    Use of CMMI in Acquisition

    Environments

    Brian Gallagher

    Lorraine Adams

    SEPG

    March 6, 2006

    SM CMM Integration, IDEAL, and SCAMPI are service marks of Carnegie Mellon University. Capability Maturity Model, Capability Maturity Modeling, CMM, and CMMI are registered in the U.S. Patent and Trademark Office

    by Carnegie Mellon University.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    2/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 2

    Tutorial AgendaIntroduction

    Part 1: Using CMMI to Encourage Good Contractor

    Practices

    Part 2: Using CMMI-AM to Improve AcquisitionPractices

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    3/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 3

    IntroductionLack of acquisition guidance is a major concern for projects involved in theacquisition and sustainmentof systems, including software-intensive systems.Over the past decade, much of the headquarters and field-level acquisition

    guidance for systems and software acquisition and sustainmenthas beenrescinded, simplified, or reduced in scope such that only minimal acquisition-related guidance remains in many acquisition areas.

    This reduction of guidance has occurred as system complexity and the

    software contribution to overall system functionality rises to unprecedentedlevels.

    Congressional- and DOD-level guidance continues to emphasize softwareacquisition process improvement, including the measurement of process

    performance by acquisition organizations

    The goal of this tutorial is to define effective and efficient acquisition practices,both directed internally toward the acquisition project and directed externallytoward the monitoring and control of the selected supplier(s). These practices

    are intended to provide a basis for acquisition process discipline whilebalancing the need for agility.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    4/204 2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 4

    Tutorial AgendaIntroduction

    Part 1: Using CMMI to Encourage Good Contractor

    Practices

    Part 2: Using CMMI-AM to Improve AcquisitionPractices

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    5/204 2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 5

    Problem StatementMany DoD contractors claim high Maturity Levels (3 andabove) as measured by the Capability Maturity ModelIntegration, yet from the perspective of acquisition programmanagers on some high visibility individual programs, forvarious reasons, individual teams are not executing to the

    level claimed in proposals.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    6/204 2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 6

    Example Program

    BackgroundLarge DoD program with multiple, geographically dispersedengineering locations.

    Multi-contractor teams (10+) using different processes.

    Several million lines of code.

    Systems engineering challenges.Combination of legacy, re-use, COTS integration and newdevelopment.

    All contractor sites are Maturity Level 3 or higher.18 months after contract award, the program office conducted aCMMI Class Bappraisal on the team.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    7/204 2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 7

    Example Program

    Appraisal Output

    0

    5

    10

    15

    20

    25

    30

    Project Mgmt Engineering

    Processes

    Process

    Mgmt

    Support

    Processes

    Number of Strengths Number of Weaknesses

    Project Mgmt Processes

    - Project Planning

    - Project Monitoring & Control

    - Integrated Project Mgmt

    - Risk Management

    Engineering Processes

    - Requirements Mgmt

    - Requirements Definition

    - Technical Solution

    - Product Integration

    - Verification (Peer Reviews)

    Support Processes- Measurement & Analysis

    - Product and Process Quality

    Assurance

    - Configuration Mgmt

    - Decision Analysis

    Process Mgmt

    - Organizational Process Focus

    - Organizational Process Definition

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    8/204 2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 8

    Example Program

    Issues Identified 1PROJECT MANAGEMENT

    Lack of project plans or having onlyincomplete, conflicting or out of dateproject plans

    Ineffective use of Integrated MasterSchedule as basis forplanning/tracking status acrossprogram

    Undefined engineering andmanagement processes on program

    Inability to track and manage actionsto closure

    Inadequate cost estimation processes,

    methods, data and tools Inadequate staffing and trainingproject personnel

    Tracking dependencies between oracross teams not defined

    Managing project data ad hoc Inability to proactively identify andmanage risks

    ENGINEERING

    Lack of understanding of theprograms requirements

    Inability to trace requirements toarchitecture/design or to testplans/procedures

    Poor linkage of functional andperformance requirements

    Inconsistent requirementsmanagement at different levels

    No criteria for makingarchitectural/design decisions amongalternatives

    Not capturing entire technical datapackage (requirements, design anddesign rationale, test results, etc)

    Efficiency of design process/methodsin question

    Late definition of integration and testprocedures

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    9/204 2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 9

    Example Program

    Issues Identified 2SUPPORT

    Difficult to identify items in configuration management baselines

    Lack of ability to manage individual versionsin incremental development

    Inability to effectively managing changes to work products throughout lifecycle

    Not conducting audits to establish/ensure integrity of baselines throughout

    incremental engineering and developmentInefficient change management process (cycle time, volume of changes)

    Roles/responsibilities of change control boards not defined

    Quality Assurance audits of products and processes not consistent

    QA involvement in system and software engineering processes not consistent

    No metrics to manage engineering activities (outside of cost/schedule data)

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    10/204 2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 10

    Example Program

    ResultsEarly and periodic Class B appraisals using CMMI identified risksto program success

    Identified risks were assigned to contractor, to acquirer, or bothbased upon who was best able to mitigate them.

    Many risks were managed jointly and cooperatively between the

    contractor and the acquirer

    Identification of and attention to risks early in the program lifecycle led to the ultimate success of the program.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    11/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 11

    High Maturity High MaturityOrganizations Projects

    WHY?

    Maturity Levels are goodindicators of organizationalpotential performance.

    They describe how the nextproject will most likely performbased on a sampling ofexisting projects.

    Maturity Levels reside at theorganizational level and arenotan indication of how an

    individual project is performing.

    XYZ Corp.

    Division

    A

    Project1

    Project2

    Project3

    Division

    B

    Division

    N

    ?

    Project5

    Project6

    Project7

    Projectx

    Projecty

    Projectz

    Project4

    MLs usuallyapply HEREbased upon

    appraisals ofTHESE

    but yourproject isHERE or HERE

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    12/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 12

    The Acquirers ConcernMY PROGRAM

    ML = ???

    Contractor AML = 5 Contractor BML = 3

    Contractor CML = 4

    PMOML = 2

    During

    source

    selection:

    How capable is acontractor team to

    deliver anoperationalcapability?

    Ongoing: How well is myprogram

    performing?

    Maturity Levels at the organizational level arenecessary but not sufficient to provide answers to

    these questions at the program level.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    13/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 13

    Key QuestionsIs the appraisal of the contractors organizational

    maturity relevant to my project?

    Did the part of the organization executing my projectparticipate in the appraisal?

    Did projects similar to mine participate in the appraisal?

    Are the appraised processes routinely used by the partof the organization executing my project?

    Are the appraised processes an integral part of the

    project execution, or are they an overlay on the the realway the work gets done?

    The BIG question: What processes will really

    be used on MY project

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    14/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 14

    Excerpt from Defense AcquisitionGuidebook Source Selection

    4.2.5.2 Capability Reviews

    Capability reviews are a useful tool

    available during source selections to assessthe offerors' capability in selected criticalprocess areas. Capability reviews may be the

    appropriate means for evaluating program-specific critical processes such as systemsengineering, software development,

    configuration management, etc.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    15/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 15

    Getting the processes that you need1. Identify the characteristics of the processes that you need on

    your project.

    2. Include process evaluation as one of the source selectioncriteria.

    3. Require the bidders to define in the proposal, the processes

    and the process outputs that they intend to use on the project.4. During source selection, evaluate the bidders processes w.r.t.

    the projects process needs using the SCAMPI method.

