upgrading existing power supply at the port of …

118
UPGRADING EXISTING POWER SUPPLY AT THE PORT OF DURBAN By Siphokazi Mnukwa 209503736 A dissertation submitted in partial fulfillment of the requirements for the degree Of Master of Science in Electrical Engineering College of Agriculture, Engineering and Science, University of KwaZulu- Natal November 2019 Supervisor: Professor A.K. Saha

Upload: others

Post on 07-Nov-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

UPGRADING EXISTING POWER SUPPLY AT THE

PORT OF DURBAN

By

Siphokazi Mnukwa

209503736

A dissertation submitted in partial fulfillment of the requirements for the

degree

Of

Master of Science in Electrical Engineering

College of Agriculture, Engineering and Science, University of KwaZulu-

Natal

November 2019

Supervisor: Professor A.K. Saha

Page 2: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

i

COLLEGE OF AGRICULTURE, ENGINEERING AND SCIENCE

As the candidate’s Supervisor I agree/do not agree to the submission of this thesis. The supervisor

must sign all copies after deleting which is not applicable

Signed: _________________________________

Professor A.K. Saha

Page 3: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

ii

COLLEGE OF AGRICULTURE, ENGINEERING AND SCIENCE

DECLARATION 1 - PLAGIARISM

I, ……………………………………….………………………., declare that

1. The research reported in this thesis, except where otherwise indicated, is my original

research.

2. This thesis has not been submitted for any degree or examination at any other university.

3. This thesis does not contain other persons’ data, pictures, graphs or other information,

unless specifically acknowledged as being sourced from other persons.

4. This thesis does not contain other persons' writing, unless specifically acknowledged as

being sourced from other researchers. Where other written sources have been quoted, then:

a. Their words have been re-written but the general information attributed to them has been

referenced

b. Where their exact words have been used, then their writing has been placed in italics and

inside quotation marks, and referenced.

5. This thesis does not contain text, graphics or tables copied and pasted from the Internet,

unless specifically acknowledged, and the source being detailed in the thesis and in the

References sections.

Signed

………………………………………………………………………………

Siphokazi Mnukwa

Siphokazi Mnukwa

Page 4: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

iii

COLLEGE OF AGRICULTURE, ENGINEERING AND SCIENCE

DECLARATION 2 - PUBLICATIONS

DETAILS OF CONTRIBUTION TO PUBLICATIONS that form part and/or include research

presented in this thesis (include publications in preparation, submitted, in press and published and

give details of the contributions of each author to the experimental work and writing of each

publication)

Publication 1

S. Mnukwa and A.K. Saha, “Implementation of Substation SCADA and Automation Systems in

the Port of Durban”, 2018 IEEE PES/IAS Power Africa Conference, pp 214 – 219, 26 – 29 June

2018, Cape Town, South Africa.

Publication 2

S. Mnukwa and A.K. Saha, "Electrical Load Flow Analysis of 132/33/11 kV Port of Durban’s

Substation”, Journal under review on Scientific.net, 2019.

Publication 3

S. Mnukwa and A.K. Saha, “SCADA and Substation Automation Systems for the Port of Durban

Power Supply Upgrade”, submitted for publication to SAUPEC/RobMech/PRASA 2020, Cape

Town, South Africa.

Signed:

Page 5: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

iv

DEDICATION

To My Son Ntsikelelo Dumakude, for always inspiring me to do my best. Thank you for being

understanding when I could not be at home to spend time or watch cartoons with you. I love you

dearly son, my number one supporter.

Philippians 4:13 “I can do all things through Christ who strengthens me”

Page 6: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

v

ACKNOWLEDGEMENTS

Firstly, I would like to give God the Almighty all the glory and praise for granting me the divine

wisdom, strength and opportunity for Education. If it was not for the Lord I would not have made

it this far.

My heartfelt appreciation goes to my supervisor Professor Akshay Kumar Saha for his

supervision, assistance, leadership and invaluable contribution towards my dissertation. Your

advice, encouragement and efforts in comments and corrections of this dissertation are highly

appreciated. Thank you for ensuring that all the equipment required for my research was available.

I would like to thank Transnet National Ports Authority: Port of Durban for allowing me the

opportunity to do my masters and for assisting by providing the equipment and resources I

required for my research. Special thanks goes to Mr. Akash Tulsie, Mr. Johan Sauerman and Mr.

Tony Francis for always supporting my career aspirations and engineering dreams.

Further thanks to my family for your constant support, motivation and always believing in me. A

special thanks to my mother Nomonde Mnukwa who never cease to pray for me. Thank you for

playing a mother’s role to my son when I was academically committed. To Wiseman Dumakude

my life partner, thank you for your moral support and encouragement at all times.

Final acknowledgement goes to the University of KwaZulu-Natal, School of Engineering, for

providing facilities and infrastructure required for my research.

Page 7: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

vi

ABSTRACT

The Port of Durban’s (PoD’s) power supply is from EThekwini Electricity (EE) at a supply

voltage of 33 kV via two main intake substations that is Stanger Street Substation (STS) and

Durban Harbour Intake (DHI) Substation. The supplied power in the Port is stepped down from

33 kV to 11/6.6 kV electrical network. The firm supply capacity for each of these substations is

limited to 17 MVA, which is no longer sufficient to supply the PoD because EE’s 33 kV electrical

infrastructure and supply cables have reached the end of their design lifespan. The existing power

supply capacity limit is under threat due to that; it will not be able to meet the additional load

required for the planned developments and expansion plans in the Port. System strengthening and

enhancements are required in order to improve the reliability of the electrical network. Increasing

the electrical supply to and within the Port will ensure a stable and reliable electrical supply.

This research is based on the increase of power supply in the PoD to 132 kV electrical network

based on the projected load requirements for planned developments in order to strengthen and

increase reliability of the network. The 132 kV electrical network was implemented in

PowaMaster software to perform the load flow analyses. Various load flow scenarios were

investigated and from the results obtained it was evident that 2 x 132 kV 40 MVA transformers

will be capable to carry the total projected Port load reliably and the electrical network will be

stable. Detailed analysis and results of different scenarios investigated is contained in this

dissertation. An automatic and interactive SCADA model of the physical power systems electrical

reticulation network was developed using Schneider CitectSCADA Software. The implemented

132/33 kV substation network model together with the hardware IEDs i.e. VAMP 255, VAMP

259, MiCOM P122 and GE F35 Feeder management protection relays provided functions for

control, data acquisition, monitoring, graphical displays, event capturing, alarming, trending and

data storage. Communication between the implemented SCADA system and the IEDs was

achieved via a communication architecture implemented that took into consideration Modbus

RTU, DNP3 and IEC 81650 communications protocols. The substation model implemented was

tested for operation at different operating and fault conditions. The effective operation was proven

for circuit breaker operation, alarming, circuit breaker fail, overcurrent, earth fault and circuit

breaker trip coil supervision under local or remote mode. Results obtained are presented and

discussed.

Page 8: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

vii

TABLE OF CONTENTS

DECLARATION 1 - PLAGIARISM ....................................................................................... ii

DECLARATION 2 - PUBLICATIONS ................................................................................. iii

DEDICATION ............................................................................................................................ iv

ACKNOWLEDGEMENTS ....................................................................................................... v

ABSTRACT ................................................................................................................................ vi

TABLE OF CONTENTS ......................................................................................................... vii

LIST OF FIGURES .................................................................................................................... x

LIST OF TABLES .................................................................................................................... xii

LIST OF ACRONYMS ........................................................................................................... xiii

CHAPTER 1: INTRODUCTION .............................................................................................. 1

1.1 Background ...................................................................................................................... 1

1.2 Motivation ........................................................................................................................ 2

1.3 Research Questions ......................................................................................................... 4

1.4 Dissertation Aims and Objectives .................................................................................. 4

1.5 Structure of the Dissertation .......................................................................................... 5

CHAPTER 2: BACKGROUND THEORY AND LITERATURE REVIEW ........................ 7

2.1 Introduction to Load Flow Studies ................................................................................ 7

2.2 Load Flow Analysis ......................................................................................................... 7

2.3 Load flow methods .......................................................................................................... 7

2.3.1 Gauss-Siedel method ............................................................................................... 8

2.3.2 Newton-Raphson method ....................................................................................... 8

2.3.3 Fast-Decoupled method .......................................................................................... 8

2.4 Introduction to Power Systems Protection ................................................................... 9

2.5 Zones of Protection ......................................................................................................... 9

2.6 Requirements of a Protection Scheme ......................................................................... 11

2.6.1 Reliability ............................................................................................................... 11

2.6.2 Selectivity ............................................................................................................... 11

2.6.3 Stability .................................................................................................................. 12

2.6.4 Speed ...................................................................................................................... 12

2.6.5 Sensitivity ............................................................................................................... 12

2.7 Protective Relaying ....................................................................................................... 12

2.7.1 Relay Operating Principle .................................................................................... 12

2.7.2 The Protection Scheme ......................................................................................... 13

2.7.3 Overcurrent Relays ............................................................................................... 14

Page 9: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

viii

CHAPTER 3: REVIEW OF THE EXISTING POWER SUPPLY AND UPGRADE

REQUIREMENTS IN THE PORT OF DURBAN ................................................................ 18

3.1 Introduction ................................................................................................................... 18

3.2 Supervisory Control and Data Acquisition Systems .................................................. 19

3.2.1 SCADA Architecture ............................................................................................ 22

3.2.2 Communications .................................................................................................... 24

3.2.3 Performance........................................................................................................... 24

3.2.4 Primary and Backup Systems .............................................................................. 26

3.3 Substation Automation Systems .................................................................................. 26

3.3.1 Substation Automation Design Requirements .................................................... 27

3.3.2 Selection of IEDs ................................................................................................... 27

3.3.3 Human Machine Interface ................................................................................... 28

3.4 Security requirements ................................................................................................... 31

3.5 Electrical Power Supply Identification ....................................................................... 32

3.5.1 Electrical Power .................................................................................................... 32

3.5.2 Redundant Power Sources ................................................................................... 33

3.6 The integration of 132 kV Substation (Langeberg) into the PoD’s Electrical

Network and SCADA System .................................................................................................. 34

CHAPTER 4: RESEARCH METHODOLOGY .................................................................... 37

4.1 Introduction ................................................................................................................... 37

4.2 Software ......................................................................................................................... 38

4.2.1 PowaMaster – Electrical Analysis Software for Transmission & Distribution

Systems 38

4.2.2 Development of SCADA and SAS using Schneider CitectSCADA Software .. 42

4.3 Analysis Summary ........................................................................................................ 44

CHAPTER 5: ELECTRICAL LOAD FLOW ANALYSIS ................................................... 45

5.1 Introduction ................................................................................................................... 45

5.2 Port Historical Load Data ............................................................................................ 45

5.3 Projected Infrastructure Developments ...................................................................... 46

5.4 Modelling and Load Flow Study .................................................................................. 47

5.4.1 Load Flow Scenario Analysis ............................................................................... 49

5.5 Load Flow Study Results .............................................................................................. 52

5.5.1 Analysis and Discussion of Results for Scenario 1, 3 and 5 ............................... 52

5.5.2 Analysis and Discussion of Results for Scenario 2, 4 and 6 ............................... 54

5.6 Conclusion ...................................................................................................................... 56

CHAPTER 6: DEVELOPMENT OF SCADA AND SAS FOR PORT OF DURBAN’S 132/

33 kV SUBSTATION POWER SUPPLY UPGRADE........................................................... 57

Page 10: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

ix

6.1 CitectSCADA System Development ............................................................................ 57

6.1.1 SCADA Communications Architecture .............................................................. 58

6.1.2 Configuration Tools .............................................................................................. 60

6.2 CitectSCADA Substation Model Testing .................................................................... 68

6.2.1 Circuit Breaker Basic Operation ......................................................................... 68

6.2.2 Bus Section Basic Operation ................................................................................ 70

6.3 Conclusion ...................................................................................................................... 75

CHAPTER 7: CONCLUSION AND RECOMMENDATIONS ........................................... 77

7.1 Conclusion ...................................................................................................................... 77

7.2 Recommendations for Future Work ........................................................................... 78

REFERENCES .......................................................................................................................... 79

APPENDICES ........................................................................................................................... 83

ANNEXURE A – MAXIMUM DEMAND RAW DATA RETRIEVED FROM SCADA

SYSTEM .................................................................................................................................... 83

ANNEXURE B – CABLE SELECTION CALCULATIONS & DATASHEETS ............... 86

ANNEXURE C – LOAD FLOW STUDY PowaMaster RESULTS ..................................... 91

ANNEXURE D – LOAD FLOW STUDY PowaMaster RESULTS ..................................... 92

ANNEXURE E – INTELLIGENT ELECTRONIC DEVICES USED .............................. 102

Page 11: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

x

LIST OF FIGURES Figure 2-1: Division of Power Systems into protection zones [2] ………………………………10

Figure 2-2: Overlapping zones of protection systems [22] . ……………………………………10

Figure 2-3: Functional Block Representing Numerical Relay Configuration [29] . ……………13

Figure 2-4: Basic Protection Scheme [24] ………………………………………………………14

Figure 2-5: Definite time of overcurrent relay [32] ……………………………………………15

Figure 2-6: IEC 60255 IDMT Relay Characteristics; TMS = 1.0 [22] …………………….……16

Figure 3-1: Historical Maximum Demand Load Profile for the Port [35] ............................... ....18

Figure 3-2: Geographically dispersed electrical substations monitored on the PoD’s SCADA

system [44] .............. …………………………………………………………………………….20

Figure 3-3: Substation Electrical Network Reticulation [44] ................................................ …...21

Figure 3-4: PoD's SCADA Architecture [46] …………………………………………….…….23

Figure 3-5: Overview of the Port’s system architecture [46, 47] ............... ……………….…….23

Figure 3-6: PoD’s Communication Network for substations [44] ........................................ …...24

Figure 3-7: Substation incomer feeder protection relay status [44] ...................................... …...26

Figure 3-8: Substation Automation Hierarchic Levels [39] ................................................. …...27

Figure 3-9: HMI flow diagram [39] ..................................................................................... …...29

Figure 3 10: Graphic Screen Tree Hierarchy [45] ………………………………….…….…….29

Figure 3-11: Application Graphic Screen Layout [44, 45] .................................................. …...30

Figure 3-12: Alarm Screen Display [45] .............................................................................. …...31

Figure 3-13: PoD’s new 132 kV Langeberg Substation Reticulation [7] ............................. …...34

Figure 3-14: Design Process Steps [55] ............................................................................... …...35

Figure 3-15: Langeberg 132 kV Substation Network and protection layout [53] …….….…….35

Figure 4-1: Methodology Block Diagram ............................................................................ …...37

Figure 4-2: PowaMaster Graphical User Interface .............................................................. …....38

Figure 4-3: Bulk Power Supply Block Diagram- Proposed New Solutions ....................... …....40

Figure 4-4: Electrical Reticulation implemented on PowaMaster of the new 132 kV

Langeberg Substation ............................................................................................................ …...41

Figure 4-5: PowaMaster generated User Report ……………………………………………….41

Figure 4-6: A combination of Legacy and IEC 61850 Automation System Design ............ …...43

Figure 5-1: Port historical load from 2013 to 2018 .............................................................. …...46

Figure 5-2: Projected electrical load demand in line with the port infrastructure

development plan. ............................................................................................................... …....47

Figure 5-3: Port Load Growth for Scenarios 1, 3 and 5 ……………………………………….…52

Figure 5-4: Voltage Levels at 132 kV and 33 kV for Scenarios 1, 3 and 5…………………….…53

Figure 5-5: Conductor Percentage Loading - Main left and right 132 kV buses and main left

and right 33 kV for Scenarios 1, 3 and 5………………………….……………….………….....54

Figure 5-6: 132 kV Main Transformer Percentage Loading for Scenarios 1, 3 and 5 ....... …......54

Figure 5-7: Port Load Growth for Scenarios 2, 4 and 6 ........................................................ …...55

Figure 5-8: Voltage Levels at 132 kV and 33 kV for Scenarios 2, 4 and 6 ........................ ….....55

Figure 5-9: Percentage Loading for Main 132 kV and 33 kV Conductors when

Scenario’s 2, 4 and 6 were implemented. .......................................................................... ….....55

Figure 5-10: 132 kV Main Transformer Percentage Loading for Scenarios 2, 4 and 6 ...... ….....56

Figure 6-1: Electrical Substation SCADA Model with Protection Devices ............ ....................58

Figure 6-2: SCADA Communications Architecture. ....... ….......................................................59

Figure 6-3: CitectSCADA Explorer Configuration Tool. ................................... ….....................60

Figure 6-4: CitectSCADA Editor Configuration Tool. ....... …....................................................60

Figure 6-5: CitectSCADA Graphics Builder Configuration Tool... ….........................................61

Figure 6-6: CitectSCADA Runtime .... ….....................................................................................61

Figure 6-7: Explanation for navigation panels. .. …......................................................................62

Figure 6-8: Electrical Network Reticulation Implemented. .. …..................................................63

Page 12: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

xi

Figure 6-9: Electrical Network Reticulation Symbols Description. ….......................................63

Figure 6-10: Alarms Page… ... .....................................................................................................64

Figure 6-11: Active Alarms Page. ... ….........................................................................................65

Figure 6-12: Summary Alarms Page. ... …....................................................................................65

Figure 6-13: Hardware Alarms Page. .. …....................................................................................66

Figure 6-14: Trends Page. .. ….....................................................................................................67

Figure 6-15: Substation Geographical Location. ........................... …..........................................67

Figure 6-16: Energized Circuit Breaker Basic Operation. ... …...................................................68

Figure 6-17: Hardware Relay Circuit Breaker Energized Status. ... ….........................................68

Figure 6-18: De-energized Circuit Breaker Basic Operation. ..... ….............................................69

Figure 6-19: Hardware Relay Circuit Breaker De-Energized Status. ... …...................................69

Figure 6-20: Energized Bus Section Basic Operation. ..... …........................................................70

Figure 6-21: De-Energized Bus Section Basic Operation. ..... …..................................................70

Figure 6-22: Incomer 1 Overcurrent Trip Status. ... ..…................................................................71

Figure 6-23: Incomer 1 Earth Fault Trip Status. .... …..................................................................72

Figure 6-24: Incomer 2 Local Mode and Disabled Controls........................................................73

Figure 6-25: Incomer 2 Local Mode when operated by Maintenance Personnel.... …................73

Figure 6-26: Incomer 2 Circuit Breaker Trip Coil Status. .. ….....................................................73

Figure 6-27: Hardware Relay Incomer 2 Circuit Breaker Trip Coil Supervision Status. .. …......74

Figure 6-28: Incomer 2 Circuit Breaker Fail Status. .. …..............................................................74

Figure 6-29: Feeder 2 3ph-G Overcurrent Trip Fault Condition. .. …..........................................75

Figure 6-30: Three Phase Current under normal and overcurrent fault conditions. .. …...............75

Page 13: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

xii

LIST OF TABLES

Table 5-1: Summary of total port load at 33 kV STS and 33 kV DHI substation incomers. …...45

Table 5-2: Planned Future projects with their estimated loads and planned commissioning

year. ….………………………………………………………………………………………….46

Table 5-3: Diversity Factor and Coincidence Factor Applied at Various Substation and

Minisubstations. ……………..………………………………………………………………….48

Table 5-4: Maximum Deviation from standard or declared Voltages. …………………………49

Table 5-5: Maximum voltages for supplies to customers above 500 V. …..………………...…49

Table 5-6: Details of the Selected Transformers for the new 132/ 33/ 11 kV Langeberg

Substation. ..……………………………………………………………………………….....…50

Table 5-7: Details of the Selected C for the new 132/ 33/ 11 kV Langeberg Substation. .…..…50

Table 6-1: Active Alarms. …………………………………………………………………...…64

Table 6-2: Alarm Summary. .………………………………………………………………...…66

Table 6-3: Overcurrent Settings and VAMPSET Tests. ……………………………………...…71

Table 6-4: Earth Fault Settings and VAMPSET Tests. ……………………………………...…72

Page 14: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

xiii

LIST OF ACRONYMS

AC Alternating Current

AD Allan Dalton Substation

AOS Applications Object Server

CF Coincidence Factor

CT Current Transformer

DC Direct Current

DF Diversity Factor

DHI Durban Harbour Intake

Substation

DNP3 Distributed Network Protocol 3

EE EThekwini Electricity

EI Extremely Inverse

GR Galaxy Repository

GS Gauss-Seidal

HMI Human Machine Interface

IDMT Inverse Definite Minimum Time

IEC International Electrotechnical

Committee

IED Intelligent Electronic Devices

IEEE Institute of Electrical and

Electronic Engineers

kVA Kilo Volt Amperes

kV Kilo Volt

LAN Local Area Network

LNs Logic Nodes

MVA Mega Volt Amperes

NR Newton-Raphson

NRS National Rationalized

Specification

PoD Port of Durban

RTU Remote Terminal Unit

SANS South African National

Standards

SAS Substation Automation Systems

SCADA Supervisory Control and Data

Acquisition

SCL Substation Configuration

Language

SI Standard Inverse

SSD Specification

STS Stanger Street Substation

TMS Time Multiplier Settings

TNPA Transnet National Ports Authority

VD Voltage Drop

VI Very Inverse

VT Voltage Transformer

Page 15: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

1

CHAPTER 1: INTRODUCTION

Power systems planning and design is one of the key aspects that needs to be considered for power

supply capacity upgrade for distributed networks. The planning and design ensures compliance

with forecasted load demands and ensuring a reliable robust electrical network and maintaining

the voltage limits [1].

The following factors influence the network design include the [1, 2]:

(a) Existing services.

(b) Geographical location.

(c) Required load or customer loads.

(d) Diversity Factor (DF) and Coincidence Factor (CF).

(e) Cable and conductor sizes and types of cable and conductor.

(f) Size, location and types of substation.

(g) Quality of supply.

(h) Voltage Drop (VD) and unbalance, within limits of design loads.

(i) Future Developments and Environmental considerations.

Power systems load flow analysis is conducted upon considering the above mentioned factors for

evaluation and analysis of the electrical network design behaviour and also for verification of

suitability of the selected equipment for the projected future loads and ensure optimal system

loading [1, 3].

To ensure quicker returns on investment, cost effective Substation Automation Systems (SAS)

are designed to operate and maintain. In order to advance the existing communications protocols

for SAS, the Institute of Electrical and Electronic Engineers (IEEE) and the International

Electrotechnical Committee (IEC) collaborated to develop and implement the Ethernet based IEC

61850 international standard. The IEC 61850 communications network and system in substations

allows for compatibility between Intelligent Electronic Devices (IEDs) of different manufacturers

[4, 5]. This standard is also equipped with descriptive object data models with standard Substation

Configuration Language (SCL) and lower integration costs [6].

1.1 Background

The Port of Durban (PoD) is the busiest in South Africa and the biggest in terms of container

capacity and plays a pivotal role in the South African economy. The PoD’s electrical supply is

integral in supporting the various Transnet facilities / terminals and revenue creating operations

contained therein. The PoD’s existing power supply is under threat, due to the planned

developments and expansion plans requiring additional load. System strengthening and

enhancements are also required. The 33 kV electrical supply to the PoD is from EThekwini

Electricity (EE) via two intake Substations and the supply capacity in each of these substations is

Page 16: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

2

limited to 17 MVA. The supply voltage from the intake substations is redistributed and stepped

down from 33 kV to 11/6.6 kV to all PoD’s consumers i.e. Durban Container Terminal connected

to Port electrical network [7]. The current Notified Maximum Demand according to the port

billing statements is 14.63 MVA. The firm supply of 17 MVA has been exceeded in the past

leaving the port with no redundant supply. The requirement to increase the container throughput

capacity at Pier 1 and Pier 2 container terminals and other infrastructure development projects at

the PoD will result in the firm supply of 17 MVA being exceeded [8,9].

According to eThekwini Municipal “By-Laws”, large power users with maximum demand

exceeding 18 MVA shall be supplied with a system voltage of 132kV. In addition, EE is phasing

out all their 33kV infrastructure and cables due to the exceeded design lifespan resulting in

obsolete spares for maintenance. The costs associated with the maintenance, operation and

sustaining infrastructure at this voltage level far exceeds the return on investment and revenue

generated for a bulk supply of this magnitude [9]. The EE system distribution voltage to large

power users is 132 kV.

Based on the abovementioned facts, the PoD had to evaluate alternative sources of power supply

solution, which will be able to cater for future loads and strengthen the network. This entails the

new 132kV, 80 MVA supply through underground cables from the existing EE’s Edwin Swales

outdoor switching station to the new 132/33 kV Langeberg outdoor PoD substation.

