US 377 at Basswood Boulevard and Kroger Drive
City Project No. 101015Council District 4
Presenting: Raul E. Lopez, P.E. City of Fort Worth – Department of Transportation and Public Works
December 13, 2018
![Page 2: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/2.jpg)
Project Location
2
Kroger Drive
Baswood Blvd
Ray
Whi
te R
d
![Page 3: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/3.jpg)
Project Limits and Phasing
Basswood Parkwood Hill Blvd/ Starwood Cir to US 377
3
Kroger DriveFrom Ray White to US 377
Phase 1 (Basswood + Int. Kroger at US377)
Phase 2 (Kroger Dr)
![Page 4: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/4.jpg)
Project Scope – Basswood Blvd.Increase eastbound capacity of Intersection ofBasswood at US 377
• Existing intersection• Two through lanes both directions• West approach has 1 left, 1 through
and 1 right turn lane at US 377
• Proposed Intersection (west approach)• Two left turn• Two through• One right turn lane
Railroad Crossing Improvements• Quiet Zone
4Existing Basswood Intersection at US 377
![Page 5: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/5.jpg)
Basswood – Existing Layout
5
Basswood Blvd
![Page 6: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/6.jpg)
Basswood - Proposed Layout
6
![Page 7: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/7.jpg)
Basswood Typical Section
7
![Page 8: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/8.jpg)
Project Scope – Kroger DrivePHASE 1
(Park Vista Cir to US 377)
• Intersection Capacity Improvements at US 377Increase from 3 to 5 lanes
• New eastbound traffic signal with new timing
• Railroad crossing quiet zone with solid median
Existing Kroger Dr. Intersection at US 377
Kroger Drive
![Page 9: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/9.jpg)
9
Kroger Dr. at US377- Proposed Layout
Phase 2Phase 1
![Page 10: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/10.jpg)
Project Scope – Kroger DrivePHASE 2
(Ray White to Park Vista Cir East)
• Corridor improvements from Park Vista Circle east to Ray White Road
3 to 4 lane road Kroger Distribution to Ray White: 2 westbound lanes + left turn lane
• Roundabout at intersection with Park Vista Circle west
• Shared pedestrian and bicycle facility
• No major drainage improvements
• Median opening on Ray White at school driveway
![Page 11: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/11.jpg)
11
Existing Kroger Drive
Kroger Drive
Park Vista Circle
Kroger Distribution Center
![Page 12: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/12.jpg)
Kroger Drive - Proposed Layout
12
![Page 13: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/13.jpg)
Kroger Dr. - Proposed Layout (1 of 3)
13
![Page 14: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/14.jpg)
14
Kroger Dr. - Proposed Layout (2 of 3)
![Page 15: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/15.jpg)
15
Kroger Dr. - Proposed Layout (3 of 3)
Phase 1Phase 2
Phase 1
![Page 16: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/16.jpg)
16
Ray White Median Opening and Left Turn Lane
North
![Page 17: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/17.jpg)
Kroger Dr. Typical Sections
17
![Page 18: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/18.jpg)
Project Cost *
18
Construction………………………………..$3.8 million…………………………………$3.9 millionFunding - 2018 Bond Program…………...$5.4 million…………………………………$5.5 million
* Funding in excess of construction cost is for Right-of-Way acquisition, engineering, permitting, etc.
BASSWOOD / KROGER at US 377 (Phase 1)
KROGER DRIVE (Phase 2)
![Page 19: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/19.jpg)
Phase 1 Project Schedule• Preliminary Design ……………………………………………Completed• Design Complete ……………………………………………..Mar 2019• Right of Way Acquisition ……………………………………..N/A• Utility Clearance ………………………………………………Jun – Dec 2019• Construction …………..………………………………………Apr 2020 – Jan 2021
Phase 2 schedule longer than Phase 1 due to ROW and greater complexity. Details to be shared at next meeting.
Next Public Meeting: Phase 1 Final Design Date and location: To be announced
19
![Page 20: US 377 at Basswood Boulevard and Kroger Drive - pid6.orgpid6.org/doc/US_377_Basswood_Kroger_20181213.pdf · 12/13/2018 · US 377 at Basswood Boulevard and Kroger Drive City Project](https://reader030.vdocuments.site/reader030/viewer/2022041200/5d428fff88c99363498d919b/html5/thumbnails/20.jpg)