    5. For the winning bidder, reference the proposed processes inthe contract.

    6. During contract execution, evaluate the contractorcompliance with the proposed processes.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    16/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 16

    Step 1: Identify Process Needs 1

    Self-assessment of project needs by the PMO

    Based upon Guidelines for using CMMI in AcquisitionPrograms(draft)

    CMMI Risk Worksheet Results

    NotImportant Important Essential

    1 2 3 4 5 6 7 8 9 10

    Project Planning

    1.Establish Estimates o o o o o o o o o

    2.Develop a Project Plan o o o o o o o o o3.Obtain Commitment to the

    Plan

    o o o o o o o o o

    Project Monitoring and Control

    4.Monitor Project AgainstPlan o o o o

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    17/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 17

    Step 1: Identify Process Needs 2

    Example

    Program is looking to select a Lead System Integrator for acomplex, multi-year, development effort

    Program is concerned with the potential LSIs ability to:

    - manage risk

    - manage suppliers- plan and track the program

    - build an integrated team

    - develop an architecture

    - integrate the various components

    The program might want to explore the bidders proposedprocesses in these CMMI process areas: PP, PMC, IPM (with

    IPPD), ISM, RD, IT, RSKM, PI

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    18/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 18

    Step 2: Source Selection CriteriaDont just require organizational Maturity Levels

    Include an evaluation of contractor-proposedprocesses as one of the factors for source selection.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    19/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 19

    Step 3: Require process proposals 1

    RFP requires all bidders to propose the processes thatthey wil l use on this project.

    Process proposals include

    a description of the process

    a list of the outputs / artifacts produced by the process.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    20/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 20

    Step 3: Require process proposals 2

    RFP Language

    L.X.X.X Product Development Capabilities

    In support of the Management Factor evaluation, the Governmentintends to conduct an evaluation of the product development andmanagement capabilities of the offeror teamproposed for application on

    this project. The evaluation will involve methods and procedures tailoredfrom the Software Engineering Institute (SEI) Standard CMMISM

    Appraisal Method for Process Improvement (SCAMPISM) Class X*

    Version 1.1 using Capability Maturity Model Integration (CMMISM) forSystems Engineering, Software Engineering, and Integrated Product and

    Process Development (CMMI-SE/SW/IPPD), Version 1.1. The offerorshall provide the SCAMPI documentation described in Attachment A ofthis RFP to support this evaluation. This documentation shall be providedin the proposal and will not be included in the page count limitations forthe proposal.

    *B or C depending on program needs

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    21/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 21

    Step 4: Evaluate process proposals 1

    Appraise the proposed processes using a SCAMPI-Cmethod.

    SCAMPI-C is suitable for process appraisal based ondocument review.

    Use an authorized Lead Appraiser with acquisitionexperience

    Ensure the appraisal team is trained and experienced

    Perform a gap analysis against the self-assessment ofproject needs established in Step 1.

    Gaps represent process-related risks to the project.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    22/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 22

    Step 4: Evaluate process proposals 2

    If the program is of sufficient size, duration, or

    complexity, consider performing SCAMPI-Bs on thebidding teams .

    Use the continuous representation, select 3 to 7

    process areas based on program risk.Use an authorized Lead Appraiser with acquisitionexperience.

    Ensure the team is trained and experienced.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    23/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 23

    Step 5: Contract proposed processesReference the proposed processes in the awarded

    contract.

    Dont tell the contractor what processes to use.

    - That could shift performance liability to the PMO if theprocesses are found to be unsuitable for the project.

    J ust tell the contractor to perform as proposed.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    24/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 24

    Step 6: Evaluate process compliance 1Excerpt from Defense Acquisition

    Guidebook Contract Monitoring

    4.2.5.3 Capability Appraisals

    the program manager retains theright to independently evaluate theprocess capabil ities of the selected

    team prior to or immediately aftercontract award. Periodicappraisals are encouraged as part of

    contract process monitoring

    activities. assessments are mostvaluable when they apply across thefull program team, and not just one

    segment of the

    organization

    Monitor the production ofprocess-related artifacts

    Perform one or moreSCAMPI-B appraisals onkey process areas toassess compliance to

    proposed processes

    Appraisal focus is oncontract monitoring, not

    process improvement

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    25/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 25

    Step 6: Evaluate process compliance 2

    Contract Monitoring Guidelines

    Dont appraise Maturity Levels

    Use the SCAMPI-B method

    Include the entire program team (prime, subs, and theacquisition program office)

    Use the continuous representation, select process areasbased on program risk (selection may evolve during programlife).

    Use an authorized Lead Appraiser

    Ensure the team is trained and experienced

    Include contractor members on the appraisal team

    Use the results as the basis for collaborative risk mitigation

    and process improvement across program team

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    26/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 26

    Benefits of Using the SCAMPI Familyof Appraisal MethodsSCAMPI Class B and Class C appraisals are consistent with the

    SCAMPI Class A Method (same steps, use of PIIs, etc.) and: are led by an authorized team lead require team training focus on areas of risk to the program without an artificial focus

    on achieving Levels are repeatable follow a publicly vetted, documented, and easily accessible

    method

    In the absence of a repeatable method with clear expectations onthe part of the acquirer and contractor communities, homegrownmethods will emerge.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    27/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 27

    SummaryMaturity Levels alone do not provide the information anacquirer needs to determine:

    How capable is a contractor team to deliver anoperational capability?

    How well is my program performing?

    Acquirers need a simple, actionable set of guidelines onhow to use the CMMI framework (models and appraisalmethods) to help reduce program risk.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    28/204

    Pittsburgh, PA 15213-3890

    Tutorial: Use of CMMI in Acquisition Environments - Page 1

    Sponsored by the U.S. Department of Defense

    2005 by Carnegie Mellon UniversityThis material is approved for public release.

    Use of CMMI in Acquisition Environments

    Part 2: Using CMMI-AM to Improve

    Acquisition Practices

    Brian Gallagher

    Lorraine Adams

    SEPG

    March 6, 2006

    SM CMM Integration, IDEAL, and SCAMPI are service marks of Carnegie Mellon University. Capability Maturity Model, Capability Maturity Modeling, CMM, and CMMI are registered in the U.S. Patent and Trademark Office

    by Carnegie Mellon University.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    29/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 2

    Using CMMI-AM to Improve Acquisition

    Practices- Contents

    Module 1 Background

    Tutorial information and background

    Module 2 CMMI-AM and Project ManagementProject Management process areas, goals, andpractices

    Module 3 CMMI-AM and EngineeringEngineering process areas, goals, and practices

    Module 4 CMMI-AM and Support and Generic Practices

    Support process areas, goals, and practices; andGeneric Practices

    Module 5 Using CMMI-AM

    Module 6 Summary and Conclusion

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    30/204

    Pittsburgh, PA 15213-3890

    Tutorial: Use of CMMI in Acquisition Environments - Page 3

    Sponsored by the U.S. Department of Defense

    2005 by Carnegie Mellon UniversityThis material is approved for public release.

    Using CMMI-AM to ImproveAcquisition Practices

    Module 1:Background

    SM CMM Integration, IDEAL, and SCAMPI are service marks of Carnegie Mellon University. Capability Maturity Model, Capability Maturity Modeling, CMM, and CMMI are registered in the U.S. Patent and Trademark Office

    by Carnegie Mellon University.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    31/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 4

    Module 1 AgendaThe State of Acquisition Practices

    Capability Maturity Model Integration

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    32/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 5

    What is Acquisition

    Question: What are the key

    activit ies that youperform when youacquire systems?

    Operational

    Need

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    33/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 6

    The State of Acquisition Practice 1The agencies assume the partnership arrangementabsolves them of all acquisition management

    responsibilities

    Virtually all (Air Force) software-intensive systems sufferfrom difficulties achieving cost, schedule, and

    performance objectives.