1.2 Motivation

Electricity is the most crucial component of infrastructure affecting economic growth therefore a

stable power network is very essential. Grid collapse situations are a result of overloaded electrical

networks that are prone to electrical failures. It is of great importance that electrical load flow

study analysis are conducted to monitor and control the load and voltage profiles in a power

systems network. This ensures effective electrical network performance and reduces disruption

to operations unexpectedly and savings on operating and maintenance costs [10] and loss of

production. Network modelling is useful for network planners, designers and operators. Network

planners are able to gather information on the status of the electrical networks and ensure that the

network caters for any planned developments requiring additional load. The design engineers

utilise modelling to verify if the selected equipment will be able to cater for the required load

demand under normal operating conditions as well as under fault conditions. The operators use

modelling to monitor and control voltages and currents keeping them within acceptable limits and

ranges [11]

Load flow study analysis will be conducted to evaluate the status of the existing PoD’s electrical

network and future developments forecast loads will be considered to ensure that the electrical

Page 17: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

3

supply upgrade will take into account the projected loads. The main objectives of electrical load

flow studies are the following:

(a) To analyse the status of the existing electrical network and ensure that the network is

reliable and robust to cater for additional forecasted loads.

(b) To obtain information regarding system voltages, currents, active and reactive power at

each point in the network and equipment percentage loading with the respect to

equipment rating.

(c) To determine the best location for new substations or new lines with respect to the load

centres and ensuring that there is sufficient capacity to cater for the demand.

(d) To ensure that voltages at different levels of a power system are monitored and

maintained at acceptable limits.

(e) Provides information of the conductor percentage loading. This ensures that the selected

conductors are not overloaded and are not operated close to their capacity limits or

thermal limits.

Gauss-Seidel (GS), the Newton Raphson (NR) and Fast Decoupled are the three commonly used

iterative methods to solve load flow analysis problems. In Chapter 5 the NR, method is used due

to its characteristics of high degree of accuracy.

The new 132 kV Langeberg substation will be located near the major Port loads as well as future

expansion developments. The design of this electrical substation system will take into

consideration the modernization of the substation system that will improve flexibility and

improved efficiency. Modern power systems substation are equipped with Intelligent Electronic

Devices (IEDs) which provide features of interoperability, advanced and efficient communication

abilities for substation monitoring, protection, control and testing. The integration between legacy

and IEC 61850 communications protocols will be considered in the SAS development for

effectively monitoring and controlling the operation of substation equipment either in remote or

local mode. The developed communications architecture via Ethernet will enable proper

integration between IEDs and communications protocols for coordinated monitoring, protection

and control of a substation. In modern SAS the data retrieved from IEDs is used to control and

operate the electrical network devices. The developed Supervisory Control And Data Acquisition

(SCADA) system will offer users/operators with Human Machine Interface (HMI) or graphical

representation of the electrical substation that will be used for controlling, monitoring and

protection of devices in real time. This function will provide maximum availability, efficiency,

reliability, safety and data integration [14, 15].

Page 18: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

4

1.3 Research Questions

Based on the load profile at the two intake substations in the Port, the load growth in the PoD has

been increasing however the supply capacity limit was never been increased. As a result the

electrical network has been under strain. This research was conducted in order to evaluate and

improve the status of PoD’s electrical network to ensure reliability and availability of supply. The

following research questions are required to be addressed:

(a) What is the impact of the load growth in a power system’s electrical network?

(b) What are the most important aspects to consider for an electrical load flow study analysis

for an electrical power systems network?

(c) What are the benefits of using SCADA systems and SAS to monitor and control an

electrical power system?

(d) For effective operation of SCADA and SAS, what are the communication protocols that

need to be considered?

(e) What is the proposed design for the PoD electrical network to cater for the new loads?

1.4 Dissertation Aims and Objectives

The main aim of the project is to increase the electricity supply capacity to the PoD to ensure

continuous reliable supply to meet the future load demand. The main objective is also to ensure

alignment with EE in phasing out 33 kV infrastructure in the Durban area. This research addressed

the following objectives:

(a) Conduct electrical load flow study to analyse the voltage stability, system reliability and

also perform the short circuit analysis of the new 132/33kV PoD substation in line with

the statutory and regulatory requirements of SANS 10142-2, NRS 034-1:2014 and NRS

048.

(b) Evaluate and investigate various projected load forecast scenarios for effective power

system network analysis.

(c) To validate if all the new selected reticulation cables and transformers as part the design

have been correctly sized and will be able to operate reliably and without compromising

security of supply with the implementation of all planned future loads.

(d) To configure, develop and implement a SCADA and SAS for monitoring and control of

an electrical power system.

(e) Design, establish and commission 132/ 33 kV Legacy and IEC 61850-based integrated

electrical network on CitectSCADA platform and test for effective operation in

conjunction with the associated hardware IEDs.

(f) Configure IEDs i.e. VAMP, MiCom P122 and GE relays individually utilising vendor

proprietary tools.

Page 19: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

5

(g) Investigate and analyse application of communication protocols such as Modbus RTU,

Distributed Network Protocol (DNP3), IEC 60870-5-103 and compare their functionality

with the IEC 61850 standard for effective integration of legacy and modern design.

(h) Examine the application of the integrated legacy and IEC 61850 technology by

implementing and testing different protections scenarios such as Circuit Breaker Failure,

Circuit Breaker Trip Coil Status, Cable Earth, Overcurrent and Earth Fault.

(i) Test the developed SCADA model for operation and isolation under local and remote

mode conditions.

(j) Testing and validating the communication and data flow between IEDs to ensure IEC

61850 compatibility is possible and effective data transfer from the IEDs using the

communications architecture implemented on the network model.

(k) Test functionality and effective operation of the substation equipment, which include

circuit breakers, isolators, supervisory features, and interactive features.

1.5 Structure of the Dissertation

Chapter One entails the background, motivation, research questions, the aims and objectives of

and an outline of the dissertation.

Chapter Two provides information on the reviewed literature and theory surrounding the research

topic. This was required to understand the fundamental elements used in this research. The

literature review focused mainly on aspects of electrical load flow study analysis and power

systems protection. It further indicates how different authors have conducted studies related to

this topic.

Chapter Three presents the review of the existing power supply and upgrade requirements in the

PoD. It investigates the PoD’s SCADA and Automation Systems and presents integration of the

new 132 kV substation network into the currently existing electrical network.

Chapter Four discusses the study methodology, process, software and the study model.

Chapter Five presents an electrical load flow study developed taking into account the future PoD’s

load requirements. The electrical network model is developed and simulated on PowaMaster

software. The objective of this study is to analyse the voltage stability, system reliability and

perform the short circuit analysis of the new 132/33kV PoD substation and verification of the

correct sizing of the selected equipment. Various simulation scenarios and results are presented

in detail.

Chapter Six presents the development of SCADA and Automation system for the PoD’s power

supply upgrade. An interactive and automatic electrical substation network model is developed

Page 20: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

6

on Schneider’s CitectSCADA software. The designed SCADA system enables the user/operator

to visualise and collect data from IEDs located at remote sites and allows for fault management

and operations functions. The implemented SCADA systems provides graphical user interface of

the electrical network, alarm features, trends and substation geographical location for the

user/operator to remotely perform functions of control and interact with the substation equipment.

Chapter Seven consolidates main research points into a final summary and conclusion, and

presents suggestions for further work.

Page 21: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

7

CHAPTER 2: BACKGROUND THEORY AND LITERATURE

REVIEW

2.1 Introduction to Load Flow Studies

This chapter entails a review of literatures related to power systems load flow analysis studies.

Extensive amount of studies have been conducted on load flow analysis. There are several

methods of modern power flow analysis used and these entails of GS, NR method and Fast-

Decoupled method [16, 17, 18, 19, 20].

In an electrical power system network, the load is not constant and changes every moment, leading

to voltage variation above tolerance levels and affects power factor and load performance [17].

The main purpose of load flow studies is to determine the steady state operation of the electrical

network. The following parameters are obtained from this study [16, 17]:

(a) Busbar voltage and current ratings and phase angle;

(b) Real and reactive Power, and;

(c) Load at each level of the busbars.

The information obtained is analysed to identify whether the current network can accommodate

any future additional load requirements and is for continuous system monitoring [16, 18].

2.2 Load Flow Analysis

In electrical power systems, power flows from generating stations to load centres, therefore

requires load flow analysis to check performance of existing system and determine the network

steady state operating conditions [17, 18, 19]. Under steady state conditions the study provides

information of the power delivered, power loses occurred in the system, current through each

branch, voltages at each bus, active and reactive power [16, 17]. The study is use to determine if

the conductors, transformers and transformers are overloaded and whether the voltages are kept

at the required limits in the event of any fault occurring in the network [17, 18]. In order to solve

a power flow problem, it is of great importance that the bus type is identified first and at each bus,

two of the four quantities |Vi|, δi, Pi and Qi are specified and the remaining two are to be calculated.

In a PQ bus, Pi and Qi are known and |Vi| and δi are to be determined. In a PV bus, Pi and |Vi| are

known therefore Qi and δi are to be determined [20].

2.3 Load flow methods

From the literature reviewed there three methods of load flow analysis used i.e. GS method, NR

method and Fast-Decoupled method [16, 17, 18, 19]. In any of these power flow techniques,

initial voltage being specified to all buses, for the first iteration, PQ bus voltage values are set to

(1+j0) whereas for PV bus voltages are set to (V+j0) [20].

Page 22: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

8

2.3.1 Gauss-Siedel method

The GS method is an iterative algorithm for solving a set of non-linear algebraic equations [16].

In order to obtain a load flow solution using GS method, the assumption is that all buses except

for the slack bus are PQ buses. The slack bus voltage is specified, there are (n-1) bus voltages

starting values of whose magnitudes and angles are assumed. These values are therefore updated

through an iterative process. In GS algorithm, equation (1) is utilised to find the final bus voltages

using successive steps of iterations [20].

𝑉𝑖 = 1

𝑌𝑖𝑖 (

𝑃𝑖−𝑗𝑄𝑖

𝑉𝑖∗ − ∑ 𝑌𝑖𝑘

𝑁𝑘=1;𝑘≠1 𝑉𝑘

𝑝) ; 𝑖 = 2, 3, … . , 𝑛 (1)

2.3.2 Newton-Raphson method

The NR method is an iterative process used for solving a set of simultaneous non-linear algebraic

equations with equal number of unknowns. It is a practical method of load flow solution of large

power networks [16, 20]. The Jacobian matrix in equation (2) provides the linearized relationship

between small changes in voltage angle ∆δ and voltage magnitude ∆V with the small changes in

active and reactive

power ∆P and ∆Q [19].

[∆𝑃∆𝑄

] = [𝐽1 𝐽2𝐽3 𝐽4

] [∆𝛿∆𝑉

] (2)

2.3.3 Fast-Decoupled method

Fast-decoupled load flow method approximate decoupling of active and reactive flows in well-

behaved power networks and additionally fixes the value of the Jacobian during the iteration in

order to avoid costs matrix decompositions [18]. In this method, for accuracy up to five iterations

are required and the speed for iterations is nearly five times that of the NR method [20].

The authours of [18] performed an analyses, design and comparison between GS method and NR

method using MATLAB. From the results obtained in this literature it was observed that in the

GS method the rate of convergence is slow and the number of iterations directly increases with

the number of buses in the system. Whereas in the NR method the rate of convergence is very

fast and the number of iterations is independent of the size of the system therefore it is higly

accurate compared to GS method [18]. According to literature [19] GS method is simple and easy

to execute however it has more iterations as the number of buses increase; NR method is more

accurate than all other methods and it provides better results in less number of iterations. Fast-

decoupled load flow method is the fastest of all methods but it is less accurate since assupmtions

are taken for fast calculation. Fast-decoupled load flow method has the least number of iterations

Page 23: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

9

[19]. NR method is more functional and effective because it produces accurate calculation of the

load line losses without depending on the number of buses [20].

2.4 Introduction to Power Systems Protection

This chapter also entails a review of literatures related power systems protection. The purpose of

an electrical power system is to generate and supply electrical energy to consumers.

The Port’s power system design ensures that electrical power is delivered at the load centres in a

reliable and economic manner [22]. The electric power systems are made up of facilities and

equipment that generate, transmit and distribute electrical energy [23]. It is very crucial that a

power system is properly designed; the system must be able to clear faults as reliably as possible

when there is a fault or disturbance on the protected equipment. It must be able to remain inactive

if the protected equipment is in a healthy state or if the fault is not within the zone of protection.

Regardless of how well designed the power system, faults and failures normally occur and these

poses a risk to life and property. Due to great amounts of energy involved, faults represent a threat

to the operation and security of power systems if the faults are not promptly corrected. Power

systems require an auxiliary system that must take corrective actions on the occurrence of a fault.

This auxiliary system is known as protection system [23, 24]. Protection systems are sets of

equipment, schemes and policies dedicated to detect faults in the protected elements of the power

systems, to disconnect the faulted element and to re-establish the service. Power Systems operate

in different operating states, therefore different fault scenarios may occur. Protection systems

must provide different schemes and equipment to detect and react to each one of these fault

scenarios, from the simplest to the most complex and compelling [24]. The protection system

should embody characteristics of reliability, selectivity, stability, speed and sensitivity. A reliable

protection system should be able isolate the fault condition as fast as possible without affecting

the whole protection system [24].

2.5 Zones of Protection

Power systems protection schemes are designed to eliminate electrical equipment damage and

prevent network failure by detecting fault conditions and isolating the failed component without

affecting the entire system [24]. To achieve these functions, the protection is arranged according

to zones and it is important that the zones of protection overlap, to ensure that the entire power

system is protected [22, 24].

Page 24: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

10

Figure 2-1: Division of Power Systems into protection zones [22]

Figure 2-1 shows typical zones of protection for a power system. From this diagram it is evident

that a zone of protection begins at a circuit-interrupting device and all the equipment are included

in the zones for maximum protection under fault conditions. The power systems configuration,

relay characteristics, equipment location determine the zones of protection [24].

Figure 2-2: Overlapping zones of protection systems [22]

Figure 2-2 above shows a typical arrangement of overlapping zones. Circuit breakers and circuit

re-closers need to be included in two overlapping zones of protection for instance a transmission

line circuit breaker would be included in the zone of protection for the bus and the zone for

transmission line. Some components may be included in special overlapping zones of protection

Page 25: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

11

for instance a large generator that is directly connected to a step up transformer may be provided

with a generator differential protective that have a zone of protection that includes the main

generator, the step up transformer and inter-closing bus work [22].

2.6 Requirements of a Protection Scheme

The main important objective of a protection system is to provide isolation of fault/problem area

in the power system quickly as quickly as possible without affecting the rest of the power system.

The purpose of using protection equipment is to minimize the duration of the fault and limiting

the damage and outage time [25]. Protection systems/devices requirements are as follows [22, 25]:

Reliability.

Selectivity.

Stability.

Speed.

Sensitivity.

2.6.1 Reliability

Reliability is the assurance that the protection will perform correctly. The protection system is

required to provide its functions to avoid damage to equipment, people and property [24]. It has

two important aspects i.e. dependability and security. Dependability indicates the ability of the

protection system to perform correctly when required whereas security is the ability to avoid

unnecessary operation during normal day-to-day operation and faults and problems outside the

designated zone of operation [25]. Reliability problems stem from incorrect design, incorrect

installation/ testing and deterioration [24].

2.6.2 Selectivity

Selectivity is the relay coordination. It is the process of applying and setting the protective relays

that overreach other relays such that they operate as fast as possible within their primary zone but

have delayed operation in their backup zone. This is necessary to allow the primary relays

assigned to this backup or overreached area time to operate [25]. In the event of a fault, the

protection scheme is required to trip only those circuit breakers whose operation is required to

isolate the fault. This property of selective tripping is also referred to as discrimination and is

achieved by time grading and unit systems [22]. Protection systems in successive zones are

arranged to operate in times that are graded through the sequence of protection devices so that

only those relevant to the faulty zone complete the tripping function. The speed response is

dependent on the severity of the fault. For clearly defined zone, unit protection systems are

applicable under fault conditions [24].

Page 26: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

12

2.6.3 Stability

Under stability conditions the external conditions outside the zone of protection are not affected

in the event of a fault [24].

2.6.4 Speed

It is very crucial that protection schemes are able to clear a fault as quickly as possible to avoid

equipment damage and loss of power. This ensures continuity of supply as it isolates the faulted

area to avoid affecting the whole power system [24, 25].

2.6.5 Sensitivity

Considering the case of overcurrent protection, the protective system must have the ability to

detect the smallest possible fault current. The smaller the current the protection system can detect,

the more sensitive it is [24]. Highly sensitive relay equipment are extremely reliable for clearing

fault at the right time [24].

2.7 Protective Relaying

The primary objective of all power systems is to maintain a very high level of continuity of service

and when intolerable conditions occur to minimize the outage times. The main function of a relay

is to isolate any elements of a power system from service in the event of a fault or under abnormal

conditions in a power system. [22, 25]. In the event of a fault condition in a power system, the

protection relays sends a trip signal to the circuit breakers to isolate the faulty section as quickly

as possible before it affects the entire system [22, 26].

2.7.1 Relay Operating Principle

According to the authors of [22, 27] power system protection used to be constituted of

electromechanical relays. Due to technological advancement nowadays, these electromechanical

relays are being replaced by digital and microprocessor-based relays or numerical relays.

Numerical relays have better operating speed, better accuracy, fewer maintenance requirements

and better communication facilities for linking to SCADA system. These relays have the ability

to verify, supervise themselves and the entire system connected to it. Mechanical switches for

protection, metering and monitoring can be wired through them for event recording and backup

[27]. Numerical relays are configured using the relay software and by inputting all parameters set

by client and it will be installed, tested and commissioned [27, 28]. Numerical relays accepts

analog inputs and process them electronically to develop a logic output representing a system

quantity and makes a decision resulting in an output signal. Sampling of analog signals and using

Page 27: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

13

an appropriate computer algorithm to create suitable digital representations of the output signals

i.e. power system voltages and currents [29].

Figure 2-3: Functional Block Representing Numerical Relay Configuration [29]

Figure 2-3 shows the functional block representing numerical relay configuration. The current

and voltage signals from the power system are processed by signal conditioners, which consists

of analog circuits such as transducers, and surge suppression circuits. The sampling clock

provides pulses at sampling frequency. A sample-and-hold circuit generally freezes the analog

input signals, in order to achieve simultaneous sampling of all signals regardless of the data

conversion speed of the analog-to-digital converter. The relaying algorithm processes the sampled

data to produce a digital output [29].

2.7.2 The Protection Scheme

Electrical power systems generate power and redistribute the electrical energy to various load

centres. Power systems protection schemes are designed to eliminate and clear faults in the

network as quickly as possible. Their function is also to isolate the faulted area without affecting

the whole power systems [22].

Page 28: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

14

Figure 2-4: Basic Protection Scheme [24]

Figure 2-4 shows the basic protection scheme arrangement, which consists of a voltage

transformer (VT), current transformer (CT), circuit breaker, and a relay. The CT measures the

current on the primary coil and steps it down to lower voltages in the secondary coil making it

more acceptable as input to the relay. The VT is used for voltage measurements and steps it down

making it acceptable as input to the relay. The relay is a decision-making element in the protection

scheme. It is triggered by current and voltage measurements obtained from CT’s and VT’s. The

relay detects an abnormal condition that could potentially endanger the entire power system and

then takes a preventative action [22]. The circuit breaker receives a trip signal from the relay to

take the necessary action required to isolate a fault condition from the system and restore supply

after the fault has been cleared [24].

2.7.3 Overcurrent Relays

An overcurrent is any current, which exceeds the ampere rating of conductors, equipment or

devices under conditions of use. Unless removed in time moderate overcurrent’s quickly overheat

the system components, damaging insulation, conductors and equipment. Types of overcurrent

protection schemes includes directional scheme, non-directional scheme, time grading scheme,

current grading scheme or a combination of time and current grading scheme [31, 32].

Overcurrent relays are used for overcurrent protection. Directional relays are mostly used because

they significantly lower fault-clearing times. Directional relays can be obtained by installing

relays that can differentiate between short circuits in the forward and reverse direction [22].

Overcurrent relays are divided into three types, which are the definite-time overcurrent relay;

instantaneous overcurrent relay and inverse-time relay [26].

2.7.3.1 Definite Time Overcurrent Relay

A definite time overcurrent relay operates after a predetermined time when the current exceeds

its pick-up value. The operating time is constant irrespective of the magnitude of the current above

the pick-up value. The desired definite operating time can be set with the help of an intentional

time delay mechanism provided in the relaying unit [26]. This type of relay is normally used in

Page 29: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

15

situations where the power system fault current varies very widely due to changes in the source

impedance, because there is no relationship between the change in time and the variation of the

fault current [22].

Figure 2-5: Definite time of overcurrent relay [32]

Figure 2-5 shows a definite time of overcurrent relay curve. Two conditions of operation must be

satisfied in this relay i.e. the current must exceed the setting value and the fault must be continuous

at least a time equal to time setting of the relay [32]. The definite time relay has lower operating

times at the lower current values. The current settings in this relay are chosen such that relay does

not operate for the maximum load current in the circuit being protected but does not operate for

a current equal or greater to the minimum expected fault current [22].

2.7.3.2 Instantaneous Overcurrent Relay

An instantaneous overcurrent relay is a relay with no intentional time delay that operates when

input current exceeds a pick-up value. In order to set these relays, pick-up current needs to be

specified and CT ratio needs to be documented. Instantaneous overcurrent relay should complete

their function every time input current exceeds the set point. When setting overcurrent relays it is

necessary to specify pick-up setting and the CT ratio [22].

2.7.3.3 Inverse Overcurrent Relay

An inverse time overcurrent relay operates when the current exceeds its pick-up value. The

operating time depends on the magnitude of the operating current and the operating time decreases

as the current increases [26]. This type of relays are normally used in situations where the

operation of the network includes high-level short-time overloads, magnetising inrush currents at

switch-on may be considerable for several tenths of a second and where relay operation must be

co-ordinated with a large number of fuses. Inverse time overcurrent relays are divided into four

types:

(a) Very inverse overcurrent relay

𝑡 = 𝑇𝑀𝑆 × 13.5

𝐼𝑟−1 (3)

Page 30: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

16

(b) Extremely inverse overcurrent relay

𝑡 = 𝑇𝑀𝑆 × 80

𝐼𝑟2−1

(4)

(c) Standard Inverse Overcurrent Relay

𝑡 = 𝑇𝑀𝑆 × 0.14

𝐼𝑟0.02−1

(5)

(d) Inverse definite minimum time (IDMT) overcurrent relay

Equations (3),(4) and (5) represents the mathematical definition of the curves in Figure 6-2 based

on a common setting current and time multiplier setting of one second [22].

Figure 2-6: IEC 60255 IDMT Relay Characteristics, TMS = 1.0 [22]

The standard inverse (SI) curve indicated in Figure 2-6 is usually appropriate for most

applications. If grading with other protection devices is not adequately achieved, either the very

inverse (VI) or extremely inverse (EI) curves can be applied [22].

2.7.3.4 Very Inverse Time Overcurrent Relay

VI time overcurrent relay is generally employed in cases where the source impedance is much

smaller than the line impedance [33]. According to the authors of [22] the VI operating

characteristic are such that the operating time is approximately doubled for reduction in current

Page 31: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

17

from seven to four times the relay current setting. This allows for the use of the same time

multiplier setting for several relays in series.

2.7.3.5 Extremely Inverse Overcurrent Relay

This relay application is mainly in electrical machines to protect them from overheating and

restoring load after a fault condition occurred. Alternators, power transformers, earthing

transformers, electrical cables and railway trolley wires are protected by the EI overcurrent relays.

Alternators are protected against overloads and internal faults. This relay is also used for reclosing

distribution circuits after a long outage [26].

