Facilities Planning, Design & Construction
University of North TexasIntegrated University Facilities Project Management Process
APPA Chicago August 2015
UNT Factoids:
36,000+ students172 Buildings including 15 Res Halls 7.1M GSF, 2.3M NASF Academic907+ acres
8/17/2015
2
AVP for FacilitiesAVP for Facilities
Facilities
Maintenance
Facilities
Maintenance
Facilities Planning, Design
& Construction
Facilities Planning, Design
& Construction
Facilities Support & Services
Facilities Support & Services
UNT Facilities Organization(Serving Academic, Housing & Dining)
318 FTE Staff
Helen Bailey, AIA, CEFP, LEED AP
Director
Facilities
Planning Design & Construction
Helen Bailey, AIA, CEFP, LEED AP
Director
Facilities
Planning Design & Construction
CADDCADD Campus PlanningCampus Planning Auxiliary PlanningAuxiliary Planning GIS mappingGIS mapping EstimatorEstimator
Administrative Coordinator
Administrative Coordinator
11 Project Management Staff +6 students1 CADD Staff + 1 student2 GIS Staff + 1 student1 Estimating staff
Typical Annual Project volume:• Major > $1M = 6• Medium $100K to $1M = 20• Minor renovation/remodels< $100K about 140
Planning, Design & Construction
8/17/2015
3
Project Management Discussion
• What is your experience with project management?
• Do you have issues with funding and budget control?
• Challenges with project closeout?• What project management
tools/processes work for your organization?
In the beginning……
The CHALLENGES in Project Management
8/17/2015
4
The Vision
• One unified simple method for running projects
• Avoid personality driven project management
• Improved customer satisfaction and credibility for FPDC & Facilities as a whole
• Easy access to project status and budget data for both client and leadership
• Formalized, efficient and easily understood procedures
• Establish project approval process and funding model
• Auditable
The Light Bulb moment!
Ah Ha! What does it take?
• Standard written processes & forms
• Getting the word out & top down support for the process
• Early order of magnitude estimates
• Ensure funding leadership supports the project at the “bright idea” stage before expending significant man-hours
• Ensure the “bright idea” meets campus objectives
• Secure funding first
8/17/2015
5
Holistic Approach
1.
Estimate
(PRE)
2.
Concept
Approval
3.
Funding Identified
4.
Project Initiation
(PIW)
5.
Scoping
6.
Budget Approval
& Funds x‐fer
7.
A/E Procurement
8.
Design
9.
Construction
10.
Occupancy
11.
Budget reconciliation
12.
Close‐out
Not tracked in CMMS system Funding & status tracked in CMMS system
Bright Idea!!!
The step-by-step process:
• PRE – preliminary scoping & estimate
• PIW – project initiation
• Detailed scoping (programming)
• Budget approval and transfer of funds
• Procurement of professional services when >$50k
• Design turn-key if under $50k
• Construction
• Substantial Completion
• Certificate of Occupancy
• Customer satisfaction survey
• Project reconciliation & closeout
• Facilities inventory updates (CAFM)
• Digital archiving
Have a check list…..
8/17/2015
6
Have a procedures manual
https://facilities.unt.edu/sites/default/files/Facilities%20Project%20Procedures%20-%20June%202010_All.pdf
Why?
Consistency Compliance Coordination Documentation
Centralized Reference Resources(Microsoft Sharepoint)
• Web links
• Network paths
• Forms
• Manuals
• Etc.
8/17/2015
7
Communication……standard emails…..
Its all the same process….
• Integrated project management into CMMS work order system
• Standard process for all Facilities multi-trade projects for procurement and budget tracking
• Early order of magnitude estimates PRE by in-house estimator
• Standardized involvement of O+M technicians during scoping, design & construction.
8/17/2015
8
• Departments/Leadership approval of concept
• Order of Magnitude for large projects
• Itemized estimate for < $50K
• Provides initial scoping based on cursory considerations
• Estimating resources include RSMeans, historical data, CTC, etc. http://facilities.unt.edu/sites/default/files/Pre
Estimate_v1_0.pdf
Project Request for Estimate (PRE)
PRE – Pre Estimate (Order of Magnitude cost)
• Early scoping
• Helps clients secure funding
• Seek grants
• Reduces sticker shock
Estimating Services
8/17/2015
9
Project Initiation Worksheet(PIW)
• Office of Space Management approval
• Client point of contact info • Details about the project• Funding source and account holder
signatures
https://facilities.unt.edu/sites/default/files/PIW_09.15.14.pdf
Definition of a “project”:
• Multi-trade
• Over $5K
• Any project with architectural changes (i.e. moves walls/doors)
8/17/2015
10
Signed Budget approval and withdraw funding
Project Funding & Accounting
• Strict funding processes• Project financial activities never post directly to client/department
accounts• No project financial activities can occur until Project Account is funded• PMA charges transferred at the same time as project funds
• “Clearing Account” concept• Set up two clearing accounts (HEAF and Local)• Budget under $100k
• Transfer from client account to clearing account(s) depending on fund types• Performed by Facilities
• Budget is $100k or more• Set up new account dedicated to single project• Transfer from client account to new project account• Performed by UNT Budget Office
• Update CMMS work order system once funding has been transferred• Project is now funded and transactions can occur
8/17/2015
11
Examples:
• Building MEP upgrades
• Paving replacement
• Roof & waterproofing
• Etc.