    I'd rather have it wrong than have it late. A senior manager (industry)

    The bottom line is schedule. My promotions and raisesare based on meeting schedule first and foremost. A programmanager (government)

    Lack of robust systems engineering practices identified

    as crit ical factor in SBIRS-High problems. Lt. Gen. Brian A. Arnold,USAF, CDR, USAF/SMC

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    34/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 7

    The State of Acquisition Practice 2Is There an Acquisition Crisis?

    Investigation of one acquisit ion program showed:

    System complexity and the programs lack of experience inprocuring major systems caused serious cost growth.

    Program lacks systems engineering and program

    management expertise. Absence of requirements stabilization process.

    Program management does not enforce timely milestones,timelines, and deliverables.

    Programs lack of process control made assessment oftechnical risk impossible.

    Programs lack of short- and long-term budget tracking makescost assessment nearly impossible.

    Program does not manage risk.

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    35/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 8

    The State of Acquisition Practice 3Whats the Problem?

    There are many. Among them,Evidence shows that an acquirers management

    processes and practices and resultant decisions canhave a negative impact on the development processes

    of the supplier

    A mismatch in Acquirer/Supplier in terms of associatedprocess capability and maturity can have unpredictable

    and even disastrous results.

    And the challenges are increasing

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    36/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 9

    Acquirer/Supplier Mismatch

    Acqu

    irer

    Supplier

    Mismatch

    Mismatch

    mature acquirer mentorslow maturity supplier

    outcome not predictable

    Immature | mature

    acquirer | supplier

    Customer encouragesshort cuts.

    Matched

    acquirer and supplierare both high maturity

    highest probability ofsuccess

    Disaster

    no discipline

    no processno product

    Technical &Mgt Skill Low

    Low

    High

    High

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    37/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 10

    Complexity in Modern SystemsMany commercial products are the result of a complex mix ofsubcomponents engineered into a system

    Most DoD weapon and information systems are at least thiscomplex

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    38/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 11

    Weapon System Complexity

    FCS Manned Ground Vehicle concept

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    39/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 12

    System of Systems Complexity

    DCGS - Worldwide

    DCGS - Regional

    Sun

    Sun

    Sun

    DCGS - Forward

    MIST/SATCOM GCS

    NationalNationalMissionMissionPartnersPartners

    ETPETPLOSLOS

    KU SATCOMKU SATCOM

    BLOSBLOS

    PredatorPredator

    AWACSAWACS

    RJRJ

    CommercialCommercialImageryImagery

    JSTARSJSTARS

    SIBRSIBR

    NationalNational

    INTINT

    IBSIBS

    Collection

    TaskReceive

    Process

    Task

    ReceiveProcess

    Exploit

    Disseminate

    Execute

    MCE

    ISRM

    AOCM3 IWPCM3 IWPC

    ARGUSARGUS

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    40/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 13

    KSLO

    C

    F/A-18C/D SMUG/RUG 14268K

    F/A-18E/F17101K

    F/A-18C/D XN-86629K

    F/A-18 Night Attack3054k

    F/A-18C/D 2130K F-14D416K F-14B 2866K

    A-7E16K

    F-14 80K

    A-4 (ARBS) 16K

    A-6E 64K

    F/A-18A/B 943K

    F-14B 364K

    AV-8B NightAt tack 1780K

    AV-8B Radar 3748K

    AH-1 NTS 1000KAH-1 764KA-E SWIP 364KAV-8B 764K0

    3000

    6000

    9000

    12000

    15000

    18000

    66 70 74 78 82 86 90 94 98 02

    Aircraf t IOC, Year

    EA-6B ICAP2BLK 89 2203K

    E-A6B ICAP148K

    EA-6B ICAP2BLK 82 395K

    EA-6B ICAP2BLK 86 779K

    06 10

    JSFUAVsNCWInter-System

    Operability

    Increasing System Complexity

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    41/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 14

    Module 1 AgendaThe State of Acquisition Practices

    Capability Maturity Model Integration

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    42/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 15

    What Can Be Done?

    Based on the premise that

    The quality of the product is governed largely

    by the process used to create the product

    We could improve the Suppliers process and practices

    But the developers have a head start (CMMI-based improvement

    programs are widespread)

    We could improve the Acquirers processes and

    practices by: increasing the visibility of the acquirers contribution to program

    success

    defining, implementing, measuring and evolving effective

    acquisition processes and practices

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    43/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 16

    How Do You Want to Work?

    Random motion lots ofenergy, not much progress

    No teamwork - each persongoes his own way

    Frequent conflict

    You never know where youllend up

    Directed motion every stepbrings you closer to the goal

    Coordinated efforts

    Cooperation

    Predictable results

    Process can make the difference

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    44/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 17

    S u n

    S un

    S un

    Focus of CMMI

    CMMI is applied here

    SW-CMM is applied here

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    45/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 18

    CMMI - Continuous SE/SW/IPPD/SS

    Organizational ProcessFocus

    Organizational ProcessDefinition

    Organizational TrainingOrganizational Process

    PerformanceOrganizational

    Innovation andDeployment

    Project PlanningProject Monitoring and

    ControlSupplier Agreement Mgmt.Integrated Project Mgmt.Risk ManagementIntegrated TeamingIntegrated Supplier Mgmt

    Quantitative Project Mgmt.

    RequirementsManagement

    RequirementsDevelopment

    Technical SolutionProduct IntegrationVerificationValidation

    ConfigurationMgmt.

    Process andProduct QualityAssurance

    Measurement &Analysis

    Decision Analysis

    and ResolutionOrganizational

    Environment for

    Integration

    Causal Analysis

    and Resolution

    CMMI

    Engineering SupportProcess

    Management

    Project

    Management

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    46/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 19

    Structure of CMMI1

    For CMMI-SW/SE

    22 ProcessAreas

    157 Goals

    539 Practices

    PROCESS

    AREA 1

    PROCESS

    AREA n

    PROCESS

    AREA 2

    SpecificPractices

    CapabilityLevels

    GenericPractices

    Specific

    Goals

    Generic

    Goals

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    47/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 20

    Perspectives on Maturity

    ML 1

    ML2

    ML3

    ML4

    ML5

    Staged

    Organization-Focused. . . for an established set of process

    areas across an organization

    Process-Focused. . . for a single process area

    or a set of process areas

    PA PACL

    0

    CL1

    CL2

    CL3

    CL

    4

    CL

    5

    PA

    Continuous

    ProcessA

    reaCapab

    ility

    CONTRACTOR AND PROCESS

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    48/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 21

    What Levels Tell Us

    CONTRACTOR AND PROCESS

    Levels are good indicators ofpotentialorganizational performance

    They describe how the next project could performbased on a sampling of existing projects

    Capability Levels and Maturity Levels reside at theorganizational level (corporation, major division)and are not an indication of how any individualproject is performing

    Note: Sometimes a project is large enough to be considered an organizational uni t (e.g. JSF, C-17)

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    49/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 22

    SummaryAcquisition is a challenging multi-disciplinary effortoccurring in a difficult environment, and demands for

    greater capabilities and increasing complexity are adding tothis challenge.

    Capable performance by BOTH the acquirer and the

    supplier are essential to program success

    A focus on PROCESS at the acquirer and at the suppliercan help.