Page 32: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

18

CHAPTER 3: REVIEW OF THE EXISTING POWER SUPPLY AND

UPGRADE REQUIREMENTS IN THE PORT OF DURBAN

3.1 Introduction

The electrical power supply to Durban Harbour is from EE’s 33 kV Congella and Old Ford Road

substations with 17 MVA capacity limit in each incomer due to infrastructure exceeding its design

lifespan. The 33 kV voltage supply at the intake substations that is Durban Harbour Intake (DHI)

Substation and Stanger Street Substation (STS) is stepped down and redistributed to 11/6.6 kV to

supply Port operations and consumers in the Ports electrical network [7, 34]. The supply 300 mm2

oil cable to STS and DHI were installed and commissioned in the early 1970’s and 2003

respectively. The Port’s historical load profile data revealed that the 17 MVA firm supply limit

was exceeded during the Port’s peak loading intervals in winter months. This compromises the

reliability and firmness of the existing network and increases the likelihood of failure. According

to the Port Master Plan, the Port has expansion plans and future developments that require

additional load demand which is not available in the currently existing network. Electrical

network system improvement that ensures a firm and robust network is required to cater for the

additional load requirements. EE is also phasing out 33 kV as a distribution voltage to large power

users [34, 35].

Figure 3-1: Historical Maximum Demand Load Profile for the Port [35]

Figure 3-1 is a graphical representation of the Port’s historical instantaneous maximum demand

load profile in comparison to the 17 MVA firm supply capacity from EE, which was exceeded

during peak periods. The port network is under strain during the winter months due to high base

loads caused by the refrigerated containers, which are imported/exported through the container

terminals. These high demand peaks have resulted in the PoD reaching the 17 MVA capacity on

the electrical network for extremely short durations of times [35]. An electrical power supply

upgrade in the Port is required to strengthen and improve the electrical network and the proposed

Page 33: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

19

supply capacity from EE is 132 kV at a capacity of 80 MVA from their 132 kV Edwin Swales

substation closest to the Port’s proposed 132 kV outdoor substation site. The electrical upgrade

includes the implementation of SCADA system and SAS for the new substation. This will enable

the monitoring and control of the electrical network. This chapter evaluates the PoD’s existing

SCADA system, SAS and evaluates what considerations need to be taken into account for

undertaking this upgrade [35].

Modern SCADA master stations are equipped with communications architectures that integrates

hardware and software in distributed systems. The real-time data transfer between various

viewing computers and servers is via the control centre’s Local Area Network (LAN) platform.

The SCADA system design in divided into three main components i.e. Master station or Control

centre, Remote Terminal Units (RTUs) and communications. A Master station is for visually

seeing the whole plant and is equipped with features and capabilities to view real-time data, plant

state and perform functions of control and monitoring remote stations [36, 37]. All the acquired

data from the whole system is collected and sent into the control centre for processing to be done.

On completion of data processing, the control centre completes the task of issuing control signals

to the required part of the system [38]. The Master station retrieves data required by substation

equipment from remote station [37]. RTUs are connected physically with equipment such as

switches, circuit breakers, etc. and they monitor and control these devices. The system HMI

enables the user/operator to view the entire plant status through raised alarms and status

indications. Alarms are automatically detected under equipment abnormal conditions that require

operator’s attention to acknowledge and resolve the conditions raising an alarm [38]. Modern

communication protocols provides data integration between master station and remote station.

The designs for SCADA systems should take into account capacity to allow the future automation

of the operation of equipment to allow future substations growth and expansion of the electrical

power system [39].

SASs are required to increase reliability and performance of electrical protection of circuits in

substations, which will improve the efficiency of power distribution [39]. These mainly rely on

automation software integrated via communications architecture to IEDs which receives and

processes signals coming from high voltage equipment [40]. IEDs play a major role in the power

systems protection because of the ability to identify the faulted area or abnormal condition in the

network and isolate it as quickly as possible before any damage to the equipment is incurred [41,

42].

3.2 Supervisory Control and Data Acquisition Systems

SCADA systems functions are to monitor and control remote or geographically dispersed systems

or plants. SCADA systems retrieves and stores data of the status of the entire plant or substation,

indicates and displays areas with abnormalities for the user/operator to take action to normalize

Page 34: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

20

the network [36]. Due to that, electrical systems are growing at a rapid rate with power plants

interconnected with the power system substation. The real-time data obtained from the SCADA

system is essential for the plant operation as the user/operator can easily execute supervisory

commands [37]. It also enables the operator to execute supervisory commands. In order to allow

for future substation growth, expansion and the inclusion of new application functions, SCADA

systems should be designed to have sufficient capacity. This will ensure that there is sufficient

capacity for adding more equipment via the primary feeders in the substation [39]. Modern

communication protocols integrate with IEDs for efficient equipment status monitoring and

control during abnormal fault conditions SCADA systems enables the user/operator to easily

identify the fault location in a complex electrical network, which improves plant productivity and

reduces maintenance costs [36]. SCADA systems consists of the following main components

[43]:

(a) Multiple RTUs, which are numerical relays.

(b) Communication channel infrastructure.

(c) Master station and HMI Computers.

Medium voltage electrical networks, building air-conditioning, standby generators and SMART

energy metering systems are monitored on the SCADA system.

Figure 3-2: Geographically dispersed electrical substations monitored on the PoD’s SCADA

system [44]

The PoD has several 33 kV substations and air conditioning plants that are monitored and

controlled on the SCADA system. Figure 3-2 is a map displaying various substations that are

Page 35: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

21

monitored and controlled on the Port’s SCADA system. The numbers on the map are explained

as follows [44]:

(a) 1 denotes the 6.6 kV Sand Bypass Substation.

(b) 2 denotes Ocean Terminal Building air-conditioning plant.

(c) 3 denotes the 33 kV incomer STS supplied from EE’s Old Fort Road substation.

(d) 4 denotes the 33 kV incomer DHI supplied from EE’s Congella substation

(e) 5 denotes the Port’s 132 kV proposed substation located at Langeberg road.

(f) 6 denotes the 33 kV Pier 2 Substation which supplies the Durban Container terminal

which is the load centre in the Port.

(g) 7 denotes Allan Dalton substation (AD) 33 kV Substation.

(h) 8 denotes Pier 1 33 kV Substation.

(i) 9 denotes the Fynnlands 33 kV Substation.

(j) 10 denotes the Millennium Tower that is utilised to navigate the ships entering the Port.

Figure 3-3: Substation Electrical Network Reticulation [44]

Figure 3-3 represents SCADA view showing 33 kV DHI intake substation electrical network

model with the 17 MVA firm capacity that is stepped down to 6.6 kV and redistributed to various

Port consumers. The real time power factor values, bus bar voltages and currents on each feeder

are displayed. From this, it is easy to identify the status of the network and easily retrieve network

parameters or data. The Operator is able to perform operation functions in this view such as

opening or closing of circuit breakers, applying earths etc. The PoD’s SCADA platform is

ArchestrA systems platform that is mainly used for industrial applications and provides features

for configuration, data deployment, cyber security, communications protocols, data management

Page 36: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

22

and storage. The system platform is equipped with high performance historian process that

archives and keeps records of production history [45].

3.2.1 SCADA Architecture

It is very crucial that the system’s physical architecture is clearly defined. In order to support the

specified functionality it is important that the servers and IEDs are physically connected via

Ethernet platform. The integration of the IEDs into a system architecture is achieved by the

interconnection of IEDs, servers, workstations and communication interfaces [36]. Modern

SCADA systems designs are equipped with communications architectures that enable

interoperability of different system. SCADA systems designs can either Centralized or a

Distributed architecture. The master station is the focal point for SCADA, which performs the

supervisory control and data acquisition as well as display, logging, data processing and archiving

functions used mainly for operations. Master station serves as an information gateway to the

utility enterprise [36]. The SCADA architectures systems are used based on application

requirements and availability objectives [39].

(a) Centralized Architecture: this configuration is for less complex applications, which entail

distribution network monitoring and control functions. In this design configuration, the

operator functions and displays are on redundant hardware platform [36, 39]. Hardware

maintenance is cheaper since there are few computers [36].

(b) Distributed Architecture: this configuration is used in complex applications demanding

more extensive data processing and availability requirements. This configuration utilizes

multiple network servers to allow for redundancy and increase capacity availability for

additional servers. This configuration has the functionality to allow different operating

systems to be used for different applications [36, 39]. The server platform is responsible

for all substation communications functions and all processing functions. In advanced

distributed systems the applications software run on multiple computing platforms [36].

Page 37: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

23

Figure 3-4: PoD's SCADA Architecture [46]

Figure 3-4 shows the ports existing distributed SCADA architecture. Currently there are six

monitoring and control stations i.e. Sand Bypass system, Millennium tower, Alan Dalton

substation, Depot Fynnlands, Ocean terminal building and fire fighting system (CFI). Alan Dalton

is the main viewing and control station that is equipped a galaxy repository (GR) server,

applications object server (AOS - standby) and the historian server. GR is a windows service that

manages the development and deployment of the application. Historian server provides process

data historisation, alarm, and event logging for application server. It exposes the data through

SQL server/ open data interface [39, 46, 47]. The historian client view is a collection of tools to

access the historical data in a historian server. It includes a feature-rich Trend application, a Query

application that allows the construction of SQL queries through a point, click interface, and report

generation through add-ons for Microsoft Excel and Word [39].

Figure 3-5: Overview of the Port’s system architecture [46, 47]

Page 38: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

24

Figure 3-5 represents an integrated Wonderware systems platform architecture, which is via

Ethernet platform. This design configuration allows for electrical network expansion and is

developed and implemented on the ArchestrA software [48].

3.2.2 Communications

Master stations utilize communication protocols to retrieve data from IED, RTUs and Gateways

for data acquisition functions in substations. SCADA systems design primary requirement is the

ability to acquire quality data at a high speed [39]. The PoD’s SCADA system utilises fibre optics

for network communications applications. The main advantage of using fibre optic is its ability

to provide high bandwidth with excellent signal-to-noise ratio (SNR). It is mainly for long

distance applications due to high performance data networking ability and is less susceptible to

electromagnetic fields [49, 50]. The entire LAN in the Port is monitored by the SCADA system.

In the event where there is loss of communication in the network or remote stations, the SCADA

system will not be able to retrieve data from the IEDs in the affected remote stations [44].

Figure 3-6: PoD’s Communication Network for substations [44]

Figure 3-6 represents the PoD’s communication network status for all the substations in the

network. The substations are interconnected via fibre optic cable and network switches. Under

normal operating conditions fibre optic cables and network switches are indicated in green colour

and indicated in red under abnormal conditions when communication is lost. This SCADA view

enables the operator the quickly identify the faulted area in the network and reduces fault finding

duration [44, 45].

3.2.3 Performance

Availability, maintainability, performance, security and expandability are the most important

aspects of SCADA system design.

Page 39: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

25

(a) System Availability: this is measured according to the availability of system functions.

This is purely dependent on the reliability of both the software and hardware. To ensure

high availability and continuity of the system, redundancy is provided. In modern

SCADA systems, most computers are connected to a redundant LAN and in a case where

one computer fails, all communications will switch over to the remaining computer. The

most critical computers are doubled so that in case of hardware or software failure, the

other one will take over the processing [36]. The SCADA software should be able to

operate in different hardware or software platforms to avoid dependency to a specific

manufacturer [39].

(b) System Maintainability: maintainability is a very crucial factor of system availability as

this minimizes repair times for hardware or software failures if the system provides good

diagnostic tools. It is of great importance that preventative maintenance, system

debugging, corrections, updates, tests and enhancements are conducted without affecting

the performance of the system [36].

(c) System Performance: in a SCADA system, the desired response time for each function

should be determined. Response time is the amount of time it takes from the instant a

function is requested until the instant the outputs from this function are available. Power

system operation and control procedures should comply with response times. In a control

centre, response time is categorized into critical and non-critical functions. The operating

conditions for a power system can be in either normal state or emergency state. In a

normal state the power system’s load and operating constraints are satisfied. In this state,

the system’s basic control and performance are met. In an emergency state of a power

system the response time is very slow, operating constraints are not satisfied, status

changes and measurement variations are very high [36].

(d) Expandability: is the ability to add new functions or equipment to the power system and

the amount of down time required without difficulty [39]. The following are

expandability limitations considered [36]:

(a) Available physical space.

(b) Power supply capacity.

(c) Heat dissipation.

(d) Processor throughput and number of processors.

(e) Memory capacity of all types.

(f) Point limits of hardware, software or protocol.

(g) Bus length, loading and traffic.

(h) Limitations on routines, addresses, labels or buffers.

(i) Unacceptable extension of scan times by increased data.

Page 40: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

26

3.2.4 Primary and Backup Systems

It is important that the designed system is equipped with both primary and backup system to

ensure that data is secured in the event of a software or hardware failure to maintain continuity in

the system functions and prevents data loss. The use of multiple servers allows for system

redundancy as one server is in active mode performing all the system functions while others are

running offline as backup. The backup system is equipped with a processor whose function is to

monitor the status of the primary system and quickly assumes this role in the event of a system

failure [39].

3.3 Substation Automation Systems

The IEDs are designed to have multiprocessor functions to send and receive data from other

devices or Master station. The IEDs accepts inputs and processes them using logic systems to

develop outputs addressed to make decisions resulting in a trip command or alarm signal. SAS is

the ability to perform control functions to devices in various areas of a power system in remote

mode [36, 51]. The PoD’s SAS utilises GE Multilin F35 feeder protection relays as a standard

IED which retrieves and displays data of equipment status, active power, bus bar voltages and

currents. These also have internal failure self-monitoring functions.

Figure 3-7: Substation incomer feeder protection relay status [44]

Figure 3-7 is the substation incomer feeder protection relay status SCADA view at DHI 33 kV

substation. The busbar is live with circuit breaker is in its closed state and the earth switch is

opened. The relay values such as the active power, reactive power, bus voltages and currents are

also displayed. [44]. Substation Integration System (SIS) is essential to perform simple or

complex automatic functions in SAS. The integration of SCADA systems and IEDs

communications protocols allows for data acquisition and control [41]. The SAS obtain plant data

that enhances the plant operations, maintenance planning and execution, and system status

monitoring in order to optimise the effective utilisation of the equipment [52].

Page 41: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

27

Substation automation consists of the following main elements [36]:

(a) HMI - this is a hardware interface, which runs software that creates graphics on video

display. SCADA HMI allows operators to view the state of any part of the power systems

plant equipment by means of alarm indicators. Alarm detection occurs under abnormal

conditions in the plant equipment and requires operator’s attention or intervention for the

power system to keep running smoothly [38].

(b) RTU – is equipped with hard-wired inputs or outputs that connects substation equipment

such as IEDs, Ethernet switches etc. for functions of control and monitoring [38]

(c) Data Concentrator – main objective is to retrieve information from all substation IEDs so

that it can be visually displayed on the SCADA system.

(d) Remote Access Controller – this device has a functionality to access the IEDs remotely for

configuration and data retrieval.

(e) SIS – this systems ensures integration between the IEDs, SCADA and local HMI for data

sharing and display for effective running of the plant [48].

3.3.1 Substation Automation Design Requirements

Figure 3-8 shows the four levels to be considered for substation automation design. Level 0

represents the IEDs that need to selected to ensure compliance and compatibility with IEC 61850

standard. Level 1 is consideration for substation LAN platform for data flow. Level 2 is the

substation RTUs interfaced with the SCADA system and physically connects substation devices

for information sharing and storage. Level 3 entails development of the communications

architecture for that to be displayed on the SCADA system [39].

Figure 3-8: Substation Automation Hierarchic Levels [39]

3.3.2 Selection of IEDs

It is of great importance that functional requirements are determined prior the selection of IEDs.

The selected IEDs should be compliant to IEC 61850 standard and possess features of

interoperability with various devices implemented in the communications architecture [36]. The

use of IEDs improves the operation and service of automation systems as they reduce the cost of

Page 42: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

28

automation and integration [36]. For functional requirements, the following have to be

considered:

(a) Effects of equipment maintenance on critical data.

(b) Provision to view I/O value and state.

(c) Provision to view point mapping.

(d) Processing time for the parameters present at IED inputs to be available as parameter

at the communication part. For each equipment item and all applicable data types data

processing capabilities shall be defined.

(e) Ease of automated data retrieval and centralized storage of trends, events, disturbances

and faults for IEDs.

(f) Input power requirements when IED will be placed on the DC system.

The RTUs obtain notifications and real time analog and digital data from the IEDs and stores the

information on the RTU database. This information is therefore processed and sent to the control

centre to be displayed on the SCADA system. RTUs are capable of the following information

related to IEDs [39].

(a) Know each IED address.

(b) Know the alternating communications routes with each IED.

(c) Know which IED can be used to carry out a specific function.

(d) Know the state of all the IEDs connected

(e) To synchronize the time of all the IEDs connected.

(f) To have access to the IEDs sequence of events storage.

3.3.3 Human Machine Interface

A HMI is an interaction between human and a technical process for control purposes. HMI is a

computer based interface that enables the operator to view the entire plant status to perform

operation functions [39, 64]. The HMI provide features that include report generation from any

historical or real-time measurement or status point, log files, links to documentation, help files

that are context sensitive, multiple users, multiple security levels, symbol template, symbol

libraries, multiple protocol support, printing etc. [7].

Page 43: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

29

Figure 3-9: HMI flow diagram [39]

Figure 3-9 shows the flow diagram for human machine power interface. The computer system at

the control centre integrates with RTU over the communication link with its transmission

protocol, acquires the remote substation a data and transfers the same to the computer system

[38]. The PoD’s HMI graphic system is designed to be self-explanatory with clearly written

English language messages indicating the available options within the specific graphic screen to

the operator. All graphic objects are represented in a simple 2–dimensional fashion. Graphic

screens are configured using the following configurations [45]:

(a) Plant overview to assist the operator with an overall understanding of the areas of the

plant that are to be controlled.

(b) Simplified block diagram to illustrate sequences, interactions and selected options.

(c) Diagrammatic representation of the process equipment using predetermined symbols to

represent the various equipment.

(d) Process and instrumentation Diagram (P&ID) using recognized instrumentation and

electrical symbols.

Figure 3-10: Graphic Screen Tree Hierarchy [45]

Page 44: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

30

The plant hierarchical structure is limited to three screen levels as shown in Figure 3-10. Overall

level is the banner, navigation area and process overview screen. Process level is the main process

mimics.

Detail level is the pop-up screens, which consists of the following [44, 45]:

(a) Detailed equipment mimics (zoom).

(b) Initial Starting conditions (if applicable).

(c) Monitor control screens (if applicable).

(d) Alarm display.

(e) Alarm histories – list of previous and active alarms.

(f) Trend displays.

(g) Device detail pop-up screens.

Figure 3-11: Application Graphic Screen Layout [44, 45]

Figure 3-11 shows the application graphic screen layout for the air-conditioning plant in the Port.

This screen is categorised into three sections i.e. Area 1, 2 and 3. Area 1 is for display and general

command buttons, area 2 direct screens request navigation buttons for various control and viewing

stations. Area 3 is the graphical view of the plant model which is a representation of the real life

system [45].

Page 45: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

31

Figure 3-12: Alarm Screen Display [45]

Figure 3-12 shows the alarm pop-up screen display on the PoD’s SCADA view. The alarm screen

displays current active alarms or short-term history alarms. Different filters can be selected for

alarm priorities, acknowledged, unacknowledged or all alarms [45].

3.4 Security requirements

It is essential to have an effective SCADA security system to prevent unauthorised access users

from making any changes to the plant. The design of the Port’s SCADA system i.e. ArchestrA

galaxy security records and audit all the alarms and events that occurred while the user was logged

on to the system. The security requirements that should be considered are the following [43]:

(a) Access Control: for protection from unauthorised users, access to selected devices

and information should be restricted [36, 45]

(b) Use control: control use of selected devices, information or both protect against

unauthorised operation of the device or use of information [36, 45].

(c) Data Integrity: ensure integrity of data on selected communication channels to protect

against unauthorised changes [36, 45].

(d) Data Confidentiality: Ensure the confidentiality of data on selected communication

channels to protect against eavesdropping [36, 45].

Page 46: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

32

(e) Restrict data flow: restrict the flow of data on communication channels to protect

against the publication of information to unauthorised sources [45]

(f) Timely response: respond to security violations by notifying the proper authority,

reporting needed forensic evidence of the violation and automatically taking timely

corrective action in mission critical or safety critical situations [43, 45].

(g) Network availability: ensure the availability of all network resources to protect

against denial of service attacks [36, 45].

Port’s SCADA system security is categorised into six privilege levels [45]:

(a) None: is a default start-up mode that does not have control privileges and is mainly

for only viewing or read only capability [45].

(b) Operator: access, monitors and controls all the areas of the entire plant for daily

system operating functions [45].

(c) Supervisor: is similar to the operator level with additional operating functions that

have restricted access [45].

(d) Maintenance: is similar to functions of operator and supervisor level options, with an

added function to conduct maintenance related options [45].

(e) Specialist: is a privilege level similar to functions of operator supervisor and

maintenance level options, with an added functionality to perform PID settings, set

points and related options [45].

(f) Administrator: is a privilege level that enables the user to access to all levels of the

system, can make changes in the system perform administrator functions [45].

3.5 Electrical Power Supply Identification

In order to prevent uninterrupted loss of power to SCADA equipment in a substation, all

equipment associated with substation automation should be powered from isolated and dedicated

electrical supply circuits. These circuits can either be DC/AC and it is of great importance that

they are isolated from all other facility loads and clearly labelled as critical equipment that should

never be disconnected. DC batteries are used to back-up AC power. Alarming to indicate loss of

either source should be provided by this equipment [36].

3.5.1 Electrical Power

The electrical power interfaces to control and data acquisition equipment shall meet the following

requirements [36]:

(a) The AC source may originate directly from the station source from a regulating/

uninterruptible power supply. AC power sources require being able to operate successfully

over a minimum range of 80% to 110%of rated voltage and frequency.

(b) The nominal AC voltage rating shall be 220 V – 240 V at 50 Hz.

Page 47: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

33

(c) Equipment on DC source shall not sustain damage if the input voltage declines below the

lower limit specified or is reversed in polarity. DC power sources shall be able to

continuously withstand the maximum design voltage.

3.5.2 Redundant Power Sources

Some substation devices are fitted with power supplies that operate nominally from station AC

service but provide internal DC backup supply from the substation DC battery or a dedicated

storage battery. For specifying dedicated batteries, the following considerations should be

specified [36]:

(a) Duration of backup power operation without battery charging i.e. not less than four hours

but not exceed twenty-four hours.

(b) Longevity of the battery sources as estimated by its shelf life on charge.

(c) Temperature range over which the battery will maintain required voltage and current

capabilities.

(d) Replacement interval for backup batteries.

(e) Precautions of possible corrosive material spill/seepage and explosive gas accumulation.

(f) Recovery time of the backup battery after a full discharge.

(g) Alarming for failure of either power supply.

Page 48: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

34

3.6 The integration of 132 kV Substation (Langeberg) into the PoD’s Electrical

Network and SCADA System

Figure 3-13: PoD’s new 132 kV Langeberg Substation Reticulation [7]

Figure 3-13 represents the proposed electrical reticulation network for the new 132 kV Langeberg

Substation supplied from EE’s 132 kV Edwin Swales substation that will be integrated to the

currently existing 33 kV Port electrical network. The electrical reticulation consists of the

following equipment [35, 53]:

(a) 2 x 132 kV, 100 MVA 500 mm2 XLPE aluminium incomer cables rated at 40 kA.

(b) 2 x 80 MVA 132/ 33 kV transformers.

(c) The new 33 kV network will be linked to the ports existing 33 kV network via DHI, Alan

Dalton (AD) and STS substations.

Page 49: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

35

The IEC 61850 standard will be used as a guide to develop the modern SCADA systems and SAS

design which will be equipped with IEDs that will enable effective functionality for power

systems protection, monitoring and control [53, 64].

Figure 3-14: Design Process Steps [55]

Figure 3-14 represents the typical design process steps that are considered when developing the

utility’s specification that incorporates the IEC 61850 standard features [54]. The design process

begins with a clearly explaining the system specification with respect to the IEC 61850 standard.

The selection of the IEDs is done to ensure correct grouping of Logic Nodes (LNs) satisfy

availability and safety criteria. Cost effective communications architecture for integration of IEDs

is designed in accordance to the IEC 61850 standard. The system design functionality allows for

spare capacity for future additional IEDs, features for redundancy and interfacing of IEDs [54,

55]. This design approach is useful for large number of IED types available and allows for easy

configuration [54, 55].

Figure 3-15: Network and protection communications layout for the new 132 kV Langeberg

Substation [53]

Page 50: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

36

Figure 3-15 shows the proposed protection and network layout for the 132 kV Langeberg

substation that will be integrated to the currently existing network.

This layout entails Landis & Gyr (L&G) energy meters for incomers, feeder protection relays and

transformer monitoring units. All these will be connected to the network switch (CISCO 3560)

via Ethernet and be assigned with Internet Protocol (IP) addresses. Communications between

devices in the Ports network will be achieved [53].