Facilities Maintenance multi-trade/complex projects = same process
In-house Design
• > $50K• Less complex• In-house expertise• Specialized scope
8/17/2015
12
Procurement of professional services >$50k
Plan Review
• O&M
• Life Safety
• User group
• Planning staff
• Management
8/17/2015
13
Project status list
• Standardized delivery methods dependent on size (in-house, JOC, CSP, CM@R, etc)
• Pre con meeting, schedule & contact list
• Submittal reviews
• Change orders (minimize)
• Technician inspections
• Final inspection
Construction
8/17/2015
14
• Concrete
• Paint
• Cabinet shop
• MEP technicians
• Sign shop
• Etc.
Use Facilities crews for smaller projects
Construction Inspections
8/17/2015
15
• Substantial Completion
• Certificate of Occupancy
• customer service survey
• Warranty
Completion
Closeout check list
8/17/2015
16
Budget Tracking in CMMS work order system
Budget Reconciliation
• Budget staff work with PM to verify all transactions are tracked and closed
• Reconcile project transactions with actual project account for a balanced budget
• PM notified of final balance
• Close project and update as reconciled
• Reports by project account match actuals
8/17/2015
17
But it’s a “living” document….An evolving process…….
• Empower the team
• Be open to suggestions for a better way of doing it.
• Understand there is always room for improvement
• Our process has evolved and changed for the better over the years.
Consider the unique aspects of the project:
Project Size
Client
Location
Funding
Schedule, etc.
Flexibility in the process is also important……….
8/17/2015
18
Facilities Inventory, Digital Archiving & building records
• Field Verification
• Coordination w/ Design groups
• Building Space Inventory Floor Plans
FM Systems & Space Management
8/17/2015
19
Capital Improvement Plan (+$1M)
Plan ahead……
Project Manager Workload
Metrics• Big Benefit of CMMS integrated project management.
• Data uses as reporting tool
Auxiliary Planning11 Projects $3,382,432
Campus Planning46 Projects $14,473,106
PM 1
PM 2
PM 3
PM 4
PM 5
PM 6
8/17/2015
20
FY 12 FY 13 FY14 FY15
PRE's received to date 124 102 138 100
PRE's submitted 11 3 0 1
PRE's in progress 4 3 1 4
PRE's in review 5 0 0
Total PRE's completed in FY 120 96 127 92
Total Budget Estimates $15,874,798 $ 8,845,526 $14,870,160 $434,017,888
Estimating Metrics
Estimating Dept.
0
5
10
15
20
25
30
8/17/2015
21
• Summer 2015
• Auxiliary Planning: $4.56M; 22 projects
• Campus Planning: $11.61M; 23 projects
• Summer 2014
• Auxiliary Services: $2.5M; 12 projects
• Campus Planning: $4.87M; 11 projects
• Estimating completed/value metrics:
• FY14 = 127 estimates, $14.8 M
• FY 15 = 92 estimates, $434 M
Facilities Planning & Construction Summer workload Summary
JOC Contractor Usage to date:
8/17/2015
22
0
20
40
60
80
100
120
Sep‐12
Oct‐12
Nov‐12
Dec‐12
Jan‐13
Feb‐13
Mar‐13
Apr‐13
May‐13
Jun‐13
Jul‐13
Aug‐13
Sep‐13
Oct‐13
Nov‐13
Dec‐13
Jan‐14
Feb‐14
Mar‐14
Apr‐14
May‐14
Jun‐14
Jul‐14
Aug‐14
Design
Construction
Punch
Project Phase Metrics
Departmental Project Load Metrics
$‐
$5,000,000
$10,000,000
$15,000,000
$20,000,000
$25,000,000
October‐11
November‐11
December‐11
January‐12
February‐12
March‐12
April‐12
May‐12
June‐12
July‐12
August‐12
September‐12
October‐12
November‐12
December‐12
January‐13
February‐13
March‐13
April‐13
May‐13
June‐13
July‐13
August‐13
September‐13
October‐13
November‐13
December‐13
January‐14
February‐14
March‐14
April‐14
May‐14
June‐14
July‐14
August‐14
8/17/2015
23
0
5
10
15
20
25
September October November December January February March April May June July August
Volume of new project requests per month
FY10 FY11 FY12 FY13 FY14
Monthly Construction Obstruction Report
Keep the public informed…”please excuse the dust”
8/17/2015
24
Successes & Lessons Learned…..
• Top-down support of process is critical
• In-house construction crew was disbanded
• Rigorous standardized training of new project management staff - a must
• Price Guarantee didn't work
• Positive audit experience
• Institution financial accounting system not integrated with CMMS work order system.
• Still refining processes for maintenance projects
• Client feedback (Very positive but a few still say – too costly & takes too long)
• Much improved paper trail
• Helps eliminate challenges between State and local funding sources for single projects
….Goals for the Future
Keep dreaming of bigger and better…..
• Automation
• Integration with institution financial accounting system
• Simplified Facilities Funding
• Methodic and global development plan
8/17/2015
25
And above all……
PIWLink: https://facilities.unt.edu/sites/default/files/PIW_09.15.14.pdf
PRELink: http://facilities.unt.edu/sites/default/files/PreEstimate_v1_0.pdf
Web page: http://facilities.unt.edu/depts/fpdc
Procedures: https://facilities.unt.edu/sites/default/files/Facilities%20Project%20Procedures%20-%20June%202010_All.pdf
Design Guidelines: https://facilities.unt.edu/sites/default/files/DESIGN%20GUIDELINES%20JUNE%202014%20rev%202_091514.pdf
What to expect: http://facilities.unt.edu/sites/default/files/M_FMC%20What%20to%20Expect_0.pdf
Useful Links: