are owned by third-party contractors and that they bear the cost of removing the facilities. The only liability for the EA holder in these cases is rehabilitation of the land (grade and seed). In cases where the EA holder owns the facilities, entries must be made to the appropriate User Input Sheet (e.g. Infrastructure for Camps) or a specific rate added to one of the “Other (user entered)” rows.
ERC calculator user guide - mining
Queensland Department of Environment and Science
Table A-2 Infrastructure User Input Sheet
Activity Options Inputs Defaults Calculated Quantities
Roads and Tracks (Defaults)
Track (earthen) - rip, grade and re-seed.
Road (gravel/crushed rock) - remove rock, grade and re-seed.
Road (gravel/crushed rock) - remove rock and replace1.
This table allows input in distance (km) or area (ha) recognizing that companies measure their disturbances differently. Only one option should be used.
None None
Roads and Tracks (User-Defined). This option allows the user to design their own road with intent to represent those on the site
Surface covering (earthen, rock, gravel, waste rock).
Distance to haul removed surface material for disposal (typically a void on-site). Ranges from < 200 m to > 6 km.
The distance from which re-surface material is sourced. Ranges from < 200 m to > 6 km.
Type of seed (native or pasture).
Key input is the length of road (km). If only the length is input a cost will be calculated using the defaults settings.
Width of the track or road.
Length of road to be ripped (if earthen) or surface to be removed (if gravel, rock or bitumen).
Thickness of surface covering.
Length of road that will be re-surfaced.
The thickness of surface material that will be replaced.
Area of re-seeding required. The default calculation assumes the entire length and width will be re-seeded.
The default calculation assumes the entire length of the road is ripped (earthen) or surface removed (rock) and graded and seeded.
Width of road = 6 m
Thickness of surface covering to be removed = 150 mm
Length of surface to be replaced = 0 km
Thickness of surface covering to be replaced (if user enters a length) = 150 mm
Volume of surface covering removed (m3)
Volume of surface covering to replace (m3)
Area requiring rehabilitation (ha)
Mine Haul Roads (Defaults)
Haul road - decompact doze, shape and rip only.
Haul road - remove contaminated surface and replace.
Haul road - remove rock cover and replace.
This table allows input in distance (km) or area (ha) recognizing that companies measure their disturbances differently. Only one option should be used.
ERC calculator user guide - mining
Queensland Department of Environment and Science
Activity Options Inputs Defaults Calculated Quantities
Mine Haul Roads (User-Defined). This option allows the user to design their own road with intent to represent those on the site
Surface covering (earthen, rock, gravel, waste rock).
Distance to haul removed surface material for disposal (typically a void on-site). Ranges from < 200 m to > 6 km.
The distance from which re-surface material is sourced. Ranges from < 200 m to > 6 km.
Type of seed (native or pasture).
Key input is the length of road (km). If only the length is input a cost will be calculated using the defaults settings.
Width of road.
Length of road to be ripped (if earthen) or surface to be removed (if gravel, rock or bitumen).
Thickness of surface covering (or accept default).
Length of road that will be re-surfaced.
The thickness of surface material that will be replaced (or accept default).
Area of re-seeding required. The default calculation assumes the entire length and width will be re-seeded.
The default calculation assumes the entire length of the road is ripped (earthen) or surface removed (rock) and graded and seeded.
Width of road = 25 m
Thickness of surface covering to be removed = 150 mm
Length of surface to be replaced = 0 km
Thickness of surface covering to be replaced (if user enters a length) = 150 mm
Volume of surface covering removed (m3)
Volume of surface covering to replace (m3)
Area requiring rehabilitation (ha)
Laydown Yards (Defaults)
Earthen.
Gravel/crushed rock.
Area of laydown yard (ha). None None
Laydown Yards (User-Defined). This option allows the user to design their own laydown yard with intent to represent those on the site
Surface covering (earthen, rock, gravel, waste rock).
Distance to haul removed surface material for disposal (typically a void on-site). Ranges from < 200 m to > 6 km.
Type of seed (native or pasture).
Key inputs are the length and width of the laydown area (m). If only these are input a cost will be calculated using the defaults settings.
Area to be ripped (if earthen) or surface to be removed (if gravel, rock or bitumen).
Thickness of surface covering (or accept default).
Area of re-seeding required. The default calculation assumes the entire length and width will be re-seeded.
The default calculation assumes the entire length of the road is ripped (earthen) or surface removed (rock) and graded and seeded.
Thickness of surface covering to be removed = 150 mm
Volume of surface covering removed (m3)
Area requiring rehabilitation (ha)
Borrow Pits None Area of borrow pit (ha). None None
Pipelines Below-ground piping Plastic Pipe 3/4 in (20mm) - 4 in (100 mm) diameter.
Below-ground piping 6 in (150 mm) - 8 in (200 mm).
Below-ground piping 10 in (250 mm) - 18 in (450 mm).
Length of pipe (m).
Number of cut and caps (below ground pipes left in place are typically flushed, then cut and capped).
Thickness of top soil (or accept default).
Volume of top soil (or accept calculation).
Number of cut and caps = 2
Width of easement (for re-seed) = 1 m
Thickness of top soil = 150 mm
Area to re-seed (ha)
Volume of top soil (m3)
ERC calculator user guide - mining
Queensland Department of Environment and Science
Activity Options Inputs Defaults Calculated Quantities
Below-ground piping 20 in (500 mm) - 36 in (1 m).
Above ground piping Plastic Pipe 3/4 in (mm) - 4 in (102 mm) diameter.
Above ground piping 6 in (150 mm) - 8 in (200 mm).
Above ground piping 10 in (250 mm) - 18 in (450 mm).
Above ground piping 20 in (500 mm) - 36 in (1 m).
Conveyed substance (tailings, water, ash).
Is pipeline to be flushed.
Is pipeline to be removed.
Distance to source growth media (m).
Fleet size for sourcing growth media (small, medium or large).
Type of seed (native or pasture).
Borrow Pits None Area of borrow pit (ha). None None
Camps Temporary and permanent camps with capacity ranges <20 to 451 to 500 persons.
Number of camps in each category. None None
Buildings Portable (e.g. 6 m X 2.4 m skid-mounted office).
Small Permanent (e.g. 400 m2 offices with ablution block, diesel genset and surrounded by 500 m2 gravel surface cover).
Medium Permanent (e.g. 800 m2 light vehicle workshop, warehouse /store, with ablution block, diesel genset and surrounded by 1000 m2 gravel surface).
Large Permanent (e.g. 1200 m2 workshops, tyre change and servicing area with multiple ablution blocks, diesel genset and surrounded by 1500 m2 gravel surface).
Number of each type of building. None None
ERC calculator user guide - mining
Queensland Department of Environment and Science
Activity Options Inputs Defaults Calculated Quantities
Communications Towers
None. Number of communications towers None None
Disconnect services
Services site.
Services remote.
Number of services to disconnect None None
Power Distribution Steel tower.
Wooden pole.
Concrete pole.
Length of distribution lines using each type of pole
None None
Power Generation Switchyard.
Substation.
Area of substation or switchyard (m2) None None
Concrete pads (not associated with facilities, camps etc1)
Thickness of slab <= 0.3m.
Thickness of slab > 0.3m.
Area of slab (m2) None None
Rail infrastructure Remove rail loop and spur, ballast etc.
Collapse, cut and remove rail loading bins.
Remove train loading facilities.
Reshape rail spur and load out areas.
Length of rail (m)
Number of bins
Area of facilities (m2)
Area of load-outs (ha)
None None
Landfills Landfill. Area of landfill (m2) None None
Sewage Treatment Plants
Sewage Treatment Plants Area of plant (m2) None None
Notes: 1. This activity allows for concrete pads that are not included in another rate. All facilities, buildings and camps include concrete pads in the rate and therefore an entry to
this table is not required.