Page 51: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

37

CHAPTER 4: RESEARCH METHODOLOGY

4.1 Introduction

This chapter presents the description of the research process. It provides information concerning

the methods used to undertake this research. This chapter describes various stages of the research,

which includes literature review conducted, review of PoD’s power supply and upgrade

requirements, load flow studies conducted, implementation of SCADA and Automation systems.

Furthermore, this chapter entails an overview of the hardware protection relays and their

communication protocols used for protection system implemented. Figure 4-1 shows the block

diagram of the methodological followed to undertake this dissertation.

Figure 4-1: Methodology Block Diagram

Figure 4-1 represents the methodology block diagram that was used in this project. The

preliminary study is the initial stage of the research development and it entails identification of a

research problem, research questions, aims and objectives. Various literatures on load flow

analysis and power systems were reviewed. A review of the PoD’s existing power supply and

upgrade requirements was done in order to identify and analyse the PoD’s Maxim demand, obtain

additional load required by planned development and analysis of the existing SCADA and

Page 52: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

38

Automation system. An electrical load flow study was conducted using PowaMaster software in

order to evaluate the impact of the additional loads on the existing electrical network. Schneider

CitectSCADA software was used to develop a 132/33 kV substation model for monitoring and

control of the electrical network.

4.2 Software

In order to address the research questions discussed in Chapter 1, PowaMaster software was

utilized to undertake the load flow study analysis of the electrical network and Schneider

CitectSCADA software was used to develop a SCADA and Automation System for monitoring

and control of the 132/33 kV substation.

4.2.1 PowaMaster – Electrical Analysis Software for Transmission & Distribution

Systems

PowaMaster is a simulation tool or system that is ideally suited for transmission and distribution

networks, substation design and building services applications. It is a PC based program, which

runs on the Microsoft Windows operating system. It provides features for the modelling of

balanced, meshed electrical networks by representing the electrical network and equipment in an

intuitive user-friendly manner. It also enables the user to model any electrical network easily,

quickly and efficiently.

Figure 4-2: PowaMaster Graphical User Interface

Page 53: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

39

Figure 4-2 represents the PowaMaster Graphical User Interface that provided a canvas on which

the network was designed. The Main Menu consists of all the pull down menus containing every

command required to execute every available function. The Toolbar allowed the user to perform

functions such as invoking the load flow, Fault Calculations and viewing the User Reports. The

network was manipulated by using the Operations Speed Menu and the layout of the network was

manipulated by using the zoom functions. The network elements were placed using the Node

Speed Menu. The Status Bar was constantly monitored to check the next action required.

4.2.1.1 Electrical Load flow Study Process Flow

The PoD’s Planning Department was consulted in order to identify the planned developments and

expansion projects as listed in the Port Electrical Master Plan that required additional loads and

their years of execution. This information was vital because the additional load was going to have

an impact in the Port’s existing electrical network. The information gathered was used to perform

load forecasting which plays a huge role in determining the required future load demand, network

reconfiguration and infrastructure development. The planned developments and expansion plans

require additional load demand which is not available in the currently existing electrical network.

Based on the required load demand requirements equipment selection calculations were done i.e.

Transformers and Cables as explained in detail in Chapter 5.

The PoD receives its Power Supply from EThekwini Municipality at 33 kV via the Port’s two

main intake substations each with a capacity limited to 17 MVA. The PoD’s electrical network

sustains revenue-creating operations; therefore, it is imperative that there is sufficient capacity

and reliability of power supply to the PoD. The Ports’ SCADA and Billing systems were

interrogated in order to obtain information on the Ports yearly Maximum Demand and Load

Profile. From the information gathered it was evident that over the years the load growth in the

Port has been increasing however, the supply capacity was never upgraded resulting in the

existing power supply being under threat. It was evident from the load profile curves that during

winter season the 17 MVA firm capacity was exceeded which compromises the existing network

reliability and firmness.

For system strengthening and enhancement, the Electrical Load Flow Study was conducted using

PowaMaster Software to improve reliability and increase the electrical supply to and within the

port ensuring a firm and reliable electrical network. The load flow study was also to verify if the

selected equipment will be suitable for the projected load growth and that was investigated by

considering six network configuration scenarios. The network configuration scenarios considered

the load forecast for a period of 5 years, 7 years and 10 years as described in Chapter 5. The

behaviour of the PoD’s electrical network was analysed post implementation of the new

Page 54: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

40

substation onto the currently existing network as part of the strengthening option due to planned

development projects that are planned to be commissioned between 2017 and 2027.

4.2.1.2 Electrical Supply Proposed Solution

Figure 4-3 shows the proposed solution high-level block diagram for the new power supply. The

PoD will obtain its 132 kV electricity supply from EThekwini Municipality Edwin Swales

outdoor yard through the 132/33 kV outdoor substation at Langeberg which will be

geographically located at Bayhead along Langeberg Road. With this power, supply arrangement

a firm supply with redundancy will be guaranteed and the supply point will be closer to the major

port loads of Durban Container Terminal and Pier as well as other future developments.

Figure 4-3: Bulk Power Supply Block Diagram- Proposed New Solutions

4.2.1.3 Electrical Network Implementation

Figure 4-4 shows the PoD’s electrical network that was implemented on PowaMaster which

consisted of the two 132 kV 500 mm2 aluminium XLPE incomer feeders at supply capacity of

100 MVA. The 40 kA rated cables will supply 2 × 132 / 33 kV 40 MVA transformers at

Langeberg Substation. The new 33 kV network is integrated to the ports existing 33 kV network

via the main substations in the Port i.e. DHI, AD and STS 33 kV substations.

Page 55: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

41

Figure 4-4: Electrical Reticulation implemented on PowaMaster of the new 132 kV Langeberg

Substation

NR method was used for network analysis. For effective performance of the new Langeberg

132/33 kV substation and the existing substations the busbar, branch or conductor and transformer

results were analysed. Figure 4-5 shows the screenshot of the user report generated on

PowaMaster with the results for busbars, branch, transformers and protection devices that were

analysed.

Figure 4-5: PowaMaster generated User Report

Page 56: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

42

4.2.2 Development of SCADA and SAS using Schneider CitectSCADA Software

In this project there were two SAS designs considered which entailed of Legacy Substation

Automation System design and IEC 61850 Substation Automation design. This consideration was

based on the available devices available at the time at the university. Legacy substation

automation communications protocols and hardware or software architectures provide basic

functionality for power systems automation. Legacy substation automation protocols designs

have technical limitations when compared to IEC 61850 designs. Over the years, technology has

evolved and there were major improvements in the power systems automation in substations from

a networking technology perspective. The latest developments in networking entail high-speed

Wide Area Network, redundant Ethernet, TCP/IP technology, high-performance embedded

processors that have improved the capabilities of the legacy substation automation protocols. The

Legacy substation automation system design was equipped with Modbus, Distributed Network

Protocol (DNP3) and IEC 60870 communication protocols, which are vendor dependent and

cannot be adopted as a complex solution [56]. These communication protocols operates at the

electronic utility level. Modbus protocol supports serial communication, optical or radio

networks, RS-232, RS-422, RS-484 serial communication or the TCCP/IP enhancements.

Modbus is mainly suitable for serial communication and is not optimized for communication over

Ethernet [64]. DNP3 is a set of communication protocols used for the interconnection of

automation systems. It is mainly used within the SCADA system and IEDs. IEC 60870 is for

communication between master stations and remote units.

IEC 61850 substation automation design provides the capability of interoperability between the

IEDs for protection, monitoring, control and automation in substations. The IEC 61850 substation

automation architecture consists of three levels i.e. Station level, Bay level and Process level.

Station level consists of the HMI and gateways to communicate with remote control centre and

integrate IEDs at bay level to the substation level. It also performs different process related

functions such as implementation of control commands for the process equipment by analysing

data from bay level IEDs. In the bay level, the process level equipment’s are connected to station

bus via IEDs at the bay level that implement monitoring, protection, control and recording

functions. Process level includes switchyard equipment, sensors and actuators. The current and

potential transformers are located at the process level to collect system data and send them to bay

level devices for automatic control and protection operations, which are achieved through circuit

breakers and remotely operated switches.

IEC 61850 communication and data transfers is via serial and modern computer networks

technologies using TCP/IP model and Ethernet encapsulation techniques [57, 58, 59].

Page 57: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

43

Figure 4-6: A combination of Legacy and IEC 61850 Automation System Design

Figure 4-6 above shows the automation system with a combination of legacy design and IEC

61850 design that was used in this project. The data transfer between the two system designs is

achieved by the RTU device in between the two systems, which functions as both IEC 61850

server and client. The RTU is designed to integrate the latest IEC 61850 technologies with legacy

technologies using configuration tools to convert protocols and create object models.

4.2.2.1 Electrical Substation Model development on CitectSCADA Platform

An automatic and interactive electrical substation model representing the physical system was

developed on the Schneider CitectSCADA platform, which was installed on the host laptop. For

data flow from IEDs to host laptop the RTU was connected to host laptop through Ethernet switch.

The RTU stored the information, variables and commands of the developed substation. The

CitectSCADA Project Editor Configuration tool was used to define and configure the substation

system components, tags, alarms and communication components. The CitectSCADA Graphics

Builder Configuration tool was used to design the graphical components of the substation. The

substation consisted of two 132 kV incomers from EE, two 132/33 kV 40 MVA transformers, a

connecting bus section on the 33 kV bus, six outgoing feeders with three on either side of the bus

section. Each incomer and feeder was equipped with isolators, circuit breakers and earth switches.

This model was equipped with control points for the operation of the circuit breakers and isolators,

visual indications of the status of switchgear modes of operation, current readings, alarms, alerts

and warnings under network fault conditions. The information communication, commands and

signals between different devices was established through IEC 61850, Modbus RTU and DNP3

protocols as per developed communications architecture explained in Chapter 6. This

communications architecture was implemented to control the operation, automation and provide

protection to the substation model equipment and switchgear.

Page 58: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

44

4.2.2.2 Testing of the implemented Electrical Substation Model

The circuit breakers and isolators basic operation i.e. Open/Close functions were tested by

clicking the created symbols on the graphics page in order to prove their practical operational

functionality. The supervisory features displayed the status alerts and visual indications of

operation for circuit breakers or isolators. The status condition was also displayed on the IEDs

HMI screen to notify the operator/user of the network status. In order to investigate the operational

effectiveness of the substation model and capturing of graphical, numeral and visual results the

system was tested under fault conditions. This was achieved using VAMPSET software to inject

current to the protection relay or IED and the triggered fault condition displayed on the SCADA

model and IED HMI display screen.

4.3 Analysis Summary

Chapter 4 outlines the methods used in order to meet the PoD’s existing power supply upgrade

requirements to ensure the firmness and availability of power supply in the Port. PowaMaster

Software was used to undertake an electrical network study analyse the prospective behaviour of

PoD’s electrical network post implementation of the new 132/33 kV substation on to the currently

existing network as part of strengthening due to the planned infrastructure development projects.

The results from this study were obtained from PowaMaster User Report, which entailed results

for transformers, conductors and all buses in the network.

The SCADA and Substation Automation system was development using Schneider

CitectSCADA software for monitoring and control of the new substation, which entailed

equipment operation, alarming and trend analysis. The implemented automation system design

was a combination of legacy design and IEC 61850 design. The implemented network model was

tested for effective operation under various fault conditions and the results were captured from

alerts, alarms, process analyst i.e. trends, SCADA model visual aids and connected IEDs HMI

display screens.

Page 59: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

45

CHAPTER 5: ELECTRICAL LOAD FLOW ANALYSIS

5.1 Introduction

This chapter entails the results of the electrical load flow study that was conducted to analyse the

voltage stability and system reliability of the PoD’s electrical network in conjunction with new

132/33 kV Langeberg Substation. The load flow analysis is based on the projected load growth

in the Port and it is in line with the statutory and regulatory requirements of SANS 10142-2 and

NRS048. The load flow study was also used to validate if all the new selected reticulation cables

and transformers as part of the design have been correctly sized and will be able to operate reliably

and without compromising security of firm supply with the implementation of all planned future

loads.

5.2 Port Historical Load Data

In order to correctly forecast the PoD’s electrical growth, in alignment with the planned

infrastructure development plans, it was of great importance to understand the historical and

current electrical demand at the port. This analysis was used to provide the basis for determining

the potential constraints on the electrical network because of project implementation and further

provide guidance on network strengthening options.

The TNPA’s energy metering database was interrogated to obtain metering values i.e. Maximum

demand. Table 5-1 below shows the summary of the total Port’s loading that was derived by the

vectorial addition of the loading at the two main incomer substations i.e. 33 kV STS and 33 kV

DHI substations. Metering data from January 2012 to October 2018 was included in this analysis.

This data was used to examine Port’s electrical load profile over the years. Figure 5-1 shows the

graphical representation of the Port’s yearly load profiles from 2012 to 2018.

Table 5-1: Summary of total port load at 33 kV STS and 33 kV DHI substation incomers

Months 2012 2013 2014 2015 2016 2017 2018

Ma

xim

um

Dem

an

ds

(kV

A)

January 9 177 7 663 9 478 8 532 8 698 8 935 8 946

February 8 251 11 061 8 302 8 753 8 724 8 405 8 730

March 8 210 12 329 8 340 8 825 8 899 9 528 9 432

April 8 304 11 251 8 184 9 187 8 700 8 702 10 350

May 9 252 10 831 9 996 9 672 10 122 10 711 11 178

June 11 061 12 329 12 084 11 688 10 876 12 770 13 527

July 12 329 11 251 14 654 12 530 12 211 13 234 13 824

August 11 251 14 630 12 481 13 471 13 404 12 624 15 093

September 10 831 12 228 11 020 11 104 11 196 12534 12 978

October 8 578 10 726 8 093 8 578 8 834 8901 11187

Page 60: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

46

November 7 980 10 771 7 867 7 870 8 958 10469

December 7 457 11 220 8 140 8 232 8 959 10917

Average 9.39 11 10 10 10 11 12

Figure 5-1: Port historical load from 2013 to 2018

5.3 Projected Infrastructure Developments

The PoD has various expansion projects listed in the corporate plan for the near future. These

projects will have significant impact on the electrical demand and are tabulated in Table 5-2

below. The load forecast was achieved by estimating the load added to the electrical network for

each year from 2018 to 2027. The most dominant projects, which will results in major increase in

electrical power, are the Berth Deepening and Pier 1 Salisbury Island projects. The load

forecasting was performed using the diversity factor considering current port operations.

Table 5-2: Planned Future projects with their estimated loads and planned commissioning year

Figure 5-2 shows the forecasted port load from 2016 to 2028. The current firm supply limit as

obtained from the supply authority is limited to 17 MVA as shown on the graph. The thermal

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Max

imu

m D

em

and

(kV

A)

Months

Yearly Load Profiles

2012

2013

2014

2015

2016

2017

2018

Project Name Load Requirements Planned

Commissioning Year

CFI Island View fire fighting

Infrastructure upgrade ± 5MVA 2021

CFI Berth 9 firefighting installation ± 2 MVA 2022

Dry Dock upgrade and new

equipment additional load that will

be connected

± 2 - 4 MVA 2024

Page 61: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

47

limit of 34 MVA as shown in the graph represents the current Port’s maximum demand when

both incomers supply the port without redundancy. The graph also shows the projected maximum

demand growth as per implementation of projects listed in Table 5-2. It is evident from the graph

that the load increases gradually over the years and remains constant at 58 MVA when the

execution of all the planned projects is completed.

Figure 5-2: Projected electrical load demand in line with the port infrastructure development

plan

5.4 Modelling and Load Flow Study

In performing the electrical load flow study, load diversification is one of the critical input

parameters because it is a true representation of the network behaviour. Another option is to

simulate with a diversity factor of 1 i.e. no diversity, which simulates the maximum theoretical

loading of the network. Since it is almost impossible for all the port loads to peak at the same

time, diversification have been applied to different port network points as per the SCADA logged

data. Equation (1) below was used to calculate the diversity factor in each substation in the

electrical network.

𝐷𝑖𝑣𝑒𝑟𝑠𝑖𝑡𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 =𝐼𝑛𝑠𝑡𝑎𝑙𝑙𝑒𝑑 𝐿𝑜𝑎𝑑

𝑅𝑢𝑛𝑛𝑖𝑛𝑔 𝐿𝑜𝑎𝑑 (1)

The raw data collected from SCADA is included in Annexure A.

PowaMaster Simulation tool was used to perform the load flow study. It is a simulation tool used

for electrical analysis of transmission and distribution systems. It caters for the modelling of

10 12

2227

39

4953 55

58

17

34

0

10

20

30

40

50

60

70

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

20

28M

axim

um

De

man

d (

MV

A)

YEARS

Projected Maximum Demand & Network Limitations

Projected Maximum Demand (MVA) Firm Supply Limit Thermal Limit

Berth Deepening including TPT

equipment upgrade and additions

(dependent on terminal operations)

± 38 – 40 MVA (Dependant on

terminal operations) 2020 -2024

Pier 1 Salisbury Island Infill

(Commissioned in phases)

± 5 – 20 MVA (dependent on

terminal operations) 2025 -2027

Ambrose Park Developments ± 20 MVA 2023

Page 62: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

48

meshed electrical networks by representing the electrical network and equipment in a user-

friendly manner. It also enables the user to easily model any electrical network quickly and

effectively. PowaMaster Simulation tool uses co-incidence factor instead of diversity factor and

equation (2) below was used to calculate this factor.

𝐶𝑜𝑖𝑛𝑐𝑖𝑑𝑒𝑛𝑐𝑒 𝐹𝑎𝑐𝑡𝑜𝑟 = 𝑅𝑢𝑛𝑛𝑖𝑛𝑔 𝐿𝑜𝑎𝑑

𝐼𝑛𝑠𝑡𝑎𝑙𝑙𝑒𝑑 𝐿𝑜𝑎𝑑=

1

𝐷𝑖𝑣𝑒𝑟𝑠𝑖𝑡𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 (2)

Table 5-3: Diversity Factor and Coincidence Factor Applied at Various Substation and

Minisubstations

Substation / Network Point Diversity Factor Coincidence Factor

DHI 33 kV LHS OF BUS 4.56 0.22

DHI 33 kV RHS OF BUS 4.60 0.218

STS 33 kV LHS OF BUS 7.97 0.13

STS 33 kV RHS OF BUS 6.35 0.157

AD 33 kV LHS OF BUS 5.62 0.178

AD 33 kV RHS OF BUS 13 0.077

1MVA School of Ports Mini Sub 5.62 0.178

1 MVA Tank Washout Mini Sub 2.49 0.40

1 MVA Bayhead Mini Sub 2.08 0.48

500 kVA Pollution Control Mini

Sub 2.17 0.46

500 kVA King Rest Mini Sub 1 2.23 0.448

1 MVA King Rest Mini Sub 2 1.37 0.73

1 MVA King Rest Mini Sub 3 1.30 0.766

The following were analysed to study the network performance of the new Langeberg 132/33 kV

substation and the currently existing substations:

Bus voltages are maintained within acceptable operating limits.

Branch power factor.

Current flow throughout the system.

Power flow throughout the system.

Equipment is not overloaded.

NRS 048-2:2003 Electricity Supply – Quality of Supply: Voltage characteristics, compatibility

levels, limits and assessment methods specification states that the maximum voltage deviation

shall not be greater than specified in Tables 5-4 and 5-5.

Table 5-4: Maximum Deviation from standard or declared Voltages

Voltage Level (V) Limit Percentage (%)

<500 V ±5

Page 63: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

49

≥500 V ±10

Table 5-5: Maximum voltages for supplies to customers above 500 V

Nominal Voltage kV Maximum Voltage kV

400 420

275 300

220 245

132 145

88 100

66 72.5

44 and below Nominal voltage +10%

It is of great importance that the voltage is within the specified limits to avoid interruptions in the

electrical network. It can be observed that in all the scenarios considered in the load flow study

conducted, the voltage levels in all the bus-bars is within acceptable limits under normal load

conditions.

5.4.1 Load Flow Scenario Analysis

It is evident from the planned projects listed in Table 5-2 that the projected load growth in the

Port is over three periods i.e. 5 years’ time for projects implemented as from 2018 to 2022. 7

years’ time for projects implemented as from 2018 to 2024 and final load growth will be in 10

years when all the implementation of projects is complete in 2027. From this, it is evident that

the load growth pattern is over 5 years, 7 years and 10 years from 2018, therefore the load flow

study forecast chosen periods were 5 years, 7 years and 10 years. There were six (6) scenarios

considered for the selected periods. The electrical network is designed in a ring feed system as a

result the whole network can be supplied from either one (1) 132/33 kV 40 MVA transformer

with the bus section closed at 33 kV or from two (2) 132/33 kV 40 MVA transformer with the

bus section open at 33 kV. This design ensures continuity of supply in case one transformer is

faulty or unable to supply the Port. Therefore, it was of great importance to investigate the stability

and reliability of the network for both feeding arrangements in each selected period.

Table 5-6 and Table 5-7 below represents the details of the selected transformers and cables for

the new 132/33/11kV Langeberg Substation respectively. The selection of the transformers and

cables took into consideration the projected load growth over a period of 10 years. In order to

select the appropriate cable, equation (3) below was used to determine full load current. With

reference to equipment datasheet in Appendix B and SANS 97. The calculated full load current

was then used to select the appropriate type and size cable that is capable to withstand. The VD

over the length of the selected cable was also determined using equation (4) with some parameters

Page 64: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

50

obtained from the manufacturer’s datasheet in Appendix B. According to SANS 10142-2 the

maximum allowable VD on the cable should be ±5%. The obtained transformer and cable

parameters were used in the electrical network implemented to perform load flow analyses on

PowerSmart Software.

𝐹𝑢𝑙𝑙 𝐿𝑜𝑎𝑑 𝐶𝑢𝑟𝑟𝑒𝑛𝑡 (𝐼𝐹𝐿) = 𝑘𝑉𝐴 ×1000

√3×𝑉×𝐶𝑜𝑠∅ (3)

𝑉𝑜𝑙𝑡𝑎𝑔𝑒 𝐷𝑟𝑜𝑝 = 𝑚𝑝𝑒𝑑𝑎𝑛𝑐𝑒 (Ω

𝑘𝑚) × 𝐶𝑎𝑏𝑙𝑒 𝐿𝑒𝑛𝑔𝑡ℎ (𝑘𝑚) × 𝐼𝐹𝐿(𝐴) (4)

Table 5-6: Details of the Selected Transformers for the new 132/ 33/ 11 kV Langeberg Substation

Name Description of Transformer Ratings Transformer

Impedance (Z%) Current Rating (A)

Trfr 1 40MVA 132kV/33kV 10.1 699.82

Trfr 2 40MVA 132kV/33kV 10.1 699.82

Trfr 3 10MVA 33kV/11kV 8.1 524.86

Trfr 4 10MVA 33kV/11kV 8.1 524.86

Table 5-7: Details of the Selected C for the new 132/ 33/ 11 kV Langeberg Substation

From Bus Name

To Bus Name

Cable Description Total Length (km)

Branch Current Rating

(A)

132 kV_1 132 kV_2 132 kV 500 mm2 Al XLPE 1Core 2.5 581

132 kV_1 132 kV_3 132 kV 500 mm2 Al XLPE 1Core 2.5 581

33 kV_1 33 kV_3 33 kV 630 mm2 Cu XLPE 1Core 0.5 684

33 kV_2 33 kV_4 33 kV 630 mm2 Cu XLPE 1Core 0.5 684

Scenario 1:

A load flow study analysis was conducted with the new 132/33 kV Langeberg substation

implemented into the existing electrical network. The load flow analysis was based on a 5 year

(2018 -2022) load projection, which is due to Port Developments as listed in Table 5-2 whereby

an additional load from the CFI Island View fire fighting infrastructure upgrade and Berth

Deepening upgrade were added to the electrical network. This scenario was performed with 2 x

40 MVA 132/33 kV transformers in operation with the bus section open at 132/33 kV main

Langeberg substation.

Scenario 2:

A load flow study analysis was conducted with the new 132/33 kV Langeberg substation

implemented into the existing electrical network. The load flow analysis was based on a 5 year

(2018 -2022) load projection, which is due to Port Developments as listed in Table 5-2 whereby

an additional load from CFI Island View fire fighting infrastructure upgrade and Berth Deepening

upgrade were added in the electrical network. This scenario was performed with 1 x 40 MVA

Page 65: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

51

132/33 kV transformer in operation with the bus section closed at 132/33 kV main Langeberg

substation.

