us-101 express bus feasibility study board of directors updateand+minutes/samtrans/boa… ·...
TRANSCRIPT
![Page 1: US-101 Express Bus Feasibility Study Board of Directors Updateand+Minutes/SamTrans/Boa… · •Transit-supportive land uses •Strong TDM programs Equity •Communities of Concern](https://reader036.vdocuments.site/reader036/viewer/2022081600/605afd875b000e3290688dec/html5/thumbnails/1.jpg)
US-101 Express Bus Feasibility Study
Board of Directors Update
July 11, 2018
![Page 2: US-101 Express Bus Feasibility Study Board of Directors Updateand+Minutes/SamTrans/Boa… · •Transit-supportive land uses •Strong TDM programs Equity •Communities of Concern](https://reader036.vdocuments.site/reader036/viewer/2022081600/605afd875b000e3290688dec/html5/thumbnails/2.jpg)
Project Status
2
Tasks In Progress Tasks Completed
Task 3: Baseline Conditions and Market Analysis
Task 4: Project Justification and
Evaluation Framework
Task 5: Modeling Methodology/
Validation
Task 6: Identification of
Conceptual Alternatives
Task 7: Initial Screening
Task 8: Technical Assessment
Task 9: Detailed Evaluation
Task 10: Funding and
Implementation Plan
Task 11: Final Report
Next Steps
Task 1: Project Management & Administration
Task 2: Public Outreach (1st Round) Task 2: Public Outreach (2nd Round)
![Page 3: US-101 Express Bus Feasibility Study Board of Directors Updateand+Minutes/SamTrans/Boa… · •Transit-supportive land uses •Strong TDM programs Equity •Communities of Concern](https://reader036.vdocuments.site/reader036/viewer/2022081600/605afd875b000e3290688dec/html5/thumbnails/3.jpg)
Project Purpose
Provide a direct, fast, frequent and
reliable transportation choice for long-
distance commute trips
within and between San Mateo, San
Francisco, and Santa Clara counties.
3
![Page 4: US-101 Express Bus Feasibility Study Board of Directors Updateand+Minutes/SamTrans/Boa… · •Transit-supportive land uses •Strong TDM programs Equity •Communities of Concern](https://reader036.vdocuments.site/reader036/viewer/2022081600/605afd875b000e3290688dec/html5/thumbnails/4.jpg)
Project Goals
4
Goal 1: Provide Mobility Options and Improved
Connections for Regional Trips
Goal 2: Increase Transit Market Share in Corridor
Goal 3: Develop a Cost-Effective Service
Goal 4: Improve Transportation Equity
Goal 5: Enhance Access to Jobs and Population
Centers
Goal 6: Support Sustainable Land Use and
Transportation Policies
![Page 5: US-101 Express Bus Feasibility Study Board of Directors Updateand+Minutes/SamTrans/Boa… · •Transit-supportive land uses •Strong TDM programs Equity •Communities of Concern](https://reader036.vdocuments.site/reader036/viewer/2022081600/605afd875b000e3290688dec/html5/thumbnails/5.jpg)
Market Analysis Factors
5
O-D Pairs • Origin-destination trip data from Streetlight,
C/CAG Model, MTC Model, and CHTS, serving:
• North-South trips focused on US-101
• Trips to, from, or through San Mateo County
• Possible intermediate stops
Regional Transit Access • Underserved by BART, Caltrain Baby Bullet,
or employer shuttle service
• Trips requiring two or more transfers via transit
Likelihood of Transit Use • Previous Express Bus Performance
• Transit-supportive land uses
• Strong TDM programs
Equity • Communities of Concern
• Underserved by long-haul transit
![Page 6: US-101 Express Bus Feasibility Study Board of Directors Updateand+Minutes/SamTrans/Boa… · •Transit-supportive land uses •Strong TDM programs Equity •Communities of Concern](https://reader036.vdocuments.site/reader036/viewer/2022081600/605afd875b000e3290688dec/html5/thumbnails/6.jpg)
Market Analysis
6
AM Peak Period County-to-County Flows, South of 101/92 Interchange
Key Takeaways
1. Most trips in cars within study corridor are relatively
short-distance and short-duration.
![Page 7: US-101 Express Bus Feasibility Study Board of Directors Updateand+Minutes/SamTrans/Boa… · •Transit-supportive land uses •Strong TDM programs Equity •Communities of Concern](https://reader036.vdocuments.site/reader036/viewer/2022081600/605afd875b000e3290688dec/html5/thumbnails/7.jpg)
Market Analysis
7
Transit Planning Context, 2017-2026
Key Takeaways
2. Upcoming
improvements to
Caltrain and BART
present strong potential
for mode shift in San
Francisco and San
Mateo counties – and
may be hard to compete
with.
![Page 8: US-101 Express Bus Feasibility Study Board of Directors Updateand+Minutes/SamTrans/Boa… · •Transit-supportive land uses •Strong TDM programs Equity •Communities of Concern](https://reader036.vdocuments.site/reader036/viewer/2022081600/605afd875b000e3290688dec/html5/thumbnails/8.jpg)
Market Analysis
8
Key Takeaways
3. Express bus service shows
greatest ridership potential in
dense areas underserved by
regional transit and employer
shuttles.
![Page 9: US-101 Express Bus Feasibility Study Board of Directors Updateand+Minutes/SamTrans/Boa… · •Transit-supportive land uses •Strong TDM programs Equity •Communities of Concern](https://reader036.vdocuments.site/reader036/viewer/2022081600/605afd875b000e3290688dec/html5/thumbnails/9.jpg)
Route Development and Evaluation
9
Develop Initial Routes
15 route concepts based on market
analysis
Initial Qualitative Screening
Result: Shortlisted 10 routes
Detailed Evaluation and
Route Comparison
Preliminary results: Six top
performing routes
![Page 10: US-101 Express Bus Feasibility Study Board of Directors Updateand+Minutes/SamTrans/Boa… · •Transit-supportive land uses •Strong TDM programs Equity •Communities of Concern](https://reader036.vdocuments.site/reader036/viewer/2022081600/605afd875b000e3290688dec/html5/thumbnails/10.jpg)
Top Performing Routes
10
One limited stop route
between San Bruno
and Sunnyvale
Three routes into
downtown San
Francisco
Two routes into
Western San
Francisco
Four bidirectional
routes, two one-
directional routes
![Page 11: US-101 Express Bus Feasibility Study Board of Directors Updateand+Minutes/SamTrans/Boa… · •Transit-supportive land uses •Strong TDM programs Equity •Communities of Concern](https://reader036.vdocuments.site/reader036/viewer/2022081600/605afd875b000e3290688dec/html5/thumbnails/11.jpg)
Public Outreach
Public outreach in July 2017 and June 2018
Two community meetings, six pop-up events,
online website and comment form
Engaged with 250+ people
11
![Page 12: US-101 Express Bus Feasibility Study Board of Directors Updateand+Minutes/SamTrans/Boa… · •Transit-supportive land uses •Strong TDM programs Equity •Communities of Concern](https://reader036.vdocuments.site/reader036/viewer/2022081600/605afd875b000e3290688dec/html5/thumbnails/12.jpg)
Next Steps
12
Summer 2018
Complete travel demand modeling and detailed route
evaluation
Identify express bus network and phased implementation plan
Develop funding strategy – SB1 funds have been allocated
Meetings with Technical Advisory Committee and stakeholder
group
Fall 2018
Complete draft and final Express Bus Feasibility Study