ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 1 Update on the NEETRAC Project High Temperature Connector Committee Testing Support Phase II Project No. 16-123 Principle Investigator: Joe Goldenburg Co-PI: Dylan Summer Project Reviewer: Nigel Hampton

Upload: others

Post on 24-Feb-2021

20 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Update on the NEETRAC Project High Temperature Connector … C119... · 2017. 10. 31. · ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 9 Test Plan (Tension

ANSI C119.7 September 2017 MeetingHigh Temperature Connector Testing

1

Update on the NEETRAC Project

High Temperature Connector Committee Testing Support Phase II

Project No. 16-123

Principle Investigator: Joe GoldenburgCo-PI: Dylan Summer

Project Reviewer: Nigel Hampton

Page 2: Update on the NEETRAC Project High Temperature Connector … C119... · 2017. 10. 31. · ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 9 Test Plan (Tension

ANSI C119.7 September 2017 MeetingHigh Temperature Connector Testing

2

Purpose• Conduct testing on connectors used with HTLS conductors

that will help the industry better understand their performance under tension

• This project will help support the ANSI C119.7 Committee on Connectors for use with High Temperature Conductor by providing information that will help them finalize a high temperature conductor test standard

• Share data (only) with the ANSI C119.7

Project No. 16-123: High Temperature Connector Committee Testing Support Phase II

Page 3: Update on the NEETRAC Project High Temperature Connector … C119... · 2017. 10. 31. · ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 9 Test Plan (Tension

ANSI C119.7 September 2017 MeetingHigh Temperature Connector Testing

3

Tasks• Order / receive materials• Finalize testing parameters with TAs and ANSI C119.7• Design and build tension frames• Current Cycle Test first loop• Current Cycle Test second loop.• Current Cycle Test third loop• Prepare closeout• Write report• Communicate with NEETRAC Technical Advisors• Communicate with ANSI C119.7 Committee

Project No. 16-123: High Temperature Connector Committee Testing Support Phase II

Page 4: Update on the NEETRAC Project High Temperature Connector … C119... · 2017. 10. 31. · ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 9 Test Plan (Tension

ANSI C119.7 September 2017 MeetingHigh Temperature Connector Testing

4

Test Plan (General 1/2)• There will be three tension conditions for each CCT loop.• For all three conditions:

– Samples consist of 1 AFL splice and 2 AFL dead-ends with Drake ACSS HS285. Thank you Gary Sibilant / EPRI for the conductor! Thank you Wayne Quesnel / AFL for the connectors!

– Samples are approximately 30 ft. long (eye to eye).– Tension will be monitored continuously.– Control temperature is set to 250° C and continuously

monitored.

Project No. 16-123: High Temperature Connector Committee Testing Support Phase II

F

Page 5: Update on the NEETRAC Project High Temperature Connector … C119... · 2017. 10. 31. · ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 9 Test Plan (Tension

ANSI C119.7 September 2017 MeetingHigh Temperature Connector Testing

5

Test Plan (General 2/2)

Project No. 16-123: High Temperature Connector Committee Testing Support Phase II

NEETRAC DC measurement:• DC resistance (10 amp) every 10th cycle using wire

equalizers, similar to the IEC method.• We plot multiple currents and resulting voltages to reduce

error.

Page 6: Update on the NEETRAC Project High Temperature Connector … C119... · 2017. 10. 31. · ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 9 Test Plan (Tension

ANSI C119.7 September 2017 MeetingHigh Temperature Connector Testing

6

Test Plan (General)• There will be three tension conditions for each CCT loop.• For all three conditions:

– Samples consist of 1 splice and 2 dead-ends with Drake ACSS HS285.– Samples are approximately 30 ft. long (eye to eye).– Tension will be monitored continuously.– Control temperature is set to 250° C and continuously monitored.– DC resistance (10 amp) every 10th cycle using wire equalizers.– DC resistance every 50th cycle using new method developed at

NEETRAC.• After 500 cycle CCT, all samples will be separated for tensile

testing.

