Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 www.dau.edu Mr. Tracy Tynan, SES Executive Director Joint Rapid Acquisition Cell Mr. Steve Blasch Professor of Reqts Mgmt DAU DSMC Mr. Darren Rhyne Professor of Sys Eng Mgmt DAU Capital & Northeast

Upload: others

Post on 17-Jul-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Urgent Capability Acquisition Pathway RDT Webcast

10 March 2020

www.dau.edu

Mr. Tracy Tynan, SESExecutive Director

Joint Rapid Acquisition Cell

Mr. Steve BlaschProfessor of Reqts Mgmt

DAU DSMC

Mr. Darren RhyneProfessor of Sys Eng Mgmt

DAU Capital & Northeast

Page 2: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Outline

• Adaptive Acquisition Framework (AAF) Overview – Mr. Rhyne

• Urgent Capability Requirements Process – Mr. Blasch

• Urgent Capability Acquisition Remarks – Mr. Tynan

• Urgent Capability Acquisition (UCA) Tenets, Noteworthy

Changes, and Website Demonstration – Mr. Rhyne

• Back-ups: UCA Pathway Policy Details and Considerations

2

Page 3: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

ADAPTIVE ACQUISITION FRAMEWORK OVERVIEWMR. DARREN RHYNE

3

Page 4: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

4

< 5 years

< 1 year

Adaptive Acquisition Framework (AAF) (new)DoDD 5000.01: The Defense Acquisition SystemDoDI 5000.02: Operation of the Adaptive Acquisition Framework

Tenets of the Defense Acquisition System1. Simplify Acquisition Policy2. Tailor Acquisition Approaches3. Empower Program Managers

4. Data Driven Analysis5. Active Risk Management6. Emphasize Sustainment

Cyb

ers

ecu

rity

PathSelection

Defense Business Systems

DoDI 5000.75

Middle Tierof

AcquisitionDoDI 5000.80

Acquisition of Services

DoDI 5000.74

Major Capability

AcquisitionDoDI 5000.xx

UrgentCapability

AcquisitionDoDI 5000.81

OP

ERA

TIO

NS

AN

D

SUST

AIN

MEN

T

Business Capability Acquisition Cycle

< 2 years

SoftwareAcquisition

(Interim)

RapidPrototyping

CapabilityNeed

Identification

Solution

Analysis

FunctionalRequirements and

Acquisition Planning

AcquisitionTesting and Deployment

CapabilitySupport

Pla

nn

ing

Ph

ase I1 I2…

MVP MVCR Rn

OD

Rapid Fieldin

g

10

MaterialSolutionAnalysis

TechnologyMaturation

and Risk Reduction

Engineering and ManufacturingDevelopment

Production andDeployment

MDD MS A MS B MS C IOC FOC

ATP ATP ATP ATP

In In InExecution Phase

OD

< 5 years

DD

Legend:ATP: Authority to ProceedDD: Disposition DecisionFOC: Full Operational CapabilityI: IterationIOC: Initial Operational CapabilityMDD: Material Development DecisionMS: MilestoneMVP: Minimum Viable ProductMVCR: Minimum Viable Capability ReleaseOD: Outcome DeterminationR: Release

1Formthe

Team

2ReviewCurrentStrategy

3PerformMarket

Research

4Define

Require-ments

5Develop

AcquisitionStrategy

6ExecuteStrategy

7Manage

Performance

PLAN DEVELOP EXECUTE

UrgentCapability

AcquisitionPathway

Adapted from Fig. 1, DoDI 5000.81

Page 5: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

AAF Policy Scorecard as of 4 Mar 20

5000.02T

Under

revision

Change 6, 23 Jan 20

DoDI 5000.02

23 Jan 20

DoDI 5000.81

31 Dec 19

DoDI 5000.80

30 Dec 19

DoDI 5000.75

Change 2

24 Jan 20

DoDI 5000.74

10 Jan 20

Memo

3 Jan 20DoDI 5010.44

16 Oct 19

Under

revision

5

Page 6: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

URGENT CAPABILITY REQUIREMENTS PROCESSMR. STEVE BLASCH

6

Page 7: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

7

Three JCIDS “Lanes”

Three Lanes: Created to address needed capabilities and

capability gaps within acceptable timeframes and risks

• Deliberate – Service, CCMD, or Agency driven

– Traditional acquisition (2+ yrs)

– Future Force Structure

– JROC/JCB/Component validates - depending

on JSD

• Emergent (JEON)– CCMD driven

– Accelerated acquisition (0-2 yrs)

– For anticipated or pending contingency

operation

– VCJCS verifies, JCB or JROC validates

• Urgent (JUON)– CCMD or other DoD component driven

– Urgent/compelling to prevent loss of life

and/or mission failure (0-2 yrs)

– For current operations

– JS J8 DDR validates Joint Needs; DoD

components assess/validate all other urgent

needs

JSD: Joint Staffing Designator

JUON: Joint Urgent Operational Need

JEON: Joint Emergent Operational Need

Source: JCIDS Manual 31 Aug 2018

Page 8: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

8

Urgent/Emergent Staffing

JUON Staffing (15 days)

JEON Staffing (31 days)

• JUON and JEON staffing begins when

the Gatekeeper receives the document

from the Sponsor

• JUON: After confirmation it meets

appropriate entry criteria, assigned to a

Lead FCB for review

• JEON: Confirmed by the VCJCS as

emergent, via the Gatekeeper and DJ8.

The VCJCS identifies validation

authority (JCB or JROC). JEON

assigned to a Lead FCB and JRAC for

collaborative review

Source: JCIDS Manual 31 Aug 2018

Page 9: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

9

JEON, JUON, UON Requirements

Considerations

Assessment of Operational Utility

• NLT six months after initial delivery

• Transition, sustainment, or alternate approaches considered

Transition of Rapidly Fielded Capability Solutions

• May be a basis for validating enduring capability requirements to support transition of rapidly fielded capability

solutions for sustainment

AND/OR

• Further development of operational utility documented by the original requirement Sponsor (if a positive

assessment)

Disposition

• Assessments recommending enduring capability requirements endorsed by the original authorizing official

• If transition occurs, Requirements Sponsor considers appropriate requirements documentation for validation

(ICD, CDD, DCR, etc.). Must sync with MDA’s direction to Solution Sponsor via ADM to transition into a POR

Source: JCIDS Manual 31 Aug 2018

Page 10: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

UNCLASSIFIED

Urgent Capability Acquisition Pathway Webcast

Mr. Tracy Tynan, Executive Director, Joint Rapid Acquisition Cell / Executive

Secretary, Warfighter Senior Integration Group

March 10, 2020

10

Page 11: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

11

Department of Defense’s Highest Priority

“DoD’s highest priority is to provide

warfighters involved in conflict or preparing for

imminent contingency operations with the

capabilities urgently needed to overcome

unforeseen threats, achieve mission success,

and reduce risk of casualties.”