    CMMI is a proven and widely accepted processimprovement model

    U i CMMI AM t I A i iti

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    50/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 1

    Using CMMI-AM to Improve Acquisition

    Practices- Contents

    Module 1 BackgroundTutorial information and background

    Module 2 CMMI-AM and Project ManagementProject Management process areas, goals, andpractices

    Module 3 CMMI-AM and EngineeringEngineering process areas, goals, and practices

    Module 4 CMMI-AM and Support and Generic Practices

    Support process areas, goals, and practices; andGeneric Practices

    Module 5 Using CMMI-AM

    Module 6 Summary and Conclusion

    Pittsburgh PA 15213 3890

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    51/204

    Pittsburgh, PA 15213-3890

    Tutorial: Use of CMMI in Acquisition Environments - Page 2

    Sponsored by the U.S. Department of Defense

    2005 by Carnegie Mellon UniversityThis material is approved for public release.

    Introduction to the CMMIAcquisition Module

    (CMMI-AM)

    SM CMM Integration, IDEAL, and SCAMPI are service marks of Carnegie Mellon University. Capability Maturity Model, Capability Maturity Modeling, CMM, and CMMI are registered in the U.S. Patent and Trademark Office

    by Carnegie Mellon University.

    Module 2:CMMI-AM and

    Project Management

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    52/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 3

    Module 2 AgendaIntroduction to the CMMI Acquisition Module

    Project Management Process Areas

    Project Planning

    Project Monitoring and Control

    Solicitation and Contract Monitoring

    Integrated Project Management

    Risk Management

    Summary

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    53/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 4

    Where Does Process Fit inAcquisition?

    at the Project Management Office (PMO)

    Management of internal PMO activitiesManagement of processes applied to projectOversight of contractors processesIntegration of contractors and PMO processes

    at the ContractorManagement of internal contractor activitiesOversight of subcontractor processes

    for integration of PMO, contractor, and

    subcontractor processes

    PMO AND PROCESS

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    54/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 5

    Process and the Roles of the PMManage process within the PMO

    Manage process applied to the project

    Exercise oversight of the contractorsprocess management

    Ensure integrationof contractor and

    PMO processes

    PM

    ContractorPMO

    Suppliers

    PMO AND PROCESS

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    55/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 6

    The PMO Management RoleThe PM is responsible for managing internal PMO

    processes. The PM must take a hands-on approach to

    Identify, define, and document process needs

    Communicate and train the PMO staff

    Support, track, measure,and review the PMOprocesses

    PMO

    PM

    Direct

    Responsi

    bility

    PMO AND PROCESS

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    56/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 7

    Program Management RoleDefine the interface between the PMO and the

    contractor using the RFP and negotiations

    Project process requirementsProject metricsProject communication needsProject risk management needs

    Manage the interface during

    contract executionReal-time monitoring of

    deliverablesKeep communication

    channels clear & openDevelop trust with contractor

    PM

    ContractorPMO

    Contract

    CommunicationProgram Risk

    PMO AND PROCESS

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    57/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 8

    Contractor Oversight Role1

    Process maturity of the contractor should be a

    consideration in source selection

    Obtain process definitions and commitments- J ust requiring a CMMI Maturity Level is NOT enough.

    - You need to ensure that high-maturity processes are appliedto YOUR project

    - Require your bidders to define the processes they will use intheir proposals

    - Evaluate the proposedprocesses as a part of

    source selection

    - Reference the processesin the contract

    Plan process integrationPM

    ContractorPMO

    Oversight

    C t t O i ht R lPMO AND PROCESS

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    58/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 9

    Contractor Oversight Role 2

    After contract award, ensure that contracted process

    commitments are kept

    Committed processes are used by the project teamProcess artifacts are evidentProcess integration is effective and monitoredConsider periodic independent appraisals of key process areas

    PM

    ContractorPMO

    Oversight

    S b t t O i ht R lPMO AND PROCESS

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    59/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 10

    Subcontractor Oversight Role

    For many systems, the bulk of the work is done bysubcontractors

    Primary responsibility for oversight of subcontractors lieswith the prime contractor

    PMO role is to ensure that prime isproviding adequate oversight tosubcontractors

    Ensure flowdown of projectprocess requirements

    Ensure integration ofprime and subcontractorprocesses

    PM

    ContractorPMO

    SuppliersIndirectO

    versight

    P I t ti R lPMO AND PROCESS

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    60/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 11

    Process Integration Role

    It is the PMOs responsibility to ensure PMO and

    Contractor processes are compatible

    Include any process must havesin the RFP- Consider specific compatibility with tools for risk,

    requirements, schedule, etc. Ensure good communications with contractor(s) regarding

    process incompatibilities Integration focus

    needed throughoutproject

    PM

    ContractorPMO

    ProcessIntegration

    CMMI Acquisition Module (CMMI AM)

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    61/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 12

    CMMI Acquisition Module (CMMI-AM)

    Focuses on effective acquisition activities and practices thatare implemented by first-level acquisition projects (e.g.,

    System Project Office/Program Manager)Acquisition practices drawn and summarized from existingsources of best practices:

    - Software Acquisition Capability Maturity Model (SA-CMM)

    - Capability Maturity Model Integration (CMMI)- FAA Integrated Capability Maturity Model (iCMM)- Section 804

    Intended to be used in conjunction with the CMMI as anacquisition lensfor interpreting the CMMI in acquisitionenvironments

    CMMI-AM a tool for the acquirer

    CMMI AM Structure

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    62/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 13

    CMMI-AM Structure

    CMMI Acquisition ModuleV 1.1

    Engineering SupportProject

    Management

    Project PlanningProject Monitor and

    ControlIntegrated Project

    Management

    Risk ManagementSolicitation and

    Contract Monitoring

    Requirements ManagementRequirements DevelopmentVerificationValidation

    Measurement andAnalysis

    Decision Analysis andResolution

    Transit ion to Operations

    and Support

    Key

    New for CMMI-AM

    Structure of CMMI AM

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    63/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 14

    Structure of CMMI-AM 1

    For CMMI-SW/SE

    12 Process

    Areas

    28 Goals

    246 Practices

    PROCESS

    AREA 1

    PROCESS

    AREA n

    SpecificPractices

    GenericPractices

    SpecificGoals

    PROCESS

    AREA 2

    plus 47 self-assessment questions

    Module 2 Agenda

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    64/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 15

    Module 2 Agenda

    Introduction to the CMMI Acquisition Module

    Project Management Process Areas

    Project Planning

    Project Monitoring and Control

    Solicitation and Contract Monitoring

    Integrated Project Management

    Risk Management

    Summary

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    65/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 16

    Project Management PAs

    Project management process areas cover the projectmanagement activities related to planning, monitoring, andcontrolling the project.

    Project Planning PPProject Monitoring and Control PMC

    Solicitation and Contract Monitoring SCM

    Integrated Project Management IPMRisk Management RSKM

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    66/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 17

    Project PlanningThe purpose of project planning is to establish andmaintain plans that define project activit ies. Foracquisition:

    Project planning starts by setting the acquisition strategy andis followed by planning the acquisition process in ever

    increasing levels of detailAs the acquisition proceeds toward selection of a supplier,the suppliers planning process should be reviewed forsufficiency

    The resulting plans should also be reviewed for consistencywith the system acquisition plans

    The acquirers and developers project planning processesare continuous and the plans evolve to meet the projects

    needs.

    Purpose of Acquisition Planning

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    67/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 18

    Purpose of Acquisition Planning

    Guide program execution

    From initiation through re-procurement and during post-

    production supportSystems, subsystems, components, spares, and services

    Minimize the time and cost of satisfying identified, validated

    needs in a manner consistent with common sense andsound business practices

    Planning evolves through an iterative process and becomes

    increasingly more definitive in describing the relationship ofthe essential elements of a program

    Paraphrased from DoD 5000 Interim Guidebook

    Poor Project Planning

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    68/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 19

    Poor Project Planning

    Symptoms

    Poor estimates lead to cost and schedule overruns.