F F

FFProject No. 16-123: High Temperature Connector Committee Testing Support Phase II

Page 7: Update on the NEETRAC Project High Temperature Connector … C119... · 2017. 10. 31. · ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 9 Test Plan (Tension

ANSI C119.7 September 2017 MeetingHigh Temperature Connector Testing

7

Test Plan (Tension Conditions 1/3)Condition 1

• Constant tension at 18% RBS– Continuous tension monitoring (1 per minute)

• Temperature cycles: temp and 250 °C for 500 cycles.– Continuous temperature monitoring (1 per minute)

• DC resistance (10 amp) every 10th cycle using wire equalizers.

• DC resistance every 50th cycle using new method developed at NEETRAC.

F

Project No. 16-123: High Temperature Connector Committee Testing Support Phase II

Page 8: Update on the NEETRAC Project High Temperature Connector … C119... · 2017. 10. 31. · ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 9 Test Plan (Tension

ANSI C119.7 September 2017 MeetingHigh Temperature Connector Testing

8

Test Plan (Tension Conditions 2/3)Condition 2

Project No. 16-123: High Temperature Connector Committee Testing Support Phase II

F

• Tension will be raised to 25% RBS and held for 20 minutes after which time displacement will be fixed.

– The tension will vary as the conductor heats and cools.– Continuous tension monitoring (1 per minute)

• Temperature cycles: room temp and 250 °C for 500 cycles.– Continuous temperature monitoring (1 per minute)

• DC resistance (10 amp) every 10th cycle using wire equalizers.

• DC resistance every 50th cycle using new method developed at NEETRAC.

Page 9: Update on the NEETRAC Project High Temperature Connector … C119... · 2017. 10. 31. · ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 9 Test Plan (Tension

ANSI C119.7 September 2017 MeetingHigh Temperature Connector Testing

9

Test Plan (Tension Conditions 3/3)Condition 3

F

Project No. 16-123: High Temperature Connector Committee Testing Support Phase II

• Tension will be raised to 25% RBS and the displacement will be fixed immediately.

– The tension will vary as the conductor heats and cools.– Tension will be resent to 25% RBS every 10th cycle.– Continuous tension monitoring (1 measurement per minute)

• Temperature cycles: room temp and 250 °C for 500 cycles.– Continuous temperature monitoring (1 per minute)

• DC resistance (10 amp) every 10th cycle using wire equalizers.

• DC resistance every 50th cycle using new method developed at NEETRAC.

Page 10: Update on the NEETRAC Project High Temperature Connector … C119... · 2017. 10. 31. · ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 9 Test Plan (Tension

ANSI C119.7 September 2017 MeetingHigh Temperature Connector Testing

10

Test Plan (Loop Diagram)

F

F

Project No. 16-123: High Temperature Connector Committee Testing Support Phase II

F

Control

Page 11: Update on the NEETRAC Project High Temperature Connector … C119... · 2017. 10. 31. · ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 9 Test Plan (Tension

ANSI C119.7 September 2017 MeetingHigh Temperature Connector Testing

11

Tension Frames

Project No. 16-123: High Temperature Connector Committee Testing Support Phase II

• Modular construction• Hydraulic system for fixed tension.• Turnbuckles for fixed displacement.

Page 12: Update on the NEETRAC Project High Temperature Connector … C119... · 2017. 10. 31. · ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 9 Test Plan (Tension

ANSI C119.7 September 2017 MeetingHigh Temperature Connector Testing

12

Tension Frames• Modular construction• Hydraulic system for fixed

tension.• Turnbuckles for fixed

displacement.

Project No. 16-123: High Temperature Connector Committee Testing Support Phase II

Page 13: Update on the NEETRAC Project High Temperature Connector … C119... · 2017. 10. 31. · ANSI C119.7 September 2017 Meeting High Temperature Connector Testing 9 Test Plan (Tension

ANSI C119.7 September 2017 MeetingHigh Temperature Connector Testing

13

Schedule• Depends on the status of an existing NEETRAC project.• If the existing project continues, connector testing will start

2/1/18.• If the other project does not continue, connector testing will

start on 12/1/18.• We will know the project status by 10/25/17.