Paragraph 1.2, “Urgent Capability Acquisition,” DoDI 5000.81, December 31, 2019

Page 12: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

12

Examples of Urgent Need Solutions

Refueling Compatibility

for Coalition Aircraft

Aerostats for surveillance

and force protection.

In Fiscal Year 2019, the Department’s

urgent operational needs portfolio

consisted of 25 Joint Urgent Operational

Needs, 14 Joint Emergent Operational

Needs, and nine Warfighter-Senior

Integration Group special interest items

totaling $1.7 billion

Counter Man-portable air

defense systems on aircraft

Significant increase in

HELLFIRE missile production

Tactical Unmanned Aerial Systems

Demilitarization of

Syrian chemical weaponsBiometricsLethal Miniature Aerial

Missile man-portable munition

Tractors for Iraqi Security

Forces to make berms

Transport Isolation System

for Ebola victims

Page 13: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

13

Urgent Capability Acquisition

Key Points:

• A tailored strategy to field capabilities to fulfill urgent operational needs or other

quick reaction capabilities in less than 2 years.

• Requirement criteria: prevent loss of life or critical mission failure.

• The estimated cost must not exceed $525 million in research,

development, and test and evaluation, or $3.065 billion for procurements

in Fiscal Year 2020 constant dollars.

• Schedule is more important than cost or performance. As a result, the Program

Management / Acquisition community assumes greater risk

Fast is more important than perfect. A 70% solution delivered

today is better than a 100% solution in five years.

Page 14: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

URGENT CAPABILITY ACQUISITION

TENETS, NOTEWORTHY CHANGES, AND

WEBSITE DEMONSTRATIONMR. DARREN RHYNE

14

Page 15: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Urgent Capability Acquisition (UCA)

Main Tenets• Fulfill urgent needs in less than 2 years.

– JUONs, JEONs, Warfighter Senior Integration Group-identified urgent issues, and

SecDef/DepSecDef Rapid Acquisition Authority determinations

• Cost thresholds <$525M RDT&E, <$3.065B Procurement, FY20 dollars

• DoD components will use all available authorities to expeditiously fund,

develop, assess, produce, deploy and sustain for the duration of the urgent

need.

• MDAs and PMs will tailor and streamline program strategies and oversight.

• Employ parallel rather than sequential processes.

• Formal milestones may not be required.

• MDA can authorize production at the same time development is approved.

DoDI 5000.81 incorporates and cancels Enclosure 13 of DoDI 5000.02 Change 5

15

Page 16: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

16

Development Milestone

Urgent Need Generation

Pre-Development (Days)

Development (Months)

Operations and Support (Months – Years)

Production and Deployment (Months)

(Disposition)

Production and Deployment Milestone

Course of Action Decision Point

Legend:

= Milestone = Activities

= Decision Point = Validation / Recommendation

= Parallel / Concurrent Processes

DoDI 5000.81 describes each of these activities in detail in Section 4: Procedures. This figure is also in the JCIDS Manual.

Back-up charts summarize these activities.

DoDI 5000.81, Figure 3. Urgent Capability Acquisitions

Page 17: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Noteworthy Changes – 1 of 8DoDI 5000.02 Enclosure 13 to DoDI 5000.81

• Adds USD(A&S) responsibility:

– Determines when a program is not appropriate for the Urgent

Capability Acquisition pathway. The USD(A&S) may disapprove use

of the Urgent Capability Acquisition pathway and direct that any

program be executed using another acquisition pathway.

17

Page 18: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Noteworthy Changes – 2 of 8DoDI 5000.02 Enclosure 13 to DoDI 5000.81

Adds Executive Director JRAC responsibilities:

2.2. EXECUTIVE DIRECTOR, JOINT RAPID ACQUISITION CELL (JRAC). Under the

authority, direction, and control of the Deputy Secretary of Defense (DepSecDef), the

Executive Director, JRAC:

a. Assigns responsibilities to the DoD Component heads for rapid resolution of joint urgent

operational needs (JUONs), joint emergent operational needs (JEONs), and Warfighter

Senior Integration Group (SIG)-identified urgent issues in accordance with DoDD 5000.71.

b. Notifies the Under Secretary of Defense (Comptroller)/Chief Financial Officer, Department of

Defense (USD(C)/CFO) of urgent need requirements, assigned solution sponsors, and

resources needed to facilitate the timely resolution of urgent warfighter needs. Assists in the

resolution of funding issues, as required.

c. Maintains visibility of DoD Component efforts to satisfy urgent warfighter actions based on

updates from solution sponsors and informs the Warfighter SIG of the status of funding,

contracting, delivery, operational performance, training, fielding, sustainment, or other issues

affecting timely fulfilment

18

Page 19: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Noteworthy Changes – 3 of 8DoDI 5000.02 Enclosure 13 to DoDI 5000.81

Adds USD(I) and USD(R&E) responsibilities:

2.5. UNDER SECRETARY OF DEFENSE FOR INTELLIGENCE. The Under

Secretary of Defense for Intelligence:

a. Advises the USD(A&S) on security, intelligence, and counterintelligence requirements

associated with DAE program technologies, developmental testing, and technical risks.

b. Advises the Components on security, counterintelligence, and intelligence matters

associated with their Urgent Capability Acquisition programs, and works with them to assess

threats and address vulnerabilities.

2.6. UNDER SECRETARY OF DEFENSE FOR RESEARCH AND ENGINEERING

(USD(R&E)). The USD(R&E) assists and advises the Executive Director, JRAC and

solution sponsors by:

a. Reviewing CJCS validated JUON/JEON requirements and providing recommendations for

their resolution.

b. Requesting data to provide technical advice and assistance to decision makers consistent

with the level of Office of the USD(R&E) engagement.

19

Page 20: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Noteworthy Changes – 4 of 8DoDI 5000.02 Enclosure 13 to DoDI 5000.81

References the new Rapid Acquisition Authority (RAA)

Manual (DoDM 5000.78, 20 Mar 19):

• RAA should be considered when, within certain limitations, a waiver of a

law, policy, directive, or regulation will greatly accelerate the delivery of

effective capability to the warfighter pursuant to Section 806(c) of Public

Law (P.L.) 107-314.

• RAA authorizes DoD [via SecDef or DepSecDef] to use funds for certain

higher priority requirements without undertaking a reprogramming action or

with use of a transfer authority. DoD Manual 5000.78 provides instructions

on submitting RAA requests.

20

Page 21: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Noteworthy Changes – 5 of 8DoDI 5000.02 Enclosure 13 to DoDI 5000.81

Highlights the analysis of safety and supportability risks:

• Emphasizes the importance of the Program Manager assessing and

documenting safety and supportability risks for each potential course of

action

• Does not require all identified deficiencies be resolved prior to production

or deployment.

– The MDA will, in consultation with the user and requirements validation authority,

determine which deficiencies must be resolved and what risks can be accepted.

– Accepted risks will allow the user community to develop tactics, techniques, and

procedures to help minimize the operational risks.

21

Page 22: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Noteworthy Changes – 6 of 8DoDI 5000.02 Enclosure 13 to DoDI 5000.81

Stresses that the acquiring organization alerts the

warfighter to the capabilities and limitations of the solution

The acquiring organization provides the warfighter with the needed capability,

to include any required training, spares, technical data to include known

hazards and accepted mishap risks, computer software, temporary or

permanent facilities or infrastructure, support equipment, maintenance, or

other logistics support necessary for operation.

22

Page 23: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Noteworthy Changes – 7 of 8DoDI 5000.02 Enclosure 13 to DoDI 5000.81

Requires notification to JRAC/DDR J-8 on Service Disposition

Decisions:

• The DoD Component will notify the Executive Director, JRAC, and the Deputy

Director for Requirements and Capability Development in the Joint Staff J-8, when

the disposition analyses for JUONs, JEONs, critical warfighter issues identified by

the Warfighter SIG, or SecDef or DepSecDef RAA determinations are to be

completed.

• The DoD Component head, and the CAE will review the disposition official’s

recommendation and, within 4 months of receipt of the recommendation, record the

DoD Component head’s transition decision in a disposition determination. The

disposition determinations for JUONs, JEONs, critical warfighter issues identified

by the Warfighter SIG, or SecDef or DepSecDef RAA determinations, will be

provided to the Executive Director, JRAC and the Deputy Director for Requirements

and Capability Development (DDRCD), Joint Staff J-8, by the Component head.

23

Page 24: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Noteworthy Changes – 8 of 8DoDI 5000.02 Enclosure 13 to DoDI 5000.81

Broadens the scope of JUON/JEON Solutions:

The word “system” was replaced by the word “capability” throughout to better

convey that the solution(s) can involve many parts of the DOTmLPF-P

spectrum. (Doctrine, Organization, Training, [existing] materiel, Leadership

and Education, Personnel, Facilities, and Policy)

24

Page 25: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

DAU UCA Pathway Site Demonstration

25

https://aaf.dau.edu/aaf/uca/

Page 26: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Summary

• The Urgent Capability Acquisition (UCA) pathway, governed

by DoDI 5000.81, incorporates and cancels Enclosure 13 of

DoDI 5000.02 Change 5

• The purpose of the Urgent Capability Acquisition (UCA)

pathway is to field capabilities to fulfill urgent existing and/or

emerging operational needs or quick reactions in less than 2

years.

• The DAU UCA pathway site is your one-stop reference for

this topic

26

Page 27: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

UCA Pathway References

• DAU Urgent Capability Acquisition pathway site https://aaf.dau.edu/aaf/uca/

• DoDI 5000.02, Operation of the Adaptive Acquisition Framework, 23 Jan 20

• DoDI 5000.81, Urgent Capability Acquisition, 31 Dec 19

• DoDI 5000.02T, Operation of the Defense Acquisition System, Change 6, 23 Jan 20– Encl. 4 Sec. 5.e. DT&E Planning Considerations for Accelerated Acquisitions & Urgent Needs Programs

– Encl. 5 Sec. 5.c.(1) TEMP Program Planning for Select Accelerated or Urgent Acquisitions

• DAG https://www.dau.edu/tools/dag– CH 1-4.2.10 Urgent Capability Acquisition

– CH 8-3.20 Rapid Fielding Testing

• DoDD 5000.71, Rapid Fulfillment of Combatant Commander Urgent Operational Needs, Change 1,

31 Aug 18

• DoDM 5000.78, Rapid Acquisition Authority, 20 Mar 19

• CJCSI 5123.01H, Charter of the Joint Requirements Oversight Council (JROC) and Implementation

of the Joint Capabilities Integration and Development System (JCIDS), 31 Aug 18

• Manual for the Operation of the Joint Capabilities Integration and Development System [aka the

JCIDS Manual], 31 Aug 18 [login required to Intelink]. See Appendix B of Enclosure A.

• DAU Communities of Practice (CoPs)– Commercial Off-the-Shelf Products and Commercial Services https://www.dau.edu/cop/csci

– Joint Rapid Acquisition https://www.dau.edu/cop/jra

27

Page 28: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

28

Links to Service Policies for UCA and Requirements

• Army

- AR 71-9, Warfighting Capabilities Determination, 15 Aug 19; Chapter 6, Urgent Operational Needs Process.

- AR 70-1, Army Acquisition Policy, 16 Jun 17; Chapter 13, Urgent Capability Acquisition.

• Navy & Marine Corps, SECNAVINST 5000.2F, 26 Mar 19. Enclosures 5 and 8 refer to DoD policy and JCIDS

• Air Force

- AFPD 10-601, Capability Requirements Development, 6 Nov 13; Chapter 7, Urgent/Emergent Operational Needs

- AF/A5R, Requirements Development Guidebook, Vol 2, Urgent Needs, 31 Oct 18, Version 3.0.

Page 29: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Questions?

29

Mr. Darren Rhyne

Professor of Systems Engineering

Defense Acquisition University

[email protected]

703-805-4612

Mr. Steve Blasch

Professor of Requirements Management

Defense Acquisition University

[email protected]

703-805-5604

Mr. Tracy Tynan, SES

Executive Director

Joint Rapid Acquisition Cell

[email protected]

703-693-0341

Mr. David Clagett

Senior Program Analyst

Joint Rapid Acquisition Cell

[email protected]

703-695-8044

Page 30: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

BACK-UP SLIDES

REQUIREMENTS BACK-UP SLIDES PLUS

URGENT CAPABILITY ACQUISITION PATHWAY

POLICY DETAILS AND CONSIDERATIONS

30

Page 31: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Formal Documentation (ICD, CDD, CDD Updates/Annex, DCR)

Future Focused, ACAT Programs

Very Structured Process

Evolved Requirements (Key Performance Parameters,

Key System Attributes)

Capabilities Based Assessments

Analysis of Alternatives

Lengthy Development

High Visibility on Program

Large Investment

Risk averse and failure-intolerant

Deliberate Requirements vs.

Urgent / Emergent Requirements Lanes

JCIDS / Non-JCIDS / Service Unique

Loss of life

Critical mission failure

Contingency operations

Near-term action

Streamlined process

Quick assessment of alternatives

Limited development if feasible

High visibility on results

<100% solution acceptable

Risks taken – schedule more important than cost

Deliberate Requirements

Urgent / Emergent Requirements

Page 32: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Urgent Capability Needs Process

JEONsJUONs

Army ONS*

Marine UUNS*

Navy – Urgent Need

AF - UON

ARMY REF* 10-Liner

UON Initiated

Review UON

Component involved

in an ongoing

contingency

(deployed or prior to

deployment) or in

advance of a

contingency

operation

Chain of

CommandJOINT ?

Component

ValidationAcquire /

Deploy

Operate /

Sustain

No

Yes

CCMD

Approve

Joint Staff

Validation

JRAC Assign

for Action

W-SIG* Management / Direction

DoDD 5000.71 Change 1, 31 Aug 18

Rapid Fulfillment of CCDR UONs

UON Requirements

CJCSI 5123.01H, 31 Aug 18

JROC Charter & JCIDS

Implementation

Execution – DoDI 5000.81,

Urgent Capability Acquisition,

31 Dec 19

(e.g.)

(e.g.)

Final

Disposition

SOCOM CMNS*

Many steps are done in parallel *CMNS = Combat Mission Needs Statement; ONS = Operational Need Statement; REF = Rapid Equipping Force; UUNS = Urgent Universal Need Statement; W-SIG = Warfighter Senior Integration Group

JRAC = Joint Rapid Acquisition Cell

32

Page 33: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

33

Transition of Rapidly Fielded

Capability SolutionsAssessment of Operational Utility Timing: For any rapidly fielded capability solution

delivered to operational users in response to a JUON or JEON, the original Requirements

Sponsor will generate an assessment of the capability solution no later than six months after

initial delivery to facilitate transition, sustainment, or alternate approaches.

Transition of Rapidly Fielded Capability Solutions (JCIDS Manual, Appendix B,

Enclosure C, Page C-B-5)

• JUONs, JEONs, and DOD Component UONs: Successful capability solutions for

JUONs, JEONs, and DOD Component UONs may serve as a basis for validating

enduring capability requirements to support transition of rapidly fielded capability

solutions for sustainment and/or further development if they have a positive

assessment of operational utility documented by the original requirement Sponsor.

• See Appendix B to Enclosure A of this manual for details of assessments of

operational utility for rapidly fielded capability solutions in support of JUONs and

JEONs.

Page 34: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

34

Disposition (JCIDS Manual, Appendix B, Enclosure A, page A-B-9)

• To provide authoritative disposition of rapidly fielded capability solutions, any

assessments recommending enduring capability requirements will be endorsed

by the original authorizing official

• Once determined that the transition will happen, the Requirements Sponsor

will consider the need to generate a CDD, DCR, or other appropriate

documentation for validation to identify the performance attributes,

DOTmLPF-P considerations, and supporting information for the balance of

development, fielding, and required sustainment to meet the follow-on

enduring capability solution. This will be in-sync with the MDA’s direction to

the Solution Sponsor via an ADM to transition the rapidly acquired solution

into a POR.

Transition of Rapidly Fielded

Capability Solutions (Continued)

Page 35: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

JUON/JEON FormatSource: JCIDS Manual, Appendix B of Enclosure A

• Administrative Data:a. Title: (Unclassified version);

b. Submitted by: (e.g. USCENTCOM);

c. Authorized by: CCMD Commander, Deputy/Vice, or Chief of Staff;

d. Primary and secondary POCs

e. Date submitted

• Operational Context and Threat AnalysisDescribe the nature of the urgency and operational impact – loss of life / critical mission failure

• Required CapabilityDescribe the capability required – not a specific solution – as well as duration of need

• FlexibilityIs a partial solution on time acceptable?

• Potential Non-Materiel SolutionsWere non-materiel options considered and instituted?

• Potential Materiel SolutionsIdentify/discuss any known viable capability solutions

• Required QuantitiesIdentify quantity and distribution requirements

• LimitationsIdentify logistics, maintenance, training, manpower issues that could inhibit closing the gap

35

Page 36: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

36

DoDI 5000.81, Urgent Capability Acquisition

Contents of DoDI 5000.81 (31 Dec 19), Summary of Major Provisions

1. Implements Urgent Capability Acquisition Pathway, incorporates & cancels Enclosure 13 of DoDI 5000.02 Change 5

2. Assigns Responsibilities to: - USD(Acquisition & Sustainment) (new)

- Executive Director, Joint Rapid Acquisition Cell (new)

- USD(Comptroller)/Chief Financial Officer (new)

- Director, Operational Test & Evaluation (revised from Enclosure 13)

- USD(Intelligence) (new)

- USD(Research & Engineering (new)

- DoD Component Heads (revised from Enclosure 13)

3. Describes Authorities, Urgent Operational Needs (UONs), and Other Quick Reaction Capabilities (minor revisions from previous policies)‒ Flow of Joint Urgent Operational Needs (JUONs) and Joint Emergent Operational Needs (JEONs)

(new)

4. Provides Procedures for Acquiring UONs (minor revisions from Enclosure 13)

Page 37: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

37

DoDI 5000.81, Urgent Capability Acquisition, Dec 31, 2019Responsibilities (changes from DoDI 5000.02 Change 5 are highlighted in red)

2.1 Under Secretary of Defense for Acquisition and Sustainment (USD(A&S)). (new)

- Is the Defense Acquisition Executive (DAE) and develops processes and procedures to enable urgent capability acquisitions and communicates updates to procedures to the acquisition workforce, as appropriate.

- Determines when a program is not appropriate for the Urgent Capability Acquisition pathway. The USD(A&S) may disapprove use of the Urgent Capability Acquisition pathway and direct that any program be executed using another acquisition pathway

Page 38: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

38

DoDI 5000.81, Urgent Capability Acquisition, Dec 31, 2019Responsibilities (changes from DoDI 5000.02 Change 5 are highlighted in red)

2.2 Executive Director, Joint Rapid Acquisition Cell (JRAC). (new)

- Assigns responsibilities to the DoD Component heads for rapid resolution of joint urgent operational needs (JUONs), joint emergent operational needs (JEONs), and Warfighter Senior Integration Group (SIG)-identified urgent issues in accordance with DoDD 5000.71.

- Notifies the Under Secretary of Defense (Comptroller)/Chief Financial Officer, Department of Defense ((USD(C)/CFO)) of urgent need requirements, assigned solution sponsors, and resources needed to facilitate the timely resolution of urgent warfighter needs. Assists in the resolution of funding issues, as required.

- Maintains visibility of DoD Component efforts to satisfy urgent warfighter actions based on updates from solution sponsors and informs the Warfighter SIG of the status of funding, contracting, delivery, operational performance, training, fielding, sustainment, or other issues affecting timely fulfilment.

