Update from ERCOT Market Services to the Board of Directors October 15, 2002. Retail Market Update. Topics ERCOT’s Master Project Plan Move-In/Move-Out Issues/Initiatives GISB 1.4 Update Data Transparency Project Update Quick Recovery Team Update New Power Transfer Update - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/1.jpg)
1
Update from ERCOT Market Services
to the Board of Directors
October 15, 2002
![Page 2: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/2.jpg)
2
Retail Market Update
Topics– ERCOT’s Master Project Plan– Move-In/Move-Out Issues/Initiatives – GISB 1.4 Update – Data Transparency Project Update– Quick Recovery Team Update– New Power Transfer Update– Market Synchronization Activities– Consumption Data Loading Reports– Lodestar Data Loading Improvements– Resettlement Update
![Page 3: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/3.jpg)
3
Master Project Plan Update
![Page 4: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/4.jpg)
4
Master Project Plan
• 2003 Proposed Projects– Project worksheet established with list of all known requested projects
• Status/Updates
• Targeted outcomes
• Resources (Funding & Headcount) required identified where known
– Internal reviews of projects with ERCOT steering committee completed
– PRS completed prioritization of projects originated by Market Participants on August 28th
– TAC approved list of priorities on September 5th
– List delivered to ERCOT BOD targeted for approval at October meeting
– 3 New projects requested since September 5th
![Page 5: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/5.jpg)
5
Master Project Plan
• 2002 Planned Projects– 51 Projects in progress– 22 Projects completed between August 1st and October 14th 2002– 5 Projects continuing on into 2003 for completion– 5 Projects removed from the 2002 plan (require reprioritization for
2003)
• 2002 Projects continuing into 2003 for completion include:– PR-20117 Internal Map Testing and Verification– PR-20079 Change Deployment Instructions_PRR281– PR-20067 Simultaneous Procurement of Ancillary Services– PR-20111 Hardening Initiatives– PR-2007801 IDR/NIDR Gap Corrections
![Page 6: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/6.jpg)
6
Master Project Plan
• 2002 Projects removed from active status (requires reprioritization to proceed)– PR-20068 Interzonal Congestion Management: Interim fix completed; any
further effort will go back through the prioritization process.
– PR-20071 Two Settlement System: Manual fix announced to market and Board. If automated solution desired a new project request will be submitted through the prioritization process.
– PR-20080 Define OOME as Instructed Deviation: PRR282 withdrawn and project canceled
– PIP106 Direct Load Control: Deleted from 2002 Active list and has been prioritized for 2003 and included in Consolidated Prioritization List.
– PR-20083 Ratcheting of OOME: Project withdrawn
![Page 7: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/7.jpg)
7
Master Project Plan
• Next Steps…– Conduct Project Management Office Procedures Training from October 30th
through November 13th 2002
– Remaining ERCOT resources aligned and scheduled against Q1 2003 projects by December 6th 2002
– Monthly project prioritization adjustments and recommendations:
• ERCOT Executive Steering Committee
• Market committees and subcommittees
• ERCOT IT and Business Teams
– Finalize and distribute documentation on the projects request/prioritization process
![Page 8: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/8.jpg)
8
Move-in and Move-out
Solutions Update
![Page 9: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/9.jpg)
9
Market Participant Meeting
![Page 10: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/10.jpg)
10
MP Visits
• Purpose– ‘Root out’ all sources of pain associated with Move-Ins
– Get each MPs opinion of worst problems
– Discuss possible solutions
– Find out if identified problems are common among all types of market participants
– Discuss concepts with consumer advocacy group
– Verify that all participants are dedicated to solving the problems and aware of the possible systemic impacts
– Discuss deployment of workarounds (Safety Net, Same CR Move-Ins, etc.)