ERC calculator user guide - mining
Queensland Department of Environment and Science
Table A-3 Overburden Dumps Piles User Input Sheet
Activity Options Inputs Defaults Calculated Quantities
Waste Rock Dumps (Defaults)
High Risk.
Medium Risk.
Low Risk.
Very Low Risk.
With characteristics determining risk level listed in the TOV.
Hyperlinks for any long-distance hauling of capping materials (follow the link and enter quantities in Miscellaneous Activities User Input Sheet.
Number of Waste Rock Dumps in each category
None None
Waste Rock Dumps (User-Defined). This option allows the user to design their own Waste Rock Dumps with intent to represent those on the site
High Risk.
Medium Risk.
Low Risk.
Very Low Risk.
With characteristics determining risk level listed in the TOV. Selection of risk category determines the capping design. For high risk caps, the minimum thicknesses are set at the default and the user cannot set lower values.
Re-profiled slope angle (<=2.8o to > 17.5o).
Length of dozer push (< 20 m to <= 500 m) for earthmoving components.
Dozer size (D6 to D11).
Haulage distances for rock for armouring of slopes, capillary break materials, top rock cover, growth media. Ranges from < 200 m to > 6 km.
Fleet size (small, medium, large or truck/shovel) for hauling rock for amour and capillary break materials, top rock layer, growth media. Ranges from < 200 m to > 6 km.
Amendment of top soil (no amend, lime, gypsum, biosolids).
Type of seed (native or pasture).
Key inputs are:
area of total footprint, flat, slope, ramps (ha) and to cap (ha) (or accept calculation default to total footprint).
average doze thickness for pushing on flat and slope (m)
If only these are input a cost will be calculated using the defaults settings.
Volume of material to push on flat and slopes, of rock to place, or capillary break materials, of low permeability layer materials, of growth media, of top rock layer (or accept calculation).
Thickness of rock armour to place on slope, thickness of capillary break layer, of low permeability layer, of top soil layer (m) (or accept default).
Area of additional capping materials (geosynthetic clay liner (GCL), geofabric, geomembrane) (ha). These are optional and in certain instances may replace other layers (e.g. GCL replacing low permeability clay layer).
Area for drainage (ha).
Area for top soil amendment.
High risk – working layer 0 m, capillary break minimum thickness 0.6 m (2 x 0.3 m), low permeability layer minimum thickness 0.5 m, rock cover layer minimum thickness 1.5 m.
Medium risk – working layer 0 m, capillary break minimum thickness 0.3 m, low permeability layer 0 m, rock cover layer minimum thickness 1.0 m.
Low risk – working layer 0 m, capillary break 0 m, low permeability layer 0 m, rock cover layer minimum thickness 0.5 m.
Very Low risk – working layer 0 m, capillary break 0 m, low permeability layer 0 m, rock cover layer 0 m.
Thickness of rock armour to place on slope (1.0 m)
Volume of material to push on flat and slopes (m3)
Volume of rock armour to push on flat and slopes (m3)
Volume of material used in capillary break layer (m3)
Volume of material used in low permeability layer (m3)
Volume of materials used in top rock layer (m3)
Volume of grow media (m3)
Area requiring re-seed (ha)
ERC calculator user guide - mining
Queensland Department of Environment and Science
Activity Options Inputs Defaults Calculated Quantities
Long haul sourcing of top soil, lime or clay (click to go to Miscellaneous Activities User Input Sheet).
Area of re-seeding required. The default calculation assumes the entire length and width will be re-seeded.
Number of geotech holes per hectare (or accept default).
Other activities – space for User to enter any other costs not included elsewhere.
Area to cap = to WRD (Waste Rock Dump) flat surface (ha)
Thickness of growth media (0.15 m)
Number of geotech holes per hectare (1)
Overburden Dumps and Spoil Piles (User-Defined). This option allows the user to design their own dumps and piles with intent to represent those on the site.
Re-profiled slope angle (<= 2.8o to > 17.5o).