Page 39: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

39

DoDI 5000.81, Urgent Capability Acquisition, Dec 31, 2019Responsibilities, continued…

2.3 Under Secretary of Defense (Comptroller)/Chief Financial Officer, Department of Defense ((USD(C)/CFO)). (new)

- Assesses DoD Component funding strategies to support urgent operational needs (UONS) and other quick reaction capabilities and identifies and recommends current execution year offsets, as necessary.

2.4 Director Operational Test and Evaluation (DOT&E) (revised).

- Monitors all urgent capability acquisition programs. (new)

- Designates select programs for DOT&E operational and live fire oversight. (new)

- For programs under DOT&E oversight, approves operational and live fire test plans. (revised)

- For programs under DOT&E oversight, approves post-deployment assessment plans at the Production and Deployment Milestones.

- As applicable, submits independent operational test and live fire reports to the Secretary of Defense, the USD(A&S), the Congressional Defense Committees, and Service components. (new)

Page 40: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

40

DoDI 5000.81, Urgent Capability Acquisition, Dec 31, 2019Responsibilities, continued..

2.5 Under Secretary of Defense for Intelligence (USD(I)). (new)

- Advises the USD(A&S) on security, intelligence, and counterintelligence requirements associated with DAE program technologies, developmental testing, and technical risks.

- Advises the Components on security, counterintelligence, and intelligence matters associated with their Urgent Capability Acquisition programs and works with them to assess threats and address vulnerabilities.

Page 41: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

41

DoDI 5000.81, Urgent Capability Acquisition, Dec 31, 2019Responsibilities, continued..

2.6 Under Secretary of Defense for Research & Engineering (USD(R&E)). (new)

- Assists and advises the Executive Director, JRAC and solution sponsors by:

Reviewing CJCS validated JUON/JEON requirements and providing recommendations for their resolution.

Requesting data to provide technical advice and assistance to decision makers consistent with the level of Office of the USD(R&E) engagement.

Page 42: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

42

DoDI 5000.81, Urgent Capability Acquisition, Dec 31, 2019Responsibilities, continued..

2.7 DoD Component Heads (minor changes from DoDI 5000.02, 7 Jan 2015, change 5, Oct 2019)

• MDAs and program managers will Tailor and streamline program strategies and oversight of urgent capability acquisitions, as appropriate.

- This includes program information, acquisition activity, and the timing and scope of decision reviews and decision levels.

- Tailoring and streamlining should be based on program complexity and the required timelines to meet urgent need capability requirements consistent with applicable laws and regulations.

Page 43: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

43

DoDI 5000.81, Urgent Capability Acquisition, Dec 31, 2019Responsibilities, continued...

2.7 DoD Component Heads, continued…

• Consistent with the emphasis on urgency, if the desired capability cannot be delivered within 2 years, the MDA will assess the suitability Assess the suitability merits of partial or interim solutions that can be fielded more rapidly, if the desired capability cannot be delivered within 2 years.

- In those cases, the actions necessary to develop the desired solution may be initiated concurrent with the fielding of the interim solution.

- Urgent Critical warfighter issues (see Glossary) identified by the Warfighter SIG, per in accordance with DoDD 5000.71, will be addressed as determined by the co-chairs of the Warfighter SIG.

Page 44: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

44

DoDI 5000.81, Urgent Capability Acquisition, Dec 31, 2019Responsibilities, continued…

2.7 DoD Component Heads, continued…

- Ensure that Acquisition decision making and associated activities will be are tailored to expedite acquisition, fielding and sustainment of the capability. Development will generally be limited, and the MDA can authorize Production can be authorized in those cases when there is limited development and a production decision is needed to maintain schedule.

- Generally, funds will have to be reprioritized and/or reprogrammed to expedite the acquisition process. Use all available authorities to quickly fund, develop, test, procure, field, and sustain capability solutions. Generally, funds will have to be reprioritized and/or reprogrammed. If a capability can be fielded within an acceptable timeline through normal PPBE system, it is not considered appropriate for urgent capability acquisition.

Page 45: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

45

DoDI 5000.81, Urgent Capability Acquisition, Dec 31, 2019Responsibilities, continued…

2.7 DoD Component Heads, continued…

- Identify and recommend potential offsets to fund urgent capability acquisition activities for a current execution year and subsequent years, as required, and participate in funding discussions between the Executive Director, JRAC, and the USD(C)/CFO.

- DoD Components will Employ, to the extent possible, parallel rather than sequential processes to identify and refine capability requirements, identify resources, and execute acquisitions to expedite delivery of solutions. Formal milestone events may not be required.

- DoD Components will Ensure financial, contracting, and other support organizations (e.g., Defense Contract Audit Agency, Defense Contract Management Agency, Component General Counsel) and prime and subcontractors involved with aspects of the acquisition efforts are fully aware of the urgency of the need and will ensure expedited action.

Page 46: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

46

DoDI 5000.81, Urgent Capability Acquisition, Dec 31, 20193. Authorities, UONs, and Other Quick Reaction Capabilities

3.1 Approval authorities for each acquisition program covered by this issuance may be delegated to a level that promotes expeditious fielding of capabilities.

3.2.a. Joint Urgent Operational Needs (JUON) and Joint Emergent Operational Needs (JEON)

- These are either an urgent need identified by a Combatant Commander, the Chairman of the Joint Chiefs of Staff (CJCS), or the Vice Chairman of the Joint Chiefs of Staff (VCJCS) involved in an ongoing contingency operation (i.e., a JUON) or an emergent need identified by a Combatant Commander, CJCS, or VCJCS for an anticipated or pending contingency operation (i.e., a JEON).

- These types of UONs are defined in CJCS Instruction 5123.01H.

- For JUONs and JEONs, the validation approval will be by the Joint Staff in accordance with the Joint Capability Integration Development System detailed in CJCS Instruction 3170.01I5123.01H.

- Program execution for JUONs and JEONs will be assigned in accordance with DoDD 5000.71.

- MDA for JUONs and JEONs will be determined at DoD Component level, except in rare cases when the MDA may be designated in an ADM signed by the DAE

Page 47: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

47

DoDI 5000.81, Urgent Capability Acquisition, Dec 31, 20193. Authorities, UONs, and Other Quick Reaction Capabilities cont.

3.2.b. DoD Component-specific UONs. These types of UONs are defined in CJCS Instruction 3170.01I 5123.01H and further discussed in DoDD 5000.71. Approval authorities for DoD Component specific UONs, including their validation, program execution, and the designation of the MDA, will be at the DoD Component level.

Page 48: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

48

DoDI 5000.81, Urgent Capability Acquisition, Dec 31, 20193. Authorities, UONs, and Other Quick Reaction Capabilities cont.