Scenario 3:

A load flow study analysis was conducted with the new 132/33 kV Langeberg substation

implemented in to the existing electrical network. The load flow analysis was based on a 7 year

(2018 -2024) load projection, which is due to Port Developments as listed in Table 5-2 whereby

an additional load from CFI Island View fire fighting infrastructure upgrade, Berth Deepening

upgrade and Ambrose park developments were added in the electrical network. This scenario was

performed with 2 x 40 MVA 132/33 kV transformers in operation with the bus section open at

132/33 kV main Langeberg substation.

Scenario 4:

A load flow study analysis was conducted with the new 132/33 kV Langeberg substation

implemented in to the existing electrical network. The load flow analysis was based on a 7 year

(2018 – 2024) load projection, which is due to Port Developments as listed in Table 5-2 whereby

an additional load from CFI Island View fire fighting infrastructure upgrade, Berth Deepening

upgrade and Ambrose park developments were added in the electrical network. This scenario was

performed with 1 x 40 MVA 132/33 kV transformer in operation with the bus section closed at

132/33 kV main Langeberg substation.

Scenario 5:

A load flow study analysis was conducted with the new 132/33 kV Langeberg substation

implemented in to the existing electrical network. The load flow analysis was based on a 10 year

(2018 – 2027) load projection which is due to Port Developments as listed in Table 5-2 whereby

an additional load from CFI Island View fire fighting infrastructure upgrade, Berth Deepening

upgrade, Ambrose park upgrade developments and Pier Infill upgrade (all projected loads

implemented in the electrical network) were added in the electrical network. This scenario was

performed with 2 x 40 MVA 132/33 kV transformers in operation with the bus section open at

132/33 kV main Langeberg substation.

Scenario 6:

A load flow study analysis was conducted with the new 132/33 kV Langeberg substation

implemented in to the existing electrical network. The load flow analysis was based on a 10 year

(2018 – 2027) load projection, which is due to Port Developments as listed in Table 5-2. These

included an additional load from CFI Island View fire fighting infrastructure upgrade, Berth

Deepening upgrade, Ambrose park developments and Pier Infill upgrade (all projected loads

Page 66: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

52

implemented in the electrical network) were added in the electrical network. This scenario was

performed with 1 x 40 MVA 132/33 kV transformer in operation with the bus section closed at

132/33 kV main Langeberg substation.

5.5 Load Flow Study Results

PowaMaster Software was used as a simulation tool to implement the PoD’s electrical network

that entails of new and existing substations and minisubstations. Annexure C shows the

implemented electrical network showing the new 132/33 kV Langeberg substation, 33/11 kV

Langeberg substation, the existing 33 kV STS substation, 33 kV DHI substation and 33 kV AD

substation. The minisubstations implemented included 11/0.4 kV 500 kVA Kingrest 1, 11/0.4 kV

1 MVA Kingrest 2, 11/0.4 kV 1 MVA Kingrest 3, 11/0.4 kV 500 kVA Pollution control, 11/0.4

kV 1 MVA Tank Washout, 11/0.4 kV 1 MVA School of ports and 11/0.4 kV 1 MVA Bayhead.

5.5.1 Analysis and Discussion of Results for Scenario 1, 3 and 5

Figure 5-3: Port Load Growth for Scenarios 1, 3 and 5

Figure 5-3 illustrated the results of the port load growth on the main 132 kV incomer bus, left and

right hand side 132 kV bus as well as the main 33 kV left and right buses. The graphical

representation shows the port load growth in each bus represented over a period of 5 years, 7

years and 10 years. From these results, it is evident that there is exponential load growth in each

bus. The main 132 KV incomer bus shows the overall total port load, which will be 42. 66 MVA

in the next 10 years.

42655.65

19178.4724135.04

19074.0823850.97

0.005000.00

10000.0015000.0020000.0025000.0030000.0035000.0040000.0045000.00

132kV_1_MainIncomer Bus

132kV_2_LHS

Bus

132kV_3_RHS

Bus

33 kV_3_LHSBus

33 kV_4_RHSBus

Max

imu

m D

em

and

(kV

A)

Bus Name

Bus Load (S)5 YR FORECAST

Bus Load (S)7 YR FORECAST

Bus Load (S)10 YR FORECAST

Page 67: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

53

Figure 5-4: Voltage Levels at 132 kV and 33 kV for Scenarios 1, 3 and 5

Figure 5-4 is graphical representation of voltage levels at the main 132 kV incomer, left and right

33 kV buses, main left and right 33 kV buses. It can be observed that post implementation of all

the loads, the network will behave as expected since all the voltages are within acceptable limits

as per NRS 048 in Table 5-4 and Table 5-5 and SANS 10142.

Figure 5-5: Conductor Percentage Loading - Main left and right 132 kV buses and main left and

right 33 kV for Scenarios 1, 3 and 5

Figure 5-5 represents the percentage loading for the main 132 kV and 33 kV cables conductors

selected. Despite the year on year load growth the selected conductors will still have sufficient

capacity to carry the Port load.

0.97

0.98

0.99

1.00

1.01

1.02

1.03

1.04

1.05

132 kV_1_MainIncomer Bus

132 kV_2_LHSBus

33 kV_3_LHS Bus 33 kV_4_RHSBus

Vo

ltag

e (

PU

)

Bus Name

Voltage_5 YR FORECAST Voltage_7 YR FORECAST

Voltage_10 YR FORECAST

14.217.91

46.61

58.68

0

10

20

30

40

50

60

70

132 kV_500 mm^2 AlXLPE_1

132 kV_500 mm^2 AlXLPE_2

33 kV_630 mm^2 CuXLPE_1

33 kV_630 mm^2 CuXLPE_2

Co

nd

uct

or

Lo

adin

g (%

)

Conductor Name

5 YR FORECAST 7 YR FORECAST 10 YR FORECAST

Page 68: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

54

Figure 5-6: 132 kV Main Transformer Percentage Loading for Scenarios 1, 3 and 5

Figure 5-6 represents the percentage loading of the two main incomer 132 kV 40 MVA

transformers. It is clear that even after 10 years load forecast implementation these transformers

will still be able to carry the total Port load, as these will still have sufficient spare capacity.

5.5.2 Analysis and Discussion of Results for Scenario 2, 4 and 6

Figure 5-7: Port Load Growth for Scenarios 2, 4 and 6

Figure 5-7 shows the Port load growth for scenarios 2, 4 and 6 when one main 132 kV 40 MVA

incomer transformer was in operation. The load growth shown is for 132 kV main incomer bus,

left and right intake132 kV buses as well the left and right main 33 kV buses. It is evident that the

total Port Load after 10 years when all the planned developments are implemented will be

approximately 60 MVA.

39.98

50.32

0

10

20

30

40

50

60

40 MVA 132/33 kV_1 40 MVA 132/33 kV_2

Traf

orm

er

Load

ing

(%)

Transformer Name

5 YR FORECAST 7 YR FORECAST 10 YR FORECAST

59899.88 60202.91

25759.1231701.47

0.00

10000.00

20000.00

30000.00

40000.00

50000.00

60000.00

70000.00

132 kV_1_MainIncomer Bus

132 kV_2_LHS Bus 33 kV_3_LHS Bus 33 kV_4_RHS Bus

Max

imu

m D

em

and

(kV

A)

Bus Name

Bus Load (S)5 YR FORECAST

Bus Load (S)7 YR FORECAST

Bus Load (S)10 YR FORECAST

Page 69: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

55

Figure 5-8: Voltage Levels at 132 kV and 33 kV for Scenarios 2, 4 and 6

Figure 5-8 is graphical representation of voltage levels at the main 132 kV incomer, left and right

33 kV buses, main left and right 33 kV buses when scenarios 2, 4 and 6 was simulated. Even in

this supply configuration, the voltage acceptable limits as stipulated by NRS 048 in Table 5-4 and

Table 5-5 and SANS 10142 are within acceptable range.

Figure 5-9: Percentage Loading for Main 132 kV and 33 kV Conductors when scenarios 2, 4

and 6 were implemented

The percentage loading for 1 x 132 kV 500 mm2 Al XLPE conductor and 2 x 33 kV 630 mm2 Cu

XLPE conductors is shown in figure 5-9. It is evident the selected cables will still be able to

withstand the total Port load as these still have spare capacity post implementation of all the

projected loads.

0.97

0.98

0.99

1.00

1.01

1.02

1.03

1.04

1.05

132 kV_1_MainIncomer Bus

132 kV_2_LHS Bus 33 kV_3_LHS Bus 33 kV_4_RHS Bus

Vo

ltag

e (

PU

)

Bus Name

Voltage_5 YR FORECAST Voltage_7 YR FORECAST Voltage_10 YR FORECAST

45.09

63.1

77.75

0

10

20

30

40

50

60

70

80

90

132 kV_500 mm^2 AlXLPE_1

33 kV_630 mm^2 CuXLPE_1

33 kV_630 mm^2 CuXLPE_2

Co

nd

uct

or

Load

ing

(%)

Conductor Name

5 YR FORECAST 7 YR FORECAST 10 YR FORECAST

Page 70: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

56

Figure 5-10: 132 kV Main Transformer Percentage Loading for Scenarios 2, 4 and 6

The implementation of scenario 2, 4 and 6 the load flow analysis was implemented with one

incomer 132 kV 40 MVA transformer in operation. Figure 5-10 shows the results of the

percentage loading of this transformer and it evident that with the exponential load growth over

the years this transformer will be overloaded by approximately 25%. This means that this

transformer on its own will not be sufficient to carry the total Port load.

5.6 Conclusion

The primary objective of Chapter 5 was to conduct a load flow study to analyse voltage profile,

system reliability of the new 132/33 kV PoD Substation in accordance to the statutory

requirements of NRS 048 and SAN 10142-2. The study also analysed the behaviour of PoD’s

electrical network post implementation of the new substation onto the currently existing network

as part of the strengthening option due to planned development projects, which are planned to be

commissioned between 2017 and 2027. It was also to validate if all the new selected reticulation

cables and transformers as part of the design have been correctly sized and will be able to operate

reliably without compromising security of firm supply with the implementation of all planned

future loads. After implementation of all the planned projects by the year 2027 when the supply

is sourced by one 132/33 kV 40 MVA as per scenarios 2, 4 and 6. The transformer will not be

able to withstand the total Port load since loading becomes 125%, which is an overload. However

when the supply is sourced via by two 132/33 kV transformers as per scenarios 1, 3 and 5, the

transformer loading becomes 39.98% and 50.38% respectively and both transformers have a spare

capacity. This transformer configuration allows for full redundancy and reliability of the network.

The selected incoming cables for all scenarios considered, will be sufficient to carry total Port

loads without compromising the reliably and stability of the PoD’s electrical network. All

voltages are within acceptable limits as required by NRS 048 and SANS 10142-2.

125.75

0

20

40

60

80

100

120

140

40 MVA 132/33 kV_1

Tran

sfo

rme

r Lo

adin

g (%

)

Transformer Name

5 YR FORECAST 7 YR FORECAST 10 YR FORECAST

Page 71: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

57

CHAPTER 6: DEVELOPMENT OF SCADA AND SAS FOR PORT

OF DURBAN’S 132/ 33 kV SUBSTATION POWER SUPPLY

UPGRADE

6.1 CitectSCADA System Development

SCADA system is a basic infrastructure of modern power systems. SCADA remote monitoring

and control system is essential to provide a fast fault restoration with minimum cost and shorter

time consuming. Substation Automation is a system that enables remote monitoring, control and

coordinate the distribution components installed in the substation. Substation SCADA and

automation systems provides protection, control, automation, monitoring and communication

capabilities as part of a comprehensive substation control and monitoring solution [60, 61, 62].

IEDs provides interoperability and advanced communications capabilities in substation

protection, coordination, control, monitoring and testing. Modern substation SCADA and

automation systems utilizes data from IEDs, control and automation capabilities within the

substation and control commands from remote users to control and operate power system devices.

The integration of IEDs, Ethernet LAN, communications protocols, communications methods,

make the whole substation a functional system with the combination of the correct physical or

virtual connections, common communication protocols, shared storage and sequential or

combination logic for coordinated monitoring, protection and control [62, 63].

Schneider CitectSCADA is a reliable, flexible and high performance SCADA software solution

for industrial processes. CitectSCADA platform was used to develop the substation automation

visualisation system for this project. An automatic and interactive SCADA model of the physical

power systems electrical reticulation network was developed to allow for remote monitoring and

control of key system parameters.

Page 72: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

58

6.1.1 SCADA Communications Architecture

Figure 6-1: Electrical Substation SCADA Model with Protection Devices

Figure 6-1 shows the 132/33 kV electrical substation network that was implemented on the

CitectSCADA software with the protection devices monitored by the SCADA system. The IEDs

used in the project were donated by the manufacturer to the University. These IEDs consisted of

MiCOM P122 relay, VAMP 255/259 relays and GE F35 feeder management relay.

Communication between the SCADA system and these devices was achieved through a

communication architecture implemented as shown in Figure 6-2. These relays provided the

user/operator with the ability to view status indication as well as fault conditions of the circuit

breaker, isolator and earth switch in question as displayed in the relay built-in HMI and as well

as in the SCADA system runtime.

Page 73: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

59

Figure 6-2: SCADA Communications Architecture

Figure 6-2 shows the simplified field SCADA system communications architecture that was

implemented in this project. This architecture is a combination of both legacy and IEC 61850

technologies and these were configured and integrated for monitoring and control of the

implemented substation electrical network.

The SCADA system consists of a number of different devices communicating with each other.

This SCADA system consists of the following devices:

IEC 61850 Client – This entails of the HMI or SCADA system accessing data from

MiCOM C264.

MiCOM C264 RTU – Accesses data from IEC 61850, IEC 60870-5-103, Modbus RTU

and DNP3 devices.

IEC 61850 Ethernet Switch – The Moxa PowerTrans PT-7728 series.

IEC 61850 IEDs – VAMP 255, VAMP 259 & GE F35 Relays.

IEC 60870-5-103, Modbus RTU & DNP3 Legacy IED – MiCOM P122

The communication channels entails the following cases of data flow:

Data flow from IEC 61850 IEDs to IEC 61850 client - MiCOM C264 RTU accesses data

from IEC 61850 IED’s i.e. VAMP 255, VAMP 259 & GE F35 feeder management relays

then HMI or SCADA systems accesses data from the MiCOM C264 RTU and displays

it.

Page 74: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

60

IEC 60870-5-103, Modbus RTU & DNP3 Legacy IED to IEC 61850 client – MiCOM

C264 RTU accesses data from legacy IEDs i.e. MiCOM P122 using DNP3, Modbus

RTU, IEC 60870-5-103 communication protocols. The MiCOM C264 RTU creates IEC

61850 object models from the data accessed from IEDs. The IEC 61850 Client i.e. HMI

or SCADA system accesses data from MiCOM C264 RTU.

6.1.2 Configuration Tools

CitectSCADA software is made up of several configuration tools i.e. CitectSCADA Explorer,

CitectSCADA Project Editor, CitectSCADA Graphics Builder, Computer Setup Editor,

Computer Setup Wizard and CitectSCADA Runtime section. Computer Setup Editor is a feature

for editing configuration files and generating reports to compare and analyse files. Computer

Setup Wizard allows the user to customize the computer’s setup and define its role and function.

Figure 6-3: CitectSCADA Explorer Configuration Tool

Figure 6-3 above shows the CitectSCADA Explorer configuration tool that was used to create

and manage the user projects; it displays a list of projects and provides direct access to the

components of each. This configuration tool is also used to rename, back up, restore or delete a

project.

Figure 6-4: CitectSCADA Editor Configuration Tool

Figure 6-4 above shows the CitectSCADA Project Editor Configuration tool that was used o

create and manage the configuration information for the project, including tags, alarms, system

components, and communications components.

Page 75: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

61

Figure 6-5: CitectSCADA Graphics Builder Configuration Tool

Figure 6-5 shows the CitectSCADA Graphics Builder configuration tool that was used to design,

create, and edit the graphics components of the project, including templates, graphics objects,

symbols, genies, and Super Genies. For this project, the configurations entailed the following

items:

a) Electrical Network Reticulation – Graphical representation of the 132/33 kV Substation.

b) Symbols Legend – Description of each symbol used in the reticulation network.

c) Alarms – Active alarms, hardware alarms, disabled alarms and alarm summary.

d) Process Analyst – Trends and Popup trends.

e) Substation Geographical Location.

Figure 6-6: CitectSCADA Runtime

Figure 6-6 shows the CitectSCADA Runtime section i.e. Startup Page that provides the active

operator interface. The runtime “Startup Page” provides the user/operator with the option to login

in and the following information is obtained from this page:

Page 76: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

62

a) Project Name

b) User – At the top left it shows the name of the user logged onto the system and at the

bottom left corner it is indicated that the login was successful.

c) Active Alarms are displayed at the bottom of the page with date and time they were raised.

d) Time and Date – Is indicated on the bottom right corner of the page.

e) Navigation Tabs:-

- Pages which entails of the main menu tab, electrical reticulation tab,

symbols legend tab and substation geographical location.

- Alarms tab which consists of active alarms, hardware alarms,

disabled alarms and summary alarms.

- Trends tab which consists of the Process Analyst and Process

Analyst Pop ups.

Figure 6-7: Explanation for navigation panels

Figure 6-7 explains the various navigation controls that are in the runtime page when various

pages are opened. These controls provide the user with ease to navigate directly to the required

page. The page templates entail of vertical and horizontal scroll bars to allow users to view

columns and rows off-screen.

Page 77: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

63

Figure 6-8: Electrical Network Reticulation Implemented

Figure 6-8 shows the interactive electrical network SCADA model of the physical system that

was implemented on Schneider’s CitectSCADA software. This model was configured and

designed to have remote control points for the operation of circuit breakers, isolators, earth

switches, visual indications of switchgear status, and modes of operation of devices, current

readings, alarms and warnings under fault conditions. The implemented electrical network

reticulation entails of 2 x 132 kV 40 MVA transformers, 33 kV Bus Section, 6 x 33 kV feeders

and circuit breakers 2, 3, 4 & 7 are communicating and can be operated i.e. Open/Closed.

Figure 6-9: Electrical Network Reticulation Symbols Description

Figure 6-9 shows the Legend tab found in the runtime with the description of symbols used in the

electrical network SCADA model implemented in CitectSCADA software. This page assist the

user with identifying the device status and provides understanding and the meaning of each device

symbol used in the graphic user interface.

Page 78: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

64

Figure 6-10: Alarms Page

Figure 6-10 shows the alarms page tab in the runtime interface, which consists of Active alarms,

alarm summary, disabled alarms and hardware alarms. The alarms raised are displayed in their

respective dedicated pages, however, the most recent alarms are always visible on every page.

The CitectSCADA alarm server manages and processes all alarms as configured in the Project

Editor. The alarm system is equipped with capabilities of being fast, reliable and provides detailed

alarm information to the user/operator. To minimize downtime the user/operator has the ability

to easily identify the faulted area of the network and isolate as quickly as possible. The

CitectSCADA system is efficient and enables the user/operator to monitor configurable alarms

i.e. variables, expressions or calculation results and reports fault conditions in the plant. The alarm

are time stamped and this is essential when differentiating between alarms that occur in rapid

succession. Alarms are structured according to colour, priority, category and time of occurrence.

Table 6-1: Active Alarms

Time Variable Tag Alarm Description of alarm

09:22:14 AM CBTC2 1_Active CBTC2 Active Status Circuit Breaker 2 Trip Coil

Active

09:12:56 PM CB2_Open CB2 Open Status Circuit Breaker 2 is Opened

09:05:45 PM CBF2_Active CBF2 Active Status Circuit Breaker 2 Fail Active

04:40:48 PM CB7_Close CB7 Close Status Circuit Breaker 7 is closed

04:40:48 PM CB4_Close CB4 Close Status Circuit Breaker 4 is closed

Table 6-1 shows some of the alarms raised as shown in Figure 6-11. The active alarm page

provides the user/operator with vital information regarding the status of the network since this

page displays the time the alarm was activated, variable tag triggered and alarm description.

Page 79: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

65

Figure 6-11: Active Alarms Page

Figure 6-11 shows active alarms page in the runtime. This page displays active alarms that are

unacknowledged or acknowledged and still in active alarm state. From this view the user/

operator is able to see the entire active alarms, the alarm on time, and the date.

Figure 6-12: Summary Alarms Page

Page 80: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

66

Figure 6-12 shows alarm summary page, which displays a historical log of alarms that have

occurred and their duration. This page is mainly for troubleshooting purposes and displaying all

the alarms raised in the electrical network system. This page has the equipment tree-view panel

displayed on the left hand side of the page for filtering of the display list. The summary alarms

filter pop up allows the user to select the alarms range, select dates, times, state and types of

alarms to display.

Table 6-2: Alarm Summary

Alarm Time Alarm

Raised

Time Alarm

Cleared

Duration Alarm Status

CB1 Close

Status

08:34:31 0 0 unacknowledged

CB2 Open

Status

08:59:23 09:04:11 00:04:43 acknowledged

CBF2 Active

Status

08:55:23 09:00:03 00:00:43 acknowledged

Table 6-2 shows some of the alarm summary as shown in Figure 6-12. The alarm summary page

displays the alarm raised, the time the alarm was cleared, the duration of the alarm and whether

the alarm was acknowledged or unacknowledged.

Figure 6-13: Hardware Alarms Page

Figure 6-13 shows hardware alarms page in the runtime. When an error occurs in CitectSCADA

operation, a hardware alarm is generated and displayed on a dedicated page within the project.

This alerts the operator to monitor the status of a system’s infrastructure or current problems.

Hardware alarms indicate if break in communications has occurred, if the Cicode cannot execute

Page 81: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

67

or if a server becomes inoperative. If the user/operator experiences problems communicating with

a device, initially check the hardware alarms page for evidence of an error.

Figure 6-14: Trends Page

Figure 6-14 shows the trends page, which entails of Process Analyst and Popup Process Analyst

tabs. CitectSCADA trends provides records of real-time and historical data of the electrical

equipment in the substation. The user/operator is able to monitor the current activity or scroll back

to view the trend history. CitectSCADA handles enormous amount of variables whilst

maintaining data integrity.

Figure 6-15: Substation Geographical Location

Figure 6-15 shows the aerial view with the geographical location of the plant/substation. This

aerial view indicates the geographical location of various 11 kV substations, 33 kV substations

and new 132 kV Substation implemented for this project indicated in green. To navigate from to

the electrical reticulation network of the substation in question, the user/operator can click on the

green indication button. This makes it easy for the user/operator to operate the network as quickly

as possible.

Page 82: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

68

6.2 CitectSCADA Substation Model Testing

The 132/33 kV substation model implemented on the CitectSCADA system was equipped with

supervisory features and interactive visual alerts that enabled the user/operator to observe the

network status. The supervisory features display functions entailed of status indicators for circuit

breakers, isolators, local or remote mode, circuit breaker trip coil supervision, cable earth, circuit

breaker fail, overcurrent trip, earth fault and three phase currents. For switchgear operation, the

SCADA model had interactive control panels for the circuit breaker and isolator. When the

user/operator clicked on the circuit breaker or isolator symbols, a pop-up window appeared,

allowing the user/operator to remotely open or close the circuit breaker or isolator taking into

consideration applicable interlocking.

6.2.1 Circuit Breaker Basic Operation

Figure 6-16: Energized Circuit Breaker Basic Operation

Figure 6-16 shows the SCADA graphical representation of the energized state of both incomer

one and two when remotely operated. From this graphical representation, it is evident that both

circuit breakers and isolator were closed while the cable earth switches were opened. The

interactive alerts for circuit breakers, isolators, earth switches and three phase currents are shown.

It can be noted that the three phase current numerical values displayed is zero due to that the

associated feeders and bus section were de-energized during this test as a result the load current

was zero amps.

Figure 6-17: Hardware Relay Circuit Breaker Energized Status

Page 83: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

69

Figure 6-17 shows the hardware relay circuit breaker energized status of incomer one when

operated remotely which corresponds to the SCADA graphical representation in Figure 6-14. It

is evident that the both the circuit breaker and isolator are closed whilst the earth switch is open.

The remote mode operation status is also indicated as well as the three-phase currents numerical

value of zero amps.

Figure 6-18: De-energized Circuit Breaker Basic Operation

Figure 6-18 shows the SCADA graphical representation of the de-energized state of both incomer

one and two when remotely operated. From this graphical representation, it is evident that the

circuit breakers were opened whilst the isolator and earth switch were closed. The interactive

alerts for circuit breakers, isolators, earth switches and three phase currents are shown. It can be

noted that the three phase current numerical values displayed is zero due to the de-energized state.

Figure 6-19: Hardware Relay Circuit Breaker De-Energized Status

Figure 6-19 shows the hardware relay circuit breaker de-energized status of incomer one when

operated remotely which corresponds to the SCADA graphical representation in Figure 6-16. It

is evident that the circuit breaker is opened. The remote mode operation status is also indicated

as well as the three-phase currents numerical value of zero amps.

Page 84: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

70

6.2.2 Bus Section Basic Operation

Figure 6-20: Energized Bus Section Basic Operation

Figure 6-20 shows the electrical substation SCADA model, which entails of two 132 kV

incomers, six feeders and one bus section. The graphical representation indicates the status of the

bus section when remotely operated through the interactive control buttons that were configured

using logic operations. It is evident that the bus section is in its closed state.

Figure 6-21: De-Energized Bus Section Basic Operation

Figure 6-21 shows the SCADA model graphical representation of the bus section when remotely

operated through the interactive control buttons that were configured using logic operations. It is

evident that the bus section is in its open state.

Page 85: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

71

6.2.3 Testing Fault Conditions using VAMPSET software

The earth fault and overcurrent fault conditions were verified using virtual software testing i.e.

VAMPSET software for VAMP 255 and VAMP 259 protection relays. The software was used to

inject the current to the protection relay and the triggered fault condition would be displayed on

the SCADA model and the relay HMI display screen.

Table 6-3: Overcurrent Settings and VAMPSET Tests

Overcurrent Test Settings

Pick-up Current (IP) 440 A

Time Multiplier Setting

(TMS)

0.5

Tripping Curve IEC STD Inverse

Virtual Test 1 Virtual Test 2 Virtual Test 3

Phase A 463 A Phase A 463 A Phase A 297 A

Phase B 463 A Phase B 463 A Phase B 297 A

Phase C 463 A Phase C 216 A Phase C 297 A

Status OC Trip Status OC Trip Status No OC Trip

Table 6-3 represents the overcurrent VAMP 259 relay settings for incomer one which include the

relay pick-up current, time multiplier setting and the tripping curve. This table further shows the

three tests by injecting current using VAMPSET software in each phase to prove overcurrent

tripping.

Figure 6-22: Incomer 1 Overcurrent Trip Status

Figure 6-22 shows the SCADA model graphical representation of an overcurrent trip condition

for test one, two and three in remote mode. For test one and test two the current injected in all

three phases and phases A and B respectively is above the pick-up current of 440A therefore the

circuit breaker tripped on overcurrent. For test 3 current injected in all the three phases is below

the pick-up current setting therefore, there is no overcurrent trip and the circuit breaker remains

Test 1 Test 2 Test 3

Page 86: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

72

closed. Due to that the testing was done using the third party software , the system diagram on

SCADA is unable to display the actual numerical current values as the relay is being tested using

it’s dedicated and copyrighted VAMPSET software.

Table 6-4: Earth Fault Settings and VAMPSET Tests

Earth Fault Test Settings

Pick-up Current (IP) 80 A

Time Multiplier Setting

(TMS)

0.05

Tripping Curve IEC STD Inverse

Test 1 (Ph-G) Test 2 (Ph-G)

Phase A 75.70 A Phase A 100 A

Status No EF Trip Status EF Trip

Table 6-4 represents the earth fault VAMP 259 relay settings for incomer one which include the

relay pick-up current, time multiplier setting and the tripping curve. This table further shows the

two tests conducted by injecting current using VAMPSET software between phase A and ground

to prove earth fault tripping.

Figure 6-23: Incomer 1 Earth Fault Trip Status

Figure 6-23 shows the SCADA model graphical representation of an earth fault trip condition for

both tests the current was injected between phase A and ground. The phase to ground current for

test one was below the pick-up current setting therefore there was no earth fault and the circuit

breaker remained closed. For test two, the phase to ground current was above the pick-up current

setting therefore, there was an earth fault and the circuit breaker tripped as shown in Figure 6-23.

Test 1 Test 2

Page 87: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

73

Figure 6-24: Incomer 2 Local Mode and Disabled Controls

Figure 6-24 shows the SCADA model graphical representation in local mode and circuit breaker

controls. When the circuit breaker mode is in local, the user/operator will not be operate it

remotely from SCADA model as the circuit breaker controls are disabled therefore the circuit

breaker can’t be closed or opened. This is a safety feature that prevents the operator from

switching the circuit breaker while the maintenance personnel is working onsite, therefore the

circuit breaker can only be physically opened or closed from the panel by the maintenance

personnel.

Figure 6-25: Incomer 2 Local Mode when operated by Maintenance Personnel

Figure 6-25 shows the SCADA model graphical representation in local mode and circuit breaker

controls. In this case the circuit breaker is operated physically by the maintenance personnel and

the user/operator can only see the status of the circuit breaker and still unable to operate remotely.

Figure 6-26: Incomer 2 Circuit Breaker Trip Coil Status

Page 88: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

74

Figure 6-26 shows the SCADA model graphical representation of circuit trip coil/ trip coil

supervision condition in remote mode. This trip condition was triggered when the power supply

was switched off. In addition to the alerts, alarms and status indicators of the SCADA model, the

relay HMI also displayed informative data to the operator/user. Figure 6-27 displays the hardware

relay results of remote mode, trip coil supervision trip, circuit breaker, isolator status and earth

switch status and the three phase currents observed when this test was undertaken. The numerical

reading captured on the incomer 2 was zero amps due to the de-energized status of the associated

feeder and bus section when this test was undertaken. The relay HMI also confirmed the

functionality of the circuit breaker trip coil supervision indicator on the SCADA model.

Figure 6-27: Hardware Relay Incomer 2 Circuit Breaker Trip Coil Supervision Status

Figure 6-28 shows the SCADA model graphical representation of circuit breaker fail and earth

fault status in remote mode. The earth fault was applied to the system, the circuit breaker of

Incomer 2 in figure 6-29 failed to trip within the appropriate time to clear the fault, therefore the

circuit breaker fail status was activated.

Figure 6-28: Incomer 2 Circuit Breaker Fail Status

Figure 6-29 shows the SCADA model graphical representation of feeder 2 overcurrent status

indication in remote mode. An overcurrent was applied to the system, the overcurrent indication

on the SCADA model was activated. The circuit breaker receives a trip signal from the feeder

protection relay to clear the fault as indicated in Figure 6-30.

Page 89: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

75

Figure 6-29: Feeder 2 3ph-G Overcurrent Trip Fault Condition

Figure 6-30: Three Phase Current under normal and overcurrent fault conditions

Figure 6-30 shows the SCADA model process analyst pop up real time trends representing the

three phase currents under normal conditions and when an overcurrent was applied to the system.

Under normal operating condition the three phase current was 199 A and when an overcurrent

was applied the circuit breaker tripped and the three phase current was now 0 A due to the circuit

breaker de-energized status.

6.3 Conclusion

The main purpose of Chapter 6 was to develop and design a SCADA and Automation system for

the 132/ 33 kV substation. Schneider CitectSCADA software was used to develop and implement

the SCADA model for the new substation. The designed SCADA system model is a representation

of real substation equipment and provides the user/operators with fault management capabilities.

The implemented SCADA systems provides graphical user interface of the electrical network,

alarm features, trends and substation geographical location enabling the user/operator to visualize

and interact with the substation equipment. This Chapter has demonstrated various tests

conducted to confirm the operation of the implemented SCADA system. The developed system

was equipped with hardware IEDs devices to perform functions of protection, control and

monitoring a power system. From a network perspective, the SCADA communications network

was developed. This communications architecture utilised the network switch to interconnect all

Page 90: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

76

devices via Ethernet communication medium. The IEC 61850 communications protocol was

implemented for power monitoring and data capture between the IEDs and the implemented

SCADA network. The IEC 61850 communications protocol enabled the user/operator the ability

to remotely control IEDs via the use of command and control. This feature improves the

operational efficiency and increases the safety of plant personnel.

Page 91: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

77

CHAPTER 7: CONCLUSION AND RECOMMENDATIONS

This chapter entails the conclusion summary based on the work conducted in each chapter as well

recommendations and future work. The methodologies and techniques presented by different

authors were reviewed and summarized in accordance to relevancy. The literatures were based

on load flow analysis, protection systems, SCADA and SAS, which is elaborated on the relevant

chapters of this dissertation.

7.1 Conclusion

The PoD is planning an expansion to cater for increased container throughput, therefore, requiring

additional load of approximately 58 MVA. The additional demand required determined the

voltage at which the power is to be supplied to the Port, which triggered the power supply upgrade

to 132 kV. For the upgrade the power supply from EE is at 132 kV stepped to down to 33 kV

and 11 kV [7, 8]. Power is transmitted from low demand areas to high demand in the grid. The

electrical infrastructure required to support the power supply upgrade due to development and

expansion plans was investigated in this dissertation. Load flow analysis was conducted to

investigate the behaviour of the existing electrical network and design for the additional load

demand requirements. The study was used as a means to determine voltages, active and reactive

power of all buses in the network, for the specified load. The selected equipment percentage

loading relative to equipment ratings was obtained to ensure these equipment will cater for the

forecasted load demand. The purpose of the study was also to ensure that the voltages are

maintained at acceptable limits. The NR method was used to obtain the power flow solution that

is within acceptable tolerances [10, 11].

PowaMaster software tool was used to conduct the electrical network load flow study to analyse

the prospective behaviour of the PoD’s electrical network post implementation the new 132/33

kV Langeberg substation onto the currently existing network as part of network strengthening

due to planned infrastructure developments. The load flow analysis was based on power supply

options that included load forecasting for a period of five, seven and ten years. Post

implementation of all the planned expansion projects by the year 2027, it was evident that it will

not be feasible to source power with one 132/33 kV 40 MVA transformer as it was overloaded by

120%. The results confirmed the feasibility to source the power supply with two 132/33 kV 40

MVA transformers due to the transformer loading of 39.98% and 50.3% respectively which

means both transformer have sufficient spare capacity. The power supply configuration allows

for full redundancy and reliability of the network. All voltages were found to be within the

acceptable ±5% limits as per SANS 10142-2 and NRS 048 requirements. The selected cables

incoming cables for all scenarios considered will be sufficient to carry total Port loads without

compromising the reliably and stability of the PoD’s electrical network.

Page 92: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

78

The SCADA and SAS was designed and developed using Schneider CitectSCADA software

platform for the 132/33 kV substation. In order to achieve the SCADA & SAS requirements, the

IEC 61850 and legacy compliant hardware i.e. relays/IEDs, RTU’s, Ethernet switches and

SCADA host software were required and utilised. A multi-protocol electrical substation network

was developed to access the effectiveness of the communications protocols i.e. Modbus RTU,

DNP3 and the IEC 61850 standard. This entailed the design and implementation of an interactive

substation SCADA model architecture, which integrated the modern and legacy IEDs. The IEC

61850 communications network and system enabled the developed substation model the

interoperability function between the IEDs of different manufacturers to perform functions of

protection, control, monitoring and automation substations. The developed system was equipped

with interactive features that enabled the user/operator to view the network status, alarming and

trending.

7.2 Recommendations for Future Work

The work performed and presented in this dissertation confirms the theories from the literatures;

however, it is not limited to the scope presented. It is therefore recommended that the following

studies but not limited to these be conducted using the same electrical power systems network,

namely:

(a) Protection grading study must be performed to safeguard correct selection of CT’s, VT’s

and relay settings at the new 132/33/ kV Langeberg substations and the coordination of

all other relays downstream.

(b) Harmonic filter or power factor correction study must be performed to ensure that the

correct capacitor sizes are selected at the 132/33/ kV Langeberg substations.

(c) Conduct fault analysis study for the whole power system network to evaluate the network

behaviour under contingency conditions.

(d) Development and implementation of security features. Assignment of privileges to user

roles that control the SCADA and SAS elements of the electrical network. This will

prevent unknown users from tampering with the electrical network and prevents

unauthorised users from accessing the system. The different privilege access levels

secures the electrical network configuration from unauthorised changes.

(e) Development and classification of alarm categories and priorities for SCADA & SAS to

enable the user/operator to attend to the most critical alarms in a power system network.

(f) Introduction of flexible renewable energy based embedded generation to reduce the

carbon footprint.

Page 93: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

79

REFERENCES

[1] R.G. Stephen: “South African National Standard 507-1:2014, Electricity Distribution –

Guidelines for the provision of electricity distributed networks in residential areas”, SABS

Standards Division, Pretoria, South Africa, 2014.

[2] Eskom Transmission Division: “South African Distribution Code, Network Code Version

6”, National Energy Regulator of South Africa (NERSA), 2014.

[3] System Operations and Planning: “The South African Grid Code, The Network Code

Version 7”, National Energy Regulator of South Africa (NERSA), 2008.

[4] B. Bjorklund, T. Einarsson and B. Lundqvist: “A user friendly implementation of IEC 61850

in a new generation of protection and control devices” ABB Power Technologies, Sweden,

2007

[5] K. Brand, T. Maeda, K. Oestrich, P. Rietmann: “First Experiences with customer

specifications of IEC 61850 based Substation Automation Systems”, Cigre Study Committee

B5 Colloquium, Calgary, Canada, 2005.

[6] D. Dolezilek and D. Hou: “IEC 61850 – What It Can and Cannot Offer to Traditional

Protection Schemes”, SEL Journal of Reliable Power, Volume 1, Number 2, 2010.

[7] Port of Durban’s 33 kV reticulation network: “PEB-33 amendment 27, 33 kV distribution

and generation HV switching diagram”, 2017.

[8] M. Peer and D. Padayachy: “Transnet Port of Durban Electrical Masterplan Rev. 4”,

Norconsult Iyanda (Pty) Ltd, 2014.

[9] S. Mnukwa and J. Sauerman: “Increase Electrical supply Capacity in PoD – Business Case”,

2018.

[10] M. Chakravorty, M. Das and S.S. Patra: “Importance of Load Flow Analysis in Voltage

Stability Studies”, 30th Indian Engineering Congress, the 21st Century Engineering: The

Make in India Pathway, December 2015, pp. 45-50.

[11] A.M. Elsayed, M.O. Foda, Y.S. Mohamed and A.A. Radwana: “ Modelling and

Reconfiguration of Middle Egypt Distribution Network”, 19th International Middle East

Power Systems Conference, Menoufia University, Egypt, 19-21 December 2017.

[12] D.C. Idoniboyeobu and B.E. Nemine: “Electrical Load Flow Studies for efficient Power

Supply in Bayelsa Stateusing Newton Raphson Technique”, International Journal of

Research in Engineering Technology, Volume 2 Issue 5, September – October 2017.

[13] B.S. Hota and A.K. Mallick: “Load flow Study in Power System”, Department of Electrical

Engineering National Institute of Technology, Rourkela, 2011.

[14] T.V. Arun, L. Lathesh and A.R. Suhas “Substation Automation system”, International

Journal of Scientific & Engineering Research, Volume 7, Issue 5, May 2016.

Page 94: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

80

[15] X. Cheng, W. Lee and X. Pan: “Electrical Substation Automation System Modernization

through the adoption of IEC 61850”, IEEE/IAS 51st Industrial & Commercial Power

Systems Technical Conference, Calgary, Canada, 2015.

[16] D.P. Kothari and I.J. Nagrath, “Modern Power System Analysis, Fourth Edition”, McGraw-

Hill Companies, New York, 2008, ISBN 978-0-07-340455-4.

[17] M.J. Katira and K.B. Porate, “Load Flow Analysis 132/11 kV Distribution Substation using

Static Var Compensator for Voltage Enhancement – A Case Study”, 2nd International

Conference on Emerging Trends in Engineering and Technology, Nagpur, India, 2009.

[18] K. Singhal, “Comparison between Load Flow Analysis Methods in Power System using

MATLAB”, International Journal of Scientific & Engineering Research, Volume 5, Issue 5,

May 2014, ISSN 2229-5518.

[19] A. Vijayvargia, S. Jain, S. Meena, V. Gupta and M. Lalwani, “Comparison between Different

Load Flow Methodologies by Analyzing Various Bus Systems”, International Journal of

Electrical Engineering, Volume 9, pp.127-138, 2016, ISSN 0974-2158.

[20] S. Chatterjee and S. Mandal, “Novel Comparison of Gauss-Siedel and Newton-Raphson

Methods for Load Flow Analysis”, International Conference on Power and Embedded Drive

Control, Chennai, India, 2017.

[21] IEEE Recommended Practice for Power System Analysis, IEEE Std. 399-1980.

[22] Network Protection & Automation Guide: Protective Relays, Measurement & Control,

Alstom Grid, 2011, ISBN 978-0-9568678-0-3.

[23] B.M. Weedy and B.J Cory, “Electrical Power Systems – Fourth Edition”, John Wiley &

Sons, Ltd, England, 1998.

[24] A.M. Sleva, “Protective Relays Principles”, Taylor Francis Group, London New York, 2013,

ISBN 978-1-4200-1417-8.

[25] J.L. Blackburn and T.J Domin, “Protective Relaying: Principles and Applications, Fourth

Edition”, Taylor Francis Group, London New York, 2013, ISBN-13: 978-1-4398-8812-4.

[26] B. Ram and D.N Vishwakarma, “Power system protection and switch gear”, Tata McGraw-

Hill publishing company Limited, 1996, ISBN 0-07-462350-8.

[27] S.P. Chowdhury and M. Nko, “Maintenance Planning and Execution of Protection Systems

in Substations in Substations in South Africa: A recent Case Study.”, 2016 IEEE, 978-1-

5090-4650-8/16.

[28] R.I. Evans and P. Spahiu, “Protection Systems that verify and supervise themselves”,

Innovative Smart Grid Technologies (ISGT Europe), 2011 2nd IEEE PES International

Conference and Exhibition.

[29] A.G. Phadke and H.S. Stanley, “Power System Relaying, Third Edition”, Research Studies

Press Limited, 2008, ISBN: 978-0-0470-05712-4.

Page 95: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

81

[30] C.R. Mason, “The art and science of protective relaying”, John Wiley and Sons, New York,

1969, ISBN 81-224-1053-7

[31] M. Chander and B. Ravindranath, “Power system protection and switchgear.” New age

international limited publishers, New Delhi, 2006, ISBN 0-85226-758-4.

[32] A.K. Saha, “Protection using fuses and relays” Course lecture notes for power systems 2,

University of Kwa-Zulu Natal, Durban, 2013.

[33] T.S. Madhava Rao, “Power system protection static relays.” Tata McGraw-Hill publishing

company Limited, 1979, ISBN 0-07-096574-9.

[34] M. Peer and D. Padayachy: “Transnet Port of Durban Electrical Masterplan Rev. 4”,

Norconsult Iyanda (Pty) Ltd, 2014.

[35] S. Mnukwa and J. Sauerman: “Increase Electrical supply Capacity in PoD – Owner

Requirements Specification”, 2015.

[36] IEEE Standard for SCADA and Automation Systems, IEEE Std C37.1, 2007

[37] A. Basuki, T.I. Priadi, A.P. Sari and H. Trirohadi, “SCADA Gateway, Smart Solution for

Combining Conventional Substation and Automation System”, 2011.

[38] M.K. Khedkar and Dr. G.M. Dhole, “Electric Power Distribution Automation”, University

Science Press, New Delhi, 2010, ISBN 978-93-80386-21-8

[39] R.R. Raul, “New EEQ S.A. SCADA and Substation Automation Project”, 2005.

[40] J. Jose, C.P. Varghese, A.J. Abraham, J. Joy and A. Koilraj, “Substation Automation Systems

for Energy Monitoring and Control Using SCADA”, International Journal of recent trends

in Engineering and research, 2017.

[41] E. Padilla, “Substation Automation Systems: Design and Implementation 1st Edition”, John

Wiley and Sons, United Kingdom, 2016, ISBN 978-1-118-98720-9

[42] C. Strauss, “Practical Electrical Network Automation and Communication System”, British

library cataloguing in publication data, Britain, 2003, ISBN 07506 58010.

[43] N. Yellamandamma, T.S. Kumar, K.V.H. Rao and A. Aggarwal, “Low Cost Solution for

Automation and Control of MV Substation using MODBUS-SCADA”, BHEL Corp R & D,

Hyderabad, India, 2009

[44] Port of Durban’s SCADA system control and view station, 2017.

[45] Transnet Automation Control Standards, Convenient Software Solutions (Pty) Ltd, 2015.

[46] Transnet National Ports Authority’s SCADA server’s layout, 2017.

[47] Wonderware Application Server – Training Manual, Schneider Electric Software, 2016.

[48] Industrial Networking, computing and Automation Solutions – Master Catalogue, MOXA

Reliable Networks Sincere Service, 2014 - 2015.

[49] H.J.A Ferrer and E.O Schweitzer: “Modern Solutions for Protection, Control and Monitoring

of Electric Power Systems”, Schweitzer Engineering Laboratories, Inc., Pullman, 2010,

ISBN: 978-0-9725026-3-4

Page 96: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

82

[50] W.J. Ackerman, “The impact of IEDs on the design of systems used for operation and control

of power systems”, ABB Inc., USA, 2002

[51] C.E. Jackson and J.W. Evans, “A network-less implementation – Case Study”, DTE Energy,

2000.

[52] W.J. Ackerman, “The impact of IEDs on the design of systems used for operation and control

of power systems”, ABB Inc., USA, 2002

[53] Port of Durban’s proposed 132 kV network and protection layout”, 2016.

[54] IEC 61850 – 6 Communication Networks and Systems in Substations – Part 6: Substation

Configuration Description Language for communication in electrical substations related to

IEDs.

[55] K.P. Brand, C. Brunner and W. Wimmer “Design of IEC 61850 based substation automation

systems according to customer requirements”, ABB Switzerland Ltd, Baden and Zurich,

Switzerland, 2004, in press.

[56] H.B. Bhubaneswar, L. Sudheendran and P. Pruthwi, “Analysis of utility communication

Protocol IEC 61850 for Substation Automation Systems”, National Conference on

Challenges & Technology in the Coming Decades, 27-28 September 2013.

[57] C. Rytaft, I. De Mesmaeker and P. Reinhardt, “Protection and substation automation:

standardization, integration and IT”, ABB Power Technologies, Energize Magazine pages

30 -35, August 2007.

[58] C. Burchell, “Specification and evaluation of substation automation systems”, Cigre,

Energize Magazine pages 27-29, December 2007.

[59] C. Brunner, K.P. Brand and W. Wimmer, “Design of IEC 61850 Based Substation

Automation Systems According to Customer Requirements”, Cigre Session, 2004.

[60] P.R Heze, L.W. Jinan and P.R. Jinan, “Consistency Analysis of SCADA data from field

Power Systems”, National Natural Science Foundation of China, 2017.

[61] D. Cheten and U.D. Dahal, “Substation automation: Matlab and OPC Driven Substation

Monitoring System.”, 2016 International Conference on Microelectrics, computing and

Communications (MicroCom), Durgapur, India.

[62] T.V. Arun, L. Lathesh and A.R. Suhas “Substation Automation System”, International

Journal of Scientific and Engineering Research, Volume 7, Issue 5, May 2016.

[63] X. Cheng, W. Lee, and X. Pan “Electrical Substation Automation System Modernization

through the Adoption of IEC 61850”, 2015 IEEE/IAS 51st Industrial & Commercial Power

Systems Technical Conference.

[64] C. Mulangu, I.E. Davidson and B. Madonsela “Advances in Telecontrol and Remote

Terminal Units for Power Substation”, IEEE Power Africa Conference, 26-29 June 2018,

Cape Town, South Africa.

Page 97: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

83

APPENDICES

ANNEXURE A – MAXIMUM DEMAND RAW DATA RETRIEVED

FROM SCADA SYSTEM

A. Total Average Demand at DHI & STS 33 kV Incomers

DateTime

DADGEN_GENERAL.PLANT_

KW_LOAD_TOT_DHI_STS33_

AVG

DateTime

DADGEN_GENERAL.PLAN

T_KW_LOAD_TOT_DHI_ST

S33_BUS

2018/07/09 00:00 8706,551758 2018/07/09 00:00 9234,400391

2018/07/08 23:50 8486,75 2018/07/08 23:50 10851,81055

2018/07/08 23:40 8964,141602 2018/07/08 23:40 8759,779297

2018/07/08 23:30 8184,699707 2018/07/08 23:30 8773,599609

2018/07/08 23:20 9044,553711 2018/07/08 23:20 10755,05078

2018/07/08 23:10 9005,386719 2018/07/08 23:10 8262,120117

2018/07/08 23:00 9635,529297 2018/07/08 23:00 8699,870117

2018/07/08 22:50 8964,138672 2018/07/08 22:50 9354,199219

2018/07/08 22:40 9168,046875 2018/07/08 22:40 8870,360352

2018/07/08 22:30 9127,49707 2018/07/08 22:30 8769

2018/07/08 22:20 10367,27832 2018/07/08 22:20 9437,160156

2018/07/08 22:10 10150,23828 2018/07/08 22:10 9815,009766

2018/07/08 22:00 9095,927734 2018/07/08 22:00 8234,469727

2018/07/08 21:50 9826,760742 2018/07/08 21:50 10003,92969

2018/07/08 21:40 9353,291016 2018/07/08 21:40 8418,790039

2018/07/08 21:30 9591,063477 2018/07/08 21:30 9773,529297

2018/07/08 21:20 9406,280273 2018/07/08 21:20 10934,75977

2018/07/08 21:10 9417,339844 2018/07/08 21:10 9312,740234

2018/07/08 21:00 9544,061523 2018/07/08 21:00 9280,480469

2018/07/08 20:50 9811,089844 2018/07/08 20:50 9603,040039

2018/07/08 20:40 9524,476563 2018/07/08 20:40 9109,980469

2018/07/08 20:30 9405,129883 2018/07/08 20:30 8990,179688

2018/07/08 20:20 9421,485352 2018/07/08 20:20 8529,379883

2018/07/08 20:10 9236,013672 2018/07/08 20:10 9054,679688

2018/07/08 20:00 8955,387695 2018/07/08 20:00 9321,950195

2018/07/08 19:50 9295,689453 2018/07/08 19:50 7515,620117

2018/07/08 19:40 9817,543945 2018/07/08 19:40 10579,92969

2018/07/08 19:30 9995,414063 2018/07/08 19:30 9538,530273

2018/07/08 19:20 9520,09375 2018/07/08 19:20 9538,519531

2018/07/08 19:10 10001,86719 2018/07/08 19:10 10400,2207

2018/07/08 19:00 9365,499023 2018/07/08 19:00 9105,390625

2018/07/08 18:50 9435,774414 2018/07/08 18:50 9409,509766

2018/07/08 18:40 10143,55762 2018/07/08 18:40 9391,070313

2018/07/08 18:30 9379,09082 2018/07/08 18:30 9967,060547

2018/07/08 18:20 9247,536133 2018/07/08 18:20 8755,169922

2018/07/08 18:10 8765,076172 2018/07/08 18:10 8778,209961

2018/07/08 18:00 8875,211914 2018/07/08 18:00 8764,400391

2018/07/08 17:50 9221,503906 2018/07/08 17:50 9275,879883

2018/07/08 17:40 9591,063477 2018/07/08 17:40 9957,860352

2018/07/08 17:30 9804,871094 2018/07/08 17:30 9460,200195

2018/07/08 17:20 9886,894531 2018/07/08 17:20 9400,290039

2018/07/08 17:10 9511,111328 2018/07/08 17:10 9842,650391

2018/07/08 17:00 10476,94727 2018/07/08 17:00 11966,93945

2018/07/08 16:50 9403,514648 2018/07/08 16:50 8902,620117

2018/07/08 16:40 8107,978027 2018/07/08 16:40 8709,089844

2018/07/08 16:30 8476,386719 2018/07/08 16:30 8833,5

DADGEN_GENERAL.PLANT_KW_LOAD_TOT_DHI_STS33_B

US

DADGEN_GENERAL.PLANT_KW_LOAD_TOT_DHI_STS3

3_AVG

Page 98: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

84

B. Top 10 Maximum Demand at DHI 33 kV Transformer Feeders

399. E22 DHI main 33 transformers

DHI Distribution

Date kVA kVAh kWh

Consumed

kVarh

Lagging

PF Usage

Period

15/08/2017

10:30

2216,28 1 108,138 950,000 570,500 0,857 Standard

10/08/2017

13:30

2207,03 1 103,516 944,000 571,500 0,855 Standard

15/08/2017

10:00

2206,71 1 103,356 949,500 562,000 0,861 Standard

10/08/2017

14:00

2200,67 1 100,335 943,000 567,000 0,857 Standard

15/08/2017

11:00

2192,61 1 096,306 941,000 562,500 0,858 Standard

15/08/2017

09:30

2184,02 1 092,010 946,000 545,500 0,866 Standard

11/09/2017

11:00

2180,62 1 090,312 932,500 565,000 0,855 Standard

11/09/2017

11:30

2177,69 1 088,845 933,500 560,500 0,857 Standard

15/08/2017

11:30

2176,35 1 088,173 936,000 555,000 0,860 Standard

10/08/2017

14:30

2170,66 1 085,330 930,000 559,500 0,857 Standard

AVERAGE 2191,26

399. E24 DHI main 33 transformers

DHI Distribution

Date kVA kVAh kWh

Consumed

kVarh

Lagging

PF Usage

Period

25/05/2017

11:00

2264,47 1 132,237 960,500 599,500 0,848 Standard

03/05/2017

13:30

2212,32 1 106,161 938,500 585,500 0,848 Standard

06/06/2017

14:00

2203,87 1 101,933 950,500 557,500 0,863 Standard

06/06/2017

14:30

2187,67 1 093,833 945,500 550,000 0,864 Standard

30/03/2017

11:00

2178,19 1 089,095 943,500 544,000 0,866 Standard

30/03/2017

10:30

2159,45 1 079,723 937,000 536,500 0,868 Standard

03/05/2017

14:00

2150,70 1 075,350 916,500 562,500 0,852 Standard

04/05/2017

10:30

2142,03 1 071,017 895,500 587,500 0,836 Standard

06/06/2017

13:30

2133,54 1 066,771 920,000 540,000 0,862 Standard

04/05/2017

10:00

2118,14 1 059,070 902,000 555,000 0,852 Standard

AVERAGE 2175,04

Page 99: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

85

C. Top 10 Maximum Demand at STS 33 kV Transformer Feeders

397. STS E74 transformers

E74 Distribution tx

Block End kVA kVAh kWh

Consumed

kVarh

Lagging

PF Usage

Period

13/02/2017

01:00

2192,92 1 096,462 987,000 477,500 0,900 Off-Peak

22/08/2017

03:30

2185,59 1 092,797 954,000 533,000 0,915 Off-Peak

16/03/2017

03:30

1857,20 928,600 853,000 367,000 0,946 Off-Peak

08/02/2017

04:00

1686,53 843,265 769,000 346,000 0,912 Off-Peak

30/01/2017

12:00

1520,49 760,243 695,500 307,000 0,915 Standard

08/06/2017

00:00

1487,61 743,803 635,500 386,500 0,854 Off-Peak

12/05/2017

18:51

1479,51 739,757 666,000 322,000 0,900 Peak

08/06/2017

00:30

1472,24 736,120 635,500 371,500 0,863 Off-Peak

30/01/2017

11:00

1466,96 733,480 673,500 290,500 0,918 Standard

08/06/2017

03:30

1460,76 730,380 633,500 363,500 0,867 Off-Peak

AVERAGE 1680,98

397. STS E74 transformers

E74 Distribution tx

Block End kVA kVAh kWh

Consumed

kVarh

Lagging

PF Usage

Period

30/01/2017

12:00

1520,49 760,243 695,500 307,000 0,915 Standard

08/06/2017

00:00

1487,61 743,803 635,500 386,500 0,854 Off-Peak

08/06/2017

00:30

1472,24 736,120 635,500 371,500 0,863 Off-Peak

30/01/2017

11:00

1466,96 733,480 673,500 290,500 0,918 Standard

08/06/2017

03:30

1460,76 730,380 633,500 363,500 0,867 Off-Peak

08/06/2017

03:00

1458,90 729,449 633,000 362,500 0,868 Off-Peak

07/06/2017

23:30

1457,34 728,670 629,500 367,000 0,864 Off-Peak

16/08/2017

23:00

1456,19 728,095 639,000 349,000 0,878 Off-Peak

22/06/2017

18:00

1452,80 726,399 666,000 290,000 0,917 Peak

08/06/2017

02:30

1450,46 725,232 629,000 361,000 0,867 Off-Peak

AVERAGE 1468,37

Page 100: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

86

ANNEXURE B – CABLE SELECTION CALCULATIONS &

DATASHEETS

A. Cable Selection & Voltage Drop Calculations – For Cable after 132/33 kV 40 MVA

TFR1

Full Load Currents at Transformer 1 132/33 kV 40 MVA:

𝑰𝑭𝑳𝟏 = 𝑺

√𝟑×𝑽=

𝟒𝟎 × 𝟏𝟎𝟔

√𝟑×𝟑𝟑×𝟏𝟎𝟑 = 𝟔𝟗𝟗. 𝟖𝟏 𝑨 Before derating for non-standard conditions

Derating factor for Depth of Burial 1.3 m is 0.93 (Obtained from cable Facts and Figures booklet).

Derating Factor for Soil Thermal Resistivity at 1.2 k.m/W is 1.00

Derating Factor for Ground temperature of 25 ˚C is 1.00

Therefore the derating Factor = 0.93 x 1.00 x 1.00 = 0.93

Considering the derating factor for the full load current at standard conditions is as follows:

𝑰𝑭𝑳𝟏(𝒔𝒕𝒅)=𝑰𝑭𝑳𝟏 × 𝑻𝒐𝒕𝒂𝒍 𝑫𝒆𝒓𝒂𝒕𝒊𝒏𝒈 𝑭𝒂𝒄𝒕𝒐𝒓 = 𝟔𝟗𝟗. 𝟖𝟏 × 𝟎. 𝟗𝟑 = 𝟔𝟓𝟎. 𝟖𝟐 𝑨

With reference to CBI MV XLPE cables, Cu 1 core, 19000/33000 V, Type A datasheet and SANS

1339:

For a current rating (Trefoil) of 650.8 A, the current cable size is chosen to be 630 mm2.

Voltage Drop for 630 mm2 Cu XLPE cable:

Voltage Drop = Impedance (Ω/km) x Cable Length (km) x Full Load Current before derating (A)

𝑉𝑜𝑙𝑡𝑎𝑔𝑒 𝐷𝑟𝑜𝑝 =0.117

1000 × 50 × 699.82 = 4.09 𝑉

%𝑉𝑜𝑙𝑡𝑎𝑔𝑒 𝐷𝑟𝑜𝑝 =4.09 𝑉

33 × 103 𝑉× 100% = 0.0124%

The % Voltage drop is way less than 5% of 33 kV therefore 630 mm2 Cu XLPE cable size is

acceptable.

Cable Selection & Voltage Drop – For Cable after 132/33 kV 40 MVA TFR2

Full Load Currents at Transformer 2 132/33 kV 40 MVA:

𝑰𝑭𝑳𝟐 = 𝑺

√𝟑×𝑽=

𝟒𝟎 × 𝟏𝟎𝟔

√𝟑×𝟑𝟑×𝟏𝟎𝟑 = 𝟔𝟗𝟗. 𝟖𝟏 𝑨 Before derating for non-standard conditions

Derating factor for Depth of Burial 1.3 m is 0.93 (Obtained from cable Facts and Figures booklet).

Derating Factor for Soil Thermal Resistivity at 1.2 k.m/W is 1.00

Derating Factor for Ground temperature of 25 ˚C is 1.00

Therefore the derating Factor = 0.93 x 1.00 x 1.00 = 0.93

Considering the derating factor for the full load current at standard conditions is as follows:

Page 101: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

87

𝑰𝑭𝑳𝟐(𝒔𝒕𝒅)=𝑰𝑭𝑳𝟐 × 𝑻𝒐𝒕𝒂𝒍 𝑫𝒆𝒓𝒂𝒕𝒊𝒏𝒈 𝑭𝒂𝒄𝒕𝒐𝒓 = 𝟔𝟗𝟗. 𝟖𝟏 × 𝟎. 𝟗𝟑 = 𝟔𝟓𝟎. 𝟖𝟐 𝑨

With reference to CBI MV XLPE cables, Cu 1 core, 19000/33000 V, Type A datasheet and SANS

1339:

For a current rating (Trefoil) of 650.8 A, the current cable size is chosen to be 630 mm2.

Voltage Drop for 630 mm2 Cu XLPE cable:

Voltage Drop = Impedance (Ω/km) x Cable Length (km) x Full Load Current before derating (A)

𝑉𝑜𝑙𝑡𝑎𝑔𝑒 𝐷𝑟𝑜𝑝 =0.117

1000 × 50 × 699.82 = 4.09 𝑉

%𝑉𝑜𝑙𝑡𝑎𝑔𝑒 𝐷𝑟𝑜𝑝 =4.09 𝑉

33 × 103 𝑉× 100% = 0.0124%

The % Voltage drop is way less than 5% of 33 kV therefore 630 mm2 Cu XLPE cable size is

acceptable.

Cable Selection & Voltage Drop – For Cable after 33/11 kV 10 MVA TFR1 & CB G02

Full Load Currents at Transformer 1 33/11 kV 10 MVA:

𝑰𝑭𝑳𝟏𝟏 = 𝑺

√𝟑×𝑽=

𝟏𝟎 × 𝟏𝟎𝟔

√𝟑×𝟏𝟏×𝟏𝟎𝟑 = 𝟓𝟐𝟒. 𝟖𝟔 𝑨 Before derating for non-standard conditions

Derating factor for Depth of Burial 1.3 m is 0.93 (Obtained from cable Facts and Figures booklet).

Derating Factor for Soil Thermal Resistivity at 1.2 k.m/W is 1.00

Derating Factor for Ground temperature of 25 ˚C is 1.00

Therefore the derating Factor = 0.93 x 1.00 x 1.00 = 0.93

Considering the derating factor for the full load current at standard conditions is as follows:

𝑰𝑭𝑳𝟏𝟏(𝒔𝒕𝒅)=𝑰𝑭𝑳𝟏𝟏 × 𝑻𝒐𝒕𝒂𝒍 𝑫𝒆𝒓𝒂𝒕𝒊𝒏𝒈 𝑭𝒂𝒄𝒕𝒐𝒓 = 𝟓𝟐𝟒. 𝟖𝟔 × 𝟎. 𝟗𝟑 = 𝟒𝟖𝟖. 𝟏𝟐 𝑨

With reference to CBI MV XLPE cables, Cu 3 core, 6350/11000 V, Type A datasheet and SANS

1339:

For a current rating (in ground) of 488.12 A, the current cable size is chosen to be 300 mm2.

Voltage Drop for 300 mm2 Cu XLPE cable:

Voltage Drop = Impedance (Ω/km) x Cable Length (km) x Full Load Current before derating (A)

𝑉𝑜𝑙𝑡𝑎𝑔𝑒 𝐷𝑟𝑜𝑝 =0.119

1000 × 50 × 524.86 = 3.12 𝑉

%𝑉𝑜𝑙𝑡𝑎𝑔𝑒 𝐷𝑟𝑜𝑝 =3.12 𝑉

11 × 103 𝑉× 100% = 0.028%

The % Voltage drop is way less than 5% of 11 kV therefore 300 mm2 Cu XLPE cable size is

acceptable.

Page 102: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

88

Cable Selection & Voltage Drop – For Cable after 33/11 kV 10 MVA TFR2 & CB G01

Full Load Currents at Transformer 2 33/11 kV 10 MVA:

𝑰𝑭𝑳𝟐𝟐 = 𝑺

√𝟑×𝑽=

𝟏𝟎 × 𝟏𝟎𝟔

√𝟑×𝟏𝟏×𝟏𝟎𝟑 = 𝟓𝟐𝟒. 𝟖𝟔 𝑨 Before derating for non-standard conditions

Derating factor for Depth of Burial 1.3 m is 0.93 (Obtained from cable Facts and Figures booklet).

Derating Factor for Soil Thermal Resistivity at 1.2 k.m/W is 1.00

Derating Factor for Ground temperature of 25 ˚C is 1.00

Therefore the derating Factor = 0.93 x 1.00 x 1.00 = 0.93

Considering the derating factor for the full load current at standard conditions is as follows:

𝑰𝑭𝑳𝟐𝟐(𝒔𝒕𝒅)=𝑰𝑭𝑳𝟐𝟐 × 𝑻𝒐𝒕𝒂𝒍 𝑫𝒆𝒓𝒂𝒕𝒊𝒏𝒈 𝑭𝒂𝒄𝒕𝒐𝒓 = 𝟓𝟐𝟒. 𝟖𝟔 × 𝟎. 𝟗𝟑 = 𝟒𝟖𝟖. 𝟏𝟐 𝑨

With reference to CBI MV XLPE cables, Cu 3 core, 6350/11000 V, Type A datasheet and SANS

1339:

For a current rating (in ground) of 488.12 A, the current cable size is chosen to be 300 mm2.

Voltage Drop for 300 mm2 Cu XLPE cable:

Voltage Drop = Impedance (Ω/km) x Cable Length (km) x Full Load Current before derating (A)

𝑉𝑜𝑙𝑡𝑎𝑔𝑒 𝐷𝑟𝑜𝑝 =0.119

1000 × 50 × 524.86 = 3.12 𝑉

%𝑉𝑜𝑙𝑡𝑎𝑔𝑒 𝐷𝑟𝑜𝑝 =3.12 𝑉

11 × 103 𝑉× 100% = 0.028%

The % Voltage drop is way less than 5% of 11 kV therefore 300 mm2 Cu XLPE cable size is

acceptable.

Page 103: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

89

B. HVCABLES MANUFACTURERS DATASHEET

Page 104: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

90

C. MV CABLES MANUFACTURERS DATASHEET

Page 105: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

91

ANNEXURE C – 132/33/11 kV Distribution Electrical Network Implemented

in PowaMaster.

Page 106: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

92

ANNEXURE D – LOAD FLOW STUDY PowaMaster RESULTS

A. Busbar Reports for Various Scenarios

Scenario 1 : 5 Year Load Forecast - 2 x 40 MVA Trfs

Bus Name Bus Load

(kVA)

Bus Load

(PF)

Voltage

pu

Voltage pu

(Angle)

3-Ph

Fault (A)

3-Ph Fault

(Angle)

11 kV_1 499.35 0.94 1.05 -1.10 4768.828 -85.436

11 kV_10 102.33 0.82 1.04 -1.63 3494.878 -81.302

11 kV_11 1272.97 0.95 1.05 -1.38 5029.272 -85.198

11 kV_115 641.88 0.81 1.04 -1.63 4030.288 -82.739

11 kV_2 1304.61 0.91 1.04 -1.58 4768.642 -85.436

11 kV_22 2296.58 0.94 1.04 -1.93 5028.819 -85.198

11 kV_3 498.46 0.92 1.05 -1.11 4595.501 -84.264

11 kV_33 491.90 0.86 1.05 -1.10 4333.988 -85.169

11 kV_4 1301.63 0.90 1.04 -1.59 4595.345 -84.264

11 kV_5 163.34 0.95 1.05 -1.12 3880.335 -78.631

11 kV_55 1594.33 0.85 1.04 -1.25 6648.799 -86.073

11 kV_6 36.61 0.81 1.04 -1.60 3880.226 -78.631

11 kV_66 309.32 0.85 1.05 -1.17 6391.623 -85.935

11 kV_7 34.01 0.96 1.05 -1.12 2940.284 -76.957

11 kV_8 602.17 0.96 1.04 -1.64 3981.634 -81.523

11 kV_9 233.77 0.85 1.05 -1.12 4080.789 -82.875

132 kV_1 14181.98 1.00 1.00 0.00 39966.488 -90

132 kV_2 6545.75 0.98 1.00 -0.03 22257.819 -87.445

132 kV_3 7905.99 0.98 1.00 -0.04 22257.444 -87.445

33 kV

STS1 SUB

1275.28 0.95 1.05 28.88 2805.143 -84.637

33 kV_1 6522.76 0.98 1.05 29.14 6355.205 -87.222

33 kV_2 7872.29 0.98 1.05 28.96 6353.262 -87.221

33 kV_3 6683.67 0.96 1.05 29.09 6025.158 -87.109

33 kV_4 8042.07 0.96 1.05 28.90 6023.215 -87.108

33 kV_44 484.24 0.86 1.05 -1.29 4277.651 -85.134

33

kV_AD1

SUB

1599.98 0.85 1.05 29.04 4736.033 -86.122

33

kV_AD2

SUB

309.52 0.85 1.05 28.88 4361.046 -85.835

33

kV_DHI1

SUB

492.92 0.86 1.05 29.07 4362.066 -85.836

33

kV_DHI2

SUB

485.23 0.86 1.05 28.87 4195.328 -85.708

33

kV_STS2

SUB

2304.89 0.94 1.05 28.54 2804.721 -84.637

400 V_1 76.65 0.95 1.05 -31.31 20336.206 -78.424

400 V_2 46.56 0.95 1.04 -31.72 20336.097 -78.424

400 V_5 33.99 0.96 1.10 -31.18 19972.135 -77.212

400 V_6 594.87 0.97 1.08 -32.99 21513.466 -78.22

Page 107: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

93

400V_3 162.76 0.95 1.10 -31.46 21383.709 -77.6

400V_4 36.52 0.81 1.08 -31.71 12310.67 -77.472

400V_7 232.13 0.85 1.09 -31.53 21634.398 -78.489

400V_8 101.66 0.82 1.09 -31.98 11859.998 -77.85

400V_9 532.32 0.81 1.06 -32.53 22099.318 -78.472

Scenario 2 : 5 Year Load Forecast - 1 x 40 MVA Trfs

Bus Name Bus Load

(kVA)

Bus Load

(PF) Voltage pu

Voltage pu

(Angle)

3-Ph

Fault (A)

3-Ph Fault

(Angle)

11 kV_1 499.36 0.94 1.04 -2.15 4763.997 -85.435

11 kV_10 102.32 0.82 1.04 -2.51 3492.48 -81.304

11 kV_11 1272.88 0.95 1.04 -2.43 5023.888 -85.197

11 kV_115 641.94 0.81 1.04 -2.50 4027.096 -82.741

11 kV_2 1304.77 0.91 1.04 -2.45 4764.173 -85.435

11 kV_22 2296.50 0.94 1.04 -2.80 5023.838 -85.197

11 kV_3 498.45 0.92 1.04 -2.16 4591.014 -84.264

11 kV_33 491.80 0.86 1.04 -2.15 4329.999 -85.168

11 kV_4 1301.78 0.90 1.04 -2.47 4591.194 -84.264

11 kV_5 163.32 0.95 1.04 -2.17 3877.151 -78.635

11 kV_55 1594.19 0.85 1.04 -2.30 6639.42 -86.071

11 kV_6 36.59 0.81 1.04 -2.47 3877.281 -78.636

11 kV_66 309.20 0.85 1.04 -2.04 6383.6 -85.933

11 kV_7 33.98 0.96 1.04 -2.17 2938.462 -76.962

11 kV_8 602.21 0.96 1.04 -2.52 3978.521 -81.525

11 kV_9 233.75 0.85 1.04 -2.17 4077.252 -82.876

132 kV_1 14322.15 0.99 1.00 0.00 39976.301 -90

132 kV_2 14517.49 0.98 1.00 -0.07 22255.893 -87.443

132 kV_3 -0.53 0.02 0.99 -1.92 916.301 -87.212

33 kV

STS1 SUB 1275.22 0.95 1.04 27.83 2800.122 -84.637

33 kV_1 14399.22 0.98 1.04 28.09 6329.599 -87.211

33 kV_2 31.19 -0.50 1.04 28.09 6329.578 -87.211

33 kV_3 6685.41 0.96 1.04 28.04 6002.127 -87.099

33 kV_4 8043.78 0.96 1.04 28.03 6001.913 -87.099

33 kV_44 484.15 0.86 1.04 -2.16 4274.055 -85.133

33

kV_AD1

SUB

1599.89 0.85 1.04 27.99 4721.779 -86.117

33

kV_AD2

SUB

309.40 0.85 1.04 28.01 4349.856 -85.831

33

kV_DHI1

SUB

492.82 0.86 1.04 28.01 4349.968 -85.832

33

kV_DHI2

SUB

485.15 0.86 1.04 28.00 4184.97 -85.705

Page 108: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

94

33

kV_STS2

SUB

2304.88 0.94 1.04 27.66 2800.075 -84.637

400 V_1 76.63 0.95 1.04 -32.36 20333.026 -78.425

400 V_2 46.54 0.95 1.04 -32.59 20333.155 -78.425

400 V_5 33.96 0.96 1.09 -32.24 19968.761 -77.213

400 V_6 594.84 0.97 1.08 -33.88 21509.837 -78.221

400V_3 162.72 0.95 1.09 -32.52 21379.839 -77.601

400V_4 36.50 0.81 1.07 -32.59 12309.512 -77.472

400V_7 232.09 0.85 1.09 -32.59 21630.43 -78.49

400V_8 101.64 0.82 1.08 -32.86 11858.895 -77.851

400V_9 532.29 0.81 1.06 -33.41 22095.578 -78.473

Scenario 3 : 7 Year Load Forecast - 2 x 40 MVA Trfs

Bus Name Bus Load

(kVA)

Bus Load

(PF) Voltage pu

Voltage pu

(Angle)

3-Ph

Fault (A)

3-Ph

Fault

(Angle)

11 kV_1 499.36 0.94 1.04 -2.28 4768.828 -85.436

11 kV_10 102.31 0.82 1.03 -3.14 3494.878 -81.302

11 kV_11 1272.79 0.95 1.04 -2.56 5029.272 -85.198

11 kV_115 642.08 0.81 1.03 -3.13 4030.288 -82.739

11 kV_2 1305.03 0.91 1.03 -3.08 4768.642 -85.436

11 kV_22 2296.34 0.94 1.03 -3.44 5028.819 -85.198

11 kV_3 498.45 0.92 1.04 -2.29 4595.501 -84.264

11 kV_33 491.72 0.86 1.04 -2.28 4333.988 -85.169

11 kV_4 1302.06 0.90 1.03 -3.10 4595.345 -84.264

11 kV_5 163.30 0.95 1.04 -2.30 3880.335 -78.631

11 kV_55 1594.09 0.85 1.04 -2.43 6648.799 -86.073

11 kV_6 36.57 0.81 1.03 -3.10 3880.226 -78.631

11 kV_66 309.01 0.85 1.04 -2.66 6391.623 -85.935

11 kV_7 33.96 0.96 1.04 -2.30 2940.284 -76.957

11 kV_8 602.29 0.96 1.03 -3.14 3981.634 -81.523

11 kV_9 233.75 0.85 1.04 -2.30 4080.789 -82.875

132 kV_1 33766.10 0.97 1.00 0.00 39966.488 -90

132 kV_2 15327.97 0.96 1.00 -0.07 22257.819 -87.445

132 kV_3 19022.24 0.95 1.00 -0.09 22257.444 -87.445

33 kV STS1

SUB

1275.14 0.95 1.04 27.70 2805.143 -84.637

33 kV_1 15155.49 0.97 1.04 28.02 6355.205 -87.222

33 kV_2 18751.84 0.97 1.04 27.55 6353.262 -87.221

33 kV_3 15337.84 0.95 1.04 27.91 6025.158 -87.109

33 kV_4 18943.13 0.95 1.04 27.41 6023.215 -87.108

33 kV_44 484.00 0.86 1.03 -2.79 4277.651 -85.134

Page 109: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

95

33 kV_AD1

SUB

1599.84 0.85 1.04 27.86 4736.033 -86.122

33 kV_AD2

SUB

309.21 0.85 1.04 27.39 4361.046 -85.835

33

kV_DHI1

SUB

492.75 0.86 1.04 27.89 4362.066 -85.836

33

kV_DHI2

SUB

485.01 0.86 1.04 27.38 4195.328 -85.708

33

kV_STS2

SUB

2304.83 0.94 1.03 27.04 2804.721 -84.637

400 V_1 76.61 0.95 1.04 -32.49 20336.206 -78.424

400 V_2 46.51 0.95 1.03 -33.22 20336.097 -78.424

400 V_5 33.94 0.96 1.09 -32.37 19972.135 -77.212

400 V_6 594.81 0.97 1.07 -34.52 21513.466 -78.22

400V_3 162.71 0.95 1.09 -32.65 21383.709 -77.6

400V_4 36.48 0.81 1.07 -33.22 12310.67 -77.472

400V_7 232.07 0.85 1.08 -32.72 21634.398 -78.489

400V_8 101.62 0.82 1.07 -33.49 11859.997 -77.85

400V_9 532.25 0.81 1.05 -34.05 22099.318 -78.472

Scenario 4 : 7 Year Load Forecast - 1 x 40 MVA Trf

Bus Name Bus Load

(kVA)

Bus Load

(PF)

Voltage

pu

Voltage pu

(Angle)

3-Ph

Fault (A)

3-Ph Fault

(Angle)

11 kV_1 499.02 0.94 1.04 -4.81 4712.568 -85.453

11 kV_10 102.28 0.82 1.04 -5.18 3464.888 -81.35

11 kV_11 1272.43 0.95 1.05 -5.10 4872.53 -85.18

11 kV_115 641.91 0.81 1.04 -5.18 3990.374 -82.781

11 kV_2 1304.42 0.91 1.04 -5.13 4712.743 -85.453

11 kV_22 2296.02 0.94 1.04 -5.49 4872.48 -85.18

11 kV_3 498.42 0.92 1.04 -4.82 4543.27 -84.293

11 kV_33 491.35 0.86 1.04 -4.81 4271.554 -85.177

11 kV_4 1301.79 0.90 1.04 -5.14 4543.449 -84.293

11 kV_5 163.28 0.95 1.04 -4.83 3843.369 -78.71

11 kV_55 1593.60 0.85 1.04 -4.96 6481.609 -86.072

11 kV_6 36.55 0.81 1.04 -5.15 3843.498 -78.71

11 kV_66 308.61 0.85 1.05 -4.72 6225.409 -85.93

11 kV_7 33.94 0.96 1.04 -4.83 2919.107 -77.029

11 kV_8 602.19 0.96 1.04 -5.19 3942.742 -81.575

11 kV_9 233.70 0.85 1.04 -4.83 4039.607 -82.915

132 kV_1 34571.03 0.95 1.00 0.00 39976.287 -90

132 kV_2 34890.48 0.94 1.00 -0.16 22255.879 -87.443

132 kV_3 -1.19 0.04 0.97 -4.50 916.297 -87.212

33 kV

STS1 SUB

1274.74 0.95 1.02 25.16 2800.112 -84.637

Page 110: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

96

33 kV_1 33928.62 0.96 1.02 25.50 6329.55 -87.211

33 kV_2 30.49 -0.49 1.02 25.50 6329.529 -87.211

33 kV_3 15343.56 0.95 1.02 25.38 6002.08 -87.099

33 kV_4 18947.99 0.95 1.02 25.35 6001.867 -87.099

33 kV_44 483.70 0.86 1.04 -4.84 4214.886 -85.141

33

kV_AD1

SUB

1599.25 0.85 1.02 25.33 4721.75 -86.117

33

kV_AD2

SUB

308.80 0.85 1.02 25.34 4349.831 -85.831

33

kV_DHI1

SUB

492.37 0.86 1.02 25.36 4349.943 -85.832

33

kV_DHI2

SUB

484.70 0.86 1.02 25.33 4184.947 -85.705

33

kV_STS2

SUB

2304.33 0.94 1.02 24.97 2800.065 -84.637

400 V_1 76.60 0.95 1.04 -35.02 20299.021 -78.44

400 V_2 46.50 0.95 1.04 -35.27 20299.152 -78.44

400 V_5 33.92 0.96 1.09 -34.90 19932.728 -77.231

400 V_6 594.81 0.97 1.07 -36.56 21467.919 -78.238

400V_3 162.69 0.95 1.09 -35.18 21338.495 -77.619

400V_4 36.47 0.81 1.07 -35.26 12296.126 -77.483

400V_7 232.03 0.85 1.09 -35.25 21588.008 -78.507

400V_8 101.61 0.82 1.08 -35.53 11846.155 -77.861

400V_9 532.23 0.81 1.06 -36.09 22052.362 -78.49

Scenario 5 : 10 Year Load Forecast - 2 x 40 MVA Trfs

Bus Name Bus Load

(kVA)

Bus Load

(PF) Voltage pu

Voltage pu

(Angle)

3-Ph

Fault (A)

3-Ph

Fault

(Angle)

11 kV_1 499.36 0.94 1.03 -2.80 4768.828 -85.436

11 kV_10 102.31 0.82 1.04 -3.79 3467.348 -81.348

11 kV_11 1272.71 0.95 1.03 -3.08 5029.272 -85.198

11 kV_115 641.77 0.81 1.04 -3.78 3993.641 -82.779

11 kV_2 1304.13 0.91 1.05 -3.73 4717.301 -85.454

11 kV_22 2296.19 0.94 1.04 -4.10 4953.394 -85.189

11 kV_3 498.45 0.92 1.03 -2.80 4595.501 -84.264

11 kV_33 2142.42 0.93 1.03 -3.55 4333.988 -85.169

11 kV_4 1301.49 0.90 1.05 -3.75 4547.686 -84.293

11 kV_5 163.29 0.95 1.03 -2.81 3880.335 -78.631

11 kV_55 1593.98 0.85 1.03 -2.95 6648.799 -86.073

11 kV_6 36.58 0.81 1.05 -3.75 3846.515 -78.705

Page 111: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

97

11 kV_66 3528.20 0.91 1.03 -4.14 6313.04 -85.934

11 kV_7 33.94 0.96 1.03 -2.81 2940.284 -76.957

11 kV_8 602.11 0.96 1.04 -3.79 3945.928 -81.573

11 kV_9 233.74 0.85 1.03 -2.81 4080.789 -82.875

132 kV_1 42655.65 0.96 1.00 0.00 39966.482 -90

132 kV_2 19178.47 0.95 1.00 -0.09 22257.817 -87.445

132 kV_3 24135.04 0.94 1.00 -0.11 22257.438 -87.445

33 kV STS1

SUB

1275.08 0.95 1.04 27.18 2805.143 -84.637

33 kV_1 18893.83 0.96 1.04 27.54 6355.205 -87.222

33 kV_2 23656.54 0.96 1.03 26.92 6353.239 -87.221

33 kV_3 19074.08 0.95 1.04 27.40 6025.158 -87.109

33 kV_4 23850.97 0.95 1.03 26.74 6023.192 -87.108

33 kV_44 2134.47 0.93 1.04 -4.20 4218.532 -85.142

33 kV_AD1

SUB

1599.77 0.85 1.04 27.34 4736.033 -86.122

33 kV_AD2

SUB

3551.31 0.91 1.03 26.56 4361.034 -85.835

33

kV_DHI1

SUB

2158.08 0.93 1.03 27.28 4362.066 -85.836

33

kV_DHI2

SUB

2149.56 0.93 1.03 26.61 4195.317 -85.708

33

kV_STS2

SUB

2304.58 0.94 1.03 26.36 2804.716 -84.637

400 V_1 76.60 0.95 1.03 -33.01 20336.206 -78.424

400 V_2 46.54 0.95 1.04 -33.87 20302.209 -78.439

400 V_5 33.92 0.96 1.08 -32.88 19972.135 -77.212

400 V_6 594.86 0.97 1.08 -35.14 21471.687 -78.237

400V_3 162.69 0.95 1.08 -33.17 21383.709 -77.6

400V_4 36.50 0.81 1.08 -33.87 12297.331 -77.482

400V_7 232.05 0.85 1.08 -33.24 21634.398 -78.489

400V_8 101.64 0.82 1.09 -34.13 11847.302 -77.86

400V_9 532.28 0.81 1.06 -34.68 22056.246 -78.489

Scenario 6 : 10 Year Load Forecast - 1 x 40 MVA Trfs

Bus Name Bus Load

(kVA)

Bus Load

(PF) Voltage pu

Voltage pu

(Angle)

3-Ph

Fault (A)

3-Ph Fault

(Angle)

11 kV_1 499.42 0.94 1.03 -7.49 4755.99 -85.438

11 kV_10 102.24 0.82 1.03 -7.88 3488.197 -81.312

11 kV_11 1272.82 0.95 1.05 -7.76 4939.618 -85.192

11 kV_115 642.00 0.81 1.03 -7.88 4021.388 -82.747

11 kV_2 1305.06 0.91 1.03 -7.83 4756.166 -85.438

11 kV_22 2296.38 0.94 1.04 -8.17 4939.568 -85.192

Page 112: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

98

11 kV_3 498.39 0.92 1.03 -7.49 4583.584 -84.269

11 kV_33 3466.16 0.91 1.04 -8.74 4264.862 -85.18

11 kV_4 1302.03 0.90 1.03 -7.84 4583.764 -84.269

11 kV_5 163.22 0.95 1.03 -7.51 3871.904 -78.647

11 kV_55 1593.85 0.85 1.04 -7.63 6545.511 -86.075

11 kV_6 36.50 0.81 1.03 -7.84 3872.034 -78.647

11 kV_66 4324.86 0.92 1.04 -8.41 6290.649 -85.935

11 kV_7 33.88 0.96 1.03 -7.50 2935.462 -76.973

11 kV_8 602.24 0.96 1.03 -7.89 3972.961 -81.533

11 kV_9 233.64 0.85 1.03 -7.51 4071.4 -82.883

132 kV_1 59899.88 0.91 1.00 0.00 39975.14 -90

132 kV_2 60202.91 0.91 1.00 -0.26 22254.734 -87.443

132 kV_3 -1.77 0.06 0.95 -7.11 989.691 -87.213

33 kV

STS1 SUB

1275.13 0.95 1.04 22.49 2791.821 -84.645

33 kV_1 57096.51 0.95 1.04 22.90 6287.423 -87.212

33 kV_2 31.24 -0.45 1.04 22.90 6287.402 -87.212

33 kV_3 25759.12 0.95 1.04 22.71 5964.173 -87.101

33 kV_4 31701.47 0.94 1.04 22.66 5963.961 -87.101

33 kV_44 3457.17 0.91 1.04 -8.80 4208.369 -85.145

33

kV_AD1

SUB

1599.50 0.85 1.04 22.65 4698.261 -86.123

33

kV_AD2

SUB

4358.25 0.91 1.03 22.44 4329.888 -85.839

33

kV_DHI1

SUB

3511.69 0.90 1.03 22.53 4330 -85.839

33

kV_DHI2

SUB

3502.65 0.90 1.03 22.46 4166.483 -85.712

33

kV_STS2

SUB

2304.68 0.94 1.03 22.29 2791.774 -84.645

400 V_1 76.54 0.95 1.03 -37.70 20327.775 -78.427

400 V_2 46.45 0.95 1.03 -37.97 20327.905 -78.427

400 V_5 33.86 0.96 1.08 -37.57 19963.197 -77.216

400 V_6 594.75 0.97 1.07 -39.27 21503.364 -78.224

400V_3 162.62 0.95 1.08 -37.86 21373.455 -77.604

400V_4 36.42 0.81 1.07 -37.96 12307.446 -77.474

400V_7 231.95 0.85 1.08 -37.93 21623.878 -78.493

400V_8 101.56 0.82 1.07 -38.24 11856.929 -77.853

400V_9 532.14 0.81 1.05 -38.80 22088.904 -78.475

Page 113: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

99

A. Cable Loading Reports for Various Scenarios

Scenario 1 : 5 Year Load Forecast - 2 x 40 MVA Trfs

From

Bus

Name

To Bus

Name

Section Conductor

Description

Total

Length

(km)

% Branch

Loading A Name

Branch

Rating A

(A)

11 kV_4 11

kV_115

11 kV 150mm2 Cu

XLPE 1Core 0.5 8.8

150 mm^2

XLPE Cu_1 365

11 kV_10 11

kV_115

11 kV 150mm2 Cu

XLPE 1Core 0.62 1.38

150 mm^2

XLPE Cu_2 365

11 kV_9 11 kV_10 11 kV 150mm2 Cu

XLPE 1Core 0.62 0

150 mm^2

XLPE Cu_3 365

11 kV_3 11 kV_9 11 kV 150mm2 Cu

XLPE 1Core 0.45 3.19

150 mm^2

XLPE Cu_4 365

11 kV_1 11 kV_3 300 XLPE 11kV

Cu 1C Tre Gnd 0.5 4.73

300 mm^2

XLPE Cu 1 C 520

11 kV_2 11 kV_4 300 XLPE 11kV

Cu 1C Tre Gnd 0.5 12.55

300 mm^2

XLPE Cu 1C 520

33 kV_4 33

kV_DHI2

SUB

33 kV 400mm2 Cu

XLPE 1Core 4 1.3 400 mm^2

Cu XLPE_4 545

33 kV_4 33

kV_STS2

SUB

33 kV 400mm2 Cu

XLPE 1Core 10.5 6.72 400 mm^2 Cu

XLPE_2 545

33 kV_3 33 kV

STS1

SUB

33 kV 400mm2 Cu

XLPE 1Core 10.5 3.71 400 mm^2 Cu

XLPE_1 545

33 kV_3 33

kV_DHI1

SUB

33 kV 400mm2 Cu

XLPE 1Core 3.5 1.33 400 mm^2 Cu

XLPE_3 545

33 kV_3 33

kV_AD1

SUB

33 kV 400mm2 Cu

XLPE 1Core 2.5 4.73 400 mm^2 Cu

XLPE_55 545

33 kV_4 33

kV_AD2

SUB

33 kV 400mm2 Cu

XLPE 1Core 3.5 0.81 400 mm^2 Cu

XLPE_66 545

11 kV_3 11 kV_5 11 kV 50mm2 Cu

XLPE 1Core 0.5 4.08

50 mm^2

XLPE Cu _1 200

11 kV_5 11 kV_6 11 kV 50mm2 Cu

XLPE 1Core 0 0

50 mm^2

XLPE Cu_2 200

11 kV_4 11 kV_6 11 kV 50mm2 Cu

XLPE 1Core 0.5 0.89

50 mm^2

XLPE Cu_3 200

132 kV_1 132 kV_2 132 kV 500mm2 Al

XLPE 1Core 2.5 4.83

500 mm^2 Al

XLPE_1 581

132 kV_1 132 kV_3 132 kV 500mm2 Al

XLPE 1Core 2.5 5.84

500 mm^2 Al

XLPE_2 581

33 kV_1 33 kV_3 33 kV 630mm2 Cu

XLPE 1Core 0.5 15.88

630 mm^2 Cu

XLPE_1 684

33 kV_2 33 kV_4 33 kV 630mm2 Cu

XLPE 1Core 0.5 19.19

630 mm^2 Cu

XLPE_2 684

11 kV_7 11 kV_8 11 kV 95mm2 Cu

XLPE 1Core 0.72 0

95 mm^2 Cu

XLPE Cu_2 290

Page 114: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

100

11 kV_3 11 kV_7 11 kV 95mm2 Cu

XLPE 1Core 1.8 0.56

95 mm^2

XLPE Cu_1 290

11 kV_4 11 kV_8 11 kV 95mm2 Cu

XLPE 1Core 0.5 10.45

95 mm^2

XLPE Cu_5 290

132 kV_2 132 kV_3 SWCH 0 0 Bus Section 1 5000

33 kV_1 33 kV_2 SWCH 0 0 Bus Section 2 5000

33 kV_3 33 kV_4 SWCH 0 0 Bus Section 3 5000

11 kV_1 11 kV_2 SWCH 0 0 Bus Section 4 5000

11 kV_3 11 kV_4 SWCH 0 0 Bus Section 5 5000

400 V_1 400 V_2 SWCH 0 0 Bus Section 6 5000

33 kV

STS1

SUB

33

kV_STS2

SUB

SWCH

0 0 Bus Section 7 5000

33

kV_DHI1

SUB

33

kV_DHI2

SUB

SWCH

0 0 Bus Section 8 5000

33

kV_AD1

SUB

33

kV_AD2

SUB

SWCH

0 0 Bus Section 9 5000

Scenario 2 : 5 Year Load Forecast - 1 x 40 MVA Trfs

From

Bus

Name

To Bus

Name

Section

Conductor

Description

Total

Length

(km)

% Branch

Loading A Name

Branch

Rating A

(A)

11 kV_4 11

kV_115

11 kV 150mm2 Cu

XLPE 1Core 0.5 8.84

150 mm^2

XLPE Cu_1 365

11 kV_10 11

kV_115

11 kV 150mm2 Cu

XLPE 1Core 0.62 1.39

150 mm^2

XLPE Cu_2 365

11 kV_9 11 kV_10 11 kV 150mm2 Cu

XLPE 1Core 0.62 0

150 mm^2

XLPE Cu_3 365

11 kV_3 11 kV_9 11 kV 150mm2 Cu

XLPE 1Core 0.45 3.21

150 mm^2

XLPE Cu_4 365

11 kV_1 11 kV_3 300 XLPE 11kV

Cu 1C Tre Gnd 0.5 4.76

300 mm^2

XLPE Cu 1 C 520

11 kV_2 11 kV_4 300 XLPE 11kV

Cu 1C Tre Gnd 0.5 12.61

300 mm^2

XLPE Cu 1C 520

33 kV_4 33

kV_DHI2

SUB

33 kV 400mm2 Cu

XLPE 1Core 4 1.3 400 mm^2

Cu XLPE_4 545

33 kV_4 33

kV_STS2

SUB

33 kV 400mm2 Cu

XLPE 1Core 10.5 6.75 400 mm^2 Cu

XLPE_2 545

33 kV_3 33 kV

STS1

SUB

33 kV 400mm2 Cu

XLPE 1Core 10.5 3.73 400 mm^2 Cu

XLPE_1 545

33 kV_3 33

kV_DHI1

SUB

33 kV 400mm2 Cu

XLPE 1Core 3.5 1.34 400 mm^2 Cu

XLPE_3 545

33 kV_3 33

kV_AD1

SUB

33 kV 400mm2 Cu

XLPE 1Core 2.5 4.76 400 mm^2 Cu

XLPE_55 545

Page 115: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

101

33 kV_4 33

kV_AD2

SUB

33 kV 400mm2 Cu

XLPE 1Core 3.5 0.82 400 mm^2 Cu

XLPE_66 545

11 kV_3 11 kV_5 11 kV 50mm2 Cu

XLPE 1Core 0.5 4.1

50 mm^2

XLPE Cu _1 200

11 kV_5 11 kV_6 11 kV 50mm2 Cu

XLPE 1Core 0 0

50 mm^2

XLPE Cu_2 200

11 kV_4 11 kV_6 11 kV 50mm2 Cu

XLPE 1Core 0.5 0.9

50 mm^2

XLPE Cu_3 200

132 kV_1 132 kV_2 132 kV 500mm2

Al XLPE 1Core 2.5 10.78

500 mm^2 Al

XLPE_1 581

132 kV_1 132 kV_3 132 kV 500mm2

Al XLPE 1Core 2.5 0

500 mm^2 Al

XLPE_2 581

33 kV_1 33 kV_3 33 kV 630mm2 Cu

XLPE 1Core 0.5 15.96

630 mm^2 Cu

XLPE_1 684

33 kV_2 33 kV_4 33 kV 630mm2 Cu

XLPE 1Core 0.5 19.27

630 mm^2 Cu

XLPE_2 684

11 kV_7 11 kV_8 11 kV 95mm2 Cu

XLPE 1Core 0.72 0

95 mm^2 Cu

XLPE Cu_2 290

11 kV_3 11 kV_7 11 kV 95mm2 Cu

XLPE 1Core 1.8 0.56

95 mm^2

XLPE Cu_1 290

11 kV_4 11 kV_8 11 kV 95mm2 Cu

XLPE 1Core 0.5 10.5

95 mm^2

XLPE Cu_5 290

132 kV_2 132 kV_3 SWCH 0 0 Bus Section 1 5000

33 kV_1 33 kV_2 SWCH 0 2.64 Bus Section 2 5000

33 kV_3 33 kV_4 SWCH 0 0 Bus Section 3 5000

11 kV_1 11 kV_2 SWCH 0 0 Bus Section 4 5000

11 kV_3 11 kV_4 SWCH 0 0 Bus Section 5 5000

400 V_1 400 V_2 SWCH 0 0 Bus Section 6 5000

33 kV

STS1

SUB

33

kV_STS2

SUB

SWCH

0 0 Bus Section 7 5000

33

kV_DHI1

SUB

33

kV_DHI2

SUB

SWCH

0 0 Bus Section 8 5000

33

kV_AD1

SUB

33

kV_AD2

SUB

SWCH

0 0 Bus Section 9 5000

Page 116: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

102

ANNEXURE E – INTELLIGENT ELECTRONIC DEVICES USED

A. IEDs Compliant to IEC 61850

Page 117: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

103

B. Legacy IEDs

Page 118: UPGRADING EXISTING POWER SUPPLY AT THE PORT OF …

104

C. Remote Terminal Unit