Length of dozer push (< 20 m to <= 500 m) for earthmoving components.
Dozer size (D6 to D11).
Haulage distances for rock for armouring of slopes, top rock cover, growth media. Ranges from < 200 m to > 6 km.
Fleet size (small, medium, large or truck/shovel) for hauling rock for amour and top rock layer, growth media. Ranges from < 200 m to > 6 km.
Amendment of top soil (no amend, lime, gypsum, biosolids).
Type of seed (native or pasture).
Long haul sourcing of top soil, lime or clay (click to go to Miscellaneous Activities User Input Sheet).
Key inputs are:
area of total footprint, flat, slope, ramps (ha) and for top rock cover (ha) (or accept calculation default to flat area).
average doze thickness for pushing on flat and slope (m).
If only these are input a cost will be calculated using the defaults settings.
Volume of material to push on flat and slopes, of rock to place, of growth media, of top rock layer (or accept calculation).
Thickness of rock armour to place on slope, thickness of top soil layer (m) (or accept default).
Area for drainage (ha).
Area for top soil amendment.
Area of re-seeding required. The default calculation assumes the entire length and width will be re-seeded.
Thickness of growth media (0.15 m)
Thickness of rock armour to place on slope (1.0 m)
Volume of material to push on flat and slopes (m3)
Volume of rock armour to push on flat and slopes (m3)
Volume of materials used in top rock layer (m3)
Volume of grow media (m3)
Area requiring re-seed (ha)
Topsoil stockpile (User-Defined). This option allows the user to design their own stockpiles and piles with intent to represent those on the site.
Length of dozer push (< 20 m to <= 500 m) for earthmoving components.
Dozer size (D6 to D11).
Haulage distance for growth media. Ranges from < 200 m to > 6 km.
Fleet size (small, medium or large) for growth media. Ranges from < 200 m to > 6 km.
Type of seed (native or pasture).
Key inputs are:
area of total footprint, flat (ha).
average doze thickness for pushing (m).
If only these are input a cost will be calculated using the defaults settings.
Volume of material to push on flat and of growth media (or accept calculation).
Area of re-seeding required. The default calculation assumes the entire length and width will be re-seeded.
Thickness of growth media (0.15 m)
Volume of material to push (m3)
Volume of grow media (m3)
Area requiring re-seed (ha)
ERC calculator user guide - mining
Queensland Department of Environment and Science
Activity Options Inputs Defaults Calculated Quantities
Long haul sourcing of top soil (click to go to Miscellaneous Activities User Input Sheet).
Other activities defined by User.
ERC calculator user guide - mining
Queensland Department of Environment and Science
Table A-4 Heap Leach Pad User Input Sheet
Activity Options Inputs Defaults Calculated Quantities
Heap Leach Pads (Defaults)
High Risk.
Medium Risk.
Low Risk.
Very Low Risk.
With characteristics determining risk level listed in the TOV.
Hyperlinks for any long-distance hauling of capping materials (follow the link and enter quantities in Miscellaneous Activities User Input Sheet.
Number of Heap Leach Pads in each category
None None
Heap Leach Pads (User-Defined). This option allows the user to design their own Heap Leach Pads with intent to represent those on the site.
High Risk.
Medium Risk.
Low Risk.
Very Low Risk.
With characteristics determining risk level listed in the TOV. Selection of risk category determines the capping design. For high risk caps, the minimum thicknesses are set at the default and the user cannot set lower values.
Re-profiled slope angle for embankments and ramps (<=2.8o to > 17.5o).
Length of dozer push (< 20 m to <= 500 m) for earthmoving components.
Haulage distances for rock for armouring of slopes, working layer, capillary break materials, top rock cover, growth media. Ranges from < 200 m to > 6 km.
Fleet size (small, medium or large and dozer sizes) for hauling rock for amour and capillary break materials, top rock layer, growth media. Ranges from < 200 m to > 6 km.
Amendment of top soil (no amend, lime, gypsum, biosolids).
Type of seed (native or pasture).
Key inputs are:
Area of total footprint, embankment and ramps (ha) and to cap (ha) (or accept calculation default to total footprint).
If only these are input a cost will be calculated using the defaults settings.
Volume of rock to place on embankment, of capillary break materials, of low permeability layer materials, of growth media, of top rock layer (or accept calculation).
Thickness of rock armour to place on embankment and ramps, of rock working layer, of capillary break layer, of low permeability layer, of top rock layer, of top soil layer (m) (or accept defaults).
Area and thickness of pile for flushing.
Area of additional capping materials (GCL, geofabric, geomembrane) (ha). These are optional and in certain instances may replace other layers (e.g. GCL replacing low permeability clay layer).
Area for drainage (ha).
Area for top soil amendment.
High risk – working layer 0 m, capillary break minimum thickness 0.6 m (2 x 0.3 m), low permeability layer minimum thickness 0.5 m, rock cover layer minimum thickness 1.5 m.
Medium risk – working layer 0 m, capillary break minimum thickness 0.3 m, low permeability layer 0 m, rock cover layer minimum thickness 1.0 m.
Low risk – working layer 0 m, capillary break 0 m, low permeability layer 0 m, rock cover layer minimum thickness 0.5 m.
Very Low risk – working layer 0 m, capillary break 0 m, low permeability layer 0 m, rock cover layer 0 m.
Thickness of rock armour to place on embankment (1.0 m)
Volume of rock armour for embankment and ramps (m3)
Volume of material used in working layer (m3)
Volume of material used in capillary break layer (m3)
Volume of material used in low permeability layer (m3)
Volume of materials used in top rock layer (m3)
Volume of pile to be flushed (m3)
Volume of grow media (m3)
Area requiring re-seed (ha)
ERC calculator user guide - mining
Queensland Department of Environment and Science
Activity Options Inputs Defaults Calculated Quantities
Long haul sourcing of top soil, lime or clay (click to go to Miscellaneous Activities User Input Sheet).
Area of re-seeding required. The default calculation assumes the entire length and width will be re-seeded.
Number of geotech holes per hectare (or accept default).
Other activities – space for User to enter any other costs not included elsewhere.
Area to cap = to HLP flat surface (ha)
Thickness of growth media (0.15 m)
Number of geotech holes per hectare (1)
ERC calculator user guide - mining
Queensland Department of Environment and Science
Table A-5 Tailings Storage Facilities User Input Sheet
Activity Options Inputs Defaults Calculated Quantities
Tailings Storage Facilities (Defaults)
High Risk.
Medium Risk.
Low Risk.
Very Low Risk.
With characteristics determining risk level listed in the TOV.
Hyperlinks for any long-distance hauling of capping materials (follow the link and enter quantities in Miscellaneous Activities User Input Sheet.
Number of Tailings Storage Facilities in each category
None None
Tailings Storage Facilities (User-Defined). This option allows the user to design their own Tailings Storage Facilities with intent to represent those on the site.
High Risk.
Medium Risk.
Low Risk.
Very Low Risk.
With characteristics determining risk level listed in the TOV. Selection of risk category determines the capping design. For high risk caps, the minimum thicknesses are set at the default and the user cannot set lower values.
Re-profiled slope angle for embankments and ramps (<=2.8o to > 17.5o).
Length of dozer push (< 20 m to <=500 m) for earthmoving components.
Haulage distances for rock for armouring of slopes, working layer, capillary break materials, top rock cover, growth media. Ranges from < 200 m to > 6 km.
Fleet size (small, medium or large and dozer sizes) for hauling rock for amour and capillary break materials, top rock layer, growth media. Ranges from < 200 m to > 6 km.
Amendment of top soil (no amend, lime, gypsum, biosolids)
Type of seed (native or pasture).
Key inputs are:
Area of total footprint, embankment and ramps (ha) and to cap (ha) (or accept calculation default to total footprint).
If only these are input a cost will be calculated using the defaults settings.
Volume of rock to place on embankment, of capillary break materials, of low permeability layer materials, of growth media, of top rock layer (or accept calculation).
Thickness of rock armour to place on embankment and ramps, of rock working layer, of capillary break layer, of low permeability layer, of top rock layer, of top soil layer (m) (or accept defaults).
Area of additional capping materials (GCL, geofabric, geomembrane) (ha). These are optional and in certain instances may replace other layers (e.g. GCL replacing low permeability clay layer).
Area for drainage (ha).
Area for top soil amendment.
High risk – working layer 0.5 m, capillary break minimum thickness 0.6 m (2 x 0.3 m), low permeability layer minimum thickness 0.5 m, rock cover layer minimum thickness 1.5 m.
Medium risk – working layer 0.5 m, capillary break minimum thickness 0.3 m, low permeability layer 0 m, rock cover layer minimum thickness 1.0 m.
Low risk – working layer 0 m, capillary break 0 m, low permeability layer 0 m, rock cover layer minimum thickness 1.0 m.
Very Low risk – working layer 0 m, capillary break 0 m, low permeability layer 0 m, rock cover layer 0 m.
Thickness of rock armour to place on embankment (1.0 m)
Volume of rock armour for embankment and ramps (m3)
Volume of material used in working layer (m3)
Volume of material used in capillary break layer (m3)
Volume of material used in low permeability layer (m3)
Volume of materials used in top rock layer (m3)
Volume of grow media (m3)
Area requiring re-seed (ha)
ERC calculator user guide - mining
Queensland Department of Environment and Science
Activity Options Inputs Defaults Calculated Quantities
Long haul sourcing of top soil, lime or clay (click to go to Miscellaneous Activities User Input Sheet).
Area of re-seeding required. The default calculation assumes the entire length and width will be re-seeded.
Number of geotech holes per hectare (or accept default).
Other activities – space for User to enter any other costs not included elsewhere.
Area to cap = to TSF flat surface (ha)
Thickness of growth media (0.15 m)
Number of geotech holes per hectare (1)
ERC calculator user guide - mining
Queensland Department of Environment and Science
Table A-6 Pits User Input Sheet
Activity Options Inputs Defaults Calculated Quantities
Basic Pit Information
None Name of the pit
Area of the pit (ha)
Explain how the pit area is derived.
Details for the required treatment(s) for that pit. Available treatments are:
Safety bund length (m).
Highwall / bench blasting area (ha), volume to bulk push (m3), volume of highwall to blast (m3), volume of benches to blast (m3).
Low wall area to make safe (ha), volume to bulk push (m3), volume to load and haul (m3).
Open pit backfill volume (m3).
None None
Safety Bund, Fencing and Signs
Safety Bund Construction Method – Excavate and Place or Haul and Place.
User Input Haulage Distance – Y or N, if Y is selected the User then selects the rock haulage distance (ranges <= 200 m to > 6,000 m). If N is selected, the default is taken.
Fleet size for rock haulage (small, medium, large).
Bund height, width at base and width at top (m) (or accept defaults).
Standard fencing length and signs (m) (or accept default).
High wall security fencing length and signs (m).
Bund height (2.5 m), width at base (5.0 m) and width at top (2.0 m)
Allowance for rock “swell” = 15%
If Haul and Place is selected, haul distance = 4 km
Standard fencing length = 1.2 X safety bund length
Bund volume per unit length (m3/m), Bund volume (m3)
Benches and Highwall Drill and Blast and Doze to Make Safe
Re-profiled slope angle (<= 2.8o to > 17.5o).
Length of dozer push (ranges <= 20 m to <= 500 m).
Dozer size.
Haulage distance for growth media.
Fleet size for growth media haulage (small, medium, large).
Type of seed (native or pasture).
Highwall / benches volume to bulk push (m3) (or accept calculation).
Growth media thickness (m) (or accept default).
Growth media volume (m3) (or accept calculation).