3.3.a. Warfighter SIG-Identified Urgent Issues.

This is a critical warfighter issue, e.g., materiel support to a coalition partner, identified by the Co-Chairs of the Warfighter SIG in accordance with DoD Directive 5000.71.* The Co-chairs of the Warfighter SIG will approve a critical an urgent warfighter issue statement and provide instructions to DoD Components on program execution and management.

3.3.b. SecDef or DepSecDef Rapid Acquisition Authority (RAA) Determination.

This is a Secretary of Defense or Deputy Secretary of Defense signed determination that is made in response to a documented deficiency following consultation with the Joint Staff.* RAA should be considered when, within certain limitations, a waiver of a law, policy, directive, or regulation will greatly accelerate the delivery of effective capability to the warfighter in accordance with pursuant to Section 806(c) of Public Law (P.L.) 107-314.

RAA authorizes DoD to use funds for certain higher priority requirements without undertaking a reprogramming action or with use of a transfer authority. DoD Manual 5000.78 provides instructions on submitting RAA requests.

*Definition moved to G.2. Definitions.

Page 49: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Rapid Acquisition Authority (RAA)Section 806 of Public Law (PL) 107-314, as amended

• SecDef and DepSecDef may waive laws, policies, regulations, testing, contract solicitation &

source selection procedures, etc.

• SecDef or DepSecDef may use <$650M of DoD funds/per FY/four RAA categories. The JRAC

recommends which will be used.

1) Urgent needs to eliminate a documented deficiency that has resulted in combat casualties or is likely to

result in combat casualties. (<$200M/FY)

2) Urgent needs to eliminate a documented deficiency that impacts an ongoing or anticipated contingency

operation and that, if left unfulfilled, could potentially result in loss of life or critical mission failure.

(<$200M/FY)

3) Urgent needs to eliminate a deficiency caused by a cyber attack resulting in critical mission failure, the loss

of life, property destruction, or economic effects, or, if left unfulfilled, is likely to result in critical mission

failure, the loss of life, property destruction, or economic effects. (<$200M/FY)

4) Compelling national security needs requiring the immediate initiation of a project under the rapid fielding or

rapid prototyping acquisition pathways [i.e., Middle Tier of Acquisition] IAW Section 804 of PL 114-92, as

amended. (<$50M/FY)

See DoDM 5000.78, Rapid Acquisition Authority, 20 Mar 19, for more info

49

Page 50: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

50

DoDI 5000.81, Figure 2. Flow of JUONs & JEONs (new)This figure illustrates the flow of JUONs & JEONs thru the JCIDS process and the relationship with the Urgent Capability Acquisition (UCA) pathway activities.

JCIDS activities are explained in the JCIDS Manual.

UCA activities are explained in DoDI 5000.81 and summarized in the following section of this presentation.

Page 51: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

51

Development Milestone

Urgent Need Generation

Pre-Development (Days)

Development (Months)

Operations and Support (Months – Years)

Production and Deployment (Months)

(Disposition)

Production and Deployment Milestone

Course of Action Decision Point

Legend:

= Milestone = Activities

= Decision Point = Validation / Recommendation

= Parallel / Concurrent Processes

DoDI 5000.81 describes each of these steps in detail in Section 4: Procedures. This figure is also in the JCIDS Manual.

Next series of charts summarize these activities. For details see DoDI 5000.81.Significant changes from Encl13, DoDI 5000.02, 7 Jan 2015, Change 5, are highlighted in red.

DoDI 5000.81, Figure 3. Urgent Capability Acquisitions

Page 52: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

52

Urgent Capability Acquisition4.2 Pre-Development Activities (summarized)

• Purpose: Assess and select a course or courses of action (COA or COAs) to field a quick reaction capability and to develop an acquisition approach.

• Initiation: Receipt of either a validated UON, approval of a critical warfighter issue statement by the co-chairs of the Warfighter SIG, per DoDD 5000.71, or a SecDef or DepSecDef RAA determination document.

• Activities:

- CAE appoints PM and designates and an MDA for JUON and JEONs assigned to the component by the Executive Director, JRAC. If DAE retains MDA authority, the DAE will appoint a PM or task a CAE to do so.

- PM, in collaboration with intended user community and the requirements validation authority:

Assesses the required capability and non-materiel options

Determines performance thresholds; ensure they are testable

Page 53: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

53

Urgent Capability Acquisition4.2 Pre-Development Activities (summarized), continued..

• Activities, continued:

Performs an analysis of potential courses of action, if not already performed, that considers:

1. The range of feasible capabilities, near, mid, and long term, to include consideration of an existing domestic or foreign-made capability.

2. The acquisition risk (cost, schedule, and performance) and the operational risk of each solution.

3. The operational risk to the requesting commander if an effective solution is not deployed in the time specified by the commander.

Assesses and documents safety and supportability risks of the potential course of action

- Presents recommended COA for review and approval by the MDA

- MDA selected COA documented in ADM (more than one COA may be selected to provide phase or incremental fielding of capabilities

Page 54: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

54

Urgent Capability Acquisition4.2 Pre-Development Activities (summarized), continued..

• Activities, continued:

- PM develops draft acquisition strategy (must include planning for O&S) and an abbreviated APB for each COA based on readily available information.

- The acquisition strategy will comply with the requirements in Table 11 of this enclosure and the items in Table 2 of Enclosure 1 that are required for ACAT II and III programs (unless modified by Table 11); information requirements applicable to ACAT II and ACAT III programs available online at https://www.dau.edu/mdid/Pages/Default.aspx:

1. Table 2. “Milestone and Phase Information Requirements.”

2. Table 6. “Exceptions, Waivers, and Alternative Management and Reporting Requirements.”

3. Table 10. “Information Requirements Unique to the Urgent Capability Acquisition Process” (also shown in Table 1 of DoDI 5000.81).

- A streamlined, highly-tailored strategy consistent with the urgency of the need will be employed. Regulatory requirements will be tailored or waived, as appropriate.

Page 55: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

55

Urgent Capability Acquisition4.2 Pre-Development Activities (summarized), continued..

• Activities, continued:

- The tailored acquisition strategy should be relatively brief and contain only essential information, such as resourcing needs and sources; key deliverables; performance parameters; key risks and mitigation approaches; a production schedule; a fielding schedule; contracting methodology and key terms; and preliminary plans for performance assessment (which may or may not include test and evaluation ), deployment, training and sustainment. of the capability and its supportability, to include software.

- When designing the acquisition strategy, the PM, in collaboration with the requesting operational commander or sponsoring user community representative will determine whether an operational prototype is necessary to reduce operational risk and, if so, include this determination and a notional assessment approach in the acquisition strategy.