    An inability to discover deviations from undocumented plans. Resources are not available/applied when needed.

    An inability to meet commitments.

    Project failure.

    Why should we care?

    Customers dont trust acquirers or suppliers who waste theirresources (i.e., loss of future business).

    No lessons learned for future projects means making the samemistakes on multiple projects.

    Unhappy customers, employees, and stakeholders means ashort life for the business.

    If you fail to plan, then you plan to fail.

    Acquisition Strategy vs. Acquisition Plan

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    69/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 20

    Acquisition Strategy vs. Acquisition Plan

    Acquisition Strategy is high-level Top-level road map for program execution from program

    initiation through post-production support.

    ITERATIVE should be updatedLevel of detail changes as you go through the phasesAs per DoDI 5000.2 required for ALL programs at:

    - Program Initiation for Ships

    - Milestone B- Milestone C- Full-Rate Production Deployment Review

    Acquisition Plan is typically for one phaseRequired by the Federal Acquisition Regulation (FAR)Focuses on specifics of the acquisitionConcerned with contract type, incentives, etc.

    Acquisition Planning Cycle

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    70/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 21

    Acquisition Planning Cycle

    StakeholdersStakeholders

    EvaluateIncremental

    Progress

    StakeholdersStakeholdersStakeholdersStakeholders

    MS B

    ExecuteAcquisition

    Strategy

    EvaluateIncremental

    Progress

    Execute

    RefinedAcquisit ion

    Strategy

    ImproveProcess

    ImproveProcess

    RefineAcquisition Strategy

    RefineAcquisit ion StrategyDevelop

    Acquisit ion Strategy

    Acq.Strategyv1.0

    Acq.Strategyv2.0

    TechDevelStrat

    AoAPlan

    Acquisition Planning Objectives

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    71/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 22

    Acquisition Planning Objectives

    Communicate!

    Identify risks- Strategies for risk mitigation- Balance risks with cost, schedule and performance

    Define expectations for all stakeholders- Role and responsibilities of all parties

    Determine how to make your program executable withinbudget and schedule constraints- Expected program changes throughout lifecycle

    Acquisition Strategy Elements

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    72/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 23

    Acquisition Strategy Elements

    Acquisition Approach

    RequirementsRisk Management

    Design ConsiderationsBusiness Strategy

    Program ManagementSupport Strategy

    From Interim Defense Acquisition Guidebook, 30 Oct 2002

    Single-Step and Evolutionary Acquisition

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    73/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 24

    g p y q

    100%

    Based on AF Program Manager Workshop presented by Mr Little

    Single-Step

    Time

    Known increment

    Deliverable Capability

    100% of requirementsknown at start

    100% of requirementsknown at start

    Known increment

    Partially

    known

    increment Unknown

    increment

    Only first incrementrequirements known at start

    Incremental

    Spiral

    Known increment Known increment

    User, developer, tester,

    sustainer use and learn

    Unknown

    increment

    Evolutionary Approach

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    74/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 25

    Evolutionary Approach

    CR TD SDD PD OS

    B

    Increment 2

    Increment 3

    A C

    B C

    B C

    Increment 1

    Adapted from dod5000.dau.mil

    = Contractor Spiral

    Development

    = Contractor Incremental

    Development

    Acquisition & Development Methods

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    75/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 26

    q p

    = fielded system

    Acquisition of a New Utility truck

    Single Step Acquisit ion, Contractor Incremental Development

    Increment 1 Hard to produce brakesIncrement 2 Easier to produce brakes

    Inc 3 Develop new interfaces

    Spiral 1 Prototype 1

    Spiral 2 Prototype 2

    Spiral 3 Prototype 3

    Inc 2SW radios for existing interfaces

    Increment 1- Interface 1

    Increment 2- Interface 2

    Inc 1 HW Upgrades

    Single Step Development

    Evolutionary Acquisit ion (Spiral), Contractor Mixed Development

    Comms System

    Program Drivers

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    76/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 27

    g

    What software and system issues might DRIVE

    your acquisit ion strategy due to the risk they pose

    to successful execution?Schedule Staffing

    Funding Test Requirements

    Requirements Stability User Support

    External Interfaces Policy Mandates

    Deployment Security

    Interoperability (Programmaticand Developmental)

    System ComplexityPrecedented / Unprecedented

    Technology Maturity

    Dealing with Drivers

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    77/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 28

    g

    Determine which present the highest risk exposure to yourprogram

    Determine how the drivers will influence your acquisitionstrategy elements

    Formulate strategies that you believe will deal with the

    risks posed by the top drivers

    Analyze the strategies to determine gaps and remaining

    high risk areas

    Acquisition Plan Contents

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    78/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 29

    qAcquisition background and objectives

    Statement of need Applicable conditions

    Cost Capability or performance

    Risks Trade-offsDelivery or performance-periodrequirements

    Plan of action (sample)

    Sources Competition

    Source-selection procedures Acquisition considerations

    Budgeting and funding Government-furnished property

    Make or buy Inherently governmental functionsTest and evaluation Logistics considerations

    Security considerations Contractor versus Governmentperformance

    Project Planning

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    79/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 30

    CMMI-AM Goals and Practices 1Specific Goal Specific Practice

    EstablishEstimates

    Estimate the Scope of the Project Establish Estimates of Work Product and Task

    Attributes Define Project Life Cycle Determine Estimates of Effort and Cost

    Develop a

    Project Plan

    Establish the Budget and Schedule

    Identify Project Risks Plan for Data Management Plan for Project Resources Plan for Needed Knowledge and Skills Plan Stakeholder Involvement

    Establish the Project PlanObtainCommitmentto the Plan

    Review Plans that Affect the Project Reconcile Work and Resource Levels Obtain Plan Commitment

    Project Planning

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    80/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 31

    Goal 1: Establish Estimates 1Estimates of project planning parameters are

    established and maintained

    Establish a top-level WBS1 to estimate the scope of theproject

    Defines tasks for the ENTIRE project, including efforts of:- The supplier - The acquirer- Other stakeholders (e.g., test community, users)

    Based upon product architecture

    Establish estimates of work product and task attributes

    Provides a basis for cost and effort estimation

    Software examples KSLOC, function points, # of objects, # ofinterfaces, data volume, etc.

    1 See MIL-HDBK-881A ( http://dcarc.pae.osd.mil/881handbook/881A.pdf)

    Project Planning

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    81/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 32

    Goal 1: Establish Estimates 2Define the project life-cycle phases upon which to scope theplanning effort

    Acquisition method- Single-Step - Evolutionary-incremental Evolutionary-spiral

    Life Cycle phases- Development - Manufacturing - Verification - Training- Deployment - Operation - Support - Disposal

    Estimate the project effort and cost for the work productsand tasks based on estimation rationale

    Define estimation rationale

    Estimate cost and effort for each work product and task

    Consider independent review of estimates

    Project Planning

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    82/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 33

    Goal 2: Develop a Project Plan 1A project plan is established and maintained as thebasis for managing the project

    Establish and maintain the projects budget and schedule Identify assumptions, constraints, major milestones

    Identify task dependencies

    Identify and analyze project risks

    Involve stakeholders in identification of risk

    Analyze impact, timeframe, and probability of occurrence

    Plan for the management of project data

    Create master list of data to be managed (formal and informal)- Identify needs for version control and configuration mgt

    Define data content and formats

    Establish requirements for security and information assurance

    Project Planning

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    83/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 34

    Goal 2: Develop a Project Plan 2Plan for necessary resources to perform the project Identify and plan for process requirements

    Identify and plan for staffing requirements

    Identify and plan for facilities and equipment requirements

    Plan for knowledge and skills needed to perform theproject

    Identify skills needed Assess available skills

    Develop a plan to fill the gaps

    Project Planning

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    84/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 35

    Goal 2: Develop a Project Plan 3Plan the involvement of identified stakeholders Identify relevant stakeholders

    Plan their involvement

    Obtain commitments for involvement

    Establish and maintain the overall project plan content

    Captures all relevant planning items to enable communication

    among the project team and stakeholders

    May be comprised of multiple plans such as- Integrated Master Plan- Integrate Master Schedule

    - Systems Engineering Management Plan- Software Development Plan

    Must be maintained throughout the acquisition

    Module 2 Agenda

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    85/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 36

    Introduction to the CMMI Acquisition Module

    Project Management Process AreasProject Planning

    Project Monitoring and Control

    Solicitation and Contract Monitoring

    Integrated Project Management

    Risk Management

    Summary

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    86/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 37

    Project Monitoring and Control1The purpose of project monitoring and control is to provideunderstanding into the projects progress so that appropriate

    corrective actions can be taken when the projectsperformance deviates significantly from the plan.

    Project Monitoring and Control2

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    87/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 38

    For Acquisition, monitoring and control functions aredirected within the acquisition project early in the processas the acquisition planning is performed and the strategy isdefined. As the acquisition process enfolds, monitoring andcontrol are essential to ensuring that appropriate resourcesare being applied and that the internal acquisition activitiesare progressing according to plan.

    Once a supplier is selected and an award is made, the roleof monitoring and control becomes two fold, concerned withboth continuing to monitor and control internally while alsomonitoring and controlling the progress of the suppliersexecution under the suppliers project plan.

    Poor Project Monitoring and Control

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    88/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 39

    Symptoms

    Lots of time is spent in meetings trying to discover projectstatus rather than reporting on it.

    Data needed for management decisions is unavailable whenneeded.

    Actions that should have been taken early arent identified untilits too late

    Why should we care?

    If you dont know whats going on, corrective action cant betaken early when its least expensive.

    Lack of management insight/oversight makes project resultshighly unpredictable, even later in the project.

    If your confidence in the status you give to your customer islow, they probably perceive it.

    Project Monitoring and Control

    CMMI AM G l d P ti

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    89/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 40

    CMMI-AM Goals and Practices

    Specific Goal Specific Practice

    Monitor ProjectAgainst Plan Monitor Project Planning Parameters Monitor Commitments Monitor Project Risks Monitor Data Management Monitor Stakeholder Involvement Conduct Progress Reviews Conduct Milestone Reviews

    Manage CorrectiveAction to Closure

    Analyze Issues Take Corrective Action Manage Corrective Action

    Module 2 Agenda

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    90/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 41

    Introduction to the CMMI Acquisition Module

    Project Management Process AreasProject Planning

    Project Monitoring and Control

    Solicitation and Contract Monitoring

    Integrated Project Management

    Risk Management

    Summary

    Solicitation and Contract Monitoring

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    91/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 42

    The purpose of Solicitation and Contract Monitoring is to preparea solicitation package that identifies the needs of a particularacquisition, to select a supplier who is best capable of satisfying

    those needs, and to establish the process for monitoring thesupplier for the duration of the contract.

    For Acquisition, the solicitation must comply with the applicable

    federal, departmental, and service acquisition regulations andpolicies. The solicitation should address issues appropriate to theproduct domain or acquisition environment (e.g., supplier processevaluations, operational safety suitability and effectiveness,certifications, architecture evaluations, and interoperability). The

    representatives responsible for these activities within the projector stakeholder organizations should be consulted for properinclusion of those activities into the solicitation and contractmonitoring process.

    Poor Solicitation and Contract Monitoring

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    92/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 43

    Symptoms

    The solicitation package does not include theagreement/contractual requirements and proposal evaluation

    criteria. The technical and management elements of proposals are not

    properly evaluated to ensure that the requirements of theagreement/contract will be satisfied.

    The selection official will not select suppliers who are qualified tosatisfy the agreement/contracts requirements for the projectsproducts..

    Why Do We Care?

    The project team will have insufficient insight into the suppliersactivities to ensure the effort is managed, controlled and complieswith contract requirements.

    The project team and supplier team will be unable to maintain

    ongoing communication and commitments.

    Solicitation and Contract Monitoring

    CMMI AM Goals and Practices

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    93/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 44

    CMMI-AM Goals and PracticesSpecific Goal Specific Practice

    Prepare for theSolicitation

    Designate a Selection Official Establish a Solicitation Package and Evaluation

    Criteria Establish Cost and Schedule Estimates Validate the Solicitation Package

    Select Suppliers Evaluate Proposals

    Use Evaluation Results to Select SuppliersAward Contracts Establish an Understanding of the Contract and

    Proposed Approach Establish Communications Processes and

    Procedures

    Coordinate Workwith Suppliers

    Monitor Selected Supplier Processes Evaluate Selected Supplier Work Products Revise the Supplier Agreement or Relationship

    Solicitation and Contract Monitoring

    Goal 1: Prepare for the Solicitation 1

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    94/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 45

    Goal 1: Prepare for the Solicitation 1The project is prepared to conduct the solicitation

    Designate a selection official responsible for making the

    selection decisionEstablish and maintain a solicitation package that includesthe needs of the acquisit ion and corresponding proposalevaluation criteria

    Define the required proposal content- Process descriptions and commitments

    - Proposed development approach (e.g., processes, tasks,activities)

    - Metrics to be provided to the PMO (including processmetrics)

    - Appropriate plans (e.g., Integrated Mgt plan, SoftwareDevelopment Plan, risk Management Plan)

    Solicitation and Contract Monitoring

    Goal 1: Prepare for the Solicitation 2

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    95/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 46

    Goal 1: Prepare for the Solicitation 2Establish and maintain independently reviewed cost andschedule estimates for the products to be acquired

    Reviewers should not be connected with the acquisition team

    or the supplier

    Validate the solicitation package with end users andpotential offerors to ensure the approach and cost andschedule estimates are realistic and can reasonably lead to a

    usable product. In a competitive environment, ensure equal access to all

    potential offerors. Provide a means for reviewers to offerclarifications of ambiguous capabilities.

    In a sole source or change order environment, ensure thatrelevant stakeholders recognize the consequences ofproposed changes

    Solicitation and Contract Monitoring

    Goal 2: Select Supplier

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    96/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 47

    Goal 2: Select SupplierSuppliers are selected based on the solicitationpackage

    Evaluate proposals according to the documented evaluationcriteria

    In addition to evaluating the technical approach, evaluate- Management practices - Sufficiency of plans- Process capabilities - Domain experience- Cost - Schedule- Past Performance

    Use proposal evaluation results as a basis to support

    selection decisions

    Solicitation and Contract Monitoring

    Goal 3: Award Contracts 1

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    97/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 48

    Goal 3: Award Contracts 1Contracts are issued based on the needs of theacquisition and the suppliers proposed approaches

    Establish and maintain a mutual understanding of thecontract with selected suppliers and end users based on theacquisition needs and the suppliers proposed approaches

    Ensure that contractual commitments are made for factorscritical to project success (e.g., process execution, metricscollection and reporting)

    Maintain mutual understanding for the duration of the contract

    Solicitation and Contract Monitoring

    Goal 3: Award Contracts 2

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    98/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 49

    Goal 3: Award ContractsEstablish and maintain communication processes andprocedures with suppliers that emphasize the needs,expectations, and measures of effectiveness to be used

    throughout the acquisition Define ground rules for

    - communication (e.g., data reported, frequency of reporting)

    - key decision-making (e.g., rationale, documentation,acquirer involvement)

    - conflict resolution

    Monitor process deployment and effectiveness

    Maintain open lines of communication

    Solicitation and Contract Monitoring

    Goal 4: Coordinate Work 1

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    99/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 50

    Goal 4: Coordinate WorkWork is coordinated with suppliers to ensure thecontract is executed properly

    Monitor and evaluate selected processes used by thesupplier based on the suppliers documented processes

    Adherence to plan

    Timeliness of deployment

    Effectiveness of processEvaluate selected supplier work products based ondocumented evaluation criteria

    Define work products to be evaluated (may include interime

    products) and evaluation criteria Ensure capacity and capability for timely and accurate

    evaluation

    Solicitation and Contract Monitoring

    Goal 4: Coordinate Work 2

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    100/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 51

    Goal 4: Coordinate WorkRevise the supplier agreement or relationship, asappropriate, to reflect changes in conditions

    Address shortfalls in both products and processes

    Offer relief when needs evolve to invalidate processrequirements, documentation requirements, reportingrequirements, etc.

    Module 2 Agenda

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    101/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 52

    Introduction to the CMMI Acquisition Module

    Project Management Process Areas

    Project Planning

    Project Monitoring and Control

    Solicitation and Contract Monitoring

    Integrated Project Management

    Risk Management

    Summary

    Integrated Project Management

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    102/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 53

    For Acquisition, integrated project management involvesestablishing project management processes consistent withand tailored from the organizations standard processes. This

    includes higher level acquisition guidance, regulations,instructions, as well as local practices established to be usedacross various projects in the local organization. Establishingan integrated project management process incorporating andinvolving all stakeholders (executive level acquisition offices,

    users, test organizations, developers, and associatedgovernment support organizations) is critical to thesuccessful development of the project.

    Formal interfaces among project stakeholders take the form

    of memorandums of understanding (MOUs), memorandumsof agreements (MOAs), contractual commitments, associatecontractor agreements and similar documents depending onthe nature of the interfaces and involved stakeholders.

    Poor Integrated Project Mgt

    S t

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    103/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 54

    Symptoms

    No defined processes for the project

    Project estimates make no reference to prior projects

    Plans do not reflect the way the project is executed

    Project staff does not know what is in the project plans

    Stakeholders are not identified and involved

    Why do we care?

    Without processes, performance is ad hoc

    Without the history of prior projects, we may make the same

    mistakes If execution doesnt follow the plans, what does it follow?

    Uninvolved stakeholders can provide last-minute surprises

    Lessons learned are not captured

    Integrated Project Management

    CMMI-AM Goals and Practices

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    104/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 55

    CMMI AM Goals and PracticesSpecific Goal Specific Practice

    Use the ProjectsDefined Process

    Establish the Projects Defined Process Use Organizational Process Assets for Planning

    Project Activities Integrate Plans

    Manage the Project Using the Integrated Plans

    Contribute to the Organizational

    Process AssetsCoordinate andCollaborate withRelevant

    Stakeholders

    Manage Stakeholder Involvement Manage Dependencies Resolve Coordination Issues

    Module 2 Agenda

    I t d ti t th CMMI A i iti M d l

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    105/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 56

    Introduction to the CMMI Acquisition Module

    Project Management Process Areas

    Project Planning

    Project Monitoring and Control

    Solicitation and Contract Monitoring

    Integrated Project Management

    Risk ManagementSummary

    Risk Management

    Th f i k t i t id tif t ti l bl

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    106/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 57

    The purpose of risk management is to identify potential problemsbefore they occur, so that risk-handling activities may be plannedand invoked as needed across the life of the product or project to

    mitigate adverse impacts on achieving objectives.

    For Acquisition, risk identification and estimation of probability ofoccurrence and impact, particularly for those risks involved inmeeting performance requirements, schedules, and cost targets,largely determines the acquisition strategy. The acquirer has a dualrole, first in assessing and managing overall project risks for theduration of the project, and second, in assessing and managing risksassociated with the performance of the supplier. As the acquisition

    progresses to the selection of a supplier, the risk specific to thesuppliers technical and management approach becomes importantto the success of the acquisition.

    Poor Risk Management

    S t

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    107/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 58

    Symptoms

    Risks are being ignored.

    Known risks to project staff are a surprise to management. Every time a new problem manifests, a new management

    technique is tried.

    Why should we care? The project may escape some of the bullets,but not all of

    them.

    No lessons learned for future projects means making the same

    mistakes on multiple projects. Repeated project failures due to unforeseen (but predictable)

    risks costs you and your organization.

    Risk Management

    CMMI-AM Goals and PracticesSpecific Goal Specific Practice

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    108/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 59

    Specific Goal Specific Practice

    Prepare for RiskManagement

    Determine Risk Sources and Categories

    Define Risk Parameters

    Establish a Risk Management Strategy

    Identify andAnalyze Risks

    Identify Risks Evaluate, Categorize, and Prioritize Risks

    Mitigate Risks Develop Risk Mitigation Plans Implement Risk Mitigation Plans

    Acquisition Risk Management 1

    What Can Acquisit ion Program Offices Do? A Few Ideas

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    109/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 60

    What Can Acquisit ion Program Offices Do? A Few Ideas

    Start a risk management program on Day 1 of the program

    Ensure that PMO staff have appropriate risk managementtraining

    Use mult iple methods to identify risk sources:- periodic risk reporting - brainstorming- voluntary risk reporting - risk report forms- taxonomy-based questionnaire (TBQ) - TBQ interviews

    Acquisition Risk Management 2

    What Can Acquisit ion Program Offices Do? A Few Ideas

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    110/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 61

    What Can Acquisit ion Program Offices Do? A Few Ideas

    Add language to RFPs and contracts that specify how risks are

    to be reported to the PMOEncourage decentralization of risk identification and analysis

    following an organizationally defined process

    Establish and maintain a schedule of joint risk reviews with allcontractors throughout the program, including joint prioritizationof the most important risks to the program

    Find ways to reward contractors for early identification of

    issues and risksDefine a process and criteria for escalating risks to the next

    higher level

    Module 2 Agenda

    Introduction to the CMMI Acquisition Module

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    111/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 62

    Introduction to the CMMI Acquisition Module

    Project Management Process Areas

    Project Planning

    Project Monitoring and Control

    Solicitation and Contract Monitoring

    Integrated Project Management

    Risk ManagementSummary

    Summary 1

    PM roles include PMO management, project management,

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    112/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 63

    PM roles include PMO management, project management,supplier oversight, indirect subcontractor oversight, and processintegration

    CMMI-AM is a tool intended to help the acquirerachieve success

    Development of a suitable acquisit ion strategy is a keycomponent of project planning

    Principal goals ofProject Planning Establish estimates Develop a project plan Obtain commitment to the plan

    Principal goals ofProject Monitoring and Control Monitor Project Against Plan Manage Corrective Action to Closure

    Summary 2

    Principal goals of Solicitation and Contract Monitoring

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    113/204

    2005 by Carnegie Mellon University Tutorial: Use of CMMI in Acquisition Environments - Page 64

    Principal goals ofSolicitation and Contract Monitoring Prepare for the Solicitation Select Suppliers

    Award Contracts Coordinate Work with Suppliers

    Principal goals ofIntegrated Project Management Use the Projects Defined Process

    Coordinate and Collaborate with Relevant Stakeholders

    Principal goals ofRisk Management Prepare for Risk Management Identify and Analyze Risks Mitigate Risks

    CMMI

    Using CMMI-AM to Improve Acquisition

    Practices- Contents

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    114/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-1CMMI-AM and Engineering v0.1

    Module 1 BackgroundTutorial information and background

    Module 2 CMMI-AM and Project ManagementProject Management process areas, goals, andpractices

    Module 3 CMMI-AM and EngineeringEngineering process areas, goals, and practices

    Module 4 CMMI-AM and Support and Generic PracticesSupport process areas, goals, and practices; and

    Generic Practices

    Module 5 Using CMMI-AM

    Module 6 Summary and Conclusion

    Pittsburgh, PA 15213-3890

    CMMI

    Using CMMI-AM to Improve

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    115/204

    CMMI Acquisit ion Module - Page M3-2

    Sponsored by the U.S. Department of Defense

    2005 by Carnegie Mellon UniversityThis material is approved for public release. Distribution is limited by the Software Engineering Institute toattendees.

    g pAcquisition Practices

    Module 3:

    CMMI-AM andEngineering

    SM CMM Integration, IDEAL, and SCAMPI are service marks of Carnegie Mellon University. Capability Maturity Model, Capability Maturity Modeling, CMM, and CMMI are registered in the U.S. Patent and Trademark Office

    by Carnegie Mellon University.

    CMMI

    Module 3 Agenda

    Engineering Process Areas

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    116/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-3CMMI-AM and Engineering v0.1

    g g

    Requirements Development

    Requirements Management

    Verification

    ValidationSummary

    CMMI

    PMO Role in Systems Engineering 1

    Inherent PMO Responsibility:

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    117/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-4CMMI-AM and Engineering v0.1

    Ensure technology readiness level is appropriate for programphase

    Develop initial system requirements in conjunction withstakeholders and ensure continued involvement

    Develop technical evaluation criteria and evaluate proposals

    during source selection

    Develop independent cost and schedule estimates for thetechnical effort

    Ensure external interfaces are properly identified andmonitored

    Ensure PMO has adequate systems engineering staff

    CMMI

    PMO Role in Systems Engineering 2

    PMO responsibility in conjunction with your contractor:

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    118/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-5CMMI-AM and Engineering v0.1

    p y j y

    Ensure contractor development method is appropriate

    Ensure contractors systems engineering processes areacceptable and being followed

    Ensure compatible processes between prime and subcontractors and between the contractor team and the PMO

    Review and approve systems engineering documentationEnsure systems engineering function is adequately integrated

    with other areas such as logistics and test

    Manage the top-level change control process

    Perform technical evaluationsSystems Integration (if applicable)

    Ensure end system meets requirements

    CMMI

    Module 3 Agenda

    Engineering Process Areas

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    119/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-6CMMI-AM and Engineering v0.1

    g g

    Requirements Development

    Requirements Management

    Verification

    ValidationSummary

    CMMI

    Requirements Development 1

    The purpose of requirements development is to produce

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    120/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-7CMMI-AM and Engineering v0.1

    p p q p pand analyze customer, product, and product-componentrequirements.

    CMMI

    Requirements Development 2

    The purpose of requirements development is to produce

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    121/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-8CMMI-AM and Engineering v0.1

    and analyze customer, product, and product-componentrequirements.

    For Acquisition, requirements development has twocontexts;

    The amalgamation and coordination of the operationalrequirements (customer requirements) into a requirementsset that will define the scope and direction of the acquisition;

    The allocation and extension of the customer requirements

    and additional acquirer requirements (e.g., architecture,formal and informal reviews, reporting or data requirements)that become the basis of the processes utilized by thesuppliers organization.

    CMMI

    Requirements Development 3

    There is a continuous iteration of requirements down through

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    122/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-9CMMI-AM and Engineering v0.1

    the multiple tiers of requirements documents associated with the

    components of the system. For example, requirements flow from the stakeholders to the

    system level to multiple subsystem levels and eventually to

    either hardware or software component levels.The responsibility for developing requirements across the levels

    is generally split between the acquirer and the supplier.

    The acquirer is generally responsible for the higher level,starting with operational requirements and the supplier is

    responsible for successive levels below that.

    CMMI

    Poor Requirements Development

    Symptoms

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    123/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-10CMMI-AM and Engineering v0.1

    Unstated requirements or poorly stated requirements lead toconfusion among staff and customers.

    Design, implementation, and test work products inconsistentlyinterpret the requirements.

    It takes a long time to get agreement on product design.

    Why should we care?

    Unusable products and unhappy customers

    Wasted time and resources building the wrongproduct

    Staff members get tired of rework because requirements havebeen re-interpreted yet again.

    Excessive spending to satisfy customer expectations

    CMMI

    Requirements: Input or Output?

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    124/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-11CMMI-AM and Engineering v0.1

    You RECEIVE requirements from your customerOperational needs

    You DELIVER requirements to your supplierThrough the solicitation, SOW, SOO, and/or contract

    Your job isTo ensure the quality of the inputsTo convert the inputs to the high-quality outputs

    CMMI

    Requirements Must be Balanced

    Stakeholder Needs /

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    125/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-12CMMI-AM and Engineering v0.1

    Adapted from COTS-Based Systems forProgram Managers

    Marketplace

    Stakeholder Needs /

    Business Processes

    Programmatics/

    Risks

    Architecture /

    Design

    Simultaneous

    Defini tion &Tradeoffs

    CMMI

    Requirements Must Evolve

    Accumulating knowledge

    D

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    126/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-13CMMI-AM and Engineering v0.1

    [EPIC 2002]

    g g

    Increasing stakeholder buy-in

    Iteratively converging

    decisions

    Definition

    & Trade

    Offs

    TIME

    Stakeholders

    Program

    Market Design

    Definition

    & TradeOffs

    CMMI

    Requirements Development

    CMMI-AM Goals and Practices

    Specific Goal Specific Practice

    D l Eli it N d

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    127/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-14CMMI-AM and Engineering v0.1

    DevelopCustomer

    Requirements

    Elicit Needs

    Develop the Customer Requirements

    DevelopProductRequirements

    Establish Product and Product- ComponentRequirements

    Allocate Product-Component Requirements

    Identify Interface RequirementsAnalyze andValidateRequirements

    Establish Operational Concepts and Scenarios

    Establish a Definition of Required Functionality

    Analyze Requirements

    Analyze Requirements to Achieve Balance Validate Requirements with Comprehensive

    Methods

    CMMI

    Module 3 Agenda

    Engineering Process Areas

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    128/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-15CMMI-AM and Engineering v0.1

    Requirements Development

    Requirements Management

    Verification

    ValidationSummary

    CMMI

    Requirements Management 1

    The purpose of requirements management is tomanage the requirements of the projects products and

  • 7/30/2019 Use of Cmmi in Acquisition Environments

    129/204

    2005 by Carnegie Mellon University CMMI Acquisition Module - Page M3-16CMMI-AM and Engineering v0.1

    manage the requirements of the project s products andproduct components and to identify inconsistencies

    between those requirements and the projects plans andwork products.

    For Acquisition, requirements management is applied to

    the requirements that are received from therequirements development process.

    CMMI

    Requirements Management 2

    During acquisition, requirements management includes

    the direct manag