Growth media thickness = 0.15 m
Highwall / benches volume to bulk push (m3)
Growth media volume (m3)
ERC calculator user guide - mining
Queensland Department of Environment and Science
Activity Options Inputs Defaults Calculated Quantities
Backfill Open Pit with Waste Rock
Haulage distance for rock and growth media (ranges <= 200 m to > 6,000 m).
Fleet size for rock and growth media haulage (small, medium, large or truck/shovel for rock).
Length of dozer push (ranges <= 20 m to <= 500 m).
Dozer size.
Type of seed (native or pasture).
Growth media thickness (m) (or accept default).
Growth media volume (m3) (or accept calculation).
Growth media thickness = 0.15 m
Growth media volume (m3)
Low Walk Shaping / Load and Haul to Make Safe
Re-profiled slope angle (<= 2.8o to > 17.5o).
Length of dozer push (ranges <= 20 m to <= 500 m).
Dozer size.
Haulage distance for low wall material (ranges <= 200 m to > 6,000 m).
Fleet size for low wall material haulage (small, medium, large).
Haulage distance for growth media (ranges <= 200 m to > 6,000 m)
Fleet size for growth media (small, medium, large).
Type of seed (native or pasture).
Bulk volume to push (m3) (or accept calculation).
Volume to load and haul (m3) (or accept calculation).
Growth media thickness (m) (or accept default).
Growth media volume (m3) (or accept calculation).
Growth media thickness = 0.15 m
Growth media volume (m3)
Open Pit Ramp Backfill (used for coal mines)
Length of dozer push for contaminated material and backfill (ranges <= 20 m to <= 500 m).
Dozer size.
Haulage distance for contaminated material, backfill and growth media (ranges <= 200 m to > 6,000 m).
Fleet size for contaminated material, backfill and growth media haulage (small, medium, large or truck/ shovel for backfill).
Type of seed (native or pasture).
Average Ramp Depth, Average Roadway width, Average ramp length (m).
Number of ramps in-Pit.
Volume of backfill (m3) (or accept calculation).
Ramp Average Roadway Contaminated material thickness (m) (or accept default).
Ramp Volume of Contaminated material (m3) (or accept calculation).
Growth media thickness (m) (or accept default).
Growth media volume (m3) (or accept calculation).
Ramp Average Roadway Contaminated material thickness = 0.5 m
Growth media thickness = 0.15 m
Volume of backfill (m3).
Ramp Volume of Contaminated material (m3).
Growth media volume (m3).
ERC calculator user guide - mining
Queensland Department of Environment and Science
Table A-7 Water Storage and Management
Activity Options Inputs Defaults Calculated Quantities
Process Water Storage, Raw Water Storage, Evaporation and other Unlined Water Storage and Other (e.g. weirs)
Lined or unlined
Haulage distance for silt (m). Ranges <=200m to > 6,000 m.
Pond name.
Size (capacity) (ML). Note this entry is for reference only and does not feature in the calculation.
Top of pond area (ha).
Wall Height above ground surface, wall width at top (m).
Slope of wall (1 in X). User enters the X (i.e. if slope is 4 m long for every 1 m high, the entry is 4).
Sediment thickness (m) (or accept default).
Proportion of land investigation costs. This is either 0, 1 or a fraction and accounts for number of structures that could be investigated in one campaign. If only 1 pond is to be investigated, the number is 1. If 5 ponds can be investigated in one campaign, the number is 0.2 (1/5).
Multiplier for liner area to account for side walls = 1.2
Sediment thickness = 0.5 m
Liner area (ha)
Width at base (m)
Cross sectional area of wall (m2)
Length of bund walls (m)
Volume of soil in bund walls (m3)
Sludge Removal (this is for sludge or sediment not associated with water structures).
Haulage distance for sludge / sediment (m). Ranges <=200m to > 6,000 m.
Name of area
Sludge thickness (m)
Volume of sludge (m3) (or accept calculation)
Volume of sludge (m3)