Page 56: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

56

Information Requirements Unique to Urgent Capability Acquisition Process (Adapted from Table 1, DoDI 5000.81)

Statutory Information Requirements:

• Assessment Approach, 10 USC 2366 and 2399.

-Due: Development and Production Decisions

-DOT&E Oversight Programs. OT and live fire test plans submitted to DOT&E for approval at Development Decision. Post-deployment assessment plans submitted to DOT&E for approval at Production and Deployment Milestone. Approval required 60 days before start of testing.

-Programs not under DOT&E oversight. Approved at Service level. May require a rapid and focused operational assessment, and live fire testing (if applicable).

• Course of Action (COA) Analysis. Assessment Requirements of Subtitle III, Title 40, U.S. Code

-Due: Development Decision

-Approved by the MDA. For JUONs, JEONs, critical warfighter issues identified by the Warfighter SIG, and SecDef or DepSecDef RAA determinations, a copy is due to the Executive Director, JRAC, within 3 business days of MDA approval.

• RAA Recommendation. Request to SecDef or DepSecDef for RAA approval. Part of development of Acquisition Strategy. MDA approves decision to request RAA at Development Decision.

Page 57: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

57

Information Requirements Unique to Urgent Capability Acquisition Process (Adapted from Table 1, DoDI 5000.81)

Information Requirement, continued..

Regulatory Information Requirements:

• Disposition Authority’s Report to DoD Component Head. Part 4.5.e of DoDI 5000.81

-Based on the disposition official’s recommendation in the Disposition Analysis, the Component Head will determine and document the disposition of the initiative and process it in accordance with applicable Component and requirements authority procedures

While above listed information requirements are specific to programs responding to urgent operational needs, they are additive to the requirements identified in Tables 2 and 6 DoDI 5000.02T (Change 6, 23 Jan 20). (See MDID tool at https://www.dau.edu/mdid/Pages/Default.aspx)

4.2.c.(5) Information technology, including National Security Systems, provided in response to an urgent operational need requires an authorization to operate in accordance with DoDI 8510.01, Risk Management Framework (RMF) for DoD Information Technology (IT), Change 2, 28 Jul 17.

Page 58: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

58

Urgent Capability Acquisition4.3.a. Entry into Development (summarized)

• Entry into development is approved by the MDA

• PM Provides: Acquisition Strategy and APB to include program requirements, schedule, activities, program

funding, the assessment approach and intermediate decision points and criteria

• The MDA will:

- Determine feasibility of fielding capability within required timelines to include consideration of the technical maturity of the preferred solution(s). If the MDA determines that the fielding of the capability cannot be accomplished in the required timelines, then the MDA may direct partial or interim solutions that can be fielded more rapidly, or may direct that the program will be managed under a different authority.

- Review the acquisition strategy and program baseline and determine whether the preferred solution:

- 1. Can be fielded within 2 years.

- 2. Does not require substantial development effort.

- 3. Is based on technologies that are proven and available.

- 4. Can be acquired under a fixed price contract.

- 5. Provides any exceptions necessary pursuant to section 804 (b)(3) of P.L. 111-383, including exceptions to the requirements of Paragraph (2)(b)1 through Paragraph (2)(b)4 (refers to 1 thru 4 above).

Page 59: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

59

Urgent Capability Acquisition4.3.a. Entry into Development (summarized), continued

• The MDA will, continued..

- Approve Acquisition Strategy and APB

- Approve initial quantities to be produced and assessed, to include required assessment and training articles.

- Decide if RAA should be requested from SECDEF or DEPSECDEF to expedite the fielding

- Approve the planned testing approach. A normal test and evaluation master plan (TEMP) is generally not necessary.

- TEMPs are usually not appropriate for efforts using urgent capability acquisition procedures when there is minimal development work and minimal development work and minimal test and evaluation to execute. Some test planning is usually required, however, in collaboration with the supporting developmental or operational test organization. The MDA may require a highly-tailored and abbreviated test plan. The abbreviated test plan will describe a performance assessment approach that will include schedule, test types and environment, and assets required. An Operational Test Plan for the required pre-deployment performance assessment is generally adequate.

Page 60: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

60

Urgent Capability Acquisition4.3.a. Entry into Development (summarized), continued..

• The MDA will, continued..

- If the defense urgent capability acquisition program is under DOT&E oversight, a TEMP is also not normally required; however, the Program Manager should prepare a combined operational and live fire test plan for DOT&E approval. A TEMP is also not normally required if the urgent capability acquisition effort is under DOT&E oversight. The PM, in collaboration with the supporting operational test organization, should prepare operational and live fire test plans for DOT&E approval, however, an operational test plan for the required pre-deployment performance assessment is generally adequate.

- Approve testing approach. If DOT&E oversight, PM prepares combined OT and live fire test plan for DOT&E approval

- Approve any waivers to statue or regulation

- Authorize release of RFPs

- Document decisions in an ADM

Page 61: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

61

Urgent Capability Acquisition 4.3.b. Development Activities (summarized)

• Assessment of performance, safety, suitability and survivability, supportability, including software, and lethality, if appropriate.

• Does not require all identified deficiencies be resolved prior to production or deployment

• MDA will, in consultation with the user and requirements validation authority, determine which deficiencies must be resolved and what risks can be accepted

Accepted risks will allow the user community to develop tactics, techniques, and procedures to help minimize the operational risks.

Page 62: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

62

Urgent Capability Acquisition4.4. Entry Into Production & Deployment (P&D) (summarized)

Entry into P&D is approved by the MDA

PM:

- Summarizes results of development activities, pre-deployment performance, and the program assessment

- Presents plan to transport, deploy, and sustain the capability, and to conduct post-deployment assessments, and to train maintenance and operating personnel

MDA, in consultation with the supporting operational test organization DT and OT and/or live fire test organization, with concurrence of DOT&E for programs under DOT&E oversight, determines:

- Whether the capability has been adequately reviewed, performs satisfactorily, is supportable, and is ready for production and deployment.

- When assessments of fielded capabilities are required.

- Whether to produce and, in coordination with the requester/user, field the system capability, and

- Approves the updated acquisition strategy (which will include the sustainment plan and program baseline)

- Documents the production decision in an ADM

Page 63: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

63

Urgent Capability Acquisition4.4. Production & Deployment Activities (summarized)

During P&D the acquiring organization provides the warfighter with the needed capability, to include any required training, spares, technical data to include known hazards and accepted mishap risks, computer software, temporary or permanent facilities or infrastructure, support equipment, maintenance, or other logistics support necessary for operation.

(1) The DoD Components will ensure that the capability and required support (e.g., field service representatives, training) are deployed by the most expeditious means possible and tracked through to their actual delivery to the user.