![Page 11: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/11.jpg)
11
MP Visits
• Audience– TDSPs (5 - CenterPoint, AEP, Oncor, Entergy, TNMP)
– AREPs (4 - Reliant Retail, AEP, TXU E, Entergy)
– CREPs (6 - Coral, GEXA, Republic, TCE, Constellation New Energy, Green Mountain)
– Vendors (2 - Exolink, EC Power)
– Consumer Protection (1 - Public Utility Council)
![Page 12: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/12.jpg)
12
MP Visits
• Results– Identified several issues that were not previously identified
– Confirmed several common problems across many Market Participants
– Discussed concepts for solving identified issues
– Developed an average ‘pain’ level and frequency for major issues based on input from each MP
– Discussed several concepts with consumer advocacy group to verify compliance with Customer Protection
– Revealed inconsistencies and improper executions of workarounds
![Page 13: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/13.jpg)
13
MIMO Workshop
![Page 14: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/14.jpg)
14
MIMO Workshops
• Methods– Three type of issues; Existing Systems, Current Execution, & Market Gaps
– Two measurements for identifying order of discussion for issues• pain level• quantity of ESI Ids affected.
– The issues that are being pursued are as follows:1. Those that rank high on the pain level and quantity affected and are expected to be
relatively easy to repair2. Those that either are easy to fix but don’t rank high on the measurements or rank
high on the measurements and are difficult to fix.3. Those that are most likely to remain as workarounds for a longer period of time.
– They rank low on pain and quantity, but appear difficult to fix
– Three time frames for solutions are being applied;• Short-Term (solutions that can be implemented immediately or prior to next April)• Mid-Term (solutions that can be implemented next year after April)• Long-Term (solutions that can be implemented after 1/1/2004)
![Page 15: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/15.jpg)
15
MIMO WorkshopL
evel
of
Pain
Number of ESI ID’s affected
Issue 1
Issue 6
Issue 3
Issue 4
Issue 5
Issue 6
Issue 2
Issue 7
Issue 8
Issue 9
Low
High
High
![Page 16: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/16.jpg)
16
MIMO WorkshopL
evel
of
Pain
Number of ESI ID’s affected
Issue 1
Issue 6
Issue 3
Issue 4
Issue 5
Issue 6
Issue 2
Issue 7
Issue 8
Issue 9
Low
High
High
Low -
Net
Effect
of Is
sue
- H
igh
![Page 17: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/17.jpg)
17
MIMO WorkshopC
ost
of A
ddre
ssin
g
Net Effect of Issue on Market
Issue 1
Issue 6
Issue 3
Issue 4
Issue 5
Issue 6
Issue 2
Issue 7Issue 8
Issue 9
Low
High
High
![Page 18: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/18.jpg)
18
MIMO WorkshopC
ost
of A
ddre
ssin
g
Net Effect of Issue on Market
Issue 1
Issue 6
Issue 3
Issue 4
Issue 5
Issue 6
Issue 2
Issue 7Issue 8
Issue 9
Low
High
High
Higher Impact
& Lower Cost
![Page 19: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/19.jpg)
19
MIMO Workshop
• Results– 32 Concepts were discussed
• 7 Concepts were dismissed for various reasons• 1 Concept was determined as solved in Version 1.5• 23 Concepts were discussed
– 4 Concepts were tabled until additional information can be obtained
– 19 Concepts were discussed at length and are being considered for recommendation to RMS
» 10 Short-Term» 9 Mid-Term
• 1 Concept was not discussed (lack of time)
![Page 20: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/20.jpg)
20
Next Steps
• MIMO Taskforce meetings– October 23, & 24 in Austin
– October 29, & 30 in Dallas (tentative)
• Recommendations to RMS at November RMS meeting– Potentially 15-24 Concepts
• Release of implementation timelines
• Development of Texas Set Change Controls, Protocol Revision Requests, and RFP(s) as needed
• Deployment of Solutions
• Re-Evaluation of Move-In/Move-Out processes
![Page 21: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/21.jpg)
21
Timeline 08-29-02 RMS establishes Task Force09-05-02 Kickoff Meeting – assignments given for MP transaction
root cause analysis10-15-02 Complete root cause analysis and comprehensive list
of business scenarios TBD Develop detailed requirements document for RFP - RMS Approves MIMO requirements document(s)
- Release RFP(s) to vendors - RFP Responses due from vendors - Summarize vendor responses for Task Force review - Recommendations to EOTF on vendor “Short List” - Vendor presentations to Task Forces - EOTF recommendation to ERCOT Board - Begin contract negotiationsEnd 1Q03 Award contract
Move-in/Move-outLong-term Solution Status
![Page 22: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/22.jpg)
22
GISB 1.4 Update
![Page 23: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/23.jpg)
23
GISB 1.4 Update
• RMS agreed at August meeting to move forward with implementing GISB 1.4 at ERCOT
• Internal testing and implementation of a GISB 1.4 interface is underway at ERCOT, – Production Sign-off scheduled for 10/25
• All production components are in place as of 10/11– Acceptance Testing and Market Participant Testing – 10/15-24
• TDTWG is surveying market participants to finalize migration readiness dates– Preliminary migration schedule reviewed at 10-4-02 TDTWG – Market Participant migration will begin week of 10-29-02– Goal is to complete migration by April 1, 2003
![Page 24: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/24.jpg)
24
ERCOT Data Transparency(ETS)
![Page 25: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/25.jpg)
25
Data Transparency Project
• ETS Phase I Progress– Development and Production Database Servers and Application Servers
are configured and installed on the network
– Report Development 99% complete
– Production testing is underway
– Database transaction loading to start 10/21
– User Documentation is being finalized
– Backup and restart procedures coordinated
– Implementation Schedule is being revised to ensure adequate testing• Estimated to move three weeks to last week in November
![Page 26: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/26.jpg)
26
Quick Recovery Team Update
![Page 27: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/27.jpg)
27
ESI Ids Reported to QRE (as of October 15, 2002)
Current Status Quantity
New 461
In Analysis 6766
In Progress 50140
Resolved 79638
Total 137005
Entity Quantity
TDSP 34271
QRE Team 7049
CR 8820
Total 50140
Point of Failure Quantity
Cause Not Reported 6990
CR 37000
ERCOT EAI 3979
ERCOT FTP 694
ERCOT Manual Process (814_08)
3428
ERCOT PaperFree 7359
ERCOT Siebel 2129
ERCOT TCH 6427
TDSP 11632
Total 79638
![Page 28: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/28.jpg)
28
New Power Transition Status
![Page 29: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/29.jpg)
29
New Power Transition
Status as of 10/11/2002
• Two ESI Ids remain to be completed
• “Scheduled” at ERCOT
• Waiting for 867-04
• Scheduled meter read date 9/24/2002 (backdated)
![Page 30: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/30.jpg)
30
Final New Power Transition Numbers
42,690 ESI IDs TXU Energy Services
37,175 ESI IDs Reliant Retail Services
2,022 ESI IDs 3rd Party Competitive Retailers
260 ESI IDs New Power Submitted Move-Outs
82,147 ESI Ids Total Transitioned
![Page 31: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/31.jpg)
31
Market Synchronization Activities
![Page 32: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/32.jpg)
32
• Objective – Address market issues resulting in an out of sync “Rep of Record” between
ERCOT, TDSP, and CR systems for all ESI IDs resulting from market startup/processing issues as well as subsequent workarounds
• Completed– ERCOT identified “Perfect Sync” and “1 Day Perfect” – sent lists to MPs– ERCOT identified out-of-sync categories at Sept 10th design meeting– Task Force identified additional ESI IDs considered “In Sync” – sent lists to MPs– Task Force prioritized 8 categories based upon potential customer impact – sent
lists to MPs
• In Progress– TDSPs and CRs to complete analysis of priority 1-4 files and respond to ERCOT
by October 18th (priority 5-6 response date TBD)– Weekly conference calls scheduled on Tuesdays through October– “How to” make repairs face-to-face meeting scheduled for October 25th
.
Market Synchronization Retailer Synchronization Project
![Page 33: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/33.jpg)
330
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
Market Synchronization Retailer Synchronization Project
Considered In Sync5,399,860
Under Analysis739,039
Non-ERCOT area Removed from Analysis
945,000
ESI IDs
0
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
Considered In Sync5,279,063
Under Analysis859,836
Non-ERCOT area Removed from Analysis
945,000
ESI IDs
September 26, 2002 Report October 16, 2002 Report
![Page 34: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/34.jpg)
34
• Next Steps
– October 15th, 22nd, 29th Follow-up Conference Calls Define items for immediate “fix” and report on progress Define issues to raise to RMS
– October 25th Face-to-face meeting to finalize decision on “backdating” fixes
– November 13th Present any disputed scenarios to RMS
– December 5th
Escalate issues to TAC (if required)
Market Synchronization Retailer Synchronization (continued)
![Page 35: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/35.jpg)
35
Market Synchronization“TDSP as LSE” Clean-up
October 10, 2002 RelationshipStatus exists after Active as of
Feb 01,2002 10/10/2002CenterPoint 8,350 505ONCOR 18,328 433TNMP 515 71CPL 2,246 793WTU 3,164 314
Market 32,603 2,116
• Objective– Ensure that all ESI ID are converted from the “TDSP as LSE” by the time True-
Up Settlement of February 2002 begins (December 7, 2002)
• Clean-up Plan – ERCOT to send TDSPs list of ESI ID affiliated
with “TDSP as LSE” any time after Feb 01, 2002 – TDSPs to provide correct effective date concurrent
with usage record prior to February 01, 2002 or identify de-energized/inactive ESI IDs
– ERCOT to make correction based upon TDSP response (complete pending orders, establish relationship, etc…)
– Weekly conference calls with TDSPs (already takes place with ONCOR and CenterPoint)
• In Progress– ERCOT to send revised lists to TDSPs by 10-21-2002– TDSPs to respond with new effective dates or status data by November 01, 2002
![Page 36: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/36.jpg)
36
Market Synchronization – Non Price to Beat
• Objective– Make necessary corrections to ensure that >1MW Customers were switched
on the correct date in January 2002• Completed Items
– Per RMS direction, ERCOT sent lists to each MP for reconciliation:• Full list of ESI ID in the >1MW project was confirmed• Still to be fixed list (subset of the full list) was also confirmed
– 1,133 ESI Ids (>1 MW) identified by CRs (meeting the April 30 deadline)• Number increase attributed to reconciliation of lists with Market
Participants– 1001 (88%) ESI IDs are corrected– 74 ( 7%) ESI IDs were agreed not to fix by TDSP and CR
• In Progress– 58 (5%) ESI IDs remaining to be fixed
• 11 – CR of RECORD needs to be fixed• 42 – Date of when CR became CR of Record needs to be fixed• 5 – where CR and TDSP are not in agreement – CR will have to escalate
![Page 37: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/37.jpg)
37
Market Synchronization – Non Price to Beat
• Next Steps– ERCOT to continue to confirm changes in Siebel and Lodestar
– Final analysis in progress at ERCOT
– ERCOT will provide suggested next steps to the submitting CR and TDSP
– Conference calls being held with TDSP to determine next steps for those ESI IDs that still need to be fixed (ERCOT metering team included on calls)
– Affected CR to determine next steps for ESI IDs where no agreement is reached
CR1 CR2 CR3 CR4 CR5 CR6 Total
TDSP 1 3 0 2 5 0 7 17
TDSP 2 0 1 0 0 0 2 3
TDSP 3 0 0 0 1 5 5 11
TDSP 4 0 1 10 1 2 13 27
Total 3 2 12 7 7 27 58
![Page 38: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/38.jpg)
38
Consumption Data Loading Reports
![Page 39: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/39.jpg)
39
% of IDR Data Loaded by MRE (as of 09-24-2002)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
7/31 8/14 8/28 9/11 9/25 10/9 10/23 11/6 11/20 12/4 12/18 1/1 1/15 1/29 2/12 2/26 3/12 3/26 4/9 4/23 5/7 5/21 6/4 6/18 7/2 7/16 7/30 8/13 8/27 9/10
CPL
WTU
ONCOR
CenterPt
TNMP
Brazos
LCRA
Rayburn
STEC
System
IDR Data Loaded into LodestarSeptember 24th Report
95% or better expected
91%
![Page 40: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/40.jpg)
40
% of IDR Data Loaded by MRE (as of 10-11-2002)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
10/1 10/15 10/29 11/12 11/26 12/10 12/24 1/7 1/21 2/4 2/18 3/4 3/18 4/1 4/15 4/29 5/13 5/27 6/10 6/24 7/8 7/22 8/5 8/19 9/2 9/16 9/30
CPL
WTU
ONCOR
CenterPt
TNMP
Brazos
LCRA
Rayburn
STEC
System
IDR Data Loaded into LodestarOctober 11th Report
95% or better expected
93%
![Page 41: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/41.jpg)
41
IDR Data Status Report 99% Data Available per MRE
As of As ofSeptember 24, 2002 October 11, 2002
CPL 12/03/01 01/14/02CenterPoint 12/31/01 12/18/01ONCOR 12/03/01 12/28/01TNMP 06/25/02 01/14/02WTU 01/22/02 01/25/02
Brazos 09/15/02 09/30/02LCRA 09/12/02 10/02/02Rayburn 08/31/02 09/30/02STEC 09/03/02 09/30/02
Market 12/20/01 01/17/02
Meter Reading Entity(MRE)
![Page 42: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/42.jpg)
42
Non-IDR Data Status Report October 14, 2002
Percent of Actual Non-IDR Datafrom October 11, 2002 Batch Process
32%
37%
20%
32% 34%
0%
34%
95% 96%
80%
92% 93% 95%
100% 99% 99% 99%95%
99%
0% NA0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
CenterPoint ONCOR TNMP CPL WTU Sharyland Market
Initial (9-25-02) -16 Days After
Final (8-14-02) - 59 Days After
Re-Settle (10-8-01) - 369 Days After
![Page 43: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/43.jpg)
43
Lodestar IDR Data Loading Improvement Recommendations by TDSPs
![Page 44: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/44.jpg)
44
• Objective – Implement process improvements which alleviate problems loading IDR
data into ERCOT’s Lodestar system
• Completed Items– ERCOT and MPs met August 15th to define scope of 9 items– Conference call held on August 26th to refine scope and follow-up– 6 items are complete (see matrix on next page)– TX SET reviewed 2 EDI related recommendations on Sept 16th (see
matrix)
• In Progress– 2 items defined for immediate action (both are currently in test)– 4 items defined as long term fixes (project request being drafted)
• Next Steps– ERCOT to define scope of “additional Lodestar Data Loading
Improvements” project
IDR Data Loading Recommendations by TDSPs
![Page 45: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/45.jpg)
45
Resettlement Update
![Page 46: Update from ERCOT Market Services to the Board of Directors October 15, 2002](https://reader036.vdocuments.site/reader036/viewer/2022062517/568136d1550346895d9e6fdb/html5/thumbnails/46.jpg)
46
Resettlement of True-up Status Update
SeptOct
NovDec
JanFeb
MarApr
MayJun
JulAug
SepOct
NovDec
20032004
December 7, 2002
True-Up Settlement of February 01, 2002
The date all ESI IDs should no longer be with
the “TDSP as LSE”.
November 1, 2002
True-Up Settlement of November 20, 2001
The date we move from the ERCOT Board resolution to the Protocols IDR Data Threshold
April 1, 2003
Date we expect to be back to six month after the trade day True-Up
Settlements
November 14, 2002
True-Up Settlement of December 17, 2001
Drop dead date for correction of Non-PTB ESID Backdating
October 16, 2002
80 re-settlements performed to date(Through Oct 18, 2001)