(2) The DoD Components will coordinate with each other and the requiring activity to verify the total number of items required, considering necessary support and spares and training assets for deployed or pre-deployment training.

Upon deployment, the capability enters Operations & Support

Page 64: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

64

Urgent Capability Acquisition4.5. Operations and Support (summarized)

• PM executes a supportability strategy that meets materiel readiness and operational support performance requirements, is safe, and sustains the capability in the most cost-effective manner.

• Capability is operated and supported consistent with MDA approved sustainment plan.

• PM or user community may propose urgently needed improvements – may be acquired using rapid acquisition procedures if within the scope of the initial requirement document.

• Post-deployment assessment conducted.

• Post-deployment assessment approaches for all programs under DOT&E oversight will be independently reviewed and approved by DOT&E.

Page 65: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

65

Urgent Capability Acquisition4.4.e. Disposition Analysis (summarized)

No later than 1 year after the program enters O&S (or earlier if directed by the DoD Component), the DoD Component will appoint an official to conduct a disposition analysis. The DoD Component will notify the Executive Director, JRAC and the Deputy Director for Requirements and Capability Development in the Joint Staff J-8, when the disposition analyses for JUONs, JEONs, critical warfighter issues identified by the Warfighter SIG, or SecDef or DepSecDef RAA determinations are to be completed. Based on the analysis, the DoD Component head and the CAE will prepare a determination document for disposition of the system.

• The disposition analysis will consider the performance of the fielded system capability, mishap data, long term operational needs, and the relationship of the capability to the component’s current and planned inventory of equipment.

• The analysis will also consider the continuation of non-materiel initiatives, the extension of science and technology developments related to the fielded capability, and the completion of MDA-approved and funded materiel improvements.

Page 66: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

66

Urgent Capability Acquisition4.4.e. Disposition Analysis (summarized), continued..

Disposition official will recommend one of the following options:

• Termination: Demilitarization or Disposal

The system capability will be demilitarized and disposed of in accordance with all legal and regulatory requirements and policy related to safety (including explosive safety) and the environment. The recommendation will be coordinated with the DoD Component or, for JUONs and JEONs, the Combatant Commands

• Sustainment for Current Contingency.

Operation and sustainment of the system capability will continue for the current contingency. Multiple sustainment decisions may be made should the capability require operations and support longer than two years; however, such sustainment decisions will be made and re-documented at least every two years. The sustained capability will continue to receive the same priority of action as the original acquisition program. This recommendation will be coordinated with the DoD Component requirements validation authority.

Page 67: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

67

Urgent Capability Acquisition4.4.e. Disposition Analysis (summarized), continued..

• Transition to Program of Record (POR)

If the system provides a needed, enduring capability serves an enduring purpose, it may be transitioned to a POR, once funded in the component’s budget. Supportability and sustainment planning should include interim contract support and contract logistics support until the capability’s formal programmed funding is established.

- The disposition official will recommend to the CAE the acquisition point of entry into the defense acquisition system, and whether the MDA should retain program authority or whether it should transition elsewhere.

- The requirements validation authority will specify the capability requirements documents required to support transition to a new or existing program of record.

Page 68: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

68

Urgent Capability Acquisition4.4.e. Disposition Determination (summarized)

• The disposition recommendation will be made to the DoD Component head for UONs, critical warfighter issues identified by the Warfighter SIG, or SecDef or DepSecDef RAA determinations.

• The DoD Component head, and the CAE will review the disposition official’s recommendation and, within 4 months of receipt of the recommendation, record the DoD Component head’s transition decision in a disposition determination. The Determination will specify the requirements documents required by the validation authority to support the transition. Programs of record will follow the procedures for such programs described in this instruction.

• The disposition determinations for JUONs, JEONs, critical warfighter issues identified by the Warfighter SIG, or SecDef or DepSecDef RAA determinations, will be provided to the Executive Director, JRAC and the Deputy Director for Requirements and Capability Development (DDRCD), Joint Staff J-8, by the Component head.

Page 69: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Some Considerations for an

Urgent Capability Acquisition

• Do you understand the requirement?

• What are the DOTmLPF-P* considerations?

• Use mature technology…What are the key technical challenges?

Alternative solutions?

• Need a flexible and accountable “acquisition” structure

• Where will the $$$$ come from?

• Training, logistic, and operational support….What is the priority?

• Know capability delivered meets user needs…How much T&E is

necessary?

69*DOTmLPF-P = Doctrine, Organization, Training, materiel (existing; no development required), Leadership & Education, Personnel, Facilities, Policy

Page 70: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Risks Associated with

Urgent Capability Acquisition

• Work with the user to determine what level of risk is acceptable;

balance operational risk with acquisition risk.

• Urgent capability fielding may result in a solution that does not

perform as planned.

• Parallel processes may incur increased cost due to urgent capability

changes.

• Incremental approach may be necessary.

• Short-term success may not meet longer-term needs.

• Sustainment planning may result in requirements for multiple

upgrades or for more costly improvements.

• Transition to a program of record may require development of DoDI

5000.02 and JCIDS documentation.

70

Page 71: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

Technical Planning Considerations in

Urgent Capability Acquisition

• Use mature technology.

• Plan on incremental development and deployment.

• Strive for a defined set of stable requirements focused on warfighter needs.

• Tailor processes to maximum extent practical (documentation, technical

reviews, testing, etc.)

• Accept risk.

• Don’t forget about the long-term (production & sustainment).

• Pick your team with specific skills + experience + intangibles.

• Right-size the program – streamline oversight.

• Document what you do (good configuration management).

• Build and maintain trust with key stakeholders.

Derived from: Debra Facktor Lepore, John M. Colombi, et. al., “Observations on Expedited Systems Engineering Practices in Military Rapid Development Projects,” 2013.

71

Page 72: Urgent Capability Acquisition Pathway RDT Webcast · 2020-03-10 · Urgent Capability Acquisition Pathway RDT Webcast 10 March 2020 Mr. Tracy Tynan, SES Executive Director Joint Rapid

T&E Planning Considerations in

Urgent Capability Acquisition

• Director, Operational Test and Evaluation (DOT&E) designates select programs for DOT&E operational and live fire oversight.

• Information Technology, including National Security Systems, requires authority to operate IAW DoDI 8510.01, Risk Management Framework.

• Work with Service Operational Test Agency (OTA) to develop an abbreviated test plan

• Testing for urgent capability acquisition programs is often incomplete/inadequate prior to fielding:

– Testing is often completed in days or weeks

– Testing focuses on safety, capabilities, and limitations; serious deficiencies may not be discovered until after fielding

– Fielded items often have interoperability, compatibility, training, or maintenance issues (little or no testing done in these areas)

– Little test